CN102605750B - Grouting reinforcement and earthquake resisting method for earth and rockfill dam - Google Patents

Grouting reinforcement and earthquake resisting method for earth and rockfill dam Download PDF

Info

Publication number
CN102605750B
CN102605750B CN201210006730.3A CN201210006730A CN102605750B CN 102605750 B CN102605750 B CN 102605750B CN 201210006730 A CN201210006730 A CN 201210006730A CN 102605750 B CN102605750 B CN 102605750B
Authority
CN
China
Prior art keywords
dam
grouting
rockfill
slip casting
earth
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201210006730.3A
Other languages
Chinese (zh)
Other versions
CN102605750A (en
Inventor
刘汉龙
杨贵
王复明
陈育民
刘彦辰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hohai University HHU
Original Assignee
Hohai University HHU
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hohai University HHU filed Critical Hohai University HHU
Priority to CN201210006730.3A priority Critical patent/CN102605750B/en
Publication of CN102605750A publication Critical patent/CN102605750A/en
Application granted granted Critical
Publication of CN102605750B publication Critical patent/CN102605750B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The invention discloses a grouting reinforcement and earthquake resisting method for an earth and rockfill dam, which includes the technical steps: using a drilling machine to drill holes at certain intervals on the upstream top and the downstream top of a dam in a range from one-quarter dam height to one-fifth dam height during filling of the dam; driving grouting casings for drilling supporting or pre-embedding horizontal grouting casings with holes in real time; injecting polymer materials into the grouting casings through grouting pipes; allowing the polymer materials to chemically react in the grouting casings and quickly swell and allowing the polymer materials to permeate into surrounding rockfill to be cemented with rockfill through voids inside the rockfill; and forming a solid flexible reinforced complex so that cohesion of rockfill complex is increased and seismic resistance of the dam is improved. The method is applicable to newly built earth and rockfill dams, is also applicable to earth and rockfill dams built already, and is fast in construction, the reinforcement is the flexible complex and adaptable to deformation of the dam under the action of seismic load, and good seismic resisting effect is achieved.

Description

A kind of earth and rockfill dam grouting and reinforcing anti-shock methods
Technical field
The invention belongs to hydraulic engineering technical field, relate to the inner slurry injection technique of a kind of rockfill and construction method, particularly a kind of earth and rockfill dam grouting and reinforcing anti-shock methods.
Background technology
China is located between circum-Pacific seismic belt and Mediterranean-Himalayas earthquake zone, geological structure is large-scale and complicated, in, strong earthquake activity is frequent, intensity is large, focus is shallow, distribution is wide, disaster is very serious, according to expert prophesy, the Future in China several years will enter Earthquake Activity Periods.Earth and rockfill dam is the conventional dam type in Hydraulic and Hydro-Power Engineering, along with continually developing and the progress of dam construction technique of water conservancy and hydropower resource, the construction development of high earth and rockfill dam rapidly, only China is built and at the 200 m level earth and rockfill dams of building existing many, dam, long river core wall rockfill dam height of dam 240 m and Lancang River Nuozhadu earth core rockfill dam height of dam 262 m, also the high earth and rockfill dam of a collection of 300 m levels will be built, as: two river mouths, two Jiangkou, Gu Shui, Ma Ji, as Dams such as U.S., thatch Ha Xia, wherein power station, two Jiangkou core wall dam is up to 312 m.These high earth and rockfill dams are positioned at high seismic intensity area mostly, and the quake-resistant safety of dam needs special attention.Earth and rockfill dam has good anti-seismic performance, there are many earth and rockfill dams to live through strong earthquakes test both at home and abroad, but the destruction of earth and rockfill dam is also very obvious after macroseism, as: in China's Tangshan Earthquakes in 1976, steep River Reservoir earth dam and Miyun Reservoir Baihe key dam have all produced serious damaged; In " 5. 12 " Wenchuan violent earthquake in 2008, although from earthquake centre there is not whole destruction in the purple level ground slab loose rock dam close to, damaged obviously.The earthquake of dam, light may be building itself occurs crack or infiltration are serious may cause the avalanche of dam body to be burst, flooding, thereby causes the secondary disaster of the huge life in downstream and property loss.
For high earth and rockfill dam, under seismic loading, easily at its dam crest position, there is " whipping effect ", cause dam crest position rockfill dynamic response larger.Rockfill is typical granular material, and resistance to overturning is poor, and the phenomenons such as loosening, slippage easily occur under seismic loading, thereby affects the resistance to overturning of dam.A large amount of seimic disaster census and numerical computations show, the most obvious position of earthquake is that dam 4/5 heights of dam are above, near maximum height of dam section and near river valley breaks place etc.Before the present invention, in engineering, conventional reinforcement means is suitably to increase width at dam crest at present; Within the scope of elevation of dam crest, adopt the reinforced structures such as geo-grid, reduce seismic horizontal permanent deformation and depression.For increasing width at dam crest, increase undoubtedly construction working amount and construction investment, but still can not solve the stability of dam crest position rockfill under dynamic load function under seismic loading.Adopt the horizontal reinforcement materials such as geo-grid to carry out reinforcement, belong to local stratiform reinforcement, belong to plane ribbing, its reinforcement effects is subject to the impact of the intensity of reinforcement material own larger, and in rock fill dam construction process, is difficult to guarantee that it is not damaged.
High polymer (organic high molecular compound is called for short macromolecular compound or macromolecule, claims again high polymer) slurry injection technique is the road-based infrastructure rapid-maintenance new technology that 20 century 70s grow up.Be used widely abroad at present, in the middle of China also tentatively applies to the maintenance of speedway.The current rapid-maintenance in infrastructure such as road, airfield runway, tunnel, bumping at bridge-head, and the antiseepage for dykes and dams as ultra-thin cut-off wall material, but its application aspect antidetonation has no report both at home and abroad.
Summary of the invention
The object of the invention is to overcome current high earth and rockfill dam dam crest under seismic loading there is " whipping effect " thus cause the phenomenons such as rockfill is loosening, slippage, and the shortcoming that the reinforcement seismic measures of routine exists at present, a kind of earth and rockfill dam grouting and reinforcing anti-shock methods of proposition.This technology belongs to three-dimensional flexible reinforcing, after the flexible reinforcing of rockfill, has good suppleness, can adapt to the distortion of dam body, also can provide cohesion, thereby reach the object that improves the problems such as earth and rockfill dam aseismic deformability simultaneously.
The present invention adopts following technical step to realize:
(1) according to aseismic design calculation achievement, determine that dam crest carries out the scope of slip casting processing, preferably from 3/4 ~ 4/5 height of dam to dam crest;
(2) when dam construction is after the elevation needing reinforcement, along axis, at upstream and downstream rockfill top, with the shape of certain rule, vertically hole as triangle or arranged in squares respectively, injected hole spacing 3 ~ 5m;
(3) adopt rig to hole, and the slip casting sleeve pipe that follows up in time hole and go along with sb. to guard him, in order to avoid rubble is stepped on hole, or perpendicular to the pre-buried slip casting sleeve pipe with injected hole of axis of dam direction level;
(4) to slip casting inside pipe casing, put into high polymer grouting pipe, by Grouting Pipe, in slip casting sleeve pipe, inject high polymer material;
(5) according to the porosity of rockfill and bore arrangement mode and scope, calculate grouting amount, by the slip casting time, carry out the control of grouting amount; The slip casting time reaches rear change grouting port position, first hoisting grouting sleeve pipe, rear hoisting grouting pipe; Carry out the rockfill slip casting of another layer of position; Form the reinforcing body of a similar cylinder centered by injected hole;
(6) boring slip castings are complete, in adjacent boring, carry out identical grouting mode, also can carry out multiple holes grouting simultaneously, until all injected holes of this elevation complete slip casting, finally form the compound antidetonation body that one deck high polymer is reinforced dam crest;
(7) proceed enrockment and fill, until default elevation repeats the step of (2)-(6), until dam embankment is to the height of setting.
Between described Grouting Pipe, by iron plate, be fixed, between iron plate and slip casting sleeve pipe, adopt air bag to seal.
Described earth and rockfill dam grouting and reinforcing anti-shock methods, the injected hole degree of depth is generally 5m, should revise according to the height of dam embankment in Practical Project, be the integral multiple of every layer of filled height.
Described earth and rockfill dam grouting and reinforcing anti-shock methods, injected hole can be vertical drilling, can be also to tilt or horizontal drilling.
Advantage of the present invention and effect are:
(1) anti seismic efficiency is good.After the present invention adopts high polymer grouting to reinforce, rockfill forms a whole non-individual body material, is different from cement injection material, and this material has good elasticity and intensity, particularly has good tensile strength.Composite material after formation belongs to flexible reinforcement, under seismic loading, can effectively reduce and absorb seismic energy, reduces in formation crack, stabilization zone.
(2) safe and reliable.Adopt high polymer grouting to reinforce around and be neutral in environment, do not endanger environment, not contaminated soil and water, material is not subject to the erosion of mould and fungi; There is good stability, can not shrink for a long time and go bad.
(3) duration is short.Adopt high polymer grouting to compare its length of time with cement injection shorter, do not need maintenance, shortened the engineering time greatly, on almost not impact of programming.
(4) cost is low.After high polymer generation chemical reaction, cubical expansivity is large, compares with cement injection, has significant economic benefit.
(5) easy construction.In work progress, can carry out upstream boring grouting reinforcing and downstream enrockment fills, both are independent of each other, and hocket simultaneously.
(6) applied widely.High polymer grouting reinforcement means both can, to reinforcing building earth and rockfill dam, also can carry out seismic hardening to built earth and rockfill dam; Reinforcing position can be the comparatively violent position of dam crest acceleration response, can be also the joint areas such as dam abutment.
Accompanying drawing explanation
General effect figure after Fig. 1 earth and rockfill dam grouting and reinforcing of the present invention;
Dam crest a-quadrant enlarged drawing in Fig. 2 Fig. 1;
In Fig. 3 Fig. 2 along the sectional drawing of B-B line;
The enlarged drawing in C region in Fig. 4 Fig. 2;
In Fig. 5 Fig. 4 along the sectional drawing of E-E line;
The enlarged drawing in D region in Fig. 6 Fig. 4;
In figure: 1 upstream enrockment, 2 core-walls, 3 downstream enrockments, 4 slip casting sleeve pipes, 5 Grouting Pipe, 6 high polymer mixtures, 7 iron plates, 8 air bags, 9 pneumatic tubes
The specific embodiment
Below in conjunction with accompanying drawing, the specific embodiment of the present invention is described in detail.Protection scope of the present invention is not limited with the specific embodiment, but is limited by claim.
As shown in Fig. 1,2,3,4,5 and 6, a kind of earth and rockfill dam grouting and reinforcing anti-shock methods, its technical step is:
In work progress first according to the Seismic Design Requirements of dam, in dam crest upstream and downstream 1/4 to 1/5 altitude range, along axis respectively at upstream rockfill (1) and downstream rockfill (3) top with the shape of certain rule as triangle or arranged in squares boring, and the slip casting sleeve pipe (4) that follows up in time, for core-wall (2) part, do not carry out slip casting processing.
In dam construction process, adopt placement in layers, when dam construction is after the elevation needing reinforcement, start to beat injected hole at dam body upstream rockfill (1) and downstream rockfill (3) surface.In work progress, consider that there is certain gradient on dam body surface, according to every layer of filled height in practice of construction, carry out drilling construction design, drilling depth is the integral multiple of filling-up thickness, be generally 5m left and right, in Practical Project, can revise according to the actual height filling, in drilling machine construction process, for avoiding rubble to step on hole, adopt the sleeve pipe of follow-up slip casting in time, injected hole diameter is generally not less than 50mm, or perpendicular to the pre-buried slip casting sleeve pipe (as shown in Figure 3) with injected hole of axis of dam direction level.
In slip casting sleeve pipe, put into high polymer grouting pipe (5) (as shown in Figure 4).Grouting Pipe is fixed together by iron plate (7), by rubber pocket (8) and slip casting sleeve pipe (4) sealing.In process of the test, by pneumatic tube (9), carry out the control of the expansion of air bag.After mixing in slip casting sleeve pipe, high polymer material there is chemical reaction, form high polymer mixture (6) (as shown in Figure 6), volume expansion, the hole by sleeve pipe periphery flows in the rockfill gap of periphery, filling hole, forms a closely cemented composite material; According to the porosity of rockfill and bore arrangement mode and scope, calculate grouting amount, by the slip casting time, carry out the control of grouting amount; The slip casting time reaches rear change grouting port position, first hoisting grouting sleeve pipe, rear hoisting grouting pipe.Carry out the rockfill slip casting of another layer of position; Form the reinforcing body of a similar cylinder centered by injected hole; A boring slip casting is complete, in adjacent boring, carries out identical grouting mode, also can carry out multiple holes grouting simultaneously, finally forms the compound antidetonation body that one deck high polymer is reinforced dam crest.
After completing the grouting and reinforcing of this layer, proceed dam embankment, after increasing 5m left and right, filled height repeats boring grouting with plunger above, until fill dam crest.

Claims (4)

1. an earth and rockfill dam grouting and reinforcing anti-shock methods, is characterized in that comprising the following steps:
(1) according to aseismic design calculation achievement, determine that dam crest carries out the scope of slip casting processing, for from 3/4 ~ 4/5 height of dam to dam crest;
(2) when dam construction is after the elevation needing reinforcement, along axis, at upstream and downstream rockfill top, with triangular arrangement, vertically hole respectively, injected hole spacing 3 ~ 5m;
(3) adopt rig to hole and the sleeve pipe of follow-up slip casting in time, or perpendicular to the pre-buried slip casting sleeve pipe with injected hole of axis of dam direction;
(4) to slip casting inside pipe casing, put into high polymer grouting pipe, by Grouting Pipe, in slip casting sleeve pipe, inject high polymer material; (5) according to the porosity of rockfill and bore arrangement mode and scope, calculate grouting amount, by the slip casting time, carry out the control of grouting amount; The slip casting time reaches rear change grouting port position, first hoisting grouting sleeve pipe, rear hoisting grouting pipe; Carry out the rockfill slip casting of another layer of position, form the reinforcing body of a similar cylinder centered by injected hole;
(6) boring slip castings are complete, carry out identical grouting mode, or carry out multiple holes grouting simultaneously in adjacent boring, until all injected holes of this elevation complete slip casting, finally form the compound antidetonation body that one deck high polymer is reinforced dam crest;
(7) proceed enrockment and fill, until default elevation repeats the step of (2)-(6), until dam embankment is to the height of setting.
2. a kind of earth and rockfill dam grouting and reinforcing anti-shock methods according to claim 1, is characterized in that: between Grouting Pipe, by iron plate, be fixed, between iron plate and slip casting sleeve pipe, adopt air bag to seal.
3. a kind of earth and rockfill dam grouting and reinforcing anti-shock methods according to claim 1, is characterized in that: the injected hole degree of depth is determined according to the height of dam embankment in Practical Project, is the integral multiple of every layer of filled height.
4. a kind of earth and rockfill dam grouting and reinforcing anti-shock methods according to claim 1, is characterized in that: injected hole is vertical drilling, or inclination or horizontal drilling.
CN201210006730.3A 2012-01-11 2012-01-11 Grouting reinforcement and earthquake resisting method for earth and rockfill dam Active CN102605750B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210006730.3A CN102605750B (en) 2012-01-11 2012-01-11 Grouting reinforcement and earthquake resisting method for earth and rockfill dam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210006730.3A CN102605750B (en) 2012-01-11 2012-01-11 Grouting reinforcement and earthquake resisting method for earth and rockfill dam

Publications (2)

Publication Number Publication Date
CN102605750A CN102605750A (en) 2012-07-25
CN102605750B true CN102605750B (en) 2014-11-19

Family

ID=46523484

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210006730.3A Active CN102605750B (en) 2012-01-11 2012-01-11 Grouting reinforcement and earthquake resisting method for earth and rockfill dam

Country Status (1)

Country Link
CN (1) CN102605750B (en)

Families Citing this family (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104131535B (en) * 2014-07-07 2015-09-23 河海大学 A kind of composite reinforced earth and rockfill dam earthquake resistant structure of high polymer and construction method thereof
CN104452676B (en) * 2014-11-11 2017-01-25 河海大学 High-polymer composite reinforcing anti-seismic high earth and rockfill dam and construction method thereof
CN106192910A (en) * 2016-08-29 2016-12-07 长江勘测规划设计研究有限责任公司 A kind of earth and rockfill dam layer of sand earthquake liquefaction ballast ruggedized construction and method under water
CN106544986B (en) * 2016-10-18 2018-12-18 重庆大学 The reinforcement means of the high polymer grouting of coral skerries airport shore protection, flexible shore protection
CN106638485B (en) * 2016-12-29 2019-06-25 重庆大学 One kind mixing rubber antidetonation earth and rockfill dam and its design and construction method
CN107059800A (en) * 2017-05-02 2017-08-18 中国电建集团贵阳勘测设计研究院有限公司 A kind of improved method of core wall dam anti-seismic structure and reinforcement chain net used
CN107246000A (en) * 2017-06-30 2017-10-13 山东科技大学 A kind of method that high polymer reinforces reclaimed ground
CN109295943B (en) * 2018-09-27 2021-04-13 湖北宜化江家墩矿业有限公司 Grouting pipe for waste slag yard and grouting using method
CN110258456A (en) * 2019-07-22 2019-09-20 杨树东 A kind of dam body and its seamless Waterproof Construction Technique of contrary sequence method
CN112903964A (en) * 2021-01-20 2021-06-04 长江水利委员会长江科学院 Side pressure test embedded sleeve hole forming method and equipment suitable for rockfill layer-by-layer filling

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3690106A (en) * 1970-02-24 1972-09-12 Dow Chemical Co Method of treating permeable formations
SU437824A1 (en) * 1972-02-21 1974-07-30 Всесоюзный Научно-Исследовательский Институт Гидротехники Им. Б.Е.Веденеева Stone-land on the dam
SU804759A1 (en) * 1979-08-15 1981-02-15 Научно-Исследовательский Секторвсесоюзного Ордена Ленина Проектно- Изыскательского И Научно-Исследова-Тельского Института "Гидропроект"Им.C.Я.Жука Dam made of locally available materials
SU1693180A1 (en) * 1989-10-12 1991-11-23 Ленинградское отделение Всесоюзного проектно-изыскательского и научно-исследовательского института "Гидропроект" им.С.Я.Жука Earth dam
JP2003020625A (en) * 2001-07-11 2003-01-24 National Institute For Rural Engineering Method for reinforcing soil structure bank body
JP3619312B2 (en) * 1996-02-19 2005-02-09 株式会社間組 Seismic isolation structure of fill dam body
JP2007239209A (en) * 2006-03-06 2007-09-20 National Agriculture & Food Research Organization Construction method of soil water storage structure
CN102051868A (en) * 2009-11-02 2011-05-11 郑州优特基础工程维修有限公司 Dam anti-seepage high polymer directional split grouting method
CN102261053A (en) * 2011-05-12 2011-11-30 河海大学 Aseismatic measure of high earth-rock dam and construction method thereof

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3690106A (en) * 1970-02-24 1972-09-12 Dow Chemical Co Method of treating permeable formations
SU437824A1 (en) * 1972-02-21 1974-07-30 Всесоюзный Научно-Исследовательский Институт Гидротехники Им. Б.Е.Веденеева Stone-land on the dam
SU804759A1 (en) * 1979-08-15 1981-02-15 Научно-Исследовательский Секторвсесоюзного Ордена Ленина Проектно- Изыскательского И Научно-Исследова-Тельского Института "Гидропроект"Им.C.Я.Жука Dam made of locally available materials
SU1693180A1 (en) * 1989-10-12 1991-11-23 Ленинградское отделение Всесоюзного проектно-изыскательского и научно-исследовательского института "Гидропроект" им.С.Я.Жука Earth dam
JP3619312B2 (en) * 1996-02-19 2005-02-09 株式会社間組 Seismic isolation structure of fill dam body
JP2003020625A (en) * 2001-07-11 2003-01-24 National Institute For Rural Engineering Method for reinforcing soil structure bank body
JP2007239209A (en) * 2006-03-06 2007-09-20 National Agriculture & Food Research Organization Construction method of soil water storage structure
CN102051868A (en) * 2009-11-02 2011-05-11 郑州优特基础工程维修有限公司 Dam anti-seepage high polymer directional split grouting method
CN102261053A (en) * 2011-05-12 2011-11-30 河海大学 Aseismatic measure of high earth-rock dam and construction method thereof

Non-Patent Citations (8)

* Cited by examiner, † Cited by third party
Title
土石坝灌浆技术的理论研究与应用;罗微;《中国优秀硕士学位论文全文数据库》;20090912;第1-14页 *
土石坝震害与抗震安全;朱晟;《水力发电学报》;20111231(第6期);第40-51页 *
朱晟.土石坝震害与抗震安全.《水力发电学报》.2011,(第6期),第40-51页. *
杨星等.高土石坝震害与抗震措施评述.《防灾减灾工程学报》.2009, *
罗微.土石坝灌浆技术的理论研究与应用.《中国优秀硕士学位论文全文数据库》.2009, *
胡军.高土石坝动力稳定分析及加固措施研究.《中国博士学位论文全文数据库》.2008, *
高土石坝动力稳定分析及加固措施研究;胡军;《中国博士学位论文全文数据库》;20080709;第1-8页 *
高土石坝震害与抗震措施评述;杨星等;《防灾减灾工程学报》;20091031;第583-590页 *

Also Published As

Publication number Publication date
CN102605750A (en) 2012-07-25

Similar Documents

Publication Publication Date Title
CN102605750B (en) Grouting reinforcement and earthquake resisting method for earth and rockfill dam
CN108193606B (en) A kind of means of defence of local scour near pier
CN107859145A (en) A kind of drainpipe is plugged into construction method under water
CN113186903A (en) Combined pile structure and construction method for treating insufficient bearing capacity of deep foundation pit construction pile by adopting combined pile structure
CN112227401A (en) Method for constructing bearing platform by filling stones in underwater stone abrupt slope area
CN103572764A (en) Watertight structure for retaining wall of ultra-deep manually excavated pile and construction method thereof
CN111472326A (en) Method and structure for building gravity dam on deep covering layer
Fu et al. Practices in constructing high rockfill dams on thick overburden layers
CN109610473A (en) A kind of construction method of the large-scale pool structure foundation pit supporting system of municipal administration
CN203729309U (en) Support system with combined double-row piles combined with vertical prestressed anchor bolts
CN210856971U (en) Pile foundation erodees reinforced structure
CN113123358B (en) Ship pool deformation prevention and control structure under action of uneven settlement of coal mining and construction method
CN210636421U (en) Underwater hollowing defect repairing device for navigation wall pile foundation of ship lock on gravel layer foundation
CN114542092A (en) Shield receiving construction method without bottom plate structure
CN210013191U (en) Connecting structure of dam abutment impact drilling groove thin impervious wall and grouted stone dam body
CN208309626U (en) A kind of floating tubular pole and its dykes and dams soil-baffling structure
CN112709252A (en) Bearing platform construction method in semi-water flooding steep rock slope
Zhang et al. Construction applicability of mechanical methods for connecting aisle in the bohai mudstone stratum with high water pressure
CN217538715U (en) A high-order sluicing hole structure for filling drainage of sand bed karst cave that can run off
CN218148482U (en) Simple foundation pile structure, system thereof and trestle
CN211200350U (en) Grouting reinforcement control system suitable for gully terrain
CN215926026U (en) Caisson type tunnel end cofferdam
CN215715469U (en) Karst area earth and rockfill dam foundation processing structure
CN214272175U (en) Grouting reinforcement structure suitable for underground cavity of building
CN114837455B (en) Method for reconstructing sunken hydraulic building

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant