Summary of the invention
The technical problem that the present invention will solve provides the pile body that a kind of construction cost is low, construction quality is high; The present invention also will provide a kind of foundation structure of this pile body of application.
In order to solve the problems of the technologies described above, a kind of octagonal pile of the present invention comprises pile body, and the cross section of said pile body is an octagon, is provided with stiffener in the pile body, and the length direction of this stiffener is consistent with pile body, is filled with pea gravel concreten between the stiffener.
As the improvement of technique scheme, said stiffener is 3 to 5, is distributed in pile body inside ringwise.
As the improvement of technique scheme, an end of said pile body is a cone point, and the other end is the plane butt end, is reduced gradually by the cross section of plane butt end to cone point.
Said stiffener is the 70# high tensile reinforcement, and said pea gravel concreten is the C25 pea gravel concreten.
A kind of foundation structure comprises concrete cushion, and said concrete cushion is connected fixing with octagonal pile body upper end, has the cushion cap that covers pile body on the concrete cushion.
Said concrete cushion edge exceeds the cushion cap edge, forms stepped.
Said stiffener is 3 to 5, is distributed in pile body inside ringwise.
One end of said pile body is a cone point, and the other end is the plane butt end, is reduced gradually by the cross section of plane butt end to cone point, and the plane butt end of said pile body is connected fixing with concrete cushion.
The invention has the beneficial effects as follows: octagonal pile than economical with materials more such as the stake of tradition side, pile tube, timber, is beneficial to the reduction construction cost in the application of pile foundation.In the application that ground is handled, also more guaranteed than pile qualities such as deep-mixed pile, castinplace piles, construct more flexibly and fast, greatly the reduction of erection time.The construction of octagonal pile is simple, adopts paddle type mill piling.Pile driving equipment is by pile monkey, pile driving frame and ancillary service formations such as (beating with replacing such as pile cover, cushion pad, pile follower).Pile driving equipment is low weight, has only about 1 ton 20,000 yuan of its cost less thaies.Pile driving frame is high 7 meters, and iron hammer weighs 300 kilograms, optional 1~3 meter of stroke.Convenient transportation, piling machinery only need 1.5 meters wide roads just can arrive, and it is obviously much lower than other machines to site requirements.
The specific embodiment
With reference to Fig. 1.A kind of octagonal pile of the present invention comprises pile body 1, and the cross section of said pile body 1 is an octagon, is provided with stiffener 2 in the pile body 1, and the length direction of this stiffener 2 is consistent with pile body, is filled with pea gravel concreten 3 between the stiffener 2.Said stiffener 2 is 3 to 5, is distributed in pile body 1 inside ringwise, is guaranteeing that pile body has under the prerequisite of sufficient intensity, the control cost of production.
In the present embodiment, an end of said pile body 1 is a cone point, and the other end is the plane butt end, is reduced gradually by the cross section of plane butt end to cone point, and pile body is driven underground more easily, can adopt small-sized pile driver construction.Said pile body 1 adopts 70# high tensile reinforcement and the pouring of C25 pea gravel concreten to form, and has higher structural strength.Manufacturing process is simple, and it is made and adopts homemade combined steel, present most octagonal pile production is that manual pouring is made.According to sectional dimension, pile body 1 mainly contains 4 kinds of specifications, is respectively 3 meters, 140 millimeters in tail footpath; 4 meters, 155 millimeters in tail footpath; 5 meters, 165 millimeters in tail footpath; 6 meters, 170 millimeters in tail footpath.
Pile body 1 length can be had made to order, and general 3~6 meters, can pile follower 1 meter, so can reach 7 meters with its Ground Treatment degree of depth.The production of this type still has no technical regulation, estimates its pile body axial compressive strength, A
pf
cφ
c=213.7kN, tension, compressive strength are obviously superior than timber.Octagonal pile is mainly used in the middle of the building foundation engineering of enclosure wall, the small-sized capital construction of individual layer, pond, various electromechanical equipments or the like; At these building engineering fields; Octagonal pile is compared with traditional side's stake, pile tube, timber, at aspects such as cost, constructions remarkable advantages is arranged all.
Octagonal pile of the present invention, side's stake of its performance and cross section 200x200 millimeter is comparatively approaching.Side's stake is following with the octagonal pile main technical requirements:
The stake of table 1 side is compared with the octagonal pile main technical requirements
A kind of foundation structure comprises concrete cushion 4, and said concrete cushion 4 is connected fixing with octagonal pile body 1 upper end; Have the cushion cap 5 that covers pile body 1 on the concrete cushion 4, said concrete cushion 4 edges exceed cushion cap 5 edges, form stepped; Said stiffener 2 is 3 to 5; Be distributed in pile body 1 inside ringwise, an end of said pile body 1 is a cone point, and the other end is the plane butt end; Cross section by plane butt end to cone point reduces gradually, and the plane butt end of said pile body 1 is connected fixing with concrete cushion 4.
Below provide some specific embodiments as aid illustration.
Embodiment 1:
Be positioned at Yunfu City transformer station, 180 millimeters thick enclosure walls and 59 equipment of 292 meters of length are arranged in the power station.Wherein the weight of equipment is 0.7 ton and does not wait to 1.0 tons; Make footing beam under the brick enclosure wall of 180 millimeters thick, per 5 meters pillars, totally 60.Because the face of land is not waited for 1 to 3 meter and is backfill, it is infeasible directly to do the direct foundation, need do the ground processing.And, one side the power station close on a fish pond, a stake machine can not get into.In this case, it is lower that we have expected that the job site requires, and job practices is octagonal pile more flexibly.
We have also contrasted two kinds of foundation treatment modes quality economically simultaneously:
1. 250x250 precast concrete square pile: only make friction pile and consider, 1 of the following needs of every enclosing wall column, but the requirement of consideration bending resistance square, the result wants two; Do one under every Equipment Foundations, by every 870 yuan of calculations, meter stake machine admission fee 60000 yuan (place is remote) adds up to 215730 yuan of investments in addition.
2. octagonal pile: only make friction pile and consider that cloth is two under every enclosing wall column, does two under every Equipment Foundations, long 5 meters of root, 1 meter of pile follower by every 50 yuan of calculations, adds up to 11900 yuan of investments.
Be because the restriction of job site is the consideration from economic factor on the one hand, and we confirm to select for use octagonal pile at last on the one hand, this power station enclosure wall, Equipment Foundations are accomplished has had nearly six months so far, and mode of occupation is good.
Embodiment 2:
An interim agitator that is positioned at moral famous scenic spot, Shuande district requires to do ground and handles, and this area's geological condition is relatively poor, and the top layer weak soil covers thicker.In application for developing, we make following assessment:
Handle if do the castinplace pile that dusts, by every square metre of distribution, need 100, every long 6 meters, considers by the cost of 50 yuan every meter of the stakes of dusting, and needs 30000 yuan of investments; As use octagonal pile instead, according to every square metre of 4 distributions, stake is long to be similarly 6 meters, considers by every 55 yuan costs, needs 22000 yuan of investments.It is thus clear that it is under the situation that effectiveness equates, select octagonal pile to reduce investment outlay relatively, and reliable.In the piling process, know the effect that ground is handled immediately, can on-the-spot quantity and the length that increases or reduce stake, also needn't as other, do detection.
Embodiment 3:
Be positioned at one small electrical room, Shuande, need make ground and handle, compare two feasible programs below:
As select for use the direct foundation to press down timber, and need 60 of 5 meters long φ 120 pine stakes, by every 70 yuan of calculating of 5 meters timbers, purchasing stake needs 4200 yuan; As use octagonal pile instead, by every 50 yuan of calculating of 5 meters long octagonal piles, purchasing stake needs 3000 yuan.It is thus clear that only the investment aspect stake has just economized 29%.Moreover this area termite is serious to the erosion of timber, and timber can not be ignored by other factor corrosion phenomenons; By contrast; The pile quality of octagonal pile uses much more stable than timber, and intensity is much bigger, and the use of saving timber also is the environmental protection of advocating now.
The above is merely preferential embodiment of the present invention, as long as realize that with basic identical means the technical scheme of the object of the invention all belongs within protection scope of the present invention.