CN102556282A - Building process for ship central control room - Google Patents

Building process for ship central control room Download PDF

Info

Publication number
CN102556282A
CN102556282A CN2012100139585A CN201210013958A CN102556282A CN 102556282 A CN102556282 A CN 102556282A CN 2012100139585 A CN2012100139585 A CN 2012100139585A CN 201210013958 A CN201210013958 A CN 201210013958A CN 102556282 A CN102556282 A CN 102556282A
Authority
CN
China
Prior art keywords
central station
floating dock
mounting
central control
completion
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2012100139585A
Other languages
Chinese (zh)
Other versions
CN102556282B (en
Inventor
洪和平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Cssc Offshore & Marine Engineering Group Co ltd
Guangzhou Shipyard International Co Ltd
Original Assignee
Guangzhou Shipyard International Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangzhou Shipyard International Co Ltd filed Critical Guangzhou Shipyard International Co Ltd
Priority to CN201210013958.5A priority Critical patent/CN102556282B/en
Publication of CN102556282A publication Critical patent/CN102556282A/en
Application granted granted Critical
Publication of CN102556282B publication Critical patent/CN102556282B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Building Environments (AREA)

Abstract

The invention discloses a building process for a ship central control room. The building process comprises the following steps of: respectively building a ground structure and a roof structure of the central control room; mounting and welding fittings on the ground structure and the roof structure of the central control room; mounting floor type large equipment on the ground structure, mounting the ground structure and the roof structure and welding the ground structure and the roof structure into a whole cabin; finishing hot work, such as complementary welding, for all the fittings of the connecting parts of wall surfaces; polishing and coating all the outer surfaces in the central control room; and finishing all mounting works of electric mounting, mechanical mounting and room mounting of the central control room. According to the building process for the ship central control room, all the fitting project (electric mounting, mechanical mounting and room mounting) mounting works of the central control room are finished before the central control room structure is mounted on a ship and an engine cabin is formed, so the workload after the central control room is mounted on the ship is greatly reduced, the whole period for building a dock (a ship platform) is shortened, and the ship building efficiency and the lean ship building capability of a shipyard are improved.

Description

A kind of build process of boats and ships central station of floating dock
Technical field
The present invention relates to marine technology, particularly a kind of modularization build process of boats and ships central station of floating dock.
Background technology
Central station of floating dock is electrical installation amount maximum in the watercraft engine room build area, relates to the independent cabin that work post is many, operation is many, cross-operation is many, flow process is the most loaded down with trivial details and complicated, construction period is the longest; Its overall progress to moulding of stern island and shipbuilding has fundamental influence.Usually the fitting-out operation of central station of floating dock is all treated just to carry out after the moulding aboard ship of central station of floating dock structure; Because of many unfavorable factors such as its integraty cycle of operations are long, receive that cross-operation influences; Cause its construction operation time in dock (building berth) long; The whole ship of influence takies dock (building berth) cycle, delays the shipbuilding progress, has restricted the shipbuilding capacity of shipyard.
If let central station of floating dock moulding on ground; Simultaneously can be with the fitting-out operation reach of central station of floating dock; Improve central station of floating dock in surface-mounted completion rate; Create enough room and time conditions for the block outfitting operation, and then also reduce the harm to the large electric equipment of costliness such as construction dust, spraying, central station of floating dock integral body only need be accomplished the work flow that must after central station of floating dock is gone on board, can carry out after going on board and carrying.That state that will help central station of floating dock is reached for each function system of full ship as early as possible the condition of launching debugging is provided, and can shorten the cycle that dock (building berth) shipyard takies, and accelerates the ship building progress, improves shipyard equilibrium, shipbuilding usefulness efficiently.
Summary of the invention
The present invention is intended to provide a kind of build process of boats and ships central station of floating dock, to improve the surface-mounted completion rate of central station of floating dock, accelerates the progress of ship building at dock (building berth), in the shortening cycle, improves the shipyard shipbuilding capacity.
The build process of boats and ships central station of floating dock of the present invention comprises the steps:
The construction of A, completion central station of floating dock earth construction;
The location and the welding of the fittings under B, the completion central station of floating dock earth construction;
C, terrestrial segment application;
D, the lifting of accomplishing the mounting of main equipment on the earth construction, location and welding;
Cable penetration fittings in E, the installation main equipment mounting;
F, with main equipment mounting polishing and paint;
G, on earth construction, accomplish in main equipments such as central control desk, main switchboard, air conditioner and the central station of floating dock other and land the installation and the protection thereof of equipment;
The construction of H, completion central station of floating dock top structure;
I, accomplish the location and the welding of the fittings of central station of floating dock top structure on ground;
J, top segmentation application;
K, central station of floating dock moulding are promptly carried top structure and earth construction on ground, are welded as whole cabin;
Benefit dress, location and the welding of near the electric connecting element L, installation top structure and the bottom construction joint and other fittingss;
The welding of the dress weldment of L1, completion central station of floating dock outside wall surface;
The connection of airduct is installed in M, the completion central station of floating dock;
The dress weldering of the annex that insulation dressing in N, the completion central station of floating dock, carpentery workshop plate are installed and used;
The installation and the welding of O, completion fireproof door frame, soundproof window;
P, collect control The chamberInside and outside wall fire operation integrity checking;
All surface in Q, the polishing central station of floating dock, and application are promptly accomplished the whole application in the central station of floating dock;
Drawing of R, the inner local cable of central station of floating dock is deposited;
Installation, local cable wiring that S, completion wall and top installing are equipped with;
T, local cable connect sealing, and carry out the protection of valuable equipment;
U, the local cable of central station of floating dock wayside equipment is carried out wiring;
The installation on V, the dressing of completion central station of floating dock, wallboard and floor; And the central station of floating dock fire protection gate is installed;
W, the central station of floating dock integral hoisting lift-launch of going on board;
X, indoor and outdoor pipeline connection also carry out tightness test;
The cable of Y, entering central station of floating dock draws and applies and wiring;
Z, furniture are marched into the arena;
In the said step, steps A-G and step H-J are parallel to carry out; The flow process that step L, step L1, step M and step N-O form is parallel carries out; The flow process that step V and step R-T form is parallel carries out; The flow process that step U and step S, T form is parallel carries out; Step X, step Y and step Z are parallel to carry out, and all the other steps are successively carried out in order.
The build process of boats and ships central station of floating dock of the present invention; Denso in building through reasonable establishment central station of floating dock, each item flow process that occupies various operations such as dress, machine dress, application, step, in proper order; The most of operations that to originally in dock (building berth), carry out in an orderly manner according to shunting, space, time; Be advanced in the ground manufacture process of central station of floating dock; And cross-operation in good time in construction realizes " shell, Xi, be coated with " institutional operation flow process, thereby can significantly improve the completion rate that build on central station of floating dock ground.Said central station of floating dock build process; Each fitting-out specialty in the central station of floating dock (Denso, occupy dress, machine dress) operation all the central station of floating dock handling carry to the ship be shaped before major part carry out; Realized that central station of floating dock single-piece modularization builds, the surface-mounted percentage of head rice of central station of floating dock greatly improves, and has significantly reduced the working out after the central station of floating dock moulding aboard ship; Thereby can effectively shorten the cycle that ship building takies dock (building berth), improve the shipbuilding capacity of shipbuilding efficiency and shipyard.In addition, in the central station of floating dock build process of the present invention, being welded on of the fittings on the central station of floating dock top structure carried out before itself and earth construction carry, and it can be accomplished on the ground, reduces labour intensity, and welding operation is very convenient, and quality guarantees easily.And; Operation that it can accomplish Densos whole on earth construction, top structure and the wall on the ground, machine is adorned and fittings of residence dress freezes; After all welding finishes; Carry out the application on central station of floating dock surface again, carry out welding operation after it can avoid central station of floating dock to be shaped aboard ship again, that avoids influencing each other and cause does over again.
Central station of floating dock method of construction of the present invention, a large amount of Densos, the reach that occupies dress and machine dress operation have improved operator's working environment, help on-the-spot productive temp arrangement and labour power tissue, be convenient to various operations and intersect in an orderly manner, walk abreast and carry out.The significantly raising of the electric installation in ground alleviates Denso work capacity aboard ship, and after the complete cross section handling of central station of floating dock place was gone on board, cable got final product wiring on the deposited ship as long as draw; It occupies the raising that dress is installed percentage of head rice, makes operating environment improve greatly, accomplish furniture march into the arena in place after, installation procedure is all over, and is follow-up energising debugging work and has created advantage.Said method of construction lets in a large number erection work in dock (building berth) stage advance on the ground and does, and for the amount that goes up fast of producing creates conditions, can guarantee to reach the optimization in efficient and cycle.Calculate the installation exercise amount through real boat measurement, its Denso percentage of head rice can reach more than 80%, and occupying the dress percentage of head rice can reach more than 85%.In addition, said method has also been improved the operating environment of coating decoration, has reduced potential potential safety hazard, has improved production efficiency, meet airtight bin will be as far as possible construction when opening wide, the aloft work needs of constructing will be as far as possible on ground the time; Avoided mutual interference mutually between application and the work post that other work post cross-operation are brought, the safety factor of coating decoration can increase, and in particular for later stage cabin work fine platform is provided.
Description of drawings
Fig. 1 is the diagram of circuit of boats and ships central station of floating dock build process according to the invention.
The specific embodiment
Fig. 1, a kind of build process of boats and ships central station of floating dock is accomplished the construction at central station of floating dock earth construction and top at first respectively.Then, earth construction is accomplished following operation successively: to the earth construction below is master's fittings location and welding with electric connecting element; The application of terrestrial segment; On the central station of floating dock earth construction, accomplish lifting, location and the welding of main equipment mounting; In the main equipment mounting, cable penetration fittings is installed; And with polishing of main equipment mounting and paint; On earth construction, accomplish in main equipments such as central control desk, main switchboard, air conditioner and the central station of floating dock other and land the installation of equipment; And adopting protective device to protect, said protective device can be triple protective devices from inside to outside that glued membrane, protective cloth cover and sheet material guard box constitute.Accomplish following operation on ground successively in the face of the central station of floating dock top structure: the lifting of the fittings of central station of floating dock top structure, location and welding, application is carried out in the top segmentation.After accomplishing the corresponding operating of earth construction and top structure respectively, top structure and earth construction are carried, be welded as whole cabin, make the central station of floating dock moulding.The benefit dress weldering of near the electric connecting element of top structure and bottom construction joint and other fittingss is installed afterwards; Accomplishing the connection of airduct in the central station of floating dock installs; The dress weldering of the annex that insulation dressing and carpentery workshop plate are installed and used in the completion central station of floating dock; Accomplish the installation and the welding of fireproof door frame, soundproof window etc.; Accomplish the central station of floating dock outside wall surface corresponding to the freeze welding of part of the fitting-out in other cabin; After (comprising on the outer wall) all fire operations of confirming central station of floating dock are complete, again all surface in the central station of floating dock is polished and whole application; Afterwards, it is deposited to carry out drawing of the inner local cable of central station of floating dock; Wall and top installing are installed fully, and carry out the local cable wiring; Carry out the installation on central station of floating dock dressing, wallboard and floor simultaneously, and the central station of floating dock fire protection gate is installed; Then, the central station of floating dock integral hoisting is gone on board; Draw thereupon and apply the wireline operation that gets into central station of floating dock and do the equipment wiring; While indoor and outdoor pipeline connection and tightness test; Last furniture is marched into the arena in place, thereby accomplishes the construction of whole central station of floating dock.

Claims (1)

1. the build process of a boats and ships central station of floating dock is characterized in that: comprise the steps:
The construction of A, completion central station of floating dock earth construction;
The location and the welding of the fittings under B, the completion central station of floating dock earth construction;
C, terrestrial segment application;
D, the lifting of accomplishing the mounting of main equipment on the earth construction, location and welding;
Cable penetration fittings in E, the installation main equipment mounting;
F, with main equipment mounting polishing and paint;
G, on earth construction, accomplish in main equipments such as central control desk, main switchboard, air conditioner and the central station of floating dock other and land the installation and the protection thereof of equipment;
The construction of H, completion central station of floating dock top structure;
I, accomplish the location and the welding of the fittings of central station of floating dock top structure on ground;
J, top segmentation application;
K, central station of floating dock moulding are promptly carried top structure and earth construction on ground, are welded as whole cabin;
Benefit dress, location and the welding of near the electric connecting element L, installation top structure and the bottom construction joint and other fittingss;
The welding of the dress weldment of L1, completion central station of floating dock outside wall surface;
The connection of airduct is installed in M, the completion central station of floating dock;
The dress weldering of the annex that insulation dressing in N, the completion central station of floating dock, carpentery workshop plate are installed and used;
The installation and the welding of O, completion fireproof door frame, soundproof window;
P, collect control The chamberInside and outside wall fire operation integrity checking;
All surface in Q, the polishing central station of floating dock, and application are promptly accomplished the whole application in the central station of floating dock;
Drawing of R, the inner local cable of central station of floating dock is deposited;
Installation, local cable wiring that S, completion wall and top installing are equipped with;
T, local cable connect sealing, and carry out the protection of valuable equipment;
U, the local cable of central station of floating dock wayside equipment is carried out wiring;
The installation on V, the dressing of completion central station of floating dock, wallboard and floor; And the central station of floating dock fire protection gate is installed;
W, the central station of floating dock integral hoisting lift-launch of going on board;
X, indoor and outdoor pipeline connection also carry out tightness test;
The cable of Y, entering central station of floating dock draws and applies and wiring;
Z, furniture are marched into the arena;
In the said step, steps A-G and step H-J are parallel to carry out; The flow process that step L, step L1, step M and step N-O form is parallel carries out; The flow process that step V and step R-T form is parallel carries out; The flow process that step U and step S, T form is parallel carries out; Step X, step Y and step Z are parallel to carry out, and all the other steps are successively carried out in order.
CN201210013958.5A 2012-01-17 2012-01-17 Building process for ship central control room Active CN102556282B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210013958.5A CN102556282B (en) 2012-01-17 2012-01-17 Building process for ship central control room

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210013958.5A CN102556282B (en) 2012-01-17 2012-01-17 Building process for ship central control room

Publications (2)

Publication Number Publication Date
CN102556282A true CN102556282A (en) 2012-07-11
CN102556282B CN102556282B (en) 2014-08-13

Family

ID=46403247

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210013958.5A Active CN102556282B (en) 2012-01-17 2012-01-17 Building process for ship central control room

Country Status (1)

Country Link
CN (1) CN102556282B (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107351979A (en) * 2017-07-10 2017-11-17 上海外高桥造船有限公司 The modular construction method of central station of floating dock
CN113184130A (en) * 2021-04-27 2021-07-30 中船澄西船舶修造有限公司 Assembling method for ship corollary equipment unit module
CN113562137A (en) * 2021-08-11 2021-10-29 上海外高桥造船有限公司 Modularized construction method between FGSS, FGSS and ship
CN113753176A (en) * 2021-09-29 2021-12-07 上海外高桥造船有限公司 Method for arranging FGSSROM units of dual-fuel ship

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH04166492A (en) * 1990-10-30 1992-06-12 Ishikawajima Harima Heavy Ind Co Ltd Equipment fitting method for module frame
CN101032995A (en) * 2007-04-06 2007-09-12 上海外高桥造船有限公司 Method of installing ship bilge equipment
CN101554919A (en) * 2009-05-08 2009-10-14 中远船务工程集团有限公司 Maritime platform mobile deck crane uninterrupted rollout bracket
CN101570234A (en) * 2008-04-29 2009-11-04 江南造船(集团)有限责任公司 Method for assembling and lifting engine room section

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH04166492A (en) * 1990-10-30 1992-06-12 Ishikawajima Harima Heavy Ind Co Ltd Equipment fitting method for module frame
CN101032995A (en) * 2007-04-06 2007-09-12 上海外高桥造船有限公司 Method of installing ship bilge equipment
CN101570234A (en) * 2008-04-29 2009-11-04 江南造船(集团)有限责任公司 Method for assembling and lifting engine room section
CN101554919A (en) * 2009-05-08 2009-10-14 中远船务工程集团有限公司 Maritime platform mobile deck crane uninterrupted rollout bracket

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
潘小寰: "船舶机舱集控室整体建造工艺技术研究", 《2011中国造船工程学会造船工艺学术委员会造船企业精益生产学术研讨会论文集》, 1 June 2011 (2011-06-01) *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107351979A (en) * 2017-07-10 2017-11-17 上海外高桥造船有限公司 The modular construction method of central station of floating dock
CN113184130A (en) * 2021-04-27 2021-07-30 中船澄西船舶修造有限公司 Assembling method for ship corollary equipment unit module
CN113562137A (en) * 2021-08-11 2021-10-29 上海外高桥造船有限公司 Modularized construction method between FGSS, FGSS and ship
CN113753176A (en) * 2021-09-29 2021-12-07 上海外高桥造船有限公司 Method for arranging FGSSROM units of dual-fuel ship

Also Published As

Publication number Publication date
CN102556282B (en) 2014-08-13

Similar Documents

Publication Publication Date Title
CN102556282B (en) Building process for ship central control room
EP3587265B1 (en) Air-transportable device for projecting pressurised liquid
RU2418722C2 (en) Method of producing aircraft fuselage compartment
CN103204225B (en) The sectional construction stage installation method of watercraft engine room discrepancy auxiliary hole
CN103661802B (en) The installation exercise method of fittings
CN102837801A (en) Construction method of ship central control room module
CN102582784A (en) Process for sectionally putting up ship berths or docks
CN105416508A (en) Method for increasing outfitting pre-installation ratio
CN107351979A (en) The modular construction method of central station of floating dock
CN105015399A (en) Integrated rescue equipment vehicle
CN103963922A (en) Installation method for stern deck mooring equipment
CN103306414A (en) Unit assembled type concealed ceiling grid system and construction method thereof
CN105711738B (en) The installation method of the anti-rolling bearing insulation in A type independent liquid cargo tank top surfaces both ends
CN113562137A (en) Modularized construction method between FGSS, FGSS and ship
US2368441A (en) Method of prefabricating ships
KR101312586B1 (en) Fitting unit of sprinkler for no-gap ceiling of a block part for a ship
CN203715209U (en) Ship body section-by-section lifting welding device
US20170203441A1 (en) System and method of performing operations on artifacts with stowable robotic pads
CN103126817A (en) Severe illness treating square cabin for integrated tower crane
CN210454590U (en) Corrosion treatment emergency shelter
CN217259773U (en) Shelter vehicle set for rush repair
CN105882889A (en) Ship paint saving technology
CN110528724A (en) A kind of pipeline separates the building of waterproof and insulation integrated wall and its composition
CN212022819U (en) Spoiler foam block with anti-mildew function
CN109158233A (en) A kind of large surface spraying flexible cable robot

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C41 Transfer of patent application or patent right or utility model
C56 Change in the name or address of the patentee
CP01 Change in the name or title of a patent holder

Address after: 510382 Guangzhou, Guangdong Province, south of Fangcun Avenue, No. 40

Patentee after: CSSC OFFSHORE & MARINE ENGINEERING (Group) Co.,Ltd.

Address before: 510382 Guangzhou, Guangdong Province, south of Fangcun Avenue, No. 40

Patentee before: GUANGZHOU SHIPYARD INTERNATIONAL Co.,Ltd.

TR01 Transfer of patent right

Effective date of registration: 20160224

Address after: 511462 Nansha District, Guangzhou, Pearl River Management District, West Road, No., the first floor of the layer on the ground floor, No. 68

Patentee after: Guangzhou Shipyard International Co.,Ltd.

Address before: 510382 Guangzhou, Guangdong Province, south of Fangcun Avenue, No. 40

Patentee before: CSSC OFFSHORE & MARINE ENGINEERING (Group) Co.,Ltd.