CN103661802B - The installation exercise method of fittings - Google Patents
The installation exercise method of fittings Download PDFInfo
- Publication number
- CN103661802B CN103661802B CN201310644625.7A CN201310644625A CN103661802B CN 103661802 B CN103661802 B CN 103661802B CN 201310644625 A CN201310644625 A CN 201310644625A CN 103661802 B CN103661802 B CN 103661802B
- Authority
- CN
- China
- Prior art keywords
- installation phase
- segmentation
- fittings
- installation
- stage
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Pipeline Systems (AREA)
Abstract
The invention discloses a kind of installation exercise method of fittings, it comprises the in-built part of ship and the in-built part of non-ship; The in-built part of ship comprises always organizes installation phase, region installation phase, system installation phase; After total group of installation phase refers to that more than two or two segmentations carry out total group, carry out fitting-out installation phase, this stage mainly installs the counter gathering pipe that fills of some segmentations and is in two fittingss closed up between segmentation; The in-built part of non-ship comprises the vertical installation phase of group, segmentation installation phase, unit assembling stage; The vertical installation phase consideration of group cannot put into some pipe fittings, the fittings that segmentation is installed after division system is finished; Segmentation installation phase is also known as segmentation pre outfitting; The unit assembling stage belongs to the category of pre outfitting, according to the feature of engine room arrangement, whole area of aircraft cabins is divided into several unit, installs in a fixing place.The present invention is divided into each stage, increases work efficiency, and shortens the installation period of fittings.
Description
Technical field
The present invention relates to a kind of operational method, particularly relate to a kind of installation exercise method of fittings.
Background technology
Ship ' s equipment refers to that hull keystone configuration has been made, machinery after ship launching, electrically, the installation of electronic machine.The fittings of boats and ships is exactly the thing on all ships except hull and marine powerplant.The installation exercise method of existing fittings adopts independent components and parts to install, and inefficiency, the installation period of fittings is long.
Summary of the invention
Technical matters to be solved by this invention is to provide a kind of installation exercise method of fittings, and it is divided into each stage, increases work efficiency, and shortens the installation period of fittings.
The present invention solves above-mentioned technical matters by following technical proposals: a kind of installation exercise method of fittings, is characterized in that, it comprises the in-built part of ship and the in-built part of non-ship;
The in-built part of ship comprises always organizes installation phase, region installation phase, system installation phase; After total group of installation phase refers to that more than two or two segmentations carry out total group, carry out fitting-out installation phase, this stage mainly installs the counter gathering pipe that fills of some segmentations and is in two fittingss closed up between segmentation, if simultaneously when crane capacity allows, segmentation front equipment base and some midget plants, all can be divided into the installation of this stage; Region installation phase mainly installs some main equipments, complete cross section carry between gathering pipe, the equipment adapter of land regions, inclined ladder between upper lower platform, main exhaust pipe and some do not carry out the pipeline of modeling; System installation phase refers in pipeline installation process produces closure workmanship process features according to pipeline system material characteristic and segmentation, the special a kind of installation phase divided out;
The in-built part of non-ship comprises the vertical installation phase of group, segmentation installation phase, unit assembling stage; The vertical installation phase consideration of group cannot put into some pipe fittings, the fittings that segmentation is installed after division system is finished; Segmentation installation phase is also known as segmentation pre outfitting, most pipe fitting and part fittings are installed in this stage and are terminated, substantially be in this stage segmentation and be inverted and be sidelong position, pipe fitting on all decks reverse side and sidewall and fittings, all can be divided into this stage installs, and will notice that the pipe fitting of all installations and fittings must not exceed segmented edges when dividing; The unit assembling stage belongs to the category of pre outfitting, according to the feature of engine room arrangement, whole area of aircraft cabins is divided into several unit, installs, carry out integral hoisting and install the process of locating to designated area, cabin after installing in a fixing place.
Preferably, described region installation phase refers in depressed place and carries installation phase and harbour installation phase.
Positive progressive effect of the present invention is: the present invention enables professional call the modeling situation of cabin fittings in time, timely communication docking, the good setting having divided the installation phase such as pipe Xi part, iron Xi part, shorten the installation period of fittings, increasing work efficiency, providing condition for shortening shipbuilding period.
Detailed description of the invention
The installation exercise method of fittings of the present invention comprises the in-built part of ship and the in-built part of non-ship, and the in-built part of ship comprises always organizes installation phase, region installation phase, system installation phase; After total group of installation phase refers to that more than two or two segmentations carry out total group, carry out fitting-out installation phase, this stage mainly installs the counter gathering pipe that fills of some segmentations and is in two fittingss closed up between segmentation, as hanging beam, inclined ladder etc.; If simultaneously when crane capacity allows, segmentation front equipment base and some midget plants, all can be divided into the installation of this stage; Region installation phase refers in depressed place and carries installation phase and harbour installation phase, this stage mainly installs some main equipments, complete cross section carry between gathering pipe, the equipment adapter of land regions, inclined ladder between upper lower platform, main exhaust pipe and some do not carry out the pipeline of modeling, as steam companion line pipe, valve remote control pipe-line etc.; System installation phase refers in pipeline installation process produces the features such as closure workmanship flow process according to pipeline system material characteristic and segmentation, the special a kind of installation phase divided out.These pipelines, in the modeling of segmentation stage, ship install whole road pipe according to pipeline system, belong to the in-built category of ship.Such as: the copper pipe in fresh water system, the PVC(polyvinylchloride on the piping of upper strata)/PE(polyethylene) pipe etc.; The in-built part of non-ship comprises the vertical installation phase of group, segmentation installation phase, unit assembling stage; The vertical installation phase of group is commonly called as the batten down stage, the consideration of this stage cannot put into some pipe fitting, fittingss etc. that segmentation is installed after division system is finished, and as the vertical ladder in part cargo tank heating pipe, cabin communication cabin component, double bottom ballast tank suction inlet, heavy caliber valve member, cabin, marks time; Segmentation installation phase is also known as segmentation pre outfitting, and most pipe fitting and part fittings are installed in this stage and terminated; Substantially be in this stage segmentation and be inverted and be sidelong position, pipe fitting on all decks reverse side and sidewall and fittings, all can be divided into this stage installs, and will notice that the pipe fitting of all installations and fittings must not exceed segmented edges when dividing, generally within segmented edges 300mm; The unit assembling stage belongs to the category of pre outfitting, according to the feature of engine room arrangement, whole area of aircraft cabins is divided into several unit, installs, carry out integral hoisting and install the process of locating to designated area, cabin after installing in a fixing place.The unit assembling stage owing to not needing directly to install in hull structure, so do not stand by hull structure group and the impact of block assembly.
The present invention makes the installation of fittings be not limited to and install fittings from sectional forming ability, need to consider operation reach, part fittings need be considered to organize vertical installation, arrive segmentation again to install, because the factors such as error also need to consider that total group is installed, such actv. shortens ssection fitting-out part installation period, decreases ssection fitting-out part setting pressure etc., creates conditions for shortening shipbuilding period.
The present invention enables professional call the modeling situation of cabin fittings in time, timely communication docking, has well divided the setting of the installation phase such as pipe Xi part, iron Xi part, has shortened the installation period of fittings, increasing work efficiency, providing condition for shortening shipbuilding period.
Above-described specific embodiment; the technical matters of solution of the present invention, technical scheme and beneficial effect are further described; be understood that; the foregoing is only specific embodiments of the invention; be not limited to the present invention; within the spirit and principles in the present invention all, any amendment made, equivalent replacement, improvement etc., all should be included within protection scope of the present invention.
Claims (2)
1. an installation exercise method for fittings, is characterized in that, it comprises the in-built part of ship and the in-built part of non-ship;
The in-built part of ship comprises always organizes installation phase, region installation phase, system installation phase; After total group of installation phase refers to that more than two or two segmentations carry out total group, carry out fitting-out installation phase, this stage mainly installs the counter gathering pipe that fills of some segmentations and is in two fittingss closed up between segmentation, if simultaneously when crane capacity allows, segmentation front equipment base and some midget plants, all can be divided into the installation of this stage; Region installation phase mainly installs some main equipments, complete cross section carry between gathering pipe, the equipment adapter of land regions, inclined ladder between upper lower platform, main exhaust pipe and some do not carry out the pipeline of modeling; System installation phase refers in pipeline installation process produces closure workmanship process features according to pipeline system material characteristic and segmentation, the special a kind of installation phase divided out;
The in-built part of non-ship comprises the vertical installation phase of group, segmentation installation phase, unit assembling stage; The vertical installation phase consideration of group cannot put into some pipe fittings, the fittings that segmentation is installed after division system is finished; Segmentation installation phase is also known as segmentation pre outfitting, most pipe fitting and part fittings are installed in this stage and are terminated, be in this stage segmentation and be inverted and be sidelong position, pipe fitting on all decks reverse side and sidewall and fittings, all can be divided into this stage installs, and will notice that the pipe fitting of all installations and fittings must not exceed segmented edges when dividing; The unit assembling stage belongs to the category of pre outfitting, according to the feature of engine room arrangement, whole area of aircraft cabins is divided into several unit, installs, carry out integral hoisting and install the process of locating to designated area, cabin after installing in a fixing place.
2. the installation exercise method of fittings as claimed in claim 1, is characterized in that, described region installation phase refers in depressed place and carries installation phase and harbour installation phase.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310644625.7A CN103661802B (en) | 2013-12-05 | 2013-12-05 | The installation exercise method of fittings |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310644625.7A CN103661802B (en) | 2013-12-05 | 2013-12-05 | The installation exercise method of fittings |
Publications (2)
Publication Number | Publication Date |
---|---|
CN103661802A CN103661802A (en) | 2014-03-26 |
CN103661802B true CN103661802B (en) | 2016-01-20 |
Family
ID=50300825
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201310644625.7A Active CN103661802B (en) | 2013-12-05 | 2013-12-05 | The installation exercise method of fittings |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN103661802B (en) |
Families Citing this family (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104590486B (en) * | 2015-01-22 | 2017-01-18 | 启东丰顺船舶重工有限公司 | Pre-outfitting technology for finished product oil and chemical ship engine room |
CN110282077B (en) * | 2018-03-19 | 2022-04-01 | 江苏现代造船技术有限公司 | Construction method for binding bridge segment in shipbuilding process |
CN110171530B (en) * | 2019-05-29 | 2021-05-04 | 广船国际有限公司 | Method for manufacturing and mounting segmented structure |
CN110877673B (en) * | 2019-10-18 | 2021-09-21 | 沪东中华造船(集团)有限公司 | Method for preassembling short pipe at ship segmented curved plate |
CN111392594A (en) * | 2020-03-24 | 2020-07-10 | 上海外高桥造船有限公司 | Hoisting method for bulk carrier cabin block and bulk carrier built by using same |
CN112249261A (en) * | 2020-10-29 | 2021-01-22 | 广船国际有限公司 | Building method of ship defense area |
CN112550625B (en) * | 2020-12-07 | 2021-11-02 | 沪东中华造船(集团)有限公司 | Building method of double-chimney block of ship |
CN113715986A (en) * | 2021-08-17 | 2021-11-30 | 中船澄西船舶修造有限公司 | Basin fitting-out unit installation method |
CN113788127A (en) * | 2021-10-28 | 2021-12-14 | 江南造船(集团)有限责任公司 | Method for segmental construction and outfitting of large chimney of container ship |
CN114954832A (en) * | 2022-06-29 | 2022-08-30 | 上海外高桥造船有限公司 | Main hull total segmentation building method and ship |
Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH05178272A (en) * | 1991-12-27 | 1993-07-20 | Ishikawajima Harima Heavy Ind Co Ltd | Compartment outfitting method for ship |
JPH07215268A (en) * | 1994-01-31 | 1995-08-15 | Mitsubishi Heavy Ind Ltd | Fitting-out method in vessel |
CN1948081A (en) * | 2006-11-03 | 2007-04-18 | 大连船舶重工集团有限公司 | Assembly ship building unit element, modularization designing method |
CN1948080A (en) * | 2006-11-03 | 2007-04-18 | 大连船舶重工集团有限公司 | Outfitting construction method of boats and ships |
CN101032995A (en) * | 2007-04-06 | 2007-09-12 | 上海外高桥造船有限公司 | Method of installing ship bilge equipment |
CN101570234A (en) * | 2008-04-29 | 2009-11-04 | 江南造船(集团)有限责任公司 | Method for assembling and lifting engine room section |
CN102320349A (en) * | 2011-07-07 | 2012-01-18 | 大连荣升船舶设备制造有限公司 | The ship ' s equipment method |
CN102582784A (en) * | 2012-03-30 | 2012-07-18 | 南通明德重工有限公司 | Process for sectionally putting up ship berths or docks |
CN102874378A (en) * | 2012-10-29 | 2013-01-16 | 南通润邦海洋工程装备有限公司 | Cabin basin fitting-out process |
-
2013
- 2013-12-05 CN CN201310644625.7A patent/CN103661802B/en active Active
Patent Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH05178272A (en) * | 1991-12-27 | 1993-07-20 | Ishikawajima Harima Heavy Ind Co Ltd | Compartment outfitting method for ship |
JPH07215268A (en) * | 1994-01-31 | 1995-08-15 | Mitsubishi Heavy Ind Ltd | Fitting-out method in vessel |
CN1948081A (en) * | 2006-11-03 | 2007-04-18 | 大连船舶重工集团有限公司 | Assembly ship building unit element, modularization designing method |
CN1948080A (en) * | 2006-11-03 | 2007-04-18 | 大连船舶重工集团有限公司 | Outfitting construction method of boats and ships |
CN101032995A (en) * | 2007-04-06 | 2007-09-12 | 上海外高桥造船有限公司 | Method of installing ship bilge equipment |
CN101570234A (en) * | 2008-04-29 | 2009-11-04 | 江南造船(集团)有限责任公司 | Method for assembling and lifting engine room section |
CN102320349A (en) * | 2011-07-07 | 2012-01-18 | 大连荣升船舶设备制造有限公司 | The ship ' s equipment method |
CN102582784A (en) * | 2012-03-30 | 2012-07-18 | 南通明德重工有限公司 | Process for sectionally putting up ship berths or docks |
CN102874378A (en) * | 2012-10-29 | 2013-01-16 | 南通润邦海洋工程装备有限公司 | Cabin basin fitting-out process |
Also Published As
Publication number | Publication date |
---|---|
CN103661802A (en) | 2014-03-26 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103661802B (en) | The installation exercise method of fittings | |
US20130199792A1 (en) | Subsea collection and containment system for hydrocarbon emissions | |
CN105416508A (en) | Method for increasing outfitting pre-installation ratio | |
CN102582784B (en) | Process for sectionally putting up ship berths or docks | |
CN204567976U (en) | A kind of ballast chamber overvoltage protection structure | |
CN104590486B (en) | Pre-outfitting technology for finished product oil and chemical ship engine room | |
CN105972375A (en) | Unmanned shipborne pipeline repairing fixture | |
CN106015784B (en) | Unmanned boat contained pipeline connector | |
CN111022002A (en) | Wellhead environment simulation platform device and simulation method for deepwater oil and gas production system | |
CN103216678A (en) | Grouting air sac method for suspending sea pipe | |
CN103910029A (en) | Engine room pump compartment fitting-out method for self-propelled drag suction dredger ship | |
CN111232145A (en) | Overall layout of deepwater semi-submersible production platform | |
CN207580088U (en) | A kind of lakes fitted type bulk carrier pipe does arrangement | |
CN202828085U (en) | Seawater pipeline structure capable of preventing pipeline corrosion and lightening pipeline weight | |
CN211547601U (en) | Rubber type breakwater with adjustable floating height | |
CN104494792A (en) | Transportation device and transportation method for ocean engineering structures | |
CN110949639B (en) | Method for repairing mooring state of sea valve of surface ship and plugging tool suitable for method | |
CN208058147U (en) | A kind of mounting device of single side seat board peculiar to vessel | |
CN103925410A (en) | Emergency repair device for submarine pipelines | |
CN102975834A (en) | Method for changing depth finder under water | |
CN110906102A (en) | Emergent accuse oil device under water | |
CN203111460U (en) | Generator module multifunctional channel for floating production storage and offloading vessel | |
CN110777728A (en) | Rubber type breakwater with adjustable floating height | |
CN109322292A (en) | A kind of vane type oil spilling recycling oil fence | |
CN103101608A (en) | Auxiliary quick floating device of water surface floating building and application method thereof |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |