CN104590486B - Pre-outfitting technology for finished product oil and chemical ship engine room - Google Patents

Pre-outfitting technology for finished product oil and chemical ship engine room Download PDF

Info

Publication number
CN104590486B
CN104590486B CN201510032169.XA CN201510032169A CN104590486B CN 104590486 B CN104590486 B CN 104590486B CN 201510032169 A CN201510032169 A CN 201510032169A CN 104590486 B CN104590486 B CN 104590486B
Authority
CN
China
Prior art keywords
pump
installation
oil
cabin
main
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510032169.XA
Other languages
Chinese (zh)
Other versions
CN104590486A (en
Inventor
刘火明
黄炳号
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nantong CIMC Sinopacific Ocean Offshore and Engineering Co Ltd
Original Assignee
Qidong Fengshun Ship Heavy Industry Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Qidong Fengshun Ship Heavy Industry Co Ltd filed Critical Qidong Fengshun Ship Heavy Industry Co Ltd
Priority to CN201510032169.XA priority Critical patent/CN104590486B/en
Publication of CN104590486A publication Critical patent/CN104590486A/en
Application granted granted Critical
Publication of CN104590486B publication Critical patent/CN104590486B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Lubrication Details And Ventilation Of Internal Combustion Engines (AREA)
  • Lubrication Of Internal Combustion Engines (AREA)

Abstract

The invention relates to a pre-outfitting technology for a finished product oil and chemical ship engine room. A platform or a bottom layer of the engine room is mounted in a forward tire manner, the pre-outfitting technology mainly includes the following stops of positioning and mounting of an engine room marine engine equipment seat frame, mounting of a pipe system, positioning and mounting of a chequered plate bracket with two layers of bottom rib positions, positioning and mounting of engine room equipment and manufacturing and mounting current correction pipes connected with the equipment. The pre-outfitting technology has the advantages that up operation is changed into down operation, so that the production efficiency can be improved; the original back surface is changed into the front surface, so that the original up work is changed into down work, the speed is high, and the labor is reduced; furthermore, the pre-outfitting technology can easily guarantee the precision, and the working efficiency is greatly improved.

Description

A kind of product oil, chemical tanker cabin advance fitting-out technique
Technical field
The present invention relates to shipbuilding field, particularly to a kind of product oil, chemical tanker cabin advance fitting-out technique.
Background technology
Before advance fitting-out, shell is regarded as carrier, all objects installed toward on shell are all called outfititem.And realize height The fitting-out inherent meaning of effect shipbuilding should be " leading fitting-out ", the ship accommodation outfitting workload in depressed place (platform) and lower water is dropped to Bottom line, so that fitting-out operation is moved forward or day process optimization, to greatest extent the every percent of completion of expanding production link, realize prefabricated And prepackage.
According to statistics, during shipbuilding, outfitting amount accounts for the 45%~55% of shipbuilding whole project.Outfitting In, piping fitting-out occupies very big ratio, and the raising with the advanced degree of ship and increase, due to piping fitting-out ship build In quantities ratio larger, duty cycle is long in addition, execution conditions are poor, means fall behind, so do well piping advance fitting-out, improve pipe The advance fitting-out rate of system is to shorten an important content of shipbuilding period.
Piping advance fitting-out is exactly by " shipboard operation land, work high above the ground level land, the outfield operation of piping installing engineering Internal field ", piping outfitting is one of cycle the longest engineering in shipbuilding.Improve piping advance fitting-out effective ways by Several below:
(1) unit assembling: also known as unit fitting-out, it is based on a certain outfititem, other outfititems depend on thereon and One assembly of shape, it is that being linked to be some outfititems with certain framework, pedestal or other connectors is whole in other words Body;
(2) segmentation prepackage: segmentation prepackage be exactly by outfititem or unit in body section manufacture process or on building berth it Before be installed to segmental structure up a kind of advance fitting-out method, the pipe dress work on building berth can be distributed to each segmentation heap by it Field even either inside, meanwhile, is that the painting work of segmentation creates good condition;
(3) complete cross section prepackage: complete cross section prepackage is also known as three-dimensional fitting-out, after it is hull assembly with two and more than two Complete the installation of outfititem again, if segmentation advance fitting-out is prepackage for the first time, then complete cross section advance fitting-out belongs to second prepackage, Because elevating capacity, production site and Operational preparation cycle etc. are limited, complete cross section advance fitting-out is not still universal, typically builds on upper strata Build and carry out with bow;
(4) basin fitting-out: basin fitting-out be exactly by the seam of double bottom block side plate and shifting board bring up to checker plate with On, a kind of fitting-out mode of outfititem or unit block is installed in the case of segmentation is just put on inner bottom plating.Basin fitting-out can expand Big cabin bottom advanced outfitting work amount, very rising.
The content of segmentation prepackage includes: the 1. prepackage of double bottom block;2. engine room platform and upper deck panel is pre- Dress;3. go up the advance fitting-out that flaggy builds segmentation;4. the prepackage of deck panel;The method of the prepackage of segmentation at present adopts towards sky operation, Precision is low, is unfavorable for keeping the safety in production, delays shipbuilding period, and waste time and energy.
Content of the invention
The technical problem to be solved in the present invention be provide a kind of adopt downward operating type, time saving and energy saving it is ensured that precision, greatly Improve greatly work efficiency, shorten product oil, the chemical tanker cabin advance fitting-out technique of shipbuilding period.
For solving above-mentioned technical problem, the technical scheme is that a kind of product oil, chemical tanker cabin advance fitting-out work Skill, its innovative point is: described engineroom flat or bottom are installed with positive tire, mainly includes determining of cabin turbine equipment mounting Position installation, the installation of piping, the checker plate support location and installation of double bottom rib position, engine room facilities location and installation and make and pacify The existing school pipe that dress is connected with equipment.
Further, the location and installation key step of described cabin turbine equipment mounting is as follows:
(1) installation of 6000mm flat equipments under stage mounting: main inclusion main sea water pump, ballast sweeping jet pump, the bilge disappear Anti- pump, fire and general service pump, pump for residue of oil, fuel oil transportation by lighter pump, diesel oil transportation by lighter pump, main frame oil pump, lubricating oil transportation by lighter pump, stern pipe lubricating oil Pump, steam cylinder oil transportation by lighter pump, water-oil separating pump, oil water separator, ballast pump, washing of tanks water pump, Cargo Oil Pump, cargo stripping pump, seawater Charging tank, the installation of fresh-water generator sea water pump;(2) installation of 6000mm flat equipments on stage mounting: main inclusion main frame fuel feeding list Unit, lubricating oil centrifugal oil separator module, central cooler, oil cooler, main engine jacket water cooling pump, low temperature fresh water pump, host high-temperature Fresh water pump, the installation of fresh water generator;(3) installation of 95000mm flat equipments under stage mounting: main inclusion main generator group, fuel oil divide Oil machine module, subsidiary engine oil supply unit, fresh water hydrophore tank, heat hydraulic pressure's cabinet, sewage treatment unit, air compressor machine, air bottle, machine The water base extinguishing device in cabin, sanitary sewage transportation by lighter pump, the installation of main frame spare part.
Further, the installation key step of described piping is as follows: (1) is first to sea water service system, bilges system, ballast system System, the heavy caliber pipe of combustion oil system are installed, and then from bottom to up other pipes are installed;(2) peace of unit Dress, lifts to after the unit segment folding of cabin bottom, and unit on platform etc. is lifted into before corresponding prepackage segment carrying Position;(3) before the tightness test of double bottom cabin, all pipe connections being connected with tank are installed, main inclusion is installed Suction in tank, row, overflow, heating, tele-thermometer, liquid level warning, liquid level gauge, depth measurement, injection, the pipeline such as ventilative and attached The installation short tube of part or seat board;(4) the heating coil location and installation of each heating compartment of double bottom;(5) it is arranged in double bottom tank Pepe support need to add compound plate, and the pepe support being arranged in tank should be installed in place before hull application.
Further, the checker plate support location and installation of described double bottom rib position is mainly connected with double bottom tank in support Meet place and compound plate is installed, during installation, should ensure that the installation direction of support angle steel should be correct.
Further, described engine room facilities location and installation is carried out after hull application terminates, the main frame under 6000mm platform Oil pump, Cargo Oil Pump, ballast pump, butterworthpump, cabin inclined ladder need to carry out after ship body folding terminates and main frame, shafting enter cabin Install, other engine room facilities all can be installed, except body section closes up region.
It is an advantage of the current invention that:
(1) become downward operation towards sky operation, can improve production efficiency, originally reverse side becomes front, originally face upward dress Operation becomes dress of bowing, not only fast but also laborsaving, and is easily guaranteed that precision, substantially increases work efficiency;
(2) power equipment can be made full use of, facilitate the use of electrical equipment, such as using gas cutting, electric welding and crane gear Deng much more convenient than on building berth;
(3) reduce work high above the ground, be conducive to keeping the safety in production;
(4) shipbuilding period can be shortened.Meeting on building berth can be mitigated using segmentation prepackage, be conducive to uniformly dividing of labour Join the dispersed placement with construction site;
(5) can pinpoint the problems ahead of time and solve problem during advance fitting-out;
(6) be conducive to the installation of weight.Pipe can be made longer, decrease joint, improve installation quality.
Specific embodiment
The invention discloses a kind of product oil, chemical tanker cabin advance fitting-out technique, engineroom flat or bottom are entered with positive tire Row is installed, and the main location and installation including cabin turbine equipment mounting, the installation of piping, the checker plate support of double bottom rib position are determined Position is installed, engine room facilities location and installation and make and install the existing school pipe being connected with equipment.
The location and installation key step of cabin turbine equipment mounting is as follows:
(1) installation of 6000mm flat equipments under stage mounting: main inclusion main sea water pump, ballast sweeping jet pump, the bilge disappear Anti- pump, fire and general service pump, pump for residue of oil, fuel oil transportation by lighter pump, diesel oil transportation by lighter pump, main frame oil pump, lubricating oil transportation by lighter pump, stern pipe lubricating oil Pump, steam cylinder oil transportation by lighter pump, water-oil separating pump, oil water separator, ballast pump, washing of tanks water pump, Cargo Oil Pump, cargo stripping pump, seawater Charging tank, the installation of fresh-water generator sea water pump;(2) installation of 6000mm flat equipments on stage mounting: main inclusion main frame fuel feeding list Unit, lubricating oil centrifugal oil separator module, central cooler, oil cooler, main engine jacket water cooling pump, low temperature fresh water pump, host high-temperature Fresh water pump, the installation of fresh water generator;(3) installation of 95000mm flat equipments under stage mounting: main inclusion main generator group, fuel oil divide Oil machine module, subsidiary engine oil supply unit, fresh water hydrophore tank, heat hydraulic pressure's cabinet, sewage treatment unit, air compressor machine, air bottle, machine The water base extinguishing device in cabin, sanitary sewage transportation by lighter pump, the installation of main frame spare part.
The installation key step of piping is as follows: (1) is first to sea water service system, bilges system, ballasting system, combustion oil system Heavy caliber pipe installed, then from bottom to up other pipes are installed;(2) installation of unit, to cabin bottom Unit segment folding after lift, unit on platform etc. lifts before corresponding prepackage segment carrying and puts in place;(3) double bottom tank Before the tightness test of room, all pipe connections being connected with tank are installed, the main suction including being arranged in tank, Row, overflow, heating, tele-thermometer, liquid level warning, liquid level gauge, depth measurement, the installation short tube of injection, the pipeline such as ventilative and annex Or seat board;(4) the heating coil location and installation of each heating compartment of double bottom;(5) pepe support being arranged in double bottom tank needs Plus compound plate, and the pepe support being arranged in tank should be installed in place before hull application.
The checker plate support location and installation of double bottom rib position mainly installs compound plate in support with double bottom tank junction, Should ensure that during installation that the installation direction of support angle steel should be correct.
Engine room facilities location and installation is carried out after hull application terminates, the main frame oil pump under 6000mm platform, Cargo Oil Pump, ballast pump, butterworthpump, cabin inclined ladder need to be installed after ship body folding terminates and main frame, shafting enter cabin, Qi Taji Chamber device all can be installed, except body section closes up region.
General principle and principal character and the advantages of the present invention of the present invention have been shown and described above.The technology of the industry , it should be appreciated that the present invention is not restricted to the described embodiments, the simply explanation described in above-described embodiment and specification is originally for personnel The principle of invention, without departing from the spirit and scope of the present invention, the present invention also has various changes and modifications, these changes Change and improvement both falls within scope of the claimed invention.Claimed scope by appending claims and its Equivalent thereof.

Claims (4)

1. a kind of product oil, chemical tanker cabin advance fitting-out technique it is characterised in that: described engineroom flat or bottom are entered with positive tire Row is installed, and the main location and installation including cabin turbine equipment mounting, the installation of piping, the checker plate support of double bottom rib position are determined Position is installed, engine room facilities location and installation and make and install the existing school pipe being connected with equipment;Described cabin turbine equipment seat The location and installation key step of frame is as follows:
(1) installation of 6000mm flat equipments under stage mounting: main include main sea water pump, ballast sweeping jet pump, bilge fire pump, Fire and general service pump, pump for residue of oil, fuel oil transportation by lighter pump, diesel oil transportation by lighter pump, main frame oil pump, lubricating oil transportation by lighter pump, stern tube lubricating oil pump, cylinder Oil barge fortune pump, water-oil separating pump, oil water separator, ballast pump, washing of tanks water pump, Cargo Oil Pump, cargo stripping pump, sea water hydrophore tank, The installation of fresh-water generator sea water pump;
(2) installation of 6000mm flat equipments on stage mounting: main inclusion main frame oil supply unit, lubricating oil centrifugal oil separator module, central authorities are cold But device, oil cooler, main engine jacket water cooling pump, low temperature fresh water pump, host high-temperature fresh water pump, the installation of fresh water generator;
(3) installation of 95000mm flat equipments under stage mounting: main inclusion main generator group, fuel oil purifier module, subsidiary engine fuel feeding Unit, fresh water hydrophore tank, heat hydraulic pressure's cabinet, sewage treatment unit, air compressor machine, air bottle, the water base extinguishing device of cabin, life Sewage of living lighters pump, the installation of main frame spare part.
2. product oil according to claim 1, chemical tanker cabin advance fitting-out technique it is characterised in that: described piping Key step is installed as follows:
(1) first the heavy caliber pipe of sea water service system, bilges system, ballasting system, combustion oil system is installed, Ran Houcong Under supreme other pipes are installed;
(2) installation of unit, lifts to after the unit segment folding of cabin bottom, and unit on platform etc. is in corresponding prepackage point Lifting before section is carried puts in place;
(3) before the tightness test of double bottom cabin, all pipe connections being connected with tank are installed, main inclusion is installed Suction in tank, row, overflow, heating, tele-thermometer, liquid level warning, liquid level gauge, depth measurement, injection, the pipeline such as ventilative and attached The installation short tube of part or seat board;
(4) the heating coil location and installation of each heating compartment of double bottom;
(5) pepe support being arranged in double bottom tank need to add compound plate, and the pepe support being arranged in tank should be in hull It is installed in place before application.
3. product oil according to claim 1, chemical tanker cabin advance fitting-out technique it is characterised in that: described double bottom The checker plate support location and installation of rib position mainly installs compound plate in support with double bottom tank junction, should ensure that and prop up during installation The installation direction of frame angle steel should be correct.
4. product oil according to claim 1, chemical tanker cabin advance fitting-out technique it is characterised in that: described cabin sets Standby location and installation is carried out after hull application terminates, the main frame oil pump under 6000mm platform, Cargo Oil Pump, ballast pump, washing of tanks Pump, cabin inclined ladder need to be installed after ship body folding terminates and main frame, shafting enter cabin, and other engine room facilities all can be pacified Dress, except body section closes up region.
CN201510032169.XA 2015-01-22 2015-01-22 Pre-outfitting technology for finished product oil and chemical ship engine room Active CN104590486B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510032169.XA CN104590486B (en) 2015-01-22 2015-01-22 Pre-outfitting technology for finished product oil and chemical ship engine room

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510032169.XA CN104590486B (en) 2015-01-22 2015-01-22 Pre-outfitting technology for finished product oil and chemical ship engine room

Publications (2)

Publication Number Publication Date
CN104590486A CN104590486A (en) 2015-05-06
CN104590486B true CN104590486B (en) 2017-01-18

Family

ID=53116635

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510032169.XA Active CN104590486B (en) 2015-01-22 2015-01-22 Pre-outfitting technology for finished product oil and chemical ship engine room

Country Status (1)

Country Link
CN (1) CN104590486B (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN206826907U (en) * 2017-06-14 2018-01-02 广船国际有限公司 A kind of polar region deck carrier
CN109353447B (en) * 2018-10-25 2022-03-15 上海船舶工艺研究所(中国船舶工业集团公司第十一研究所) Heating coil installation method for chemical ship liquid cargo tank
CN109911107A (en) * 2019-03-14 2019-06-21 上海江南长兴造船有限责任公司 A kind of fabrication and installation method of existing school pipe
CN110182300A (en) * 2019-04-22 2019-08-30 沪东中华造船(集团)有限公司 A kind of pre-buried construction method of container ship side sectional pipe Xi part
CN110171530B (en) * 2019-05-29 2021-05-04 广船国际有限公司 Method for manufacturing and mounting segmented structure

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4126309B2 (en) * 2005-05-24 2008-07-30 株式会社新来島どっく Outfitting unit in the engine casing
CN201856883U (en) * 2010-09-30 2011-06-08 江苏新扬子造船有限公司 Ship pipe system unit produced in internal field of workshop
CN102874378A (en) * 2012-10-29 2013-01-16 南通润邦海洋工程装备有限公司 Cabin basin fitting-out process
CN103507913A (en) * 2013-09-12 2014-01-15 南通明德重工有限公司 Design method for subsection division of chemical carrier
CN103661802A (en) * 2013-12-05 2014-03-26 江苏新时代造船有限公司 Method for installing outfitting parts
CN103910029A (en) * 2014-04-15 2014-07-09 南通长航船舶配件有限公司 Engine room pump compartment fitting-out method for self-propelled drag suction dredger ship

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH04163293A (en) * 1990-10-26 1992-06-08 Ishikawajima Harima Heavy Ind Co Ltd Outfitting method for engine room

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4126309B2 (en) * 2005-05-24 2008-07-30 株式会社新来島どっく Outfitting unit in the engine casing
CN201856883U (en) * 2010-09-30 2011-06-08 江苏新扬子造船有限公司 Ship pipe system unit produced in internal field of workshop
CN102874378A (en) * 2012-10-29 2013-01-16 南通润邦海洋工程装备有限公司 Cabin basin fitting-out process
CN103507913A (en) * 2013-09-12 2014-01-15 南通明德重工有限公司 Design method for subsection division of chemical carrier
CN103661802A (en) * 2013-12-05 2014-03-26 江苏新时代造船有限公司 Method for installing outfitting parts
CN103910029A (en) * 2014-04-15 2014-07-09 南通长航船舶配件有限公司 Engine room pump compartment fitting-out method for self-propelled drag suction dredger ship

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
CCS万吨级船舶轮机管系预舾装研究;刘火明;《造船技术》;20141028(第5期);第36-39页 *
国外船舶舾装现状与发展趋势;李兰美等;《造船技术》;20070601(第3期);第4-8页 *
机舱单元预舾装的设计和应用;祝国强;《造船技术》;19830531(第5期);第13-17页 *

Also Published As

Publication number Publication date
CN104590486A (en) 2015-05-06

Similar Documents

Publication Publication Date Title
CN104590486B (en) Pre-outfitting technology for finished product oil and chemical ship engine room
CN201010891Y (en) Self-elevating producing and oil-storing platform
CN103661802B (en) The installation exercise method of fittings
CN204527563U (en) Middle deep water semi-submersible drilling platform
CN104029798B (en) Self installation production platform
CN104805821B (en) Marine oil field natural gas compressing processes jack-up unit
CN106275253A (en) A kind of method that ship launching leading sea water moves electromotor in advance
CN202807547U (en) Self-diving and self-floating type underwater oil production and storage device
CN216477277U (en) Offshore heavy oil thermal recovery floating well head platform in shallow sea area
CN203714151U (en) Concrete transportation pumping ship
CN1209265C (en) Shallow sea submarine pipeline (cable) detecting and maintaining device
CN105539723A (en) Construction method for chemical carrier deck outfitting unit
CN111232145A (en) Overall layout of deepwater semi-submersible production platform
CN104986824A (en) Gravity-type ship bilge water pre-treatment device
CN115180101A (en) Underwater local dry land maintenance method and system
CN209096935U (en) A kind of placement layout of diesel oil/LNG double fuel Power Vessel fuel storage device
CN113148037B (en) Platform seawater supply system with multiple switchable modes
CN101628701B (en) Ship-type movable explosion-proof oiling device
CN204606131U (en) A seawater main pipe system applied to marine engineering auxiliary ships
CN107336804B (en) Self installation drinking water production oil storage platform deeply
CN204266186U (en) Marine oil field natural gas compressing process jack-up unit
CN103910029A (en) Engine room pump compartment fitting-out method for self-propelled drag suction dredger ship
CN205837138U (en) A kind of marine oil and gas stimulation work ship
CN208085979U (en) Dry chamber for repairing jacket under water
CN208705051U (en) Low-speed marine diesel engine multipurpose testing table frame

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20210819

Address after: 226200 Haigong Avenue 888, Qidong City, Nantong City, Jiangsu Province

Patentee after: NANTONG CIMC PACIFIC OCEAN MARINE ENGINEERING Co.,Ltd.

Address before: 226200 No. 5555 Haigong Avenue, Qidong Haigong Shipbuilding Industrial Park, Nantong City, Jiangsu Province

Patentee before: QIDONG FENGSHUN SHIP HEAVY INDUSTRY Co.,Ltd.