CN107351979A - The modular construction method of central station of floating dock - Google Patents
The modular construction method of central station of floating dock Download PDFInfo
- Publication number
- CN107351979A CN107351979A CN201710557606.9A CN201710557606A CN107351979A CN 107351979 A CN107351979 A CN 107351979A CN 201710557606 A CN201710557606 A CN 201710557606A CN 107351979 A CN107351979 A CN 107351979A
- Authority
- CN
- China
- Prior art keywords
- central station
- floating dock
- lower unit
- unit
- upper unit
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B63—SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
- B63B—SHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING
- B63B73/00—Building or assembling vessels or marine structures, e.g. hulls or offshore platforms
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Structural Engineering (AREA)
- Chemical & Material Sciences (AREA)
- Combustion & Propulsion (AREA)
- Mechanical Engineering (AREA)
- Ocean & Marine Engineering (AREA)
- Installation Of Indoor Wiring (AREA)
Abstract
The invention discloses a kind of modular construction method of central station of floating dock.Method of construction includes step:In the segmentation stage, the advance fitting-out that central station of floating dock is fabricated onto iron Xi parts, electric Xi parts, piping part, airduct from structure is completed, to be built into central station of floating dock modular assembly;Central station of floating dock modular assembly is the hexahedron structure of closing, upper unit and lower unit upper unit and lower unit are respectively provided with top and bottom, upper unit also has cavity, the top of upper unit has the open top connected with cavity, the top pressure of upper unit is located at the top of lower unit, accommodating cavity is surrounded between the cavity of upper unit and the top of lower unit, the bottom of lower unit is used to press located at the deck of ship;The structure manufacture of central station of floating dock includes manufacturing upper unit and lower unit.The method of construction can shorten central station of floating dock integrality fitting-out cycle, dock cycle, reduce the damage of electrical equipment.
Description
Technical field
The present invention relates to shipbuilding field, more particularly to a kind of modular construction method of central station of floating dock.
Background technology
Engine control room is the heart of ship, and the electric energy of generator output fully enters central station of floating dock, by a series of
After complicated control system functionalization, then the equipment for being output to correlation, make while necessary power source is provided to equipment
Equipment has safeguard protection and automatic control function.Central station of floating dock is most concentrated, electrically as Denso, residence dress workload in area of aircraft cabins
Workload is maximum, be related to that work post is more, flow is cumbersome, outfititem is more and complicated, process more than and cross-operation is more, construction period is most long
Special independent cabin, on stern island shaping, whole ship build overall progress have vital influence.
Due to more with the various connecting interfaces in other regions of cabin, so installation requirement is high, cycle length.The installation of central station of floating dock
State directly affects the fitting-out integrality in ship launching stage, influences the ship harbour installation and debugging cycle.
At present, conventional Ship Design is all by central station of floating dock design in some segmentation of cabin, without independent division
Out.In work progress, hull is carried to corresponding segment, after central station of floating dock is molded, by the equipment of central station of floating dock progressively lift into
It is interior, then central station of floating dock structure (including closedtop lid) is welded, is finally gradually completing a series of work, including iron Xi parts,
Electric Xi parts, the welding of pipe Xi parts, the installation of each equipment, cable laying and wiring, the decoration of inside etc., the cycle is longer.Because its is complete
The unfavorable factors such as the whole sex work cycle is long, cross-operation influences, cause grow its construction operation time in dock, influence whole ship
Take dock cycle.In addition, when being constructed in cabin, the damage also easily to expensive large electric equipment such as dust, spraying.
So as to which the installation method of central station of floating dock has that the central station of floating dock integrality fitting-out cycle is longer, dock cycle in the prior art
The defects of longer, fragile electrical equipment.
The content of the invention
The technical problem to be solved in the present invention be in order to overcome the central station of floating dock integrality fitting-out cycle of the prior art it is longer,
The defects of dock cycle is longer, fragile electrical equipment, there is provided the method that a kind of modularization of central station of floating dock is built.
The present invention is that solve above-mentioned technical problem by following technical proposals:
A kind of modular construction method of central station of floating dock, its feature are that the modular construction method of the central station of floating dock includes
Following steps:
S1, in the segmentation stage, complete central station of floating dock and the pre- Xi of iron Xi parts, electric Xi parts, piping part, airduct be fabricated onto from structure
Dress, to be built into a central station of floating dock modular assembly;
Wherein, the central station of floating dock modular assembly is the hexahedron structure of closing, and the central station of floating dock modular assembly includes top
Unit and lower unit, the upper unit and the lower unit are respectively provided with top and bottom, and the upper unit also has
Cavity, the top of the upper unit have the open top connected with the cavity, and the top pressure of the upper unit is located at
Accommodating cavity is surrounded between the top of the top of the lower unit, the cavity of the upper unit and the lower unit, it is described
The bottom of lower unit is used to press located at the deck of ship;
The structure manufacture of central station of floating dock includes manufacturing the upper unit and the lower unit.
In the technical program, installation exercise of the central station of floating dock after structural integrity during cabin drape forming shifts to an earlier date
Carry out in good time on to ground, treat that collection control lifting is gone on board, cable benefit drawing is applied, wiring connects with indoor and outdoor pipe as long as completing, very
Fast can completes fitting-out installment work, solves the contradiction of the integrality work period length of central station of floating dock;The modularization of central station of floating dock is built
The method of making reduces the fitting-out installation workload after dock carries, and is advantageous to improve the overall progress of shipbuilding;Meanwhile reduce
When being constructed in cabin, the damage to the large electric equipment of costliness such as dust, spraying.
It is preferred that in step S1Including step:
S11, the anti-state of the lower unit completed will be manufactured place, be respectively completed iron Xi parts, piping in the lower unit
The advance fitting-out of part and airduct.
It is preferred that in step S11Afterwards, step S1Also include step:
S12, sand washing and application are carried out to the lower unit;
S13, the lower unit is moved to total group platform;
S14, overturn the lower unit so that the lower unit normal state place, the lower unit top install
Pedestal;
S15, central control desk, main distribution board and air conditioner be attached to the pedestal;
Wherein, the pedestal, the central control desk, the main distribution board and the air conditioner are respectively positioned on the accommodating cavity.
It is preferred that step S1Including step:
S21, the anti-state of the upper unit completed will be manufactured place, be respectively completed iron Xi parts and wind in the lower unit
The advance fitting-out of pipe.
It is preferred that in step S21Afterwards, step S1Also include step:
S22, sand washing and application are carried out to the upper unit;
S23, the lower unit is moved to total group platform;
S24, overturn the upper unit so that the upper unit normal state place.
It is preferred that step S11-S14With step S21-S24It is parallel to carry out, step S1Also include step:
S31, upper unit pressure is located at the lower unit, complete the upper unit and the lower unit
Assembling, forms preliminary modular assembly.
In the technical program, manufacture, fitting-out, spraying and the manufacture of lower unit of upper unit, fitting-out, spraying are simultaneously
Carry out, it is possible to increase realize the efficiency of fitting-out integrality, shorten whole ship construction period.
It is preferred that in step S31Afterwards, step S1Also include step:
S41, structure inspection declaration is carried out to the preliminary modular assembly and paint is repaired.
It is preferred that S41Afterwards, step S1Also include step:
S51, in the preliminary modular assembly installation insulation dressing and lining plate;
S61, complete the advance fitting-out of electric Xi parts;
S71, complete fireproof door frame, soundproof window installation and welding.
It is preferred that S71Afterwards, step S1Also include step:
S81, the integrality of the fire operation of the inside and outside wall of the preliminary modular assembly is checked;
S91, all surface in the polishing preliminary modular assembly, and carry out application.
It is preferred that S91Afterwards, step S1Also include step:
S101, the drawing of completing a part of cable in the preliminary modular assembly applies;
S111, by the central station of floating dock modular assembly integral hoisting to hull;
Wherein, a part of cable is embedded in the lining plate in advance, except a part of cable in the central station of floating dock
The drawing of cable in addition is applied to carry out in the dock stage.
It on the basis of common sense in the field is met, above-mentioned each optimum condition, can be combined, it is each preferably real to produce the present invention
Example.
The positive effect of the present invention is:
The modular construction method of the central station of floating dock reduces the fitting-out installation workload after dock carries, and is advantageous to improve ship
The overall progress that oceangoing ship is built;By installation exercise of the central station of floating dock after structural integrity during cabin drape forming, ground is advanceed to
It is upper to carry out in good time, wait that collecting control lifting goes on board, and draws deposited, wiring to be connected with indoor and outdoor pipe, soon may be used as long as completing cable and mending
To complete fitting-out installment work, solves the contradiction of the integrality work period length of central station of floating dock;Reduce simultaneously when being constructed in cabin,
The damage to the large electric equipment of costliness such as dust, spraying.
Brief description of the drawings
Fig. 1 is the flow chart of the modular construction method of the central station of floating dock of a preferred embodiment of the present invention.
Embodiment
Name preferred embodiment, and become apparent from intactly illustrating the present invention with reference to accompanying drawing.
The modular construction method of central station of floating dock includes step:In the segmentation stage, complete central station of floating dock and be fabricated onto iron Xi from structure
The advance fitting-out of part, electric Xi parts, piping part, airduct, to be built into a central station of floating dock modular assembly.Wherein, central station of floating dock modular assembly is
The hexahedron structure of closing, the central station of floating dock modular assembly include upper unit and lower unit, the upper unit and described
Lower unit is respectively provided with top and bottom, and the upper unit also has a cavity, the top of the upper unit with it is described
The open top of cavity connection, the top pressure of the upper unit are located at the top of the lower unit, the upper unit
Accommodating cavity is surrounded between the top of cavity and the lower unit, the bottom of the lower unit is used to press the first located at ship
Plate;The structure manufacture of central station of floating dock includes manufacturing the upper unit and the lower unit.
In the present embodiment, the installation exercise by central station of floating dock after structural integrity during cabin drape forming, in advance
Carry out in good time on to ground, treat that collection control lifting is gone on board, cable benefit drawing is applied, wiring connects with indoor and outdoor pipe as long as completing, very
Fast can completes fitting-out installment work, solves the contradiction of the integrality work period length of central station of floating dock;The modularization of central station of floating dock is built
The method of making reduces the fitting-out installation workload after dock carries, and is advantageous to improve the overall progress of shipbuilding;Meanwhile reduce
When being constructed in cabin, the damage to the large electric equipment of costliness such as dust, spraying.
Specifically, as shown in figure 1, the modular construction method of central station of floating dock specifically includes following steps:
Step 11, the anti-state of lower unit completed will be manufactured place, be respectively completed iron Xi parts in lower unit, piping part and
The advance fitting-out of airduct.
Step 12, sand washing and application are carried out to lower unit;
Step 13, lower unit is moved to total group platform;
Step 14, upset lower unit are so that lower unit normal state is placed, in the top installation pedestal of lower unit;
Step 15, central control desk, main distribution board and air conditioner be attached to pedestal;
Step 21, the anti-state of upper unit completed will be manufactured place, be respectively completed iron Xi parts and airduct in lower unit
Advance fitting-out.
Step 22, sand washing and application are carried out to upper unit;
Step 23, lower unit is moved to total group platform;
Step 24, upset upper unit are so that upper unit normal state is placed.
Step 31, upper unit pressure be located at lower unit, complete the assembling of upper unit and lower unit, formed tentatively
Modular assembly;
Step 41, structure inspection declaration and paint repairing are carried out to preliminary modular assembly;
Step 51, installation insulation dressing and lining plate in preliminary modular assembly;
Step 61, the advance fitting-out for completing electric Xi parts;
Step 71, the installation and welding for completing fireproof door frame, soundproof window;
Step 81, the integrality to the fire operation of the inside and outside wall of preliminary modular assembly check;
All surface in step 91, the preliminary modular assembly of polishing, and carry out application;
The drawing of a part of cable is applied in step 101, the completion preliminary modular assembly;
Step 111, by central station of floating dock modular assembly integral hoisting to hull.
Wherein, in the present embodiment, the pedestal in step 15, central control desk, main distribution board and air conditioner are respectively positioned on top
In the accommodating cavity that unit and lower unit are formed.
Further, step 11- steps 15 and step 21-24 are carried out parallel, mutually then again from step 31 to step 111 according to
Order is carried out.In the present embodiment, equivalent to manufacture, fitting-out, spraying and the manufacture of lower unit of, upper unit, fitting-out,
Spraying is carried out simultaneously, it is possible to increase is realized the efficiency of fitting-out integrality, is shortened whole ship construction period.
Further, a part of cable in step 101 is embedded in lining plate in advance, in central station of floating dock except a part of cable with
The drawing of outer cable is applied to carry out in the dock stage.In the present embodiment, except the cable that must be completed in the dock stage
Draw outside applying, the drawing of other cables is applied to be carried out before the docking stage is entered.
Further, before step 91 is to all surface application in preliminary modular assembly, step 81 is first carried out
The integrality of fire operation is checked, can further reduce the damage of the large electric equipment to costliness.
The modular construction method had advanceed to platform or internal field by what is carried out originally in the dock stage, fundamentally shortened
Dock cycle and harbour cycle.Outfitting (Denso, machine dress and residence dress) installation exercise of central station of floating dock is in central station of floating dock cabin
Structure has been completed before being molded to carrying, cabin on ship, and the workload after central station of floating dock is gone on board is greatly reduced, and exists so as to shorten whole ship
The cycle that dock is built.In addition, the damage of dust and application to the large electric equipment of costliness can be reduced.
Although the embodiment of the present invention is the foregoing described, it will be appreciated by those of skill in the art that this is only
For example, protection scope of the present invention is to be defined by the appended claims.Those skilled in the art without departing substantially from
On the premise of the principle and essence of the present invention, various changes or modifications can be made to these embodiments, but these changes and
Modification each falls within protection scope of the present invention.
Claims (10)
- A kind of 1. modular construction method of central station of floating dock, it is characterised in that the modular construction method of the central station of floating dock include with Lower step:S1, in the segmentation stage, complete central station of floating dock and the advance fitting-out of iron Xi parts, electric Xi parts, piping part, airduct be fabricated onto from structure, to build Cause a central station of floating dock modular assembly;Wherein, the central station of floating dock modular assembly is the hexahedron structure of closing, and the central station of floating dock modular assembly includes upper unit And lower unit, the upper unit and the lower unit are respectively provided with top and bottom, the upper unit also has cavity, The top of the upper unit has the open top that connect with the cavity, the top pressure of the upper unit be located at it is described under Accommodating cavity is surrounded between the top of the top of portion's unit, the cavity of the upper unit and the lower unit, the bottom is single The bottom of member is used to press located at the deck of ship;The structure manufacture of central station of floating dock includes manufacturing the upper unit and the lower unit.
- 2. the modular construction method of central station of floating dock as claimed in claim 1, it is characterised in that in step S1Including step:S11, the anti-state of the lower unit completed will be manufactured place, be respectively completed iron Xi parts in the lower unit, piping part and The advance fitting-out of airduct.
- 3. the modular construction method of central station of floating dock as claimed in claim 2, it is characterised in that in step S11Afterwards, step S1 Also include step:S12, sand washing and application are carried out to the lower unit;S13, the lower unit is moved to total group platform;S14, overturn the lower unit so that the lower unit normal state place, in the top installation pedestal of the lower unit;S15, central control desk, main distribution board and air conditioner be attached to the pedestal;Wherein, the pedestal, the central control desk, the main distribution board and the air conditioner are respectively positioned on the accommodating cavity.
- 4. the modular construction method of central station of floating dock as claimed in claim 3, it is characterised in that step S1Including step:S21, the anti-state of the upper unit completed will be manufactured place, be respectively completed iron Xi parts and airduct in the lower unit Advance fitting-out.
- 5. the modular construction method of central station of floating dock as claimed in claim 4, it is characterised in that in step S21Afterwards, step S1 Also include step:S22, sand washing and application are carried out to the upper unit;S23, the lower unit is moved to total group platform;S24, overturn the upper unit so that the upper unit normal state place.
- 6. the modular construction method of central station of floating dock as claimed in claim 5, it is characterised in that step S11-S14With step S21- S24It is parallel to carry out, step S1Also include step:S31, by the upper unit pressure be located at the lower unit, complete the assembling of the upper unit and the lower unit, Form preliminary modular assembly.
- 7. the modular construction method of central station of floating dock as claimed in claim 6, it is characterised in that in step S31Afterwards, step S1 Also include step:S41, structure inspection declaration is carried out to the preliminary modular assembly and paint is repaired.
- 8. the modular construction method of central station of floating dock as claimed in claim 7, it is characterised in that S41Afterwards, step S1Also include Step:S51, in the preliminary modular assembly installation insulation dressing and lining plate;S61, complete the advance fitting-out of electric Xi parts;S71, complete fireproof door frame, soundproof window installation and welding.
- 9. the modular construction method of central station of floating dock as claimed in claim 8, it is characterised in that S71Afterwards, step S1Also include Step:S81, the integrality of the fire operation of the inside and outside wall of the preliminary modular assembly is checked;S91, all surface in the polishing preliminary modular assembly, and carry out application.
- 10. the modular construction method of central station of floating dock as claimed in claim 9, it is characterised in that S91Afterwards, step S1Also include Step:S101, the drawing of completing a part of cable in the preliminary modular assembly applies;S111, by the central station of floating dock modular assembly integral hoisting to hull;Wherein, a part of cable is embedded in the lining plate in advance, in the central station of floating dock in addition to a part of cable Cable drawing be applied to the dock stage carry out.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710557606.9A CN107351979A (en) | 2017-07-10 | 2017-07-10 | The modular construction method of central station of floating dock |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710557606.9A CN107351979A (en) | 2017-07-10 | 2017-07-10 | The modular construction method of central station of floating dock |
Publications (1)
Publication Number | Publication Date |
---|---|
CN107351979A true CN107351979A (en) | 2017-11-17 |
Family
ID=60293496
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710557606.9A Pending CN107351979A (en) | 2017-07-10 | 2017-07-10 | The modular construction method of central station of floating dock |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107351979A (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108313200A (en) * | 2017-12-29 | 2018-07-24 | 南通中远船务工程有限公司 | Crude oil rejects ship quarters module trapeze integral hoisting method |
CN113562137A (en) * | 2021-08-11 | 2021-10-29 | 上海外高桥造船有限公司 | Modularized construction method between FGSS, FGSS and ship |
CN113602447A (en) * | 2021-08-11 | 2021-11-05 | 上海外高桥造船有限公司 | Centralized control room unit modular construction and assembly method and ship |
CN113753176A (en) * | 2021-09-29 | 2021-12-07 | 上海外高桥造船有限公司 | Method for arranging FGSSROM units of dual-fuel ship |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2010095114A (en) * | 2008-10-15 | 2010-04-30 | Daiko Sangyo:Kk | Compartment module for marine vessels |
CN102556282A (en) * | 2012-01-17 | 2012-07-11 | 广州广船国际股份有限公司 | Building process for ship central control room |
CN102837801A (en) * | 2012-08-20 | 2012-12-26 | 江苏新世纪造船有限公司 | Construction method of ship central control room module |
CN103204222A (en) * | 2012-01-12 | 2013-07-17 | 江苏新世纪造船有限公司 | Engine control room modular production |
KR20140028252A (en) * | 2012-08-28 | 2014-03-10 | 현대중공업 주식회사 | Engin room inner bottom structure of lng-fsru hull |
-
2017
- 2017-07-10 CN CN201710557606.9A patent/CN107351979A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2010095114A (en) * | 2008-10-15 | 2010-04-30 | Daiko Sangyo:Kk | Compartment module for marine vessels |
CN103204222A (en) * | 2012-01-12 | 2013-07-17 | 江苏新世纪造船有限公司 | Engine control room modular production |
CN102556282A (en) * | 2012-01-17 | 2012-07-11 | 广州广船国际股份有限公司 | Building process for ship central control room |
CN102837801A (en) * | 2012-08-20 | 2012-12-26 | 江苏新世纪造船有限公司 | Construction method of ship central control room module |
KR20140028252A (en) * | 2012-08-28 | 2014-03-10 | 현대중공업 주식회사 | Engin room inner bottom structure of lng-fsru hull |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108313200A (en) * | 2017-12-29 | 2018-07-24 | 南通中远船务工程有限公司 | Crude oil rejects ship quarters module trapeze integral hoisting method |
CN113562137A (en) * | 2021-08-11 | 2021-10-29 | 上海外高桥造船有限公司 | Modularized construction method between FGSS, FGSS and ship |
CN113602447A (en) * | 2021-08-11 | 2021-11-05 | 上海外高桥造船有限公司 | Centralized control room unit modular construction and assembly method and ship |
CN113753176A (en) * | 2021-09-29 | 2021-12-07 | 上海外高桥造船有限公司 | Method for arranging FGSSROM units of dual-fuel ship |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107351979A (en) | The modular construction method of central station of floating dock | |
CN102582784B (en) | Process for sectionally putting up ship berths or docks | |
CN104512558B (en) | Method for the assembly of an aircraft fuselage and fuselage manufacturing station | |
CN102887220B (en) | Electric thruster pedestal and welding method thereof | |
WO2023274423A1 (en) | Modular wind turbine blade and method for manufacturing same | |
JP2011526861A (en) | Method for attaching a dome shaped pressure bulkhead to the rear of an aircraft and apparatus for carrying out this method | |
CN110440429A (en) | Subway arch top ventilation shaft assembling constructing method | |
CN107600314B (en) | Integral hoisting method is built in thin plate multilayer | |
CN104453248A (en) | Complex irregular-shaped multi-layer net rack construction method based on layered modular assembling technology | |
US11136094B2 (en) | Construction method for column platform barrel deck and topsides, and column platform | |
CN106133312A (en) | Wind turbine nacelle structure | |
CN102837801A (en) | Construction method of ship central control room module | |
CN109747775A (en) | The parallel building technology of FPSO modular unitization | |
CN112550625B (en) | Building method of double-chimney block of ship | |
CN109606551A (en) | A kind of modularization yacht and assemble method | |
CN102556282B (en) | Building process for ship central control room | |
CN102632965A (en) | Combined type module ship and module connecting way thereof | |
CN207360518U (en) | Sealing device for the interim floating of ship | |
CN105346672A (en) | Ship machining method | |
CN106968371B (en) | A kind of construction method of the high wing articulated structure drifted by wind of curtain wall construction | |
CN105926999B (en) | 2.5 tons of freight weight limit helicopter handling noise reduction computer room mechanisms of one kind and processing technology | |
CN114954832A (en) | Main hull total segmentation building method and ship | |
CN202703846U (en) | Fixation compound plate | |
CN205954867U (en) | Wind -force, special transformer substation of photovoltaic power generation use rain -proof water structure | |
CN109747786A (en) | 400 tons of pulling winch support constructions and installation method in ocean engineering cabin |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |