CN102494536A - Construction method for dust-fall pipe of sintering chamber - Google Patents

Construction method for dust-fall pipe of sintering chamber Download PDF

Info

Publication number
CN102494536A
CN102494536A CN2011103972463A CN201110397246A CN102494536A CN 102494536 A CN102494536 A CN 102494536A CN 2011103972463 A CN2011103972463 A CN 2011103972463A CN 201110397246 A CN201110397246 A CN 201110397246A CN 102494536 A CN102494536 A CN 102494536A
Authority
CN
China
Prior art keywords
depositing dust
dust pipe
perforate
dust
pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2011103972463A
Other languages
Chinese (zh)
Other versions
CN102494536B (en
Inventor
郭周周
侯秀
马平太
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
MCC Tiangong Group Corp Ltd
Original Assignee
MCC Tiangong Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by MCC Tiangong Group Corp Ltd filed Critical MCC Tiangong Group Corp Ltd
Priority to CN 201110397246 priority Critical patent/CN102494536B/en
Publication of CN102494536A publication Critical patent/CN102494536A/en
Application granted granted Critical
Publication of CN102494536B publication Critical patent/CN102494536B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The invention relates to a construction method for a dust-fall pipe of a sintering chamber, which comprises the steps of (1) installing an I beam rail on an upper embedded casing pipe of a concrete beam above the dust-fall pipe corresponding to the lower bottom surface of the sintering chamber, and assembling an electric hoist on the I beam rail; (2) lifting a hopper under the dust-fall pipe to the installation position; (3) installing a pipe support and a leakage seat; (4) installing a main pipe; (5) opening a hole at the upper portion of the dust-fall pipe; (6) opening a hole at the lower portion of the dust-fall pipe; and (7) installing a reinforced plate on the dust-fall pipe, and finishing installing the dust-fall pipe of the sintering chamber. The construction method for the dust-fall pipe of the sintering chamber is simple and practical and free of large lifting machinery, effectively shortens installation time of the dust-fall pipe, improves construction efficiency, reduces construction cost, improves construction quality, and is safe and reliable.

Description

Agglomerating chamber's depositing dust pipe construction method
Technical field
The invention belongs to metallurgical system agglomerating chamber depositing dust pipe field, especially a kind of agglomerating chamber depositing dust pipe construction method.
Background technology
Metallurgical system agglomerating chamber depositing dust pipe divides two, is positioned at below the sintering pallet, and general erection sequence is the installation of after agglomerating chamber's major project is accomplished, just carrying out the depositing dust pipe; Be restricted because of clear height is installed, the big machinery profit is not used, and difficulty of construction strengthens; Require the construction period short, installation in the past generally is to adopt many to lead chain and use artificial or set up temporary platform in the side and install, and this kind method installation progress is slow; Manual work and mechanical appliances are many, and potential safety hazard is more.
Summary of the invention
The objective of the invention is to overcome the deficiency of prior art, a kind of agglomerating chamber depositing dust pipe construction method is provided, this construction method is simple; Need not large-scale hoisting machinery, effectively shortened the depositing dust pipe set-up time, improved efficiency of construction; Reduce construction cost, improved construction quality.
The present invention solves its technical problem and realizes through following technical scheme:
A kind of agglomerating chamber depositing dust pipe construction method, the step that its method comprises is:
(1), service sleeve is installed the I-shaped beam orbit on the beams of concrete of corresponding agglomerating chamber bottom surface above the depositing dust pipe, on the I-beam track, adorns an electric block;
(2), the funnel under the depositing dust pipe is winched to the installation site;
(3), conduit saddle is installed and is leaked seat, it is integrally welded to leak seat and conduit saddle;
(4), install and be responsible for:, from inside outwards install according to actual conditions; The depositing dust pipe is divided into some joints, and every joint length is 2-3m, and single-unit weight is no more than the electric block rated load weight, and the depositing dust pipe is put into assigned address from the hole for hoist lifting, welds between straightening then, the tube and tube;
(5), depositing dust pipe top perforate: the top perforate of depositing dust pipe is connected with airduct; Airduct is winched to depositing dust pipe top; Draw from the airduct center and to throw to the depositing dust pipe; Based on the perforate on the depositing dust pipe of airduct size, airduct should be waited for airduct is connected completion with top equipment after with the welding of depositing dust pipe and carrying out then;
(6), depositing dust pipe bottom perforate: the bottom perforate of depositing dust pipe is welded with leaking seat, should be in advance with being responsible for and leaking the seat outside weldings, then based on the perforate of funnel size for preventing to be responsible for distortion before the perforate; After perforate is accomplished; With jack funnel is sling, welded with leaking seat, and the about full weld seam of mending;
(7), the stiffened panel on the depositing dust pipe is installed, agglomerating chamber's depositing dust pipe installs.
And, two electric blocks are installed on the described I-beam track.
Advantage of the present invention and beneficial effect are:
1, this agglomerating chamber depositing dust pipe construction method is employed on the beams of concrete of the corresponding agglomerating chamber in depositing dust pipe top bottom surface service sleeve the I-shaped beam orbit is installed, and on the I-beam track, adorns an electric block.With electric block lifting depositing dust pipe, saved large-scale hoisting machinery, rationally utilized installing space, reduced installation cost, reduced the potential safety hazard of construction, guaranteed the construction period of engineering.
2, this agglomerating chamber depositing dust pipe construction method can adopt two electric blocks are installed on the I-beam track, and the depositing dust pipe is installed in segmentation, shortens the engineering time, improves efficiency of construction, guarantees the construction continuity.
3, construction method of the present invention is simple, need not large-scale hoisting machinery, effectively shortened the depositing dust pipe set-up time, and improved efficiency of construction, reduced construction cost, improved construction quality, be a kind of safe and reliable agglomerating chamber's depositing dust pipe construction method.
Description of drawings
Fig. 1 is for using structural representation of the present invention.
The specific embodiment
Through specific embodiment the present invention is made further detailed description below, following examples are descriptive, are not determinate, can not limit protection scope of the present invention with this.
A kind of agglomerating chamber depositing dust pipe construction method, the step that its method comprises is:
(1), service sleeve is installed I-shaped beam orbit 6 on the beams of concrete 2 of corresponding agglomerating chamber 3 bottom surfaces above the depositing dust pipe 1; On the I-beam track, adorn an electric block 10; Also can adopt two electric blocks; Carry out segmentation and install, electric block is through steel wire rope 11 lifting depositing dust pipes, and embodiment of the invention electric block shown in the drawings is one; Calculate the size of required I-steel and the lifting capacity of required electric block according to lifting capacity, utilize electric block, have the order merogenesis that depositing dust pipe and other auxiliary part are installed;
(2), the funnel under the depositing dust pipe 5 is winched to the installation site;
(3), conduit saddle 7 is installed and is leaked seat 4, install the back and guarantee that conduit saddle absolute altitude, axis meet design, code requirement, it is integrally welded with conduit saddle to leak seat, the stability of increase integral body;
(4), install and be responsible for:, from inside outwards install according to actual conditions; The depositing dust pipe is divided into some joints, and every joint length is 2-3m, and single-unit weight is no more than the electric block rated load weight, and the depositing dust pipe is put into assigned address from the hole for hoist lifting, welds between straightening then, the tube and tube;
(5), depositing dust pipe top perforate: the top perforate of depositing dust pipe is connected with airduct 9; Airduct is winched to depositing dust pipe top; Draw from the airduct center and to throw to the depositing dust pipe; Based on the perforate on the depositing dust pipe of airduct size, airduct should be waited for airduct is connected completion with top equipment after with the welding of depositing dust pipe and carrying out then;
(6), depositing dust pipe bottom perforate: the bottom perforate of depositing dust pipe is welded with leaking seat, should be in advance with being responsible for and leaking the seat outside weldings, then based on the perforate of funnel size for preventing to be responsible for distortion before the perforate; After perforate is accomplished; With jack funnel is sling, welded with leaking seat, and the about full weld seam of mending;
(7), the stiffened panel 8 on the depositing dust pipe is installed, agglomerating chamber's depositing dust pipe installs.

Claims (2)

1. agglomerating chamber's depositing dust pipe construction method, it is characterized in that: the step that this method comprises is:
(1), service sleeve is installed the I-shaped beam orbit on the beams of concrete of corresponding agglomerating chamber bottom surface above the depositing dust pipe, on the I-beam track, adorns an electric block;
(2), the funnel under the depositing dust pipe is winched to the installation site;
(3), conduit saddle is installed and is leaked seat, it is integrally welded to leak seat and conduit saddle;
(4), install and be responsible for:, from inside outwards install according to actual conditions; The depositing dust pipe is divided into some joints, and every joint length is 2-3m, and single-unit weight is no more than the electric block rated load weight, and the depositing dust pipe is put into assigned address from the hole for hoist lifting, welds between straightening then, the tube and tube;
(5), depositing dust pipe top perforate: the top perforate of depositing dust pipe is connected with airduct; Airduct is winched to depositing dust pipe top; Draw from the airduct center and to throw to the depositing dust pipe; Based on the perforate on the depositing dust pipe of airduct size, airduct should be waited for airduct is connected completion with top equipment after with the welding of depositing dust pipe and carrying out then;
(6), depositing dust pipe bottom perforate: the bottom perforate of depositing dust pipe is welded with leaking seat, should be in advance with being responsible for and leaking the seat outside weldings, then based on the perforate of funnel size for preventing to be responsible for distortion before the perforate; After perforate is accomplished; With jack funnel is sling, welded with leaking seat, and the about full weld seam of mending;
(7), the stiffened panel on the depositing dust pipe is installed, agglomerating chamber's depositing dust pipe installs.
2. agglomerating chamber according to claim 1 depositing dust pipe construction method is characterized in that: two electric blocks are installed on the described I-beam track.
CN 201110397246 2011-12-05 2011-12-05 Construction method for dust-fall pipe of sintering chamber Active CN102494536B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201110397246 CN102494536B (en) 2011-12-05 2011-12-05 Construction method for dust-fall pipe of sintering chamber

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201110397246 CN102494536B (en) 2011-12-05 2011-12-05 Construction method for dust-fall pipe of sintering chamber

Publications (2)

Publication Number Publication Date
CN102494536A true CN102494536A (en) 2012-06-13
CN102494536B CN102494536B (en) 2013-09-25

Family

ID=46186380

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201110397246 Active CN102494536B (en) 2011-12-05 2011-12-05 Construction method for dust-fall pipe of sintering chamber

Country Status (1)

Country Link
CN (1) CN102494536B (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103615893A (en) * 2013-11-06 2014-03-05 中冶天工集团有限公司 Method for mounting dust settling flue of sintering chamber
CN103791730A (en) * 2014-03-03 2014-05-14 王强 Arrangement structure of dust fall pipes of sintering machine
CN104016260A (en) * 2014-06-25 2014-09-03 中国五冶集团有限公司 Compartment funnel slipping mounting method and slipping mounting mechanism
CN110127520A (en) * 2019-05-10 2019-08-16 上海二十冶建设有限公司 The small lattice funnel of large-type sinterer and dust-fall pipe installation method
CN111379900A (en) * 2020-03-31 2020-07-07 中国二十二冶集团有限公司 Method for installing indoor horizontal large flue of large sintering plant

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2004103527A1 (en) * 2003-05-21 2004-12-02 Chang Un Lee Rotary pulse type filter dust collector
CN101721862A (en) * 2009-12-12 2010-06-09 山西省电力公司电力建设四公司 Meta-synthesis construction method of 600MW unit bag-type dust remover
CN101829470A (en) * 2010-05-15 2010-09-15 山西省电力公司电力建设四公司 Construction technique of electric bag compound type dust remover
CN101928576A (en) * 2009-06-19 2010-12-29 中冶成工上海五冶建设有限公司 Installation method of dry-quenching secondary dust cleaner
CN201776265U (en) * 2010-08-05 2011-03-30 安徽龙华竹业有限公司 Dust-removing device for large producing department

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2004103527A1 (en) * 2003-05-21 2004-12-02 Chang Un Lee Rotary pulse type filter dust collector
CN101928576A (en) * 2009-06-19 2010-12-29 中冶成工上海五冶建设有限公司 Installation method of dry-quenching secondary dust cleaner
CN101721862A (en) * 2009-12-12 2010-06-09 山西省电力公司电力建设四公司 Meta-synthesis construction method of 600MW unit bag-type dust remover
CN101829470A (en) * 2010-05-15 2010-09-15 山西省电力公司电力建设四公司 Construction technique of electric bag compound type dust remover
CN201776265U (en) * 2010-08-05 2011-03-30 安徽龙华竹业有限公司 Dust-removing device for large producing department

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103615893A (en) * 2013-11-06 2014-03-05 中冶天工集团有限公司 Method for mounting dust settling flue of sintering chamber
CN103791730A (en) * 2014-03-03 2014-05-14 王强 Arrangement structure of dust fall pipes of sintering machine
CN103791730B (en) * 2014-03-03 2015-10-21 王强 A kind of sintering machine dust-fall pipe arrangement
CN104016260A (en) * 2014-06-25 2014-09-03 中国五冶集团有限公司 Compartment funnel slipping mounting method and slipping mounting mechanism
CN104016260B (en) * 2014-06-25 2016-03-02 中国五冶集团有限公司 Little lattice funnel slide installation method and slippage installing mechanism
CN110127520A (en) * 2019-05-10 2019-08-16 上海二十冶建设有限公司 The small lattice funnel of large-type sinterer and dust-fall pipe installation method
CN110127520B (en) * 2019-05-10 2021-01-01 上海二十冶建设有限公司 Method for installing small-lattice funnel and dust-settling pipe of large sintering machine
CN111379900A (en) * 2020-03-31 2020-07-07 中国二十二冶集团有限公司 Method for installing indoor horizontal large flue of large sintering plant
CN111379900B (en) * 2020-03-31 2022-02-08 中国二十二冶集团有限公司 Method for installing indoor horizontal large flue of large sintering plant

Also Published As

Publication number Publication date
CN102494536B (en) 2013-09-25

Similar Documents

Publication Publication Date Title
CN102494536B (en) Construction method for dust-fall pipe of sintering chamber
CN103264968B (en) The construction method of plug-in tower crane support beam structure in Super High Core Walls Structure
CN207513158U (en) Concrete stack shell constructing device
CN109184189B (en) Construction method for conical shell silo top structure of large-diameter silo
CN106836836B (en) A kind of secondary hydraulic lifting installation method of Flue Gas Desulphurization for Coal-burning Power Plant tower transformation
CN105804400A (en) Hoisting construction method of curved truss
CN107246270A (en) The small space of shield machine rapidly station-crossing construction method
CN107795122A (en) Concrete stack shell constructing device and construction method
CN105692468A (en) Large latticed shell type arch crown integral elevation hoisting mechanism and using method thereof
CN105442866A (en) Protective dismantle and assembly method for large-scale towering steel structures
CN108678388A (en) The short mast multiple spot integral hoisting construction engineering method of large capacity circle storage tank
CN205000974U (en) A tire formula automatic rising equipment rack for tunnel excavation construction
CN104314009B (en) Big sections hoisting mechanism and using method
CN104801836A (en) Offshore wind power generation jacket foundation flange installation method
CN106544959B (en) The construction method of king-tower lifting segment and bridge main tower saddle containing saddle
CN106015824A (en) Hydrostatic test plugging device and method for prestressed concrete cylinder pipe
CN103206075B (en) Suspension platform for construction of steel reinforced concrete cantilever structure
CN101109028A (en) Method of upside-down mounting hydraulic pressure lifting of converter shell
CN105798491A (en) Welding construction method for steel pipe column casings of steel pipe column
CN203359856U (en) Support beam structure for external tower crane in high-rise core tube
CN206544877U (en) A kind of desulfurizing tower Promotion Transformation jacking apparatus
CN109252682A (en) A kind of rope bearing structure hound installation method
CN205742952U (en) Elevator civil engineering mobile platform
CN102392550A (en) Reverse installation method for flue gas desulfurization and absorption tower
CN203222981U (en) Suspended platform for steel reinforced concrete cantilever structure construction

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant