CN102493465A - 填土场地锚碇式锚拉桩支挡结构 - Google Patents

填土场地锚碇式锚拉桩支挡结构 Download PDF

Info

Publication number
CN102493465A
CN102493465A CN2011104118329A CN201110411832A CN102493465A CN 102493465 A CN102493465 A CN 102493465A CN 2011104118329 A CN2011104118329 A CN 2011104118329A CN 201110411832 A CN201110411832 A CN 201110411832A CN 102493465 A CN102493465 A CN 102493465A
Authority
CN
China
Prior art keywords
anchorage
type pull
retaining structure
anchorage type
soldier pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2011104118329A
Other languages
English (en)
Inventor
史宇
廖海
向智军
康景文
陈建光
林润钟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Southwest Architectural Design and Research Institute Co Ltd
Original Assignee
China Southwest Architectural Design and Research Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Southwest Architectural Design and Research Institute Co Ltd filed Critical China Southwest Architectural Design and Research Institute Co Ltd
Priority to CN2011104118329A priority Critical patent/CN102493465A/zh
Publication of CN102493465A publication Critical patent/CN102493465A/zh
Pending legal-status Critical Current

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

本发明公开了一种填土场地锚碇式锚拉桩支挡结构,它是由支护桩、钢筋网和锚碇型拉杆组成,锚碇型拉杆一端固定设有锚碇,另一端设有螺纹和螺母,支护桩中预设有拉杆孔,拉杆孔呈水平状,钢筋网固定安装在支护桩上,并在钢筋网上喷有混凝土。本发明中将支护桩嵌欠在预设桩位,锚碇型拉杆随着填土作业的增高被顺序埋进填土层中,充分利用填土施工形成的土体密实度,以增加锚碇型拉杆的侧阻力和抗拉能力,减少了支护桩的直径,进而减少了混凝土用量和钢材用量,缩短了支护结构的施工周期,节约了工程造价。

Description

填土场地锚碇式锚拉桩支挡结构
技术领域
本发明涉及一种建筑施工领域,具体说是一种填土场地锚碇式锚拉桩支挡结构。
背景技术
目前人们在修建蓄水池、小型基坑及垃圾填埋场等建筑领域中均广泛采用支护桩、钢筋网和锚杆作为支护结构,在填土完毕后将锚杆通过支护桩上的锚杆孔斜插入新近填土层中,在回填土层较高时,其为防止新近填土层垮塌,往往采用增加支护桩直径和锚杆长度的方式来达到防止新近填土层垮塌的目的,但是这种以靠增加支护桩直径和锚杆长度的技术结构势必会增加工程成本,若增加支护桩直径则会增加混凝土和钢材用量,若增加锚杆长度同样会增加钢材用量,并且由于锚杆固定时需要采用钻孔施工作业,因而施工方式较为复杂,难度也相对较大,不利于缩短工程建设周期。
发明内容
为了解决现有技术结构的不足,本发明提供一种填土场地锚碇式锚拉桩支挡结构,不仅可以对填土层起到有效的支护作用,而且施工速度较快,有效缩短了工程建设周期,节约工程建设成本。
本发明是通过下述技术方案来实现的:它是由支护桩、钢筋网和锚碇型拉杆组成,锚碇型拉杆一端固定设有锚碇,另一端设有螺纹和螺母,支护桩中预设有拉杆孔,钢筋网固定安装在支护桩上,并且支护桩中的拉杆孔呈水平状,钢筋网上喷有混凝土。本发明中由于锚碇型拉杆随着填土作业的增高而被顺序埋进填土层中,将原锚杆的钻孔施工变为挖槽作业,降低了施工难度,缩短了工程建设周期,并且充分利用填土施工形成的土体密实度,以增加锚碇型拉杆的侧阻力和抗拉能力,进而可减小支护桩的直径,节约材料。
本发明的有益效果是:不仅可以对填土层起到有效的支护作用,而且可以减小支护桩的直径,缩短锚杆的长度,节约了成本,并且采用本发明进行支护作业时可将原锚杆的钻孔施工变为挖槽施工,降低了施工难度,有效缩短了工程建设周期,节约工程建设成本,产品结构简单,施工方便,便于推广使用。
附图说明
下面结合附图对本发明作进一步的说明。
图1为本发明的主视结构示意图。
图2为本发明的剖面结构示意图。
图中代码说明:1支护桩;2拉杆孔;3钢筋网;4a、4b、4c、4d锚碇型拉杆;5支护桩桩梁;6锚碇;7螺母。
具体实施方式
如图1、图2所示,本发明由支护桩(1)、钢筋网(3)、锚碇型拉杆(4a、4b、4c、4d)组成,其中在支护桩(1)上设有拉杆孔(2),在锚碇型拉杆(4a、4b、4c、4d)的两端分别设置有锚碇(6)和螺母(7)。使用时,将支护桩固定设置在预设桩位处,并将钢筋网固定在支护桩一侧,同时在其一侧进行填土作业,在填土层接近支护桩第一拉杆孔位时将锚碇型拉杆(4a)固定在第一拉杆孔位处,然后继续进行填土作业至第二拉杆孔位,并继续将锚碇型拉杆(4b)固定在第二拉杆孔位处,以此类推直至填土作业完成,并在钢筋网上喷涂混凝土,使支护桩和钢筋网形成一个整体支护面板,达到防止新填土层垮塌的目的。在实际运用,当填土层较高时,可在支护桩顶端增设支护桩桩梁(5),以增强支护桩的稳定性,同时可适当增加锚碇(6)的直径,以进一步增强锚杆的抗拉能力。
需要说明的是,本发明中采用5根支护桩,每根支护桩上采用4根锚碇型拉杆来作为支挡结构,但在实际运用中,可根据实际填土作业的需要来增加或减少支护桩和锚碇型拉杆的数量。

Claims (3)

1.一种填土场地锚碇式锚拉桩支挡结构,其特征是:它是由支护桩、钢筋网和锚碇型拉杆组成,锚碇型拉杆一端固定设有锚碇,另一端设有螺纹和螺母,支护桩中预设有拉杆孔,钢筋网固定安装在支护桩上。
2.根据权利要求1所述的一种填土场地锚碇式锚拉桩支挡结构,其特征是:支护桩中的拉杆孔呈水平状。
3.根据权利要求1所述的一种填土场地锚碇式锚拉桩支挡结构,其特征是:钢筋网上喷有混凝土。
CN2011104118329A 2011-12-12 2011-12-12 填土场地锚碇式锚拉桩支挡结构 Pending CN102493465A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011104118329A CN102493465A (zh) 2011-12-12 2011-12-12 填土场地锚碇式锚拉桩支挡结构

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011104118329A CN102493465A (zh) 2011-12-12 2011-12-12 填土场地锚碇式锚拉桩支挡结构

Publications (1)

Publication Number Publication Date
CN102493465A true CN102493465A (zh) 2012-06-13

Family

ID=46185321

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011104118329A Pending CN102493465A (zh) 2011-12-12 2011-12-12 填土场地锚碇式锚拉桩支挡结构

Country Status (1)

Country Link
CN (1) CN102493465A (zh)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103046561A (zh) * 2012-12-31 2013-04-17 中国建筑西南勘察设计研究院有限公司 锚拉排桩锚碇墙复合式支挡结构
CN103046547A (zh) * 2012-12-31 2013-04-17 中国建筑西南勘察设计研究院有限公司 锚碇锚杆组合型支挡结构
CN103806451A (zh) * 2014-03-12 2014-05-21 中国建筑西南勘察设计研究院有限公司 一种锚碇型基坑加固结构及其施工方法
CN106013180A (zh) * 2016-05-31 2016-10-12 重庆交通大学 一种新型深填斜坡中桩基稳控系统
CN107816053A (zh) * 2017-11-27 2018-03-20 佛山科学技术学院 一种土木工程用的桩柱结构

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2659966Y (zh) * 2003-03-21 2004-12-01 武汉化工学院 深基坑肋桩竖拱喷锚组合支护结构
KR100468034B1 (ko) * 2002-06-19 2005-01-27 주식회사 도담이앤씨 앵커링을 이용한 보강토 옹벽 시공방법
CN200985510Y (zh) * 2006-11-09 2007-12-05 上海市第一建筑有限公司 拉锚式围护结构
CN101225661A (zh) * 2008-02-02 2008-07-23 浙江环宇建设集团有限公司 桩加锚基坑支护工法
CN201224889Y (zh) * 2008-06-20 2009-04-22 云南省公路规划勘察设计院 一种高填方支挡工程中的高轻型锚定板挡墙
CN201671108U (zh) * 2010-04-27 2010-12-15 中国科学院武汉岩土力学研究所 一种沿河路肩预应力锚索桩板墙
KR20110024476A (ko) * 2009-09-02 2011-03-09 (주)컴퍼지트솔루션코리아 어스 앵커, 복합 쉘 파일을 이용한 주열식 옹벽 및 그 시공 방법

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100468034B1 (ko) * 2002-06-19 2005-01-27 주식회사 도담이앤씨 앵커링을 이용한 보강토 옹벽 시공방법
CN2659966Y (zh) * 2003-03-21 2004-12-01 武汉化工学院 深基坑肋桩竖拱喷锚组合支护结构
CN200985510Y (zh) * 2006-11-09 2007-12-05 上海市第一建筑有限公司 拉锚式围护结构
CN101225661A (zh) * 2008-02-02 2008-07-23 浙江环宇建设集团有限公司 桩加锚基坑支护工法
CN201224889Y (zh) * 2008-06-20 2009-04-22 云南省公路规划勘察设计院 一种高填方支挡工程中的高轻型锚定板挡墙
KR20110024476A (ko) * 2009-09-02 2011-03-09 (주)컴퍼지트솔루션코리아 어스 앵커, 복합 쉘 파일을 이용한 주열식 옹벽 및 그 시공 방법
CN201671108U (zh) * 2010-04-27 2010-12-15 中国科学院武汉岩土力学研究所 一种沿河路肩预应力锚索桩板墙

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103046561A (zh) * 2012-12-31 2013-04-17 中国建筑西南勘察设计研究院有限公司 锚拉排桩锚碇墙复合式支挡结构
CN103046547A (zh) * 2012-12-31 2013-04-17 中国建筑西南勘察设计研究院有限公司 锚碇锚杆组合型支挡结构
CN103046561B (zh) * 2012-12-31 2016-02-03 中国建筑西南勘察设计研究院有限公司 锚拉排桩锚碇墙复合式支挡结构
CN103806451A (zh) * 2014-03-12 2014-05-21 中国建筑西南勘察设计研究院有限公司 一种锚碇型基坑加固结构及其施工方法
CN103806451B (zh) * 2014-03-12 2016-05-25 中国建筑西南勘察设计研究院有限公司 一种锚碇型基坑加固结构及其施工方法
CN106013180A (zh) * 2016-05-31 2016-10-12 重庆交通大学 一种新型深填斜坡中桩基稳控系统
CN107816053A (zh) * 2017-11-27 2018-03-20 佛山科学技术学院 一种土木工程用的桩柱结构

Similar Documents

Publication Publication Date Title
CN203741868U (zh) 一种带组合锚索的钢筋混凝土挡墙结构
CN203639942U (zh) 拱形挡土墙
CN202323962U (zh) 疏排管桩与土钉墙复合支护结构
CN102493465A (zh) 填土场地锚碇式锚拉桩支挡结构
CN102330432A (zh) 面板式框架预应力锚杆柔性支护结构及其施工方法
CN102605773B (zh) 注浆成型扩底钻孔灌注桩的施工方法及其挤扩装置
CN102330431A (zh) 格构式框架预应力锚杆柔性支护结构及其施工方法
CN206941608U (zh) 一种地下连续墙基坑支护结构
CN108661069A (zh) 临近河道路面荷载下旧挡墙加固的墙桩锚组合结构及方法
CN203795438U (zh) 微型锚拉桩与土钉墙联合支挡结构
CN103397787A (zh) 一种钢筋混凝土柱双向x交叉托换技术
CN204753567U (zh) 一种配筋高压旋喷支护桩结构
CN203821381U (zh) 矩形预应力灌注桩
CN202017214U (zh) 冻土地基电力杆塔基础
CN103993604A (zh) 疏排桩锚基坑支护结构
CN102493463A (zh) 圆形挖孔暗肋锚杆型支护结构
CN206646521U (zh) 一种排桩复合全粘结锚杆支护结构
CN202369993U (zh) 对拉式灌注桩基坑支护结构
CN203905036U (zh) 预应力混凝土管桩劲性填芯结构
CN203684222U (zh) 旋喷扩大头预应力锚杆桩锚联合支护结构
CN202787275U (zh) 新型气动冲击锚管式土钉墙
CN206337566U (zh) 基坑竖向预应力锚杆支撑结构
CN203668926U (zh) 混凝土锥形桩基础
CN103741688A (zh) 分体式全长注浆锚固设施
CN203129154U (zh) 井字梁基坑支护结构

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20120613