CN102433865A - 半地下式电站厂房上游侧墙体的建造方法 - Google Patents
半地下式电站厂房上游侧墙体的建造方法 Download PDFInfo
- Publication number
- CN102433865A CN102433865A CN2012100056648A CN201210005664A CN102433865A CN 102433865 A CN102433865 A CN 102433865A CN 2012100056648 A CN2012100056648 A CN 2012100056648A CN 201210005664 A CN201210005664 A CN 201210005664A CN 102433865 A CN102433865 A CN 102433865A
- Authority
- CN
- China
- Prior art keywords
- wall
- power station
- upstream side
- side body
- side wall
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E10/00—Energy generation through renewable energy sources
- Y02E10/20—Hydro energy
Landscapes
- Revetment (AREA)
Abstract
本发明公开了一种半地下式电站厂房上游侧墙体的建造方法,包括混凝土结构的电站厂房,沿电站厂房位于地下部分的上游侧墙体纵向中线浇筑后浇带;后浇带与对应的上游侧墙体接触面布设钢丝网,沿每片钢丝网的纵向中线分别布设遇水膨胀止水条;在后浇带与对应的上游侧墙体接缝处分别布设紫铜止水片;在上游侧墙体内自下而上布设多层并缝钢筋,并缝钢筋水平贯穿后浇带布设;在上游侧墙体浇注前首先在其外表面布设聚乙烯闭孔泡沫板,沿上游侧墙体上部外侧回填沟的底部布设排水槽;在回填沟的底部及其侧面铺设无砂混凝土垫层,向回填沟内回填块石混凝土。按照本发明建造的半地下式电站厂房具有结构简单、安全可靠、成本低、电站厂房结构尺寸小等优点。
Description
技术领域
本发明涉及电站厂房结构,尤其涉及半地下式电站厂房上游侧墙体的建造方法及外部排水系统设计。
背景技术
半地下式电站厂房的上游侧墙体部分的嵌入岩壁,一般布置在引水系统下游河岸岸边,是水电站设计经常采用的一种厂房形式。对于半地下式电站厂房,由于其设备要求,一般为大跨度(30m-80m)、高边墙(20m-30m)结构。电站主体受力结构位于地面以下,且具有地下水位高、水压力大、发电机层以上的边墙缺乏约束的特点。按照设计与施工规范规定,地下墙体结构每20m-30m设置一道变形缝,分缝时边墙在水平荷载作用下,上游边墙位移过大,难以满足电站桥机的运行要求。为满足电站桥机运行要求,目前采取加厚墙体,并配置大量结构钢筋,使得建造成本大大增加。
发明内容
本发明目的在于提供一种结构简单、安全可靠、造价低的半地下电站厂房结构。
为实现上述目的,本发明采取下述技术方案:
本发明所述半地下式电站厂房上游侧墙体的建造方法,包括建造于引水系统下游河岸岸边混凝土结构的电站厂房,沿所述电站厂房位于地下部分的上游侧墙体纵向中线浇筑后浇补偿收缩混凝土,即后浇带;所述后浇带的厚度与上游侧墙体一致,宽度1.8-2.2米;后浇带与对应的上游侧墙体接触面分别布设钢丝网,沿每片钢丝网的纵向中线分别布设遇水膨胀止水条;在后浇带与对应的上游侧墙体接缝处分别布设紫铜止水片;在上游侧墙体内自下而上布设多层并缝钢筋,所述的每一层并缝钢筋分别水平贯穿后浇带布设;在上游侧墙体浇注前首先在其外表面布设80-120毫米厚的聚乙烯闭孔泡沫板,待上游侧墙体浇注完毕达到混凝土设计强度后,沿上游侧墙体上部外侧回填沟的底部布设与集水井相连通的排水槽;在回填沟的底部及其侧面铺设无砂混凝土垫层,最后向回填沟内回填块石混凝土。
按照本发明建造的半地下式电站厂房具有结构简单、安全可靠、成本低、电站厂房结构尺寸小等优点。具体表现在以下几方面:
1、电站上游侧混凝土墙体与岩石及块石混凝土之间设置厚聚乙烯闭孔泡沫板,当岩石发生小变形时,其产生的水平位移被聚乙烯闭孔泡沫板消耗掉,不产生对结构的水平压力。
2、沿电站上游侧混凝土墙体上部外侧开设回填沟,在回填沟的底部布设与集水井相连通的排水槽,并在回填沟的底部和相对于上游侧墙体的一侧面铺设无砂混凝土垫层;这样,上游汇集地下水会沿着无砂混凝土排水槽及无砂混凝土排水垫层汇集到集水井,达到降低上游侧混凝土墙体水压力之目的。
3、在上游侧墙体中部纵向布设后浇带,不仅解决了设置变形缝造成的上游侧墙体水平位移过大问题,达到满足电站桥机及其它设备安全运行要求,同时又解决了施工期混凝土温度变形给电站厂房结构带来的影响,和上游侧墙体进行分缝时使厂房结构设计十分复杂的局面。
4、上游侧墙体与后浇带之间布设紫铜止水片、钢丝网、遇水膨胀止水条及并缝钢筋,避免了外水渗入厂房,保证电站具有良好的运行环境。
附图说明:
图1是按照本发明建造的半地下式电站厂房上游侧墙体的纵剖面结构示意图。
图2是本发明所述上游侧墙体的横断面结构示意图。
具体实施方式:
如图1、2所示,本发明所述半地下式电站厂房上游侧墙体的建造方法,包括建造于大坝引水系统下游河岸岸边混凝土结构的电站厂房1,沿所述电站厂房1位于地下嵌入岩壁部分的上游侧墙体2纵向中线浇筑后浇补偿收缩混凝土,即后浇带3;所述后浇带3的厚度与上游侧墙体一致,宽度2米;后浇带3与对应的上游侧墙体2接触面分别布设钢丝网4、5,沿每片钢丝网4、5的纵向中线分别布设遇水膨胀止水条6、7;在后浇带3与对应的上游侧墙体2接缝处分别布设紫铜止水片8、9;在上游侧墙体2内自下而上布设多层并缝钢筋10、11,所述的每一层并缝钢筋10、11分别水平贯穿后浇带3布设;在上游侧墙体2浇注前首先在其外表面布设80-120毫米厚的聚乙烯闭孔泡沫板12,待上游侧墙体2浇注完毕达到混凝土设计强度后,沿上游侧墙体2上部外侧回填沟的底部布设与集水井相连通的排水槽13;在回填沟的底部及其侧面铺设无砂混凝土垫层14,最后向回填沟内回填块石混凝土15。
Claims (1)
1.一种半地下式电站厂房上游侧墙体的建造方法,包括建造于引水系统下游河岸岸边混凝土结构的电站厂房(1),其特征在于:沿所述电站厂房(1)位于地下部分的上游侧墙体(2)纵向中线浇筑后浇补偿收缩混凝土,即后浇带(3);所述后浇带(3)的厚度与上游侧墙体一致,宽度1.8-2.2米;后浇带(3)与对应的上游侧墙体(2)接触面分别布设钢丝网(4、5),沿每片钢丝网(4、5)的竖向中线分别布设遇水膨胀止水条(6、7);在后浇带(3)与对应的上游侧墙体(2)接缝处分别布设紫铜止水片(8、9);在上游侧墙体(2)内自下而上布设多层并缝钢筋(10、11),所述的每一层并缝钢筋(10、11)分别水平贯穿后浇带(3)布设;在上游侧墙体(2)浇注前首先在其外表面布设80-120毫米厚的聚乙烯闭孔泡沫板(12),待上游侧墙体(2)浇注完毕达到混凝土设计强度后,沿上游侧墙体(2)上部外侧回填沟的底部布设与集水井相连通的排水槽(13);在回填沟的底部及其侧面铺设无砂混凝土垫层(14),最后向回填沟内回填块石混凝土(15)。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2012100056648A CN102433865A (zh) | 2012-01-10 | 2012-01-10 | 半地下式电站厂房上游侧墙体的建造方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2012100056648A CN102433865A (zh) | 2012-01-10 | 2012-01-10 | 半地下式电站厂房上游侧墙体的建造方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN102433865A true CN102433865A (zh) | 2012-05-02 |
Family
ID=45982195
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2012100056648A Pending CN102433865A (zh) | 2012-01-10 | 2012-01-10 | 半地下式电站厂房上游侧墙体的建造方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102433865A (zh) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103306305A (zh) * | 2013-06-26 | 2013-09-18 | 中建六局土木工程有限公司 | 一种岔道坑施工方法 |
CN105178648A (zh) * | 2015-10-13 | 2015-12-23 | 中国电建集团成都勘测设计研究院有限公司 | 易渗山区水电站用岸边厂房结构 |
CN108035323A (zh) * | 2017-12-12 | 2018-05-15 | 成都鼎智汇科技有限公司 | 具有耐腐蚀管道的地下式水电站 |
CN108677895A (zh) * | 2018-07-27 | 2018-10-19 | 中国电建集团成都勘测设计研究院有限公司 | 用于水利发电工程的发电厂房布置结构 |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2002275875A (ja) * | 2001-03-13 | 2002-09-25 | Kankyo Kikaku 21:Kk | 地下構造体の地中埋設工法 |
CN101493011A (zh) * | 2008-12-30 | 2009-07-29 | 中国科学院武汉岩土力学研究所 | 一种软弱膨胀型围岩巷道支护方法 |
CN101519881A (zh) * | 2009-03-23 | 2009-09-02 | 中设建工集团有限公司 | 地下室后浇带施工工艺 |
CN201381861Y (zh) * | 2008-12-30 | 2010-01-13 | 中国科学院武汉岩土力学研究所 | 一种软弱膨胀型围岩巷道支护装置 |
CN102116033A (zh) * | 2011-01-07 | 2011-07-06 | 中国建筑第四工程局有限公司 | 深基坑盲沟集水井降排水方法及装置 |
-
2012
- 2012-01-10 CN CN2012100056648A patent/CN102433865A/zh active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2002275875A (ja) * | 2001-03-13 | 2002-09-25 | Kankyo Kikaku 21:Kk | 地下構造体の地中埋設工法 |
CN101493011A (zh) * | 2008-12-30 | 2009-07-29 | 中国科学院武汉岩土力学研究所 | 一种软弱膨胀型围岩巷道支护方法 |
CN201381861Y (zh) * | 2008-12-30 | 2010-01-13 | 中国科学院武汉岩土力学研究所 | 一种软弱膨胀型围岩巷道支护装置 |
CN101519881A (zh) * | 2009-03-23 | 2009-09-02 | 中设建工集团有限公司 | 地下室后浇带施工工艺 |
CN102116033A (zh) * | 2011-01-07 | 2011-07-06 | 中国建筑第四工程局有限公司 | 深基坑盲沟集水井降排水方法及装置 |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103306305A (zh) * | 2013-06-26 | 2013-09-18 | 中建六局土木工程有限公司 | 一种岔道坑施工方法 |
CN103306305B (zh) * | 2013-06-26 | 2015-07-01 | 中建六局土木工程有限公司 | 一种岔道坑施工方法 |
CN105178648A (zh) * | 2015-10-13 | 2015-12-23 | 中国电建集团成都勘测设计研究院有限公司 | 易渗山区水电站用岸边厂房结构 |
CN108035323A (zh) * | 2017-12-12 | 2018-05-15 | 成都鼎智汇科技有限公司 | 具有耐腐蚀管道的地下式水电站 |
CN108677895A (zh) * | 2018-07-27 | 2018-10-19 | 中国电建集团成都勘测设计研究院有限公司 | 用于水利发电工程的发电厂房布置结构 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103205979B (zh) | 高温环境下大型筏基施工方法 | |
CN205276316U (zh) | 组合式预制管廊 | |
CN101581088B (zh) | 冲填砂浆结石坝施工方法 | |
CN104420480B (zh) | 湿陷性黄土地区综合管网的布置方法及结构 | |
CN107794942B (zh) | 一种下穿河床综合管廊结构的施工方法 | |
CN102296572B (zh) | 坝后设弃渣场的土石坝坝体渗流监测结构及其施工方法 | |
CN102660936A (zh) | 一种用聚氯乙烯膜进行坝墙防渗的方法 | |
CN102433865A (zh) | 半地下式电站厂房上游侧墙体的建造方法 | |
CN104120686A (zh) | 一种高弹模垫座式复合坝 | |
CN202787334U (zh) | 一种隧道施工中深井管的封闭结构 | |
CN104131576B (zh) | 一种止水帷幕抗渗构造的施工方法 | |
CN208981282U (zh) | 一种高地震区混凝土面板堆石坝坝顶结构 | |
CN204326059U (zh) | 一种软土地层地下连续墙混凝土灌注施工结构 | |
CN104214454B (zh) | 固废处理场渗滤液导排管与穿坝管连接结构及施工方法 | |
CN202416274U (zh) | 半地下式电站厂房上游侧墙体结构 | |
CN205875096U (zh) | 一种堆石自溃坝 | |
CN218622343U (zh) | 一种预埋减压泄水机构 | |
CN205330162U (zh) | 一种预制叠合楼板预埋管道止水装置 | |
CN204343283U (zh) | 软土地层地下连续墙施工结构 | |
CN101705668B (zh) | 可在动水中修建的壅水水工建筑物结构及其施工方法 | |
CN103015405A (zh) | 一种地下连续墙防渗漏方法 | |
CN107940102B (zh) | 地下原水管道保护施工方法 | |
CN103993609B (zh) | 硅灰砂导排滤水多功能快硬凝结体人工修补基坑止水帷幕 | |
CN105672251A (zh) | 一种骑跨现有污水管的地下连续墙槽段施工方法 | |
CN101812853B (zh) | 游泳池基础主动抗浮施工方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C12 | Rejection of a patent application after its publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20120502 |