CN102403674A CN2011103413498A CN201110341349A CN102403674A CN 102403674 A CN102403674 A CN 102403674A CN 2011103413498 A CN2011103413498 A CN 2011103413498A CN 201110341349 A CN201110341349 A CN 201110341349A CN 102403674 A CN102403674 A CN 102403674A
Authority
CN
China
Prior art keywords
support
live
hoop
cross arm
wire work
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2011103413498A
Other languages
Chinese (zh)
Other versions
CN102403674B (en
Inventor
张建华
张立学
李军
王世成
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
HULUDAO POWER SUPPLY COMPANY LIAONING ELECTRIC POWER Co Ltd
State Grid Corp of China SGCC
Original Assignee
HULUDAO POWER SUPPLY COMPANY LIAONING ELECTRIC POWER Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by HULUDAO POWER SUPPLY COMPANY LIAONING ELECTRIC POWER Co Ltd filed Critical HULUDAO POWER SUPPLY COMPANY LIAONING ELECTRIC POWER Co Ltd
Priority to CN201110341349.8A priority Critical patent/CN102403674B/en
Publication of CN102403674A publication Critical patent/CN102403674A/en
Application granted granted Critical
Publication of CN102403674B publication Critical patent/CN102403674B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The invention provides a live-wire work insulating cross arm. A hoop is retained on a pole through a jackscrew; supports are mounted outwards and slantwise on the hoop at intervals of 120 degrees through a support-hoop connector; a support rope tying head is arranged at the upper end of the support; a diameter adjusting hoop is connected to the upper portion of the hoop; a center rod is connected to the upper portion of the diameter adjusting hoop; a support center head is arranged at the upper end of the center rod; a pull rope is connected between the support center head and the support rope tying head; a hook pulley is connected to each support rope tying head through a rope; and a hook is tied to the lower portion of the hook pulley. The live-wire work insulating cross arm is capable of replacing a lead through live-wire work, and also capable of effectively controlling the air gaps and safe distances between the lead and the cross arm and other wires arranged in parallel on the same pole; in short, the live-wire work insulating cross arm is convenient to mount, simple to operate, and universal to multiple layers of leads. Besides, the live-wire work insulating cross arm is applicable to mounting leads through live-live work on a power transmission device.

Description

A kind of live line working insulator crossarm
Technical field
The present invention is to provide the power transmission lines fixture of electric field, specifically a kind of live line working insulator crossarm.
Background technology
Domestic existing 10kV live line working insulator crossarm can't effectively use at present, exists unsafe drawback, has not only increased operating personnel's hazards but also has not had the requirement that improves power supply reliability again.And need to have a power failure and change insulator crossarm, reduced operating efficiency.
Summary of the invention
In order to overcome the shortcoming of existing insulator crossarm, the invention provides a kind of live line working insulator crossarm.This cross-arm is through installing leg-of-mutton support on electric pole, installation lifting rope pulley and suspension hook lift lead on each support, solve the technical problem of the charged installation of lead.
The scheme that technical solution problem of the present invention is adopted is:
On electric pole, be installed with anchor ear, be separated by 120 ° on the anchor ear, be provided with the stent bolt fag end in the support upper end through support and the outward-dipping support that is equipped with of anchor ear link through jackscrew; Be connected with the diameter adjustment hoop on anchor ear top; Diameter adjustment hoop top is connected with center pole, is provided with the carriage center head in the center pole upper end, is connected with stay cord between carriage center head and the stent bolt fag end; On each stent bolt fag end, be connected with lifting hook pulley through rope, bolt has suspension hook in the bottom of lifting hook pulley.The square tube that support adopts epoxy resin composite material to process.
Good effect, the present invention is when the charged for replacement lead, and the vertical load that original cross-arm is carried lead is transferred on the insulator crossarm, guarantees the lead secure.And utilize up-down on the insulator crossarm device with the height lifting or the reduction in various degree of three-phase conducting wire.The effectively air gap of other circuit of pilot and cross-arm and parallel lines on same tower and safe distance have the advantages that easy for installation, simple to operate, multi-layer conductor leads can both be general.Suiting on power transmission device, to be used for charged installation lead uses.
Description of drawings
Fig. 1 is insulator crossarm configuration state figure of the present invention
Among the figure, 0. electric pole, 1. anchor ear, 2. support, 2.1. support and anchor ear link, 2.2. stent bolt fag end, 3. diameter adjustment hoop, 4. carriage center head, 5. stay cord, 6. suspension pulley, 6.1. suspension hook, 7. center pole.
Embodiment
On electric pole, be installed with anchor ear 1 through jackscrew; Be separated by 120 ° on the anchor ear through support and the anchor ear link 2.1 outward-dipping supports 2 that are equipped with; Be provided with stent bolt fag end 2.2 in the support upper end, be connected with diameter adjustment hoop 3 on anchor ear top, diameter adjustment hoop top is connected with center pole 7; Be provided with carriage center 4 in center pole upper end; Be connected with stay cord 5 between carriage center head and the stent bolt fag end, on each stent bolt fag end, be connected with lifting hook pulley 6 through rope, bolt has suspension hook 6.1 in the bottom of lifting hook pulley.
The square tube that support adopts epoxy resin composite material to process guarantees insulation property.
Use of the present invention:
The lead of installing is in advance fastened on suspension hook, and the pulling rope makes the suspension hook setting height of slinging, and carries out charged installation lead.According to the length of cross-arm, through pulling up and the center pole that falls, the angle of support and electric pole is increased or dwindle, thereby change two at a distance of the distance between the support, realize adapting to the requirement of cross-arm length.
Cross-arm is used for the pull-up lead.Through the length of degree of tightness stay cord and the rope lengths on lifting hook pulley top, can make unsettled lead reach setting height.
Utilize existing insulator crossarm that it is combined into triangle and sling lead, the characteristic through mechanics is decomposed the vertical load of lead, makes the upper and lower convergent-divergent of lead through stringing again.Can make the vertical range of lead reach suitable operation height.
Be fixed on the fulcrum bottom of discipline lead on the anchor ear of holding electric pole tightly, lock anchor ear, prevent that insulator crossarm from waving with jackscrew.
Characteristics of the present invention:
1, industrial frequency withstand voltage 45KV did not have punch-through in 1 minute.
2, mechanical strength and hot strength reach the specification technique index.
3, insulation property reach the specification technique index.
4, restringing under can electriferous state.
When the present invention can the charged for replacement lead, the vertical load that original cross-arm is carried lead was transferred on the insulator crossarm, assurance lead secure.And the up-down on the insulator crossarm device capable of using is with the height lifting or the reduction in various degree of three-phase conducting wire.The effectively air gap of other circuit of pilot and cross-arm and parallel lines on same tower and safe distance have the advantages that easy for installation, simple to operate, multi-layer conductor leads can both be general.Overcome the difficulty of all straight line poles replacing cross-arms.

Claims (2)

1. live line working insulator crossarm; It is characterized in that: go up at electric pole (0) and be installed with anchor ear (1), be separated by 120 ° on the anchor ear, be provided with stent bolt fag end (2.2) in the support upper end through support and the outward-dipping support (2) that is equipped with of anchor ear link (2.1) through jackscrew; Be connected with diameter adjustment hoop (3) on anchor ear top; Diameter adjustment hoop top is connected with center pole (7), is provided with carriage center head (4) in the center pole upper end, is connected with stay cord (5) between carriage center head and the stent bolt fag end; On each stent bolt fag end, be connected with lifting hook pulley (6) through rope, bolt has suspension hook (6.1) in the bottom of lifting hook pulley.
2. a kind of live line working cross-arm according to claim 1 is characterized in that: the square tube that support adopts epoxy resin composite material to process.
CN201110341349.8A 2011-11-02 2011-11-02 A kind of live-wire work insulating cross arm Active CN102403674B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201110341349.8A CN102403674B (en) 2011-11-02 2011-11-02 A kind of live-wire work insulating cross arm

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201110341349.8A CN102403674B (en) 2011-11-02 2011-11-02 A kind of live-wire work insulating cross arm

Publications (2)

Publication Number Publication Date
CN102403674A true CN102403674A (en) 2012-04-04
CN102403674B CN102403674B (en) 2015-09-09

Family

ID=45885597

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201110341349.8A Active CN102403674B (en) 2011-11-02 2011-11-02 A kind of live-wire work insulating cross arm

Country Status (1)

Country Link
CN (1) CN102403674B (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106099747A (en) * 2016-06-24 2016-11-09 国网山东省电力公司济南供电公司 Livewire work conduction wire riser
CN106602459A (en) * 2016-11-28 2017-04-26 国家电网公司 Movable support of insulating operating rod
CN110697590A (en) * 2019-11-13 2020-01-17 国网上海市电力公司 Wire lifting device for electrified pole erection removal and ground potential pole erection removal method
CN114075891A (en) * 2021-11-29 2022-02-22 山东广域科技有限责任公司 Auxiliary mounting device for electric pole cross arm
CN114914845A (en) * 2022-03-14 2022-08-16 国网山东省电力公司聊城供电公司 Live-line operation repairing tool for overhead line

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4973795A (en) * 1989-11-09 1990-11-27 Sharpe Robert F Temporary transmission hot line crossarm and method of replacing transmission hot line crossarms
JPH0833136A (en) * 1994-07-11 1996-02-02 Fujikura Ltd Electric wire lifting method at suspension support
JP2002281624A (en) * 2001-03-22 2002-09-27 Chubu Electric Power Co Inc Derrick apparatus for use in working at summit of transmission steel tower
CN2591814Y (en) * 2002-09-04 2003-12-10 山东鲁能智能技术有限公司 Adjustable supporting device
CN201199612Y (en) * 2008-03-28 2009-02-25 安徽省电力公司滁州供电公司 Insulating cross-arm raiser for 10kV distributing line
CN201601455U (en) * 2009-12-04 2010-10-06 河南省电力公司洛阳供电公司 Insulation crossarm
CN201694757U (en) * 2010-06-22 2011-01-05 江苏省电力公司徐州供电公司 Rotation type lifting device
CN102191874A (en) * 2011-03-25 2011-09-21 河南省电力公司郑州供电公司 Insulating cross arm with movable arc grooves
CN202308978U (en) * 2011-11-02 2012-07-04 辽宁省电力有限公司葫芦岛供电公司 Live working insulated cross arm

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4973795A (en) * 1989-11-09 1990-11-27 Sharpe Robert F Temporary transmission hot line crossarm and method of replacing transmission hot line crossarms
JPH0833136A (en) * 1994-07-11 1996-02-02 Fujikura Ltd Electric wire lifting method at suspension support
JP2002281624A (en) * 2001-03-22 2002-09-27 Chubu Electric Power Co Inc Derrick apparatus for use in working at summit of transmission steel tower
CN2591814Y (en) * 2002-09-04 2003-12-10 山东鲁能智能技术有限公司 Adjustable supporting device
CN201199612Y (en) * 2008-03-28 2009-02-25 安徽省电力公司滁州供电公司 Insulating cross-arm raiser for 10kV distributing line
CN201601455U (en) * 2009-12-04 2010-10-06 河南省电力公司洛阳供电公司 Insulation crossarm
CN201694757U (en) * 2010-06-22 2011-01-05 江苏省电力公司徐州供电公司 Rotation type lifting device
CN102191874A (en) * 2011-03-25 2011-09-21 河南省电力公司郑州供电公司 Insulating cross arm with movable arc grooves
CN202308978U (en) * 2011-11-02 2012-07-04 辽宁省电力有限公司葫芦岛供电公司 Live working insulated cross arm

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106099747A (en) * 2016-06-24 2016-11-09 国网山东省电力公司济南供电公司 Livewire work conduction wire riser
CN106099747B (en) * 2016-06-24 2018-02-16 国网山东省电力公司济南供电公司 Livewire work conduction wire riser
CN106602459A (en) * 2016-11-28 2017-04-26 国家电网公司 Movable support of insulating operating rod
CN110697590A (en) * 2019-11-13 2020-01-17 国网上海市电力公司 Wire lifting device for electrified pole erection removal and ground potential pole erection removal method
CN114075891A (en) * 2021-11-29 2022-02-22 山东广域科技有限责任公司 Auxiliary mounting device for electric pole cross arm
CN114914845A (en) * 2022-03-14 2022-08-16 国网山东省电力公司聊城供电公司 Live-line operation repairing tool for overhead line

Also Published As

Publication number Publication date
CN102403674B (en) 2015-09-09

Similar Documents

Publication Publication Date Title
CN104158049B (en) A kind of earthing clamp device and operational method thereof
CN102420401B (en) Triangular insulating hanging fulcrum bar
CN102403674B (en) A kind of live-wire work insulating cross arm
WO2012088987A1 (en) Maintenance tool for insulator of direct current transmission line
CN201323409Y (en) Tool for live line replacing of high voltage transmission line V-shaped insulator chain
CN104505766A (en) Tool and method for live replacement of 500kV strain insulator strings in substations
CN204885990U (en) Transmission line yoke plate hoisting device
CN106451214B (en) A kind of combination tool of charged for replacement extra-high voltage same tower double circuit strain insulator
CN102938545A (en) Device enabling erected line of 10 KV distribution network to cross optical cable
CN203103882U (en) Insulation bracing frame for live 10kV cable lead disconnection and connection operation
CN102761077B (en) Insulating hoisting bracket for strain insulator string of 1000kV extra-high alternating current line
CN202308978U (en) Live working insulated cross arm
CN105133916A (en) Auxiliary hanging bracket for mounting of upper frame on telegraph pole
CN102881440B (en) Transformer bushing outgoing line installation frame
CN104283156B (en) Wire lifting device for power distribution line
CN202353100U (en) Triangular insulation lifting strut
CN217281883U (en) Insulating pull rod for protecting live-wire stringing
CN204793832U (en) Join in marriage electrified maintenance in many loop lines of net way and carry lineman's utensil
CN103606849A (en) Multi-bundled live conductor lifting device for transmission tower and special fixture of multi-bundled live conductor lifting device
CN104113014A (en) Upward carrying wire lifting trolley
CN204290154U (en) A kind of replacing insulator under electrified specific purpose tool
CN204179565U (en) A kind of steel tower power transmission line jockey
CN103809011A (en) Lightning arrester resistive-current testing tool
CN203277934U (en) Grounding wire
CN201312079Y (en) Clamping apparatus for live line replacement of suspended insulator in middle of 500KV untypical tangent tower via splicing method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
ASS Succession or assignment of patent right

Owner name: STATE GRID CORPORATION OF CHINA

Effective date: 20121212

C41 Transfer of patent application or patent right or utility model
TA01 Transfer of patent application right

Effective date of registration: 20121212

Address after: 125000 Huludao City, Liaoning province Longgang district on the road No. 5

Applicant after: Huludao Power Supply Company, Liaoning Electric Power Co., Ltd.

Applicant after: State Grid Corporation of China

Address before: 125000 Huludao City, Liaoning province Longgang district on the road No. 5

Applicant before: Huludao Power Supply Company, Liaoning Electric Power Co., Ltd.

C53 Correction of patent of invention or patent application
CB03 Change of inventor or designer information

Inventor after: Zhang Jianhua

Inventor after: Zhang Lixue

Inventor after: Li Jun

Inventor after: Wang Shicheng

Inventor after: Chen Yu

Inventor before: Zhang Jianhua

Inventor before: Zhang Lixue

Inventor before: Li Jun

Inventor before: Wang Shicheng

COR Change of bibliographic data

Free format text: CORRECT: INVENTOR; FROM: ZHANG JIANHUA ZHANG LIXUE LI JUN WANG SHICHENG TO: ZHANG JIANHUA ZHANG LIXUE LI JUN WANG SHICHENG CHEN YU

C14 Grant of patent or utility model
GR01 Patent grant