CN102403674B - A kind of live-wire work insulating cross arm - Google Patents
A kind of live-wire work insulating cross arm Download PDFInfo
- Publication number
- CN102403674B CN102403674B CN201110341349.8A CN201110341349A CN102403674B CN 102403674 B CN102403674 B CN 102403674B CN 201110341349 A CN201110341349 A CN 201110341349A CN 102403674 B CN102403674 B CN 102403674B
- Authority
- CN
- China
- Prior art keywords
- bracket
- hoop
- head
- rope
- wires
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 239000000725 suspension Substances 0.000 claims description 5
- 239000002131 composite material Substances 0.000 claims description 3
- 239000003822 epoxy resin Substances 0.000 claims description 3
- 229920000647 polyepoxide Polymers 0.000 claims description 3
- 238000009434 installation Methods 0.000 abstract description 7
- 230000005540 biological transmission Effects 0.000 abstract description 3
- 230000005611 electricity Effects 0.000 abstract description 3
- 239000004020 conductor Substances 0.000 description 6
- 238000009413 insulation Methods 0.000 description 2
- 238000000034 method Methods 0.000 description 2
- 230000015556 catabolic process Effects 0.000 description 1
- 230000003247 decreasing effect Effects 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 230000005684 electric field Effects 0.000 description 1
- 230000008092 positive effect Effects 0.000 description 1
- 238000013341 scale-up Methods 0.000 description 1
Landscapes
- Electric Cable Installation (AREA)
Abstract
本发明提供的是一种带电作业绝缘横担。在电杆上通过顶丝卡装有抱箍,抱箍上相隔120°通过支架与抱箍连接架向外倾斜安装有支架,在支架上端设有支架栓绳头,在抱箍上部连接有直径调节箍,直径调节箍上部连接有中心杆,在中心杆上端设有支架中心头,支架中心头与支架栓绳头之间连接有拉绳,在每个支架栓绳头上通过绳索连接有吊钩滑轮,在吊钩滑轮的下部栓有吊钩。本发明能够带电更换导线,能够有效的控制导线与横担及同杆并架的其它线路的空气间隙和安全距离,具有安装方便、操作简单、多层导线都能够通用的特点。适宜在电力输送装置上用于带电安装导线中应用。
The invention provides an insulating cross arm for live work. A hoop is installed on the pole through the top wire clip, and a bracket is installed on the hoop at an interval of 120° through the bracket and the hoop connecting frame to tilt outwards. A bracket tether head is provided on the upper end of the bracket, and a diameter is connected to the upper part of the hoop. Adjusting hoop, the upper part of the diameter adjusting hoop is connected with a center rod, the upper end of the center rod is provided with a bracket center head, a pull rope is connected between the bracket center head and the bracket tethering head, and a hanging rope is connected to each bracket tethering head through a rope. The hook pulley is bolted with a hook at the bottom of the hook pulley. The invention can replace the wires with electricity, can effectively control the air gap and safety distance between the wires and the cross arm and other lines on the same pole, and has the characteristics of convenient installation, simple operation, and multi-layer wires can be used universally. It is suitable for use in live installation wires on power transmission devices.
Description
技术领域 technical field
本发明提供的是电气领域的电力传输线路安装用具,具体地说是一种带电作业绝缘横担。 The invention provides a power transmission line installation tool in the electrical field, in particular an insulating cross arm for live work.
背景技术 Background technique
目前国内现有的10kV带电作业绝缘横担无法有效使用,存在着不安全的弊端,不仅增加了作业人员的危险因素而且又起不到提高供电可靠性的要求。且需要停电更换绝缘横担,降低了工作效率。 At present, the existing domestic 10kV live working insulating cross arm cannot be used effectively, and there are disadvantages of unsafety, which not only increases the risk factors of operators, but also fails to meet the requirements of improving the reliability of power supply. And it is necessary to cut off the power to replace the insulating cross arm, which reduces the work efficiency.
发明内容 Contents of the invention
为了克服现有绝缘横担的缺点,本发明提供了一种带电作业绝缘横担。该横担通过在电杆上安装三角形的支架,在每个支架上安装吊绳滑轮和吊钩进行吊装导线,解决导线带电安装的技术问题。 In order to overcome the shortcomings of the existing insulating cross-arm, the invention provides an insulating cross-arm for live work. The cross arm solves the technical problem of live wire installation by installing triangular brackets on the pole, and installing rope pulleys and hooks on each bracket to hoist the wires.
本发明解决技术问题所采用的方案是: The scheme that the present invention solves technical problem adopts is:
在电杆上通过顶丝卡装有抱箍,抱箍上相隔120°通过支架与抱箍连接架向外倾斜安装有支架,在支架上端设有支架栓绳头,在抱箍上部连接有直径调节箍,直径调节箍上部连接有中心杆,在中心杆上端设有支架中心头,支架中心头与支架栓绳头之间连接有拉绳,在每个支架栓绳头上通过绳索连接有吊钩滑轮,在吊钩滑轮的下部栓有吊钩。支架采用环氧树脂复合材料制成的方管。 A hoop is installed on the pole through the top wire clip, and a bracket is installed on the hoop at an interval of 120° through the bracket and the hoop connecting frame to tilt outwards. A bracket tether head is provided on the upper end of the bracket, and a diameter is connected to the upper part of the hoop. Adjusting hoop, the upper part of the diameter adjusting hoop is connected with a center rod, the upper end of the center rod is provided with a bracket center head, a pull rope is connected between the bracket center head and the bracket tethering head, and a hanging rope is connected to each bracket tethering head through a rope. The hook pulley is bolted with a hook at the bottom of the hook pulley. The bracket is a square tube made of epoxy resin composite material.
积极效果,本发明在带电更换导线时,将原有的横担承载导线的垂直荷重转移到绝缘横担上来,保证导线稳固可靠。并且利用绝缘横担装置上的升降将三相导线的高度不同程度的提升或降低。能够有效的控制导线与横担及同杆并架的其它线路的空气间隙和安全距离,具有安装方便、操作简单、多层导线都能够通用的特点。适宜在电力输送装置上用于带电安装导线中应用。 The positive effect is that the present invention transfers the vertical load of the original cross-arm carrying the wire to the insulating cross-arm when the wire is replaced with electricity, ensuring that the wire is stable and reliable. And the height of the three-phase wires can be raised or lowered to varying degrees by using the lifting on the insulating cross-arm device. It can effectively control the air gap and safety distance between the conductor and the cross-arm and other lines paralleled on the same pole. It has the characteristics of convenient installation, simple operation, and universal multi-layer conductors. It is suitable for use in live installation wires on power transmission devices.
附图说明 Description of drawings
图1为本发明绝缘横担结构状态图 Fig. 1 is the state diagram of the insulating cross-arm structure of the present invention
图中,0.电杆,1.抱箍,2.支架,2.1.支架与抱箍连接架,2.2.支架栓绳头,3.直径调节箍,4.支架中心头,5.拉绳,6.悬吊滑轮,6.1.吊钩,7.中心杆。 In the figure, 0. Pole, 1. Hoop, 2. Bracket, 2.1. Bracket and hoop connecting frame, 2.2. Bracket tie rope head, 3. Diameter adjustment hoop, 4. Bracket center head, 5. Pull rope, 6. Suspension pulley, 6.1. Hook, 7. Center rod.
具体实施方式 Detailed ways
在电杆上通过顶丝卡装有抱箍1,抱箍上相隔120°通过支架与抱箍连接架2.1向外倾斜安装有支架2,在支架上端设有支架栓绳头2.2,在抱箍上部连接有直径调节箍3,直径调节箍上部连接有中心杆7,在中心杆上端设有支架中心头4,支架中心头与支架栓绳头之间连接有拉绳5,在每个支架栓绳头上通过绳索连接有吊钩滑轮6,在吊钩滑轮的下部栓有吊钩6.1。 A hoop 1 is installed on the pole through a top wire clip, and a bracket 2 is installed on the hoop at a distance of 120° through the bracket and the hoop connecting frame 2.1. The upper part is connected with a diameter adjustment hoop 3, and the upper part of the diameter adjustment hoop is connected with a center rod 7, and the upper end of the center rod is provided with a bracket center head 4, and a stay rope 5 is connected between the bracket center head and the bracket tie rope head. Be connected with suspension hook pulley 6 by rope on the rope end, be bolted with suspension hook 6.1 at the bottom of suspension hook pulley.
支架采用环氧树脂复合材料制成的方管,保证绝缘性能。 The bracket adopts a square tube made of epoxy resin composite material to ensure insulation performance.
本发明的使用过程: The use process of the present invention:
将预安装的导线拴在吊钩上,拉动绳索,使吊钩吊起到设定高度,进行带电安装导线。根据横担的长度,通过拔起和下落中心杆,使支架与电杆的夹角增大或缩小,从而改变两相距支架之间的距离,实现适应横担长度的要求。 Tie the pre-installed wires to the hook, pull the rope to lift the hook to the set height, and install the wires live. According to the length of the cross arm, the angle between the bracket and the pole is increased or decreased by pulling up and down the center pole, thereby changing the distance between the two supports to meet the requirements of the length of the cross arm.
横担用于拉起导线。通过松紧拉绳的长度和吊钩滑轮上部的绳索长度,能够使悬空导线达到设定高度。 The cross arm is used to pull up the wire. By the length of the elastic stay rope and the length of the rope on the upper part of the hook pulley, the suspended conductor can reach the set height.
利用已有的绝缘横担将其组合成三角形把导线吊起,通过力学的特性使导线的垂直荷重进行分解,再通过紧线使导线上、下缩放。能够使导线的垂直距离达到适当作业高度。 Use the existing insulating cross-arms to combine them into triangles to lift the wires, decompose the vertical load of the wires through the mechanical characteristics, and then make the wires scale up and down by tightening the wires. It can make the vertical distance of the wire reach the proper working height.
把中项导线的支点底端固定在抱紧电杆的抱箍上,用顶丝锁紧抱箍,防止绝缘横担摇摆。 Fix the bottom end of the fulcrum of the middle conductor on the hoop that holds the pole tightly, and lock the hoop with the top wire to prevent the insulating cross arm from swinging.
本发明的特点: Features of the present invention:
1、工频耐压45KV,1分钟内无击穿现象。 1. The power frequency withstand voltage is 45KV, and there is no breakdown within 1 minute.
2、机械强度和拉伸强度达到规范技术指标。 2. The mechanical strength and tensile strength meet the standard technical indicators.
3、绝缘性能达到规范技术指标。 3. The insulation performance reaches the standard technical index.
4、能够带电状态下更换导线。 4. The wire can be replaced under the charged state.
本发明能够带电更换导线时,将原有的横担承载导线的垂直荷重转移到绝缘横担上来,保证导线稳固可靠。并且可利用绝缘横担装置上的升降将三相导线的高度不同程度的提升或降低。能够有效的控制导线与横担及同杆并架的其它线路的空气间隙和安全距离,具有安装方便、操作简单、多层导线都能够通用的特点。克服了所有直线杆更换横担的困难。 The invention can transfer the vertical load of the original cross arm carrying the wire to the insulating cross arm when the wire is replaced with electricity, so as to ensure the stability and reliability of the wire. And the height of the three-phase wires can be raised or lowered to varying degrees by using the lifting on the insulating cross-arm device. It can effectively control the air gap and safety distance between the conductor and the cross-arm and other lines paralleled on the same pole. It has the characteristics of convenient installation, simple operation, and universal multi-layer conductors. It overcomes the difficulty of replacing the cross arm with all straight rods.
Claims (2)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201110341349.8A CN102403674B (en) | 2011-11-02 | 2011-11-02 | A kind of live-wire work insulating cross arm |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201110341349.8A CN102403674B (en) | 2011-11-02 | 2011-11-02 | A kind of live-wire work insulating cross arm |
Publications (2)
Publication Number | Publication Date |
---|---|
CN102403674A CN102403674A (en) | 2012-04-04 |
CN102403674B true CN102403674B (en) | 2015-09-09 |
Family
ID=45885597
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201110341349.8A Active CN102403674B (en) | 2011-11-02 | 2011-11-02 | A kind of live-wire work insulating cross arm |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102403674B (en) |
Families Citing this family (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106099747B (en) * | 2016-06-24 | 2018-02-16 | 国网山东省电力公司济南供电公司 | Livewire work conduction wire riser |
CN106602459A (en) * | 2016-11-28 | 2017-04-26 | 国家电网公司 | Movable support of insulating operating rod |
CN110697590B (en) * | 2019-11-13 | 2024-05-07 | 国网上海市电力公司 | Wire lifting device for electrified vertical removing pole and ground potential vertical removing method |
CN114075891B (en) * | 2021-11-29 | 2023-05-26 | 山东广域科技有限责任公司 | Auxiliary installation device for cross arm of electric pole |
CN114914845B (en) * | 2022-03-14 | 2024-05-24 | 国网山东省电力公司聊城供电公司 | A live working and inspection tool for overhead lines |
CN115021142B (en) * | 2022-05-06 | 2024-08-09 | 国网山东省电力公司青岛供电公司 | Tool for replacing top cap of 10kV distribution line pole in electrified mode and replacement method |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4973795A (en) * | 1989-11-09 | 1990-11-27 | Sharpe Robert F | Temporary transmission hot line crossarm and method of replacing transmission hot line crossarms |
CN201199612Y (en) * | 2008-03-28 | 2009-02-25 | 安徽省电力公司滁州供电公司 | 10kV distribution line insulation cross-arm lifter |
CN201601455U (en) * | 2009-12-04 | 2010-10-06 | 河南省电力公司洛阳供电公司 | Insulated cross arm |
CN102191874A (en) * | 2011-03-25 | 2011-09-21 | 河南省电力公司郑州供电公司 | Insulating cross arm with movable arc grooves |
CN202308978U (en) * | 2011-11-02 | 2012-07-04 | 辽宁省电力有限公司葫芦岛供电公司 | Live working insulated cross arm |
Family Cites Families (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP3401751B2 (en) * | 1994-07-11 | 2003-04-28 | 株式会社フジクラ | How to transfer electric wires from wire-drawing wheel to suspension clamp at the time of work on tight line |
JP4349604B2 (en) * | 2001-03-22 | 2009-10-21 | 中部電力株式会社 | Derrick device for top work of transmission tower |
CN2591814Y (en) * | 2002-09-04 | 2003-12-10 | 山东鲁能智能技术有限公司 | Adjustable supporting device |
CN201694757U (en) * | 2010-06-22 | 2011-01-05 | 江苏省电力公司徐州供电公司 | A rotary lifting device |
-
2011
- 2011-11-02 CN CN201110341349.8A patent/CN102403674B/en active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4973795A (en) * | 1989-11-09 | 1990-11-27 | Sharpe Robert F | Temporary transmission hot line crossarm and method of replacing transmission hot line crossarms |
CN201199612Y (en) * | 2008-03-28 | 2009-02-25 | 安徽省电力公司滁州供电公司 | 10kV distribution line insulation cross-arm lifter |
CN201601455U (en) * | 2009-12-04 | 2010-10-06 | 河南省电力公司洛阳供电公司 | Insulated cross arm |
CN102191874A (en) * | 2011-03-25 | 2011-09-21 | 河南省电力公司郑州供电公司 | Insulating cross arm with movable arc grooves |
CN202308978U (en) * | 2011-11-02 | 2012-07-04 | 辽宁省电力有限公司葫芦岛供电公司 | Live working insulated cross arm |
Also Published As
Publication number | Publication date |
---|---|
CN102403674A (en) | 2012-04-04 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102403674B (en) | A kind of live-wire work insulating cross arm | |
CN107069562B (en) | Replacing insulator under electrified method and load transfer device | |
CN201323409Y (en) | Tool for live line replacing of high voltage transmission line V-shaped insulator chain | |
CN103066526B (en) | A kind of ground connection line method and separated earthing instrument for ultra-high-tension power transmission line | |
CN105162028A (en) | Method for replacing linear insulator of 220kV steel pipe tower in live working state | |
CN103887735A (en) | Linear charged wire lifting device of electric transmission line | |
CN203787855U (en) | A straight-line electrified wire lifting device for transmission lines | |
CN102916372B (en) | 10kV multi-circuit lines on the same pole mesophase spherule wire lifting instrument | |
CN103746316B (en) | A device and method for live replacement of straight-line corner tower insulator strings | |
CN202308978U (en) | Live working insulated cross arm | |
CN104283156B (en) | Wire lifting device for power distribution line | |
CN210779825U (en) | Device for replacing whole string of tension insulators at cross arm end and wire end of direct-current transmission line | |
CN109904824B (en) | Small wire line lifting cross arm | |
CN203839885U (en) | 10kV/35kV double-loop straight-line electrified pole replacing device | |
CN102354929A (en) | V-shaped insulator string suspension device | |
CN205544113U (en) | Cross arm for transmission tower | |
CN204983880U (en) | Supplementary gallows of wire pole roof -rack installation | |
CN202276117U (en) | Hanging device for V-shaped insulator strips | |
CN201312079Y (en) | Clamping apparatus for live line replacement of suspended insulator in middle of 500KV untypical tangent tower via splicing method | |
CN203932824U (en) | The glass insulator strings elevator system of dangling | |
CN202550391U (en) | High-voltage power maintenance implement | |
CN103606849A (en) | Multi-bundled live conductor lifting device for transmission tower and special fixture of multi-bundled live conductor lifting device | |
CN204118597U (en) | A kind of line lifter for distribution line | |
CN201674161U (en) | SZ type double-circuit straight line tower live replacement suspension insulator suspension wire fixture assembly | |
CN105633888A (en) | Cross arm for transmission tower |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
ASS | Succession or assignment of patent right |
Owner name: STATE GRID CORPORATION OF CHINA Effective date: 20121212 |
|
C41 | Transfer of patent application or patent right or utility model | ||
TA01 | Transfer of patent application right |
Effective date of registration: 20121212 Address after: 125000 Huludao City, Liaoning province Longgang district on the road No. 5 Applicant after: Huludao Power Supply Company, Liaoning Electric Power Co., Ltd. Applicant after: State Grid Corporation of China Address before: 125000 Huludao City, Liaoning province Longgang district on the road No. 5 Applicant before: Huludao Power Supply Company, Liaoning Electric Power Co., Ltd. |
|
C53 | Correction of patent for invention or patent application | ||
CB03 | Change of inventor or designer information |
Inventor after: Zhang Jianhua Inventor after: Zhang Lixue Inventor after: Li Jun Inventor after: Wang Shicheng Inventor after: Chen Yu Inventor before: Zhang Jianhua Inventor before: Zhang Lixue Inventor before: Li Jun Inventor before: Wang Shicheng |
|
COR | Change of bibliographic data |
Free format text: CORRECT: INVENTOR; FROM: ZHANG JIANHUA ZHANG LIXUE LI JUN WANG SHICHENG TO: ZHANG JIANHUA ZHANG LIXUE LI JUN WANG SHICHENG CHEN YU |
|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |