CN201601455U - Insulated cross arm - Google Patents
Insulated cross arm Download PDFInfo
- Publication number
- CN201601455U CN201601455U CN2009202765093U CN200920276509U CN201601455U CN 201601455 U CN201601455 U CN 201601455U CN 2009202765093 U CN2009202765093 U CN 2009202765093U CN 200920276509 U CN200920276509 U CN 200920276509U CN 201601455 U CN201601455 U CN 201601455U
- Authority
- CN
- China
- Prior art keywords
- cross
- cross bar
- arc
- arm
- live
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Insulators (AREA)
Abstract
本实用新型公开的绝缘横担由横杆(1)、弧形连接件(2)、链锁(3)及卡槽(4)构成,横杆为圆形中空结构,采用复合绝缘材料制作,在所述横杆的中间部位设置有弧形连接件,在该弧形连接件两侧的横杆上分别固定连接有链锁用于与电杆固定连接,在所述横杆的两边端分别设置有卡槽用于固定导线。本实用新型解决了带电作业中带电更换10KV架空线路单横担中绝缘工具与电杆铁横担不匹配的问题,由于其为中空结构,且采用复合绝缘材料制作,不仅重量轻、安装方便、耐压性能高、强度大、伸缩范围大(链锁使用电杆长度在
左右)、经济实用,而且提高了带电作业的安全系数和带电作业的工作效率。The insulating cross arm disclosed by the utility model is composed of a cross bar (1), an arc-shaped connector (2), a chain lock (3) and a card slot (4). The cross bar is a circular hollow structure and is made of a composite insulating material. An arc-shaped connector is arranged in the middle of the cross bar, and chain locks are respectively fixedly connected to the cross bars on both sides of the arc-shaped connector for fixed connection with the electric pole. A card slot is provided for fixing the wire. The utility model solves the problem that the insulation tool in the single cross-arm of the 10KV overhead line does not match with the electric pole iron cross-arm in the live-line operation. Because it is a hollow structure and made of composite insulating materials, it is not only light in weight, easy to install, High pressure resistance, high strength, and large expansion range (the length of the pole used for the chain lock is within
Left and right), economical and practical, and improve the safety factor of live work and the work efficiency of live work.Description
技术领域technical field
本实用新型属于配电线路带电作业用横担技术来源,主要涉及的是一种绝缘横担,适用于在10KV架空线路带电作业使用。The utility model belongs to the technical source of a cross arm for live work on distribution lines, and mainly relates to an insulating cross arm, which is suitable for live work on 10KV overhead lines.
背景技术Background technique
随着社会现代化水平的不断提高,对供电可靠性的要求也越来越高。如何才能做到不停电、少停电,满足经济社会对电力不间断供电的需求呢?大力开展配电线路带电作业是供电企业提高供电可靠率、实现不间断供电的有效措施,是城市电网减少计划停电时间、缩短故障停电时间的迫切需要,同时也在实现电网安全可靠运行、减少电能损失、提高电网经济效益方面发挥着十分积极的作用。With the continuous improvement of the level of social modernization, the requirements for power supply reliability are also getting higher and higher. How can we achieve non-stop power supply, less power outages, and meet the needs of the economy and society for uninterrupted power supply? Vigorously carrying out live work on distribution lines is an effective measure for power supply companies to improve power supply reliability and achieve uninterrupted power supply. It is an urgent need for urban power grids to reduce planned power outages and shorten fault outages. It plays a very positive role in reducing losses and improving the economic benefits of the power grid.
横担是配电线路架空线路的主要部件之一。目前,在10KV架空线路单回线路采用的横担多为铁横担,由于长年的风吹雨淋,铁横担会出现腐蚀、老化、变形等现象,如不及时更换,会增加故障停电次数,给电网运行造成安全隐患。以往在带电更换横担时,一般采用斗臂车专用的绝缘支杆进行更换。该绝缘支杆宽150mm、厚70mm、长2200mm,体积笨重,两端导线卡槽全部是金属构件,不仅会增加带电作业人员的危险系数,而且在安装时,经常出现绝缘支杆与铁横担长度不匹配的现象(绝缘支杆两端通常会超出铁横担及导线250mm左右),带电提升或回落导线非常麻烦,给作业带来了诸多不便,影响工作效率。The cross arm is one of the main components of the overhead line of the distribution line. At present, the cross-arms used in the single-circuit lines of 10KV overhead lines are mostly iron cross-arms. Due to years of wind and rain, iron cross-arms will appear corrosion, aging, deformation and other phenomena. If they are not replaced in time, failures and power outages will increase. times, causing safety hazards to the power grid operation. In the past, when the cross-arm was replaced with electricity, it was generally replaced with an insulating support rod dedicated to bucket arm vehicles. The insulating pole is 150mm wide, 70mm thick, and 2200mm long. The phenomenon of length mismatch (the two ends of the insulating pole usually exceed the iron cross arm and the wire by about 250mm), and it is very troublesome to lift or drop the wire when it is live, which brings a lot of inconvenience to the operation and affects the work efficiency.
发明内容Contents of the invention
本实用新型的目的由此产生,提出一种绝缘横担。解决带电作业中更换横担时工具与电杆铁横担不匹配的问题,增加了带电作业时的安全系数,提高了带电更换横担的工作效率,延长了横担的使用寿命。The purpose of this utility model arises thus, proposes a kind of insulating cross arm. It solves the problem that the tool does not match the electric pole iron cross arm when replacing the cross arm in live work, increases the safety factor during live work, improves the work efficiency of live cross arm replacement, and prolongs the service life of the cross arm.
本实用新型实现上述目的采取的技术方案是:其由横杆、弧形连接件、链锁及卡槽构成,横杆为圆形中空结构,采用复合绝缘材料制作,在所述横杆的中间部位设置有弧形连接件,在该弧形连接件两侧的横杆上分别固定连接有链锁用于与电杆固定连接,在所述横杆的两边端分别设置有卡槽用于固定导线。The technical solution adopted by the utility model to achieve the above purpose is: it is composed of a cross bar, an arc-shaped connector, a chain lock and a card slot. The cross bar is a circular hollow structure made of composite insulating material. There are arc-shaped connectors at the position, and chain locks are fixedly connected to the crossbars on both sides of the arc-shaped connectors for fixed connection with the electric poles. wire.
本实用新型解决了带电作业中带电更换10KV架空线路单横担中绝缘工具与电杆铁横担不匹配的问题,由于其为中空结构,且采用复合绝缘材料制作,不仅重量轻、安装方便、耐压性能高、强度大、伸缩范围大(链锁使用电杆长度在左右)、经济实用,而且提高了带电作业的安全系数和带电作业的工作效率。The utility model solves the problem that the insulation tool in the single cross-arm of the 10KV overhead line does not match with the electric pole iron cross-arm in the live-line operation. Because it is a hollow structure and made of composite insulating materials, it is not only light in weight, easy to install, High pressure resistance, high strength, and large expansion range (the length of the pole used for the chain lock is within Left and right), economical and practical, and improve the safety factor of live work and the work efficiency of live work.
附图说明Description of drawings
附图为本实用新型的结构示意图。Accompanying drawing is the structural representation of the utility model.
图中:1、横杆,2、弧形连接件,3、链锁,4、卡槽。In the figure: 1. cross bar, 2. arc connector, 3. chain lock, 4. card slot.
具体实施方式Detailed ways
结合附图,给出本实用新型的实施例如下:In conjunction with accompanying drawing, provide the embodiment of the present utility model as follows:
如图所示:本实用新型所述的绝缘横担由横杆1、弧形连接件2、链锁3及卡槽4构成,横杆1为圆形中空结构,采用复合绝缘材料制作,厚5mm、直径50mm、长1700mm,耐压45KV,承重达到70kg,均符合《电力安全规程》规定。弧形连接件2采用绝缘材料制作,套接在横杆1的中间部位,其弧形度与电杆的半圆弧相吻合。在弧形连接件2的本体上分别固定连接有链锁3用于与电杆固定连接。在横杆1的两边端分别设置有卡槽4用于固定导线,卡槽4也采用复合绝缘材料制作,在其上端设置有锁板,使用时将导线放入卡槽4用锁板固定后就可防止导线从卡槽4中滑落,进一步提高作业的安全系数和供电的可靠性。As shown in the figure: the insulating cross arm described in the utility model is composed of a
使用时,采用斗臂车在需要更换铁横担的上方400mm-600mm左右部位安装本绝缘横担,使弧形连接件2的弧形部位紧贴在电杆的弧面上,用链锁收紧固定,用斗臂车将导线放入绝缘卡槽内后,即可进行对横担的更换。When in use, use a bucket arm truck to install this insulating cross arm at the position about 400mm-600mm above the iron cross arm that needs to be replaced, so that the arc-shaped part of the arc-
Claims (2)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN2009202765093U CN201601455U (en) | 2009-12-04 | 2009-12-04 | Insulated cross arm |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN2009202765093U CN201601455U (en) | 2009-12-04 | 2009-12-04 | Insulated cross arm |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN201601455U true CN201601455U (en) | 2010-10-06 |
Family
ID=42812515
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN2009202765093U Expired - Fee Related CN201601455U (en) | 2009-12-04 | 2009-12-04 | Insulated cross arm |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN201601455U (en) |
Cited By (14)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN102191874A (en) * | 2011-03-25 | 2011-09-21 | 河南省电力公司郑州供电公司 | Insulating cross arm with movable arc grooves |
| CN102403674A (en) * | 2011-11-02 | 2012-04-04 | 辽宁省电力有限公司葫芦岛供电公司 | Live-wire work insulating cross arm |
| CN102966258A (en) * | 2012-11-30 | 2013-03-13 | 湖州电力局 | Temporary supporting crossarm for live working |
| CN103107494A (en) * | 2012-11-23 | 2013-05-15 | 重庆市电力公司江北供电局 | Conductive-wire and cable fixing supporting device |
| CN103247971A (en) * | 2013-05-24 | 2013-08-14 | 上海凡扬电力器具有限公司 | Portable three-phase conductor synchronous lifting holding pole |
| CN103510739A (en) * | 2013-10-24 | 2014-01-15 | 国网湖南省电力公司带电作业中心 | Multifunctional combinatorial insulation cross arm |
| CN104917097A (en) * | 2015-05-28 | 2015-09-16 | 国家电网公司 | Conductor lifter |
| CN105048348A (en) * | 2015-08-27 | 2015-11-11 | 国网浙江宁波市鄞州区供电公司 | Protection shielding cover of tension porcelain bottle |
| CN105048391A (en) * | 2015-08-27 | 2015-11-11 | 国网浙江宁波市鄞州区供电公司 | Shielding hood for supporting lead |
| CN105048349A (en) * | 2015-08-27 | 2015-11-11 | 国网浙江宁波市鄞州区供电公司 | Shielding hood for hot-line work |
| CN105186359A (en) * | 2015-08-27 | 2015-12-23 | 国网浙江宁波市鄞州区供电公司 | Cross-arm shielding cover |
| CN106602469A (en) * | 2017-02-16 | 2017-04-26 | 国网宁夏电力公司银川供电公司 | Overhead line insulation isolation device |
| CN107165466A (en) * | 2017-06-09 | 2017-09-15 | 江苏神马电力股份有限公司 | Composite cross arm and transmission pole |
| CN112242687A (en) * | 2020-11-04 | 2021-01-19 | 国网江苏省电力有限公司扬州市江都区供电分公司 | An adaptive cable support |
-
2009
- 2009-12-04 CN CN2009202765093U patent/CN201601455U/en not_active Expired - Fee Related
Cited By (25)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN102191874A (en) * | 2011-03-25 | 2011-09-21 | 河南省电力公司郑州供电公司 | Insulating cross arm with movable arc grooves |
| CN102191874B (en) * | 2011-03-25 | 2014-08-13 | 国家电网公司 | Insulating cross arm with movable arc grooves |
| CN102403674A (en) * | 2011-11-02 | 2012-04-04 | 辽宁省电力有限公司葫芦岛供电公司 | Live-wire work insulating cross arm |
| CN102403674B (en) * | 2011-11-02 | 2015-09-09 | 辽宁省电力有限公司葫芦岛供电公司 | A kind of live-wire work insulating cross arm |
| CN103107494A (en) * | 2012-11-23 | 2013-05-15 | 重庆市电力公司江北供电局 | Conductive-wire and cable fixing supporting device |
| CN103107494B (en) * | 2012-11-23 | 2015-07-08 | 重庆市电力公司江北供电局 | Conductive-wire and cable fixing supporting device |
| CN102966258A (en) * | 2012-11-30 | 2013-03-13 | 湖州电力局 | Temporary supporting crossarm for live working |
| CN102966258B (en) * | 2012-11-30 | 2015-06-17 | 湖州电力局 | Temporary supporting crossarm for live working |
| CN103247971A (en) * | 2013-05-24 | 2013-08-14 | 上海凡扬电力器具有限公司 | Portable three-phase conductor synchronous lifting holding pole |
| CN103247971B (en) * | 2013-05-24 | 2015-08-05 | 上海凡扬电力器具有限公司 | A kind of portable three-phase conducting wire Synchronous lifting pole |
| CN103510739A (en) * | 2013-10-24 | 2014-01-15 | 国网湖南省电力公司带电作业中心 | Multifunctional combinatorial insulation cross arm |
| CN104917097A (en) * | 2015-05-28 | 2015-09-16 | 国家电网公司 | Conductor lifter |
| CN105048348A (en) * | 2015-08-27 | 2015-11-11 | 国网浙江宁波市鄞州区供电公司 | Protection shielding cover of tension porcelain bottle |
| CN105048391A (en) * | 2015-08-27 | 2015-11-11 | 国网浙江宁波市鄞州区供电公司 | Shielding hood for supporting lead |
| CN105048349A (en) * | 2015-08-27 | 2015-11-11 | 国网浙江宁波市鄞州区供电公司 | Shielding hood for hot-line work |
| CN105186359A (en) * | 2015-08-27 | 2015-12-23 | 国网浙江宁波市鄞州区供电公司 | Cross-arm shielding cover |
| CN106602469A (en) * | 2017-02-16 | 2017-04-26 | 国网宁夏电力公司银川供电公司 | Overhead line insulation isolation device |
| CN107165466A (en) * | 2017-06-09 | 2017-09-15 | 江苏神马电力股份有限公司 | Composite cross arm and transmission pole |
| WO2018223829A1 (en) * | 2017-06-09 | 2018-12-13 | 江苏神马电力股份有限公司 | Composite cross-arm and transmission mast |
| EP3461972A4 (en) * | 2017-06-09 | 2020-03-11 | Jiangsu Shemar Electric Co., Ltd. | COMPOSITE CROSSING AND TRANSMISSION MAST |
| AU2018271335B2 (en) * | 2017-06-09 | 2020-07-02 | Jiangsu Shemar Electric Co., Ltd. | Composite cross-arm and transmission mast |
| AU2018271335B9 (en) * | 2017-06-09 | 2020-11-12 | Jiangsu Shemar Electric Co., Ltd. | Composite cross-arm and transmission mast |
| US11421437B2 (en) | 2017-06-09 | 2022-08-23 | Jiangsu Shemar Electric Co., Ltd. | Composite crossarm and transmission pole |
| CN112242687A (en) * | 2020-11-04 | 2021-01-19 | 国网江苏省电力有限公司扬州市江都区供电分公司 | An adaptive cable support |
| CN112242687B (en) * | 2020-11-04 | 2021-06-04 | 国网江苏省电力有限公司扬州市江都区供电分公司 | Self-adaptive cable support |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN201601455U (en) | Insulated cross arm | |
| CN201466635U (en) | A Composite Insulation Tower Insulation Tower Head | |
| CN102306920A (en) | Anti-oscillation arrangement and configuration method for phase-to-phase spacers of ultrahigh-voltage compact power transmission line | |
| CN202970091U (en) | 220-kilovolt same-rod two-circuit tower head full composite material steel pipe rod | |
| CN202930802U (en) | Movable type distribution transformer allowing uninterruptible power supply mounting and dismounting | |
| CN204552245U (en) | A kind of extra-high voltage direct-current tangent tower of wire vertical arrangement | |
| CN202872250U (en) | An installing clamp of a live working wire clamp | |
| CN209293540U (en) | A 110kV double-circuit lattice composite cross-arm transmission tower on the same tower | |
| CN201355752Y (en) | Insulated conductor live peeling bracket for distribution line | |
| CN201438617U (en) | Electric lifting tool for linear insulator string on ZM tower | |
| CN202039638U (en) | Lead screw lifting type insulating cross arm | |
| CN203260334U (en) | Composite-core round-aluminum-strand overhead insulated cable | |
| CN201556885U (en) | Tool for single hanging and twin suspension insulator string capable of solving problem of earth potential electrified transmission line replacement | |
| CN202042864U (en) | Unbalance insulation earthing device for half-composite pole tower | |
| CN214384849U (en) | Spacing insulating support rod | |
| CN202882514U (en) | 220-kilovolt all-angle single-circuit drilling cross tower | |
| CN202925981U (en) | 750kV composite material cross arm | |
| CN201994614U (en) | Conducting-wire expander | |
| CN201181597Y (en) | New weather-resistant overhead insulated cables with aluminum stranded conductors | |
| CN201274224Y (en) | Transformer laying construction with wire leaded out on one side | |
| CN206023125U (en) | A kind of tubular bus connector | |
| CN204258144U (en) | A kind of 400 volts of phase modulation supports | |
| CN203977960U (en) | A kind of assembly type lightning protection electric pole | |
| CN204407828U (en) | A kind of power distribution station cross-arm | |
| CN204167810U (en) | A kind of lightning protection pillar insulator live line working wire stripping support |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant | ||
| C17 | Cessation of patent right | ||
| CF01 | Termination of patent right due to non-payment of annual fee |