CN102392651A - 全风化花岗岩隧道开挖施工方法 - Google Patents

全风化花岗岩隧道开挖施工方法 Download PDF

Info

Publication number
CN102392651A
CN102392651A CN201110389526XA CN201110389526A CN102392651A CN 102392651 A CN102392651 A CN 102392651A CN 201110389526X A CN201110389526X A CN 201110389526XA CN 201110389526 A CN201110389526 A CN 201110389526A CN 102392651 A CN102392651 A CN 102392651A
Authority
CN
China
Prior art keywords
bow member
steel bow
tunnel
excavation
core soil
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201110389526XA
Other languages
English (en)
Other versions
CN102392651B (zh
Inventor
马登科
李林
苏桂杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Mechanization Engineering Co Ltd Of Group Of Zhongtie No5 Bureau
China Railway No 5 Engineering Group Co Ltd
Mechanisation Engineering Co Ltd of China Railway No 5 Engineering Group Co Ltd
Original Assignee
Mechanization Engineering Co Ltd Of Group Of Zhongtie No5 Bureau
China Railway No 5 Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Mechanization Engineering Co Ltd Of Group Of Zhongtie No5 Bureau, China Railway No 5 Engineering Group Co Ltd filed Critical Mechanization Engineering Co Ltd Of Group Of Zhongtie No5 Bureau
Priority to CN201110389526.XA priority Critical patent/CN102392651B/zh
Publication of CN102392651A publication Critical patent/CN102392651A/zh
Application granted granted Critical
Publication of CN102392651B publication Critical patent/CN102392651B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

本发明公开了一种全风化花岗岩隧道开挖施工方法,开挖前采用Ф42mm注浆小导管进行超前支护;然后按步骤开挖,第一步,沿隧道轮廓线开挖上台阶的钢拱架槽,预留核心土,在其两侧下面设注浆锁脚锚管;第二步,人工架设钢拱架,人工修边,锚喷施工;第三步,开挖全部上台阶剩下的核心土,再沿隧道轮廓线先单侧开挖下台阶的钢拱架槽到隧道底部,在其下面设注浆锁脚锚管;第四步,人工架设钢拱架,人工修边,锚喷施工;预留核心土,用同样方法,交叉完成下台阶另一侧的钢拱架槽开挖、锁脚锚管、架设钢拱架、修边、锚喷施工;第五步,开挖全部下台阶剩下的核心土,再开挖隧底;第六步,拼装隧底钢拱架,修边,锚喷施工后,完成初支闭合成环。

Description

全风化花岗岩隧道开挖施工方法
技术领域
本发明涉及一种隧道开挖施工方法,特别是涉及一种全风化花岗岩隧道开挖施工方法。
背景技术
花岗岩地层在我国南方丘陵地区分布较广,其特点是未风化的花岗岩是很好的持力层,各项物理力学指标均优,但完全风化的花岗岩由于在风化过程中除石英外其它矿物基本风化为粘土矿物(主要为高岭土),导致全风化花岗岩力学性能急剧降低。
全风化花岗岩具有以下特点:
①外观特征可辨,结构松散无胶结,自稳性差,遇水易软化、崩解,失水收缩,经地下水扰动后易流淌;
②岩体渗透性微弱,渗透系数在10-4cm/s左右;
③风化岩夹含孔隙水和残存裂隙水,处于饱和状态。
目前,针对全风化花岗岩隧道开挖没有一套全面的施工工法。
发明内容
本发明要解决的问题是,提供一种通用可行的全风化花岗岩隧道开挖施工方法,解决全风化花岗岩隧道初支易坍塌、初支变形大侵入二衬轮廓线等涉及隧道施工安全和质量的技术问题。
本发明的技术方案是:在全风化花岗岩隧道开挖前,采用Ф42mm注浆小导管进行超前支护;然后隧道分上台阶、下台阶、隧底按步骤开挖,根据全风化花岗岩自稳时间短的特点,第一步,沿隧道轮廓线开挖上台阶的钢拱架槽,预留核心土,在其两侧下面设注浆锁脚锚管;第二步,在钢拱架槽内人工架设钢拱架,钢拱架顶在注浆锁脚锚管上,人工修边,锚喷施工;第三步,开挖全部上台阶剩下的核心土,再沿隧道轮廓线先单侧开挖下台阶的钢拱架槽到隧道底部即落底,在其下面设注浆锁脚锚管;第四步,在钢拱架槽内人工架设钢拱架,钢拱架顶在注浆锁脚锚管上,人工修边,锚喷施工。预留核心土,用同样方法,交叉完成下台阶另一侧的钢拱架槽开挖、锁脚锚管、架设钢拱架、修边、锚喷施工,即双侧落底;第五步,开挖全部下台阶剩下的核心土,再开挖隧底。第六步,拼装隧底钢拱架,修边,锚喷施工后,完成初支闭合成环。
在全风化花岗岩隧道开挖前,采用Ф42mm小导管进行超前支护, 长3.5~4m,环向间距30~40cm,纵向搭接长度不小于1.0m,外插角5~10度,注1:1水泥浆,注浆压力不低于0.5~1MPa。
在第一步中,采用200或300型反铲挖掘机,沿隧道轮廓线开挖上台阶的钢拱架槽,每次开挖1~2榀钢拱架间距长度,间距一般0.6~1m,预留核心土,在其两侧下面各设Ф42mm注浆锁脚锚管2根。
在第二步中,在钢拱架槽人工架设I18~I20工字钢钢拱架,钢拱架顶在注浆锁脚锚管上,按钢拱架轮廓人工严格修边,进行锚喷初支施工。
在第三步中,采用200或300型反铲挖掘机,开挖全部上台阶剩下的核心土,再沿隧道轮廓线先单侧开挖下台阶的钢拱架槽到隧道底部即落底,在其下面设注浆锁脚锚管。
在第四步中,在钢拱架槽人工架设I18~I20工字钢钢拱架,钢拱架顶在注浆锁脚锚管上,并使下台阶钢拱架与上台阶钢拱架连接成一个整体,按钢拱架轮廓人工严格修边,进行锚喷初支施工;预留核心土,用同样方法,交叉完成下台阶另一侧的钢拱架槽开挖、锁脚锚管、架设钢拱架、修边、锚喷施工,即双侧落底。
在第五步中,采用200或300型反铲挖掘机,开挖全部下台阶剩下的核心土,再开挖隧底。
在第六步中,拼装隧底钢拱架,并使下台阶钢拱架与隧底钢拱架连接成一个整体,按钢拱架轮廓修边,进行锚喷初支施工后,完成初支闭合成环
本发明采用“嵌拱修边”的施工方法,有效避免了超欠挖,开挖轮廓圆顺,围岩受力状态最佳。按此方法施工,可有效解决全风化花岗岩隧道初支易坍塌、初支变形大侵入二衬轮廓线等问题,有效保证隧道施工安全和质量。
附图说明
图1为本发明的施工顺序示意图,即开挖上台阶预留核心土施工示意图;
图2为本发明的施工顺序示意图,即架立上台阶钢拱架、人工修边、初支施工示意图;
图3为本发明的施工顺序示意图,即开挖上台阶核心土、单侧落底施工示意图;
图4为本发明的施工顺序示意图,即交叉开挖下台阶、双侧落底施工示意图;
图5为本发明的施工顺序示意图,即开挖下台阶核心土及隧底施工示意图;
图6为本发明的施工顺序示意图,即拼装隧底钢拱架,初支闭合成环施工示意图。
具体实施方式
本发明的实施例:在全风化花岗岩隧道开挖前,采用Ф42mm小导管进行超前支护, 长3.5~4m,环向间距30~40cm,纵向搭接长度不小于1.0m,外插角5~10度,注1:1水泥浆,注浆压力不低于0.5~1MPa。然后根据全风化花岗岩自稳时间短的特点,隧道分上台阶、下台阶、隧底按步骤开挖,第一步,由于全风化花岗岩硬度很低,采用200或300型反铲挖掘机,沿隧道轮廓线开挖上台阶的钢拱架槽,每次开挖1~2榀钢拱架间距长度(间距一般0.6~1m,视渗水量而定),预留核心土,在其两侧下面各设Ф42mm注浆锁脚锚管2根,如图1所示意。第二步,在钢拱架槽内人工架设I18~I20工字钢钢拱架,钢拱架顶在注浆锁脚锚管上,架设完毕,按钢拱架轮廓人工严格修边,进行锚喷初支施工,如图2所示意。第三步,采用200或300型反铲挖掘机,开挖全部上台阶剩下的核心土,即完成上台阶开挖。再沿隧道轮廓线先单侧开挖下台阶的钢拱架槽到隧道底部(即落底),在其下面设注浆锁脚锚管,如图3所示意。第四步,在钢拱架槽内人工架设I18~I20工字钢钢拱架,钢拱架顶在注浆锁脚锚管上,并使下台阶钢拱架与上台阶钢拱架连接成一个整体,按钢拱架轮廓人工严格修边,进行锚喷初支施工。预留核心土,用同样方法,交叉完成下台阶另一侧的钢拱架槽开挖、锁脚锚管、架设钢拱架、修边、锚喷施工(即双侧落底),如图4所示意;第五步,采用200或300型反铲挖掘机,开挖全部下台阶剩下的核心土,即完成下台阶开挖;再开挖隧底,如图5所示意。第六步,拼装隧底钢拱架,并使下台阶钢拱架与隧底钢拱架连接成一个整体,按钢拱架轮廓严格修边,进行锚喷初支施工后,完成初支闭合成环,如图6所示意。

Claims (8)

1.一种全风化花岗岩隧道开挖施工方法,其特征在于:在全风化花岗岩隧道开挖前,采用Ф42mm注浆小导管进行超前支护;然后隧道分上台阶、下台阶、隧底按步骤开挖,第一步,沿隧道轮廓线开挖上台阶的钢拱架槽,预留核心土,在其两侧下面设注浆锁脚锚管;第二步,在钢拱架槽内人工架设钢拱架,钢拱架顶在注浆锁脚锚管上,人工修边,锚喷施工;第三步,开挖全部上台阶剩下的核心土,再沿隧道轮廓线先单侧开挖下台阶的钢拱架槽到隧道底部即落底,在其下面设注浆锁脚锚管;第四步,在钢拱架槽内人工架设钢拱架,钢拱架顶在注浆锁脚锚管上,人工修边,锚喷施工;预留核心土,用同样方法,交叉完成下台阶另一侧的钢拱架槽开挖、锁脚锚管、架设钢拱架、修边、锚喷施工,即双侧落底;第五步,开挖全部下台阶剩下的核心土,再开挖隧底;第六步,拼装隧底钢拱架,修边,锚喷施工后,完成初支闭合成环。
2.根据权利要求1所述的全风化花岗岩隧道开挖施工方法,其特征在于:在全风化花岗岩隧道开挖前,采用Ф42mm小导管进行超前支护, 长3.5~4m,环向间距30~40cm,纵向搭接长度不小于1.0m,外插角5~10度,注1:1水泥浆,注浆压力不低于0.5~1MPa。
3.根据权利要求1所述的全风化花岗岩隧道开挖施工方法,其特征在于:在第一步中,采用200或300型反铲挖掘机,沿隧道轮廓线开挖上台阶的钢拱架槽,每次开挖1~2榀钢拱架间距长度,间距一般0.6~1m,预留核心土,在其两侧下面各设Ф42mm注浆锁脚锚管2根。
4.根据权利要求1所述的全风化花岗岩隧道开挖施工方法,其特征在于:在第二步中,在钢拱架槽人工架设I18~I20工字钢钢拱架,钢拱架顶在注浆锁脚锚管上,按钢拱架轮廓人工严格修边,进行锚喷初支施工。
5.根据权利要求1所述的全风化花岗岩隧道开挖施工方法,其特征在于:在第三步中,采用200或300型反铲挖掘机,开挖全部上台阶剩下的核心土,再沿隧道轮廓线先单侧开挖下台阶的钢拱架槽到隧道底部即落底,在其下面设注浆锁脚锚管。
6.根据权利要求1所述的全风化花岗岩隧道开挖施工方法,其特征在于:在第四步中,在钢拱架槽人工架设I18~I20工字钢钢拱架,钢拱架顶在注浆锁脚锚管上,并使下台阶钢拱架与上台阶钢拱架连接成一个整体,按钢拱架轮廓人工严格修边,进行锚喷初支施工;预留核心土,用同样方法,交叉完成下台阶另一侧的钢拱架槽开挖、锁脚锚管、架设钢拱架、修边、锚喷施工,即双侧落底。
7.根据权利要求1所述的全风化花岗岩隧道开挖施工方法,其特征在于:在第五步中,采用200或300型反铲挖掘机,开挖全部下台阶剩下的核心土,再开挖隧底。
8.根据权利要求1所述的全风化花岗岩隧道开挖施工方法,其特征在于:在第六步中,拼装隧底钢拱架,并使下台阶钢拱架与隧底钢拱架连接成一个整体,按钢拱架轮廓修边,进行锚喷初支施工后,完成初支闭合成环。
CN201110389526.XA 2011-11-30 2011-11-30 全风化花岗岩隧道开挖施工方法 Active CN102392651B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201110389526.XA CN102392651B (zh) 2011-11-30 2011-11-30 全风化花岗岩隧道开挖施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201110389526.XA CN102392651B (zh) 2011-11-30 2011-11-30 全风化花岗岩隧道开挖施工方法

Publications (2)

Publication Number Publication Date
CN102392651A true CN102392651A (zh) 2012-03-28
CN102392651B CN102392651B (zh) 2014-10-22

Family

ID=45860020

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201110389526.XA Active CN102392651B (zh) 2011-11-30 2011-11-30 全风化花岗岩隧道开挖施工方法

Country Status (1)

Country Link
CN (1) CN102392651B (zh)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102926757A (zh) * 2012-09-07 2013-02-13 中铁五局(集团)有限公司 山岭软弱大跨隧道两台阶四步开挖支护的施工方法
CN103850688A (zh) * 2014-03-24 2014-06-11 昆明理工大学 一种复杂断层破碎带大断面巷道动态迭加耦合支护方法
CN104533427A (zh) * 2014-11-25 2015-04-22 广东省长大公路工程有限公司 一种雨季山区花岗岩隧道围岩开挖施工方法

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101105131A (zh) * 2007-08-17 2008-01-16 中铁十二局集团有限公司 一种适用于铁路大断面ⅳ、ⅴ级围岩隧道的开挖方法
CN101725358A (zh) * 2008-10-31 2010-06-09 中铁四局集团有限公司 隧道超浅埋不均匀风化地层开挖施工方法
CN101864963A (zh) * 2010-05-26 2010-10-20 中铁二十三局集团第三工程有限公司 一种大断面黄土隧道施工方法
CN101906974A (zh) * 2010-08-09 2010-12-08 中铁第一勘察设计院集团有限公司 一种特大断面黄土隧道的支护结构及其施工方法
CN101906975A (zh) * 2010-08-09 2010-12-08 中铁第一勘察设计院集团有限公司 一种特大断面黄土隧道下穿铁路的支护结构及其施工方法
CN102042019A (zh) * 2010-11-11 2011-05-04 中铁十三局集团第四工程有限公司 浅埋大跨软塑粘土隧道两台阶五步开挖的施工方法
CN102061923A (zh) * 2010-11-28 2011-05-18 山东科技大学 保护既有建筑物的隧道施工方法
CN102213099A (zh) * 2011-05-23 2011-10-12 中铁二院工程集团有限责任公司 四线大跨台基复合拱形隧道衬砌构造

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101105131A (zh) * 2007-08-17 2008-01-16 中铁十二局集团有限公司 一种适用于铁路大断面ⅳ、ⅴ级围岩隧道的开挖方法
CN101725358A (zh) * 2008-10-31 2010-06-09 中铁四局集团有限公司 隧道超浅埋不均匀风化地层开挖施工方法
CN101864963A (zh) * 2010-05-26 2010-10-20 中铁二十三局集团第三工程有限公司 一种大断面黄土隧道施工方法
CN101906974A (zh) * 2010-08-09 2010-12-08 中铁第一勘察设计院集团有限公司 一种特大断面黄土隧道的支护结构及其施工方法
CN101906975A (zh) * 2010-08-09 2010-12-08 中铁第一勘察设计院集团有限公司 一种特大断面黄土隧道下穿铁路的支护结构及其施工方法
CN102042019A (zh) * 2010-11-11 2011-05-04 中铁十三局集团第四工程有限公司 浅埋大跨软塑粘土隧道两台阶五步开挖的施工方法
CN102061923A (zh) * 2010-11-28 2011-05-18 山东科技大学 保护既有建筑物的隧道施工方法
CN102213099A (zh) * 2011-05-23 2011-10-12 中铁二院工程集团有限责任公司 四线大跨台基复合拱形隧道衬砌构造

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102926757A (zh) * 2012-09-07 2013-02-13 中铁五局(集团)有限公司 山岭软弱大跨隧道两台阶四步开挖支护的施工方法
CN102926757B (zh) * 2012-09-07 2015-09-09 中铁五局(集团)有限公司 山岭软弱大跨隧道两台阶四步开挖支护的施工方法
CN103850688A (zh) * 2014-03-24 2014-06-11 昆明理工大学 一种复杂断层破碎带大断面巷道动态迭加耦合支护方法
CN104533427A (zh) * 2014-11-25 2015-04-22 广东省长大公路工程有限公司 一种雨季山区花岗岩隧道围岩开挖施工方法

Also Published As

Publication number Publication date
CN102392651B (zh) 2014-10-22

Similar Documents

Publication Publication Date Title
CN101994513B (zh) 上半断面完成全断面帷幕注浆隧道施工方法
CN102606167B (zh) 浅埋暗挖隧道横向注浆导管沉降控制施工方法
CN102562075B (zh) 一种大断面软弱围岩隧道三台阶六部短距施工方法
CN102606168B (zh) 防止浅埋暗挖隧道开挖时沉降变形的施工方法
CN109681210A (zh) 一种断面暗挖隧道施工的双侧壁导坑法
CN205154174U (zh) 软弱围岩隧道管棚超前支护施工结构
CN105350973A (zh) 一种大跨断面黄土隧道下穿高速公路的施工方法
CN105156121A (zh) 一种大断面黄土隧道进洞浅埋段的施工方法
CN103410527A (zh) 围岩中含湿陷性黄土和软岩的隧道初期支护施工方法
CN103306683A (zh) 一种开挖深埋隧道时洞内综合降水的施工方法
CN101408106A (zh) 小管棚超前注浆法
CN103835729A (zh) 深部长距离巷道围岩地面预注浆加固工艺
CN205117357U (zh) 基于自钻式螺旋管棚的软弱围岩隧道超前支护结构
CN205117356U (zh) 自钻式螺旋管棚
CN104234726A (zh) 一种穿越富水不整合接触带隧道的洞内降排水施工方法
CN104405411A (zh) 超大变断面隧道支护结构
CN103867209A (zh) 一种地铁竖井分层、分段转横通道施工开挖进洞的方法
CN102392651A (zh) 全风化花岗岩隧道开挖施工方法
CN109139018A (zh) 深孔袖阀管注浆与水平旋喷相结合的隧道施工方法及系统
CN104153783B (zh) 一种富含地下水及松散砂卵石引水洞施工工艺
CN109184742B (zh) 一种高压富水软弱围岩山岭隧道的超前预注浆方法
CN102606173B (zh) 一种处理隧道变形段、加快掘进的施工方法
CN204436407U (zh) 一种大断面软弱围岩隧道双层初期支护预防地质灾害发生的结构
CN104612714A (zh) 在穿越围岩较差地质条件下的矿山法隧道施工方法及结构
CN104863613A (zh) 岩质地层暗挖地下结构高边墙锚拉初支结构及施工方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
EE01 Entry into force of recordation of patent licensing contract

Application publication date: 20120328

Assignee: Mechanization engineering Co., Ltd of group of ZhongTie No.5 bureau

Assignor: China Railway five Bureau (Group) Co., Ltd.|China Railway five Bureau Group mechanized engineering Co., Ltd.

Contract record no.: 2015430000120

Denomination of invention: Completely weathered granite tunnel excavation construction method

Granted publication date: 20141022

License type: Exclusive License

Record date: 20150728

LICC Enforcement, change and cancellation of record of contracts on the licence for exploitation of a patent or utility model