CN102213099A - 四线大跨台基复合拱形隧道衬砌构造 - Google Patents

四线大跨台基复合拱形隧道衬砌构造 Download PDF

Info

Publication number
CN102213099A
CN102213099A CN2011101329900A CN201110132990A CN102213099A CN 102213099 A CN102213099 A CN 102213099A CN 2011101329900 A CN2011101329900 A CN 2011101329900A CN 201110132990 A CN201110132990 A CN 201110132990A CN 102213099 A CN102213099 A CN 102213099A
Authority
CN
China
Prior art keywords
arch
tunnel
greatly
lines
striden
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2011101329900A
Other languages
English (en)
Inventor
朱勇
卿伟宸
杨昌宇
高扬
陶伟明
李敬
林本涛
张慧玲
章慧健
甘目飞
巩江峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Eryuan Engineering Group Co Ltd CREEC
Original Assignee
China Railway Eryuan Engineering Group Co Ltd CREEC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Eryuan Engineering Group Co Ltd CREEC filed Critical China Railway Eryuan Engineering Group Co Ltd CREEC
Priority to CN2011101329900A priority Critical patent/CN102213099A/zh
Publication of CN102213099A publication Critical patent/CN102213099A/zh
Pending legal-status Critical Current

Links

Images

Abstract

四线大跨台基复合拱形隧道衬砌构造,可有效控制四线大跨隧道拱顶沉降,避免因拱脚下沉、拱顶变形导致衬砌开裂甚至发生塌方事件,以确保隧道施工和运营的稳定及安全性。它包括由内而外设置的超前支护结构、初期支护结构和二次衬砌结构。所述二次衬砌结构包括拱部二次衬砌结构(31)、隧道两侧的台座基础结构(32)及仰拱;所述超前支护结构包括拱部超前支护结构(11)、台座基础侧壁超前支护结构(12);所述初期支护结构包括拱部初期支护结构(21)、台座基础侧壁初期支护结构(22);拱部初期支护结构(21)和拱部二次衬砌结构(31)的下端分别支承于隧道两侧台座基础结构(32)的上端。

Description

四线大跨台基复合拱形隧道衬砌构造
技术领域
本发明涉及铁路隧道衬砌构造,特别涉及一种软岩地层浅埋段四线大跨隧道衬砌构造。
背景技术
我国是一个多山的国家,尤其是西南山区地形、地质条件极为复杂,桥隧比重大,在建及拟建的大部分铁路线路中,隧道比重占线路总长的50%以上,部分段落隧道比重达90%以上,由于由地形、运能等限制,大量车站布置需伸入隧道内。近年来随着路网建设向山区发展,西南地区以沪昆客专、云桂、成兰等为代表的高标准铁路前期设计工作正在开展,由于受曲线半径大、地形地质条件复杂、环保要求高等多种因素的制约,铁路沿线部分地段设站条件极为困难,诸如四线大跨车站隧道不可避免。
在隧道修建过程中,隧道洞口浅埋段历来就是施工的难点,对于四线大跨隧道,由于跨度大、埋深浅、围岩荷载大,且洞口浅埋段山体表层岩石大都风化极为严重,强度低,稳定性差,采用传统的支护结构和开挖方式,开挖后拱脚下沉大,拱顶变形不宜控制,甚至导致衬砌开裂、失稳,造成坍塌事故。因此,为了确保施工和运营安全,必须优化支护结构型式,改善支护受力性态,有效提高支护结构的整体承载能力,以便有效控制超浅埋段四线大跨隧道拱顶沉降,避免支护开裂甚至塌方发生。
隧道衬砌结构作为隧道工程的永久受力结构,因此必须做到安全、可靠。
发明内容
本发明所要解决的技术问题是提供一种四线大跨台基复合拱形隧道衬砌构造,可有效控制四线大跨隧道拱顶沉降,避免因拱脚下沉、拱顶变形导致衬砌开裂甚至发生塌方事件,以确保隧道施工和运营的稳定及安全性。
本发明解决其技术问题所采用的技术方案如下:
本发明的四线大跨台基复合拱形隧道衬砌构造,包括由内而外设置的超前支护结构、初期支护结构和二次衬砌结构,其特征是:所述二次衬砌结构包括拱部二次衬砌结构、隧道两侧的台座基础结构及仰拱;所述超前支护结构包括拱部超前支护结构、台座基础侧壁超前支护结构;所述初期支护结构包括拱部初期支护结构、台座基础侧壁初期支护结构;拱部初期支护结构和拱部二次衬砌结构的下端分别支承于隧道两侧台座基础结构的上端。
在上述技术方案中,所述拱部超前支护是由径向间隔布设的外层大管棚、内层大管棚复合构成,或者根据地形地质情况采用单层大管棚或中管棚。
本发明的有益效果是,将两侧台座基础结构,作为拱部初期支护结构和拱部二次衬砌结构的承载基础,有效地解决了四线大跨隧道施工中拱部支护下沉变形的问题;拱部围岩竖向荷载通过拱部支护结构由台座基础结构传至基底;与一般单、双线铁路衬砌不同,仰拱不承受由拱墙结构传来的围岩竖向荷载,因此仰拱曲率半径可根据基底围岩情况尽量放大,甚至采用底板结构,可以大大减小开挖工程量;拱部采用双层大管棚超前支护可增大管棚刚度,防止软弱围岩下沉、松弛和坍塌,从而有效减小开挖变形对地表的影响;
附图说明
本说明书包括如下一幅附图:
图1是本发明四线大跨台基复合拱形隧道衬砌构造的断面结构示意图。
图中示出构件、部位名称及所对应标记:拱部超前支护结构11、内层大管棚11a、外层大管棚11b、台座基础侧壁超前支护结构12、拱部初期支护结构21、拱部喷射混凝土层21a、拱部型钢钢架21b、拱部系统锚杆21c、台座基础侧壁初期支护结构22、台座基础侧壁喷射混凝土层22a、台座基础侧壁型钢钢架22b、台座基础侧壁系统锚杆22c、锁脚锚管22d、拱部二次衬砌结构31、台座基础结构32、仰拱33。
具体实施方式
下面结合附图和实施例对本发明进一步说明。
参照图1,本发明的四线大跨台基复合拱形隧道衬砌构造,包括由外而内设置的超前支护结构、初期支护结构和二次衬砌结构。所述二次衬砌结构包括拱部二次衬砌结构31、隧道两侧的台座基础结构32,以及仰拱33。所述超前支护结构包括拱部超前支护结构11、台座基础侧壁超前支护结构12。参照图1,所述初期支护结构包括拱部初期支护结构21、台座基础侧壁初期支护结构22。拱部初期支护结构21和拱部二次衬砌结构31的下端分别支承于隧道两侧台座基础结构32的上端,即以两侧台座基础结构作为拱部支护体系的承载体,解决软岩四线大跨隧道施工中拱脚下沉、拱顶沉降不宜控制,支护结构易变形的问题。除此之外,拱部围岩竖向荷载通过拱部支护结构由拱座结构传至基底,与一般单、双线铁路衬砌不同,仰拱不承受由拱墙结构传来的围岩竖向荷载,因此仰拱曲率半径可根据基底围岩情况尽量放大,甚至采用底板结构,可以大大减小开挖工程量。参照图1,拱部超前支护是由径向间隔布设的外层大管棚11b、内层大管棚11a复合构成,即拱部采用双层大管棚超前支护可增大管棚刚度,防止软弱围岩下沉、松弛和坍塌,从而有效减小开挖变形对地表的影响。根据地形地质情况,拱部超前支护也可采用单层大管棚或中管棚。
参照图1,所述拱部初期支护结构21包括覆盖拱部围岩的拱部喷射混凝土层21a和沿隧道开挖方向间隔布设且埋设于拱部喷射混凝土层21a内的拱部型钢钢架21b,以及沿拱部梅花形布置的系统锚杆21c。相邻两榀拱部型钢钢架21b间由环向间隔设置的纵向连接筋连接。所述拱部喷射混凝土层21a内加设钢筋网。
参照图1,所述台座基础侧壁初期支护结构22包括覆盖台座基础侧壁围岩的喷射混凝土层22a和沿隧道开挖方向间隔布设且埋设于喷射混凝土层22a内的型钢钢架22b,以及设置在型钢钢架22b下端的锁脚锚管22d。相邻两榀型钢钢架22b间由环向间隔设置的纵向连接筋连接。所述台座基础侧壁初期支护结构22还包括沿台座基础侧壁面梅花形布置的系统锚杆22c。所述台座基础侧壁喷射混凝土层22a内加设环向钢筋网。
参照图1,所述台座基础侧壁超前支护结构12由在台座基础侧壁喷射混凝土层22a外一定范围内向外倾斜一定外插角环向间隔布设的中管棚或小导管构成。
下面以改建铁路贵(阳)昆(明)线六盘水至沾益段乌蒙山二号隧道为实施例进一步说明本发明。乌蒙山二号隧道全长12260m,为六沾铁路最长隧道,受扒挪块车站地形限制和运营管理需要,扒挪块车站伸入乌蒙山二号隧道出口段,形成四线车站隧道,长538m。最大开挖跨度达28.42m,最大开挖面积为354.30m2。洞口段地层主要为泥岩,地表层风化,土体松散。洞口段具体支护参数如下:
1、拱部设双层大管棚,即由内层大管棚11a、外层大管棚11b构成拱部超前支护结构11。钢管管径108mm,壁厚均为5mm。大管棚环向设置范围延伸至台座基础顶部。管棚外插角控制在1°范围内,大管棚施工完成后方可进行隧道掘进施工。
2、根据本发明四线大跨台基复合拱形隧道衬砌构造的特点,工法上必须先施工两侧导洞以浇筑两侧台座基础结构32,以台座基础结构32作为拱部荷载的承载体,因此对于台座基础侧壁超前支护结构12和初期支护结构22参数仅需根据围岩情况及两侧导洞开挖尺寸来确定。本工程中,台座基础侧壁超前支护结构12采用中管棚,钢管直径75mm,壁厚4.5mm;台座基础侧壁初期支护结构22采用C25喷砼形成喷射混凝土层22a,厚度为27cm,其内设置φ8mm钢筋网,网格间距20cm×20cm,纵向间隔设置I20a型钢钢架22b加强支护,间距0.8m一榀,相邻两榀钢架间环向间隔设置φ22mm纵向连接钢筋,环向间距1.0m。基底设置φ50mm边墙锁脚锚管22d,长5m。
3、拱部初期支护结构21采用C25喷砼形成拱部喷射混凝土层21a,厚度为40cm,其内设置φ8mm钢筋网,网格间距20cm×20cm;纵向间隔设置HW300拱部型钢钢架21b加强支护,钢架间距0.6m一榀,相邻两榀钢架间环向间隔设置φ22mm纵向连接钢筋,环向间距1.0m。
拱部二次衬砌结构31及仰拱33采用C35钢筋混凝土;台座基础结构32采用C35砼。
采用本发明四线大跨台基复合拱形隧道衬砌构造,在施工中保证了拱部支护结构稳定、有效解决软岩四线大跨隧道施工中拱脚下沉大,拱顶沉降不宜控制等问题。确保了施工全过程处于安全、稳定、优质的可控状态,具有广阔的推广应用前景。
以上所述只是用图解说明本发明四线大跨台基复合拱形隧道衬砌构造的一些原理,并非是要将本发明局限在所示和所述的具体结构和适用范围内,故凡是所有可能被利用的相应修改以及等同物,均属于本发明所申请的专利范围。

Claims (9)

1.四线大跨台基复合拱形隧道衬砌构造,包括由内而外设置的超前支护结构、初期支护结构和二次衬砌结构,其特征是:所述二次衬砌结构包括拱部二次衬砌结构(31)、隧道两侧的台座基础结构(32)及仰拱;所述超前支护结构包括拱部超前支护结构(11)、台座基础侧壁超前支护结构(12);所述初期支护结构包括拱部初期支护结构(21)、台座基础侧壁初期支护结构(22);拱部初期支护结构(21)和拱部二次衬砌结构(31)的下端分别支承于隧道两侧台座基础结构(32)的上端。
2.如权利要求1所述的四线大跨台基复合拱形隧道衬砌构造,其特征是:所述拱部超前支护是由径向间隔布设的外层大管棚(11b)、内层大管棚(11a)复合构成。
3.如权利要求1所述的四线大跨台基复合拱形隧道衬砌构造,其特征是:所述拱部超前支护采用单层大管棚或中管棚。
4.如权利要求1所述的四线大跨台基复合拱形隧道衬砌构造,其特征是:所述拱部初期支护结构(21)包括覆盖拱部围岩的拱部喷射混凝土层(21a)和沿隧道开挖方向间隔布设且埋设于拱部喷射混凝土层(21a)内的拱部型钢钢架(21b),以及沿拱部梅花形布置的拱部系统锚杆(21c)。
5.如权利要求4所述的四线大跨台基复合拱形隧道衬砌构造,其特征是:所述拱部喷射混凝土层(21a)内加设钢筋网。
6.如权利要求1所述的四线大跨台基复合拱形隧道衬砌构造,其特征是:所述台座基础侧壁初期支护结构(22)包括覆盖台座基础侧壁围岩的喷射混凝土层(22a)和沿隧道开挖方向间隔布设且埋设于喷射混凝土层(22a)内的型钢钢架(22b),以及设置在型钢钢架(22b)下端的锁脚锚管(22d)。
7.如权利要求6所述的四线大跨台基复合拱形隧道衬砌构造,其特征是:所述台座基础侧壁初期支护结构(22)还包括沿还包括沿台座基础侧壁面梅花形布置的系统锚杆(22c)。
8.如权利要求6所述的四线大跨台基复合拱形隧道衬砌构造,其特征是:所述台座基础侧壁喷射混凝土层(22a)内加设钢筋网。
9.如权利要求1所述的四线大跨台基复合拱形隧道衬砌构造,其特征是:所述台座基础侧壁超前支护结构(12)由在喷射混凝土层(22a)外一定范围内向外倾斜一定外插角环向间隔布设的中管棚或小导管构成。
CN2011101329900A 2011-05-23 2011-05-23 四线大跨台基复合拱形隧道衬砌构造 Pending CN102213099A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011101329900A CN102213099A (zh) 2011-05-23 2011-05-23 四线大跨台基复合拱形隧道衬砌构造

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011101329900A CN102213099A (zh) 2011-05-23 2011-05-23 四线大跨台基复合拱形隧道衬砌构造

Publications (1)

Publication Number Publication Date
CN102213099A true CN102213099A (zh) 2011-10-12

Family

ID=44744605

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011101329900A Pending CN102213099A (zh) 2011-05-23 2011-05-23 四线大跨台基复合拱形隧道衬砌构造

Country Status (1)

Country Link
CN (1) CN102213099A (zh)

Cited By (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102392651A (zh) * 2011-11-30 2012-03-28 中铁五局(集团)有限公司 全风化花岗岩隧道开挖施工方法
CN102562093A (zh) * 2012-02-21 2012-07-11 山东盛大矿业股份有限公司 全长锚固密集型树脂锚杆喷锚网支护方法
CN103075164A (zh) * 2012-12-28 2013-05-01 成都中铁隆工程集团有限公司 一种双洞二衬依次同步推进施工工艺
CN103147771A (zh) * 2013-03-24 2013-06-12 中铁二院工程集团有限责任公司 一种大跨度高回填明洞结构
CN103195449A (zh) * 2013-03-24 2013-07-10 中铁二院工程集团有限责任公司 大跨度重荷载明洞预应力钢筋混凝土衬砌结构
CN103603679A (zh) * 2013-09-17 2014-02-26 中国神华能源股份有限公司 用于支护隧道拱部的拱顶钢架与隧道施工方法
CN103939112A (zh) * 2014-05-07 2014-07-23 中铁第一勘察设计院集团有限公司 下穿沟谷隧道双层超前支护结构
CN105156141A (zh) * 2015-08-31 2015-12-16 中国电建集团成都勘测设计研究院有限公司 控制顺向陡倾层状结构岩石隧道边墙超挖的支护方法
CN105156137A (zh) * 2015-08-31 2015-12-16 中国电建集团成都勘测设计研究院有限公司 Ⅴ~ⅵ级围岩中的隧道边墙初期支护方法
CN105736017A (zh) * 2015-07-27 2016-07-06 中铁十二局集团有限公司 一种隧道初期支护不对称单元正反布置拱架结构
CN106014452A (zh) * 2016-07-08 2016-10-12 山东大学 一种适用于地下隧洞的高强约束混凝土支护体系
CN108194096A (zh) * 2017-12-27 2018-06-22 中铁二院工程集团有限责任公司 墙脚基座式无仰拱型隧道衬砌结构及其排水系统
CN108222960A (zh) * 2017-12-27 2018-06-29 中铁二院工程集团有限责任公司 隧底设置泄水通道的v形拱座底板型衬砌及其排水系统构造
CN109812277A (zh) * 2019-02-28 2019-05-28 中铁十八局集团有限公司 一种高落差垂直悬岩隧道主动防护双层管棚安全出洞方法
CN110017144A (zh) * 2019-04-04 2019-07-16 甘肃省交通规划勘察设计院股份有限公司 一种考虑基底加固处理的黄土隧道三台阶施工方法
CN114086993A (zh) * 2021-11-30 2022-02-25 中铁第四勘察设计院集团有限公司 一种超大断面隧道的支护体系及开挖方法

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001311393A (ja) * 2000-04-28 2001-11-09 Hajime Matsuoka トンネルの構造及びトンネル構築方法
KR100770593B1 (ko) * 2007-02-28 2007-10-29 김승한 곡면패널 시공방법
CN201738932U (zh) * 2010-08-09 2011-02-09 中铁第一勘察设计院集团有限公司 一种特大断面黄土隧道的支护结构
CN202090933U (zh) * 2011-05-23 2011-12-28 中铁二院工程集团有限责任公司 四线大跨台基复合拱形隧道衬砌构造

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001311393A (ja) * 2000-04-28 2001-11-09 Hajime Matsuoka トンネルの構造及びトンネル構築方法
KR100770593B1 (ko) * 2007-02-28 2007-10-29 김승한 곡면패널 시공방법
CN201738932U (zh) * 2010-08-09 2011-02-09 中铁第一勘察设计院集团有限公司 一种特大断面黄土隧道的支护结构
CN202090933U (zh) * 2011-05-23 2011-12-28 中铁二院工程集团有限责任公司 四线大跨台基复合拱形隧道衬砌构造

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
向亮: "重庆地铁六号线四线大跨隧道设计与施工研究", 《科技创新导报》, no. 12, 30 April 2011 (2011-04-30), pages 120 *
杜建华等: "浅埋暗挖大跨三联拱隧道施工技术", 《铁道建筑》, no. 04, 30 April 2010 (2010-04-30), pages 44 - 47 *

Cited By (24)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102392651A (zh) * 2011-11-30 2012-03-28 中铁五局(集团)有限公司 全风化花岗岩隧道开挖施工方法
CN102392651B (zh) * 2011-11-30 2014-10-22 中铁五局(集团)有限公司 全风化花岗岩隧道开挖施工方法
CN102562093A (zh) * 2012-02-21 2012-07-11 山东盛大矿业股份有限公司 全长锚固密集型树脂锚杆喷锚网支护方法
CN102562093B (zh) * 2012-02-21 2014-10-15 山东盛大矿业股份有限公司 全长锚固密集型树脂锚杆喷锚网支护方法
CN103075164A (zh) * 2012-12-28 2013-05-01 成都中铁隆工程集团有限公司 一种双洞二衬依次同步推进施工工艺
CN103075164B (zh) * 2012-12-28 2015-02-18 成都中铁隆工程集团有限公司 一种双洞二衬依次同步推进施工工艺
CN103147771A (zh) * 2013-03-24 2013-06-12 中铁二院工程集团有限责任公司 一种大跨度高回填明洞结构
CN103195449A (zh) * 2013-03-24 2013-07-10 中铁二院工程集团有限责任公司 大跨度重荷载明洞预应力钢筋混凝土衬砌结构
CN103603679A (zh) * 2013-09-17 2014-02-26 中国神华能源股份有限公司 用于支护隧道拱部的拱顶钢架与隧道施工方法
CN103603679B (zh) * 2013-09-17 2015-08-12 中国神华能源股份有限公司 用于支护隧道拱部的拱顶钢架与隧道施工方法
CN103939112A (zh) * 2014-05-07 2014-07-23 中铁第一勘察设计院集团有限公司 下穿沟谷隧道双层超前支护结构
CN105736017B (zh) * 2015-07-27 2018-07-06 中铁十二局集团有限公司 一种隧道初期支护不对称单元正反布置拱架结构
CN105736017A (zh) * 2015-07-27 2016-07-06 中铁十二局集团有限公司 一种隧道初期支护不对称单元正反布置拱架结构
CN105156137A (zh) * 2015-08-31 2015-12-16 中国电建集团成都勘测设计研究院有限公司 Ⅴ~ⅵ级围岩中的隧道边墙初期支护方法
CN105156141A (zh) * 2015-08-31 2015-12-16 中国电建集团成都勘测设计研究院有限公司 控制顺向陡倾层状结构岩石隧道边墙超挖的支护方法
CN106014452A (zh) * 2016-07-08 2016-10-12 山东大学 一种适用于地下隧洞的高强约束混凝土支护体系
CN106014452B (zh) * 2016-07-08 2017-05-31 山东大学 一种适用于地下隧洞的高强约束混凝土支护体系
CN108194096A (zh) * 2017-12-27 2018-06-22 中铁二院工程集团有限责任公司 墙脚基座式无仰拱型隧道衬砌结构及其排水系统
CN108222960A (zh) * 2017-12-27 2018-06-29 中铁二院工程集团有限责任公司 隧底设置泄水通道的v形拱座底板型衬砌及其排水系统构造
CN109812277A (zh) * 2019-02-28 2019-05-28 中铁十八局集团有限公司 一种高落差垂直悬岩隧道主动防护双层管棚安全出洞方法
CN109812277B (zh) * 2019-02-28 2020-07-17 中铁十八局集团有限公司 一种高落差垂直悬岩隧道主动防护双层管棚安全出洞方法
CN110017144A (zh) * 2019-04-04 2019-07-16 甘肃省交通规划勘察设计院股份有限公司 一种考虑基底加固处理的黄土隧道三台阶施工方法
CN110017144B (zh) * 2019-04-04 2020-12-04 甘肃省交通规划勘察设计院股份有限公司 一种考虑基底加固处理的黄土隧道三台阶施工方法
CN114086993A (zh) * 2021-11-30 2022-02-25 中铁第四勘察设计院集团有限公司 一种超大断面隧道的支护体系及开挖方法

Similar Documents

Publication Publication Date Title
CN102213099A (zh) 四线大跨台基复合拱形隧道衬砌构造
CN102758632B (zh) 岩质地层双初支分层法修建大型地下结构的方法
CN102226403B (zh) 地铁大跨度车站主体拱盖法施工方法及车站主体结构
CN101864987B (zh) 一种大倾角煤层沿空留巷充填墙体的构筑方法
CN102226399A (zh) 软岩四线大跨隧道三台阶以索代撑开挖施工方法
CN102226398A (zh) 软岩四线大跨隧道复合双侧壁撑索转换开挖施工方法
CN104389628B (zh) 滑坡地段隧道加固装置及加固施工方法
CN104047613B (zh) 煤矿巷道底板用锚固方法
CN102758642A (zh) 上软下硬地层大跨隧道叠合承载拱结构及其施工方法
CN101592032A (zh) 浅埋下穿高速公路不均匀地层超大断面隧道的初期支护构造
CN106013171B (zh) 一种深基坑侧壁的半刚性半柔性支护结构和方法
CN204418187U (zh) 地铁保护区域土钉墙结合双排桩深基坑复合支护结构
CN102226407A (zh) 四线大跨隧道索拱联合初期支护构造
CN204729099U (zh) 岩质地层暗挖三层地铁车站伞盖结构
CN201991017U (zh) 基于拱盖法施工成型的地铁大跨度车站主体结构
CN105626083A (zh) 一种通透肋式连拱隧道的施工方法
CN102606168B (zh) 防止浅埋暗挖隧道开挖时沉降变形的施工方法
CN104612696B (zh) 大断面暗挖地铁车站在粉细砂层中穿越高架桥柱洞法施工方法
CN106567718A (zh) 一种复合地层单拱超大跨地铁车站拉槽支撑代换的施工方法
CN107965341A (zh) 一种大断面硐室管棚管网混凝土支护方法
CN106869969A (zh) 一种软岩超大断面隧道的开挖支护施工方法
CN101324071B (zh) 通透肋式拱梁隧道
CN102748040A (zh) 地铁大跨度车站主体结构及其柱拱法施工方法
CN105370289A (zh) 一种复杂环境既有管线超长浅埋暗挖施工方法
CN106640096A (zh) 穿越回填土段及过渡段隧道的施工方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20111012