CN102383375A - Construction method for quickly mounting large steel bridge on urban main road - Google Patents
Construction method for quickly mounting large steel bridge on urban main road Download PDFInfo
- Publication number
- CN102383375A CN102383375A CN2011102290363A CN201110229036A CN102383375A CN 102383375 A CN102383375 A CN 102383375A CN 2011102290363 A CN2011102290363 A CN 2011102290363A CN 201110229036 A CN201110229036 A CN 201110229036A CN 102383375 A CN102383375 A CN 102383375A
- Authority
- CN
- China
- Prior art keywords
- steel
- case beam
- steel case
- channel
- iron
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 229910000831 Steel Inorganic materials 0.000 title claims abstract description 122
- 239000010959 steel Substances 0.000 title claims abstract description 122
- 238000010276 construction Methods 0.000 title claims abstract description 10
- 238000006073 displacement reaction Methods 0.000 claims abstract description 28
- 238000009434 installation Methods 0.000 claims abstract description 15
- 238000003466 welding Methods 0.000 claims abstract description 6
- XEEYBQQBJWHFJM-UHFFFAOYSA-N Iron Chemical compound [Fe] XEEYBQQBJWHFJM-UHFFFAOYSA-N 0.000 claims description 48
- 229910052742 iron Inorganic materials 0.000 claims description 24
- 230000000694 effects Effects 0.000 claims description 12
- 238000000034 method Methods 0.000 description 13
- 230000007812 deficiency Effects 0.000 description 1
- 230000002950 deficient Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 239000000463 material Substances 0.000 description 1
Images
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
The invention discloses a construction method for quickly installing a large-sized steel bridge in an urban main road, which is characterized by comprising the technical steps of installing 2-3 pieces of positioning I-steel or channel steel on one side of a temporary support of the steel bridge to be erected, controlling the left and right displacement of a steel box girder in the horizontal direction, installing two pieces of positioning I-steel or channel steel on two ends of the temporary support of a bridge pier of the steel bridge to be erected, controlling the up and down displacement of the steel box girder in the vertical direction, welding a positioning steel plate at the bottom of the steel box girder to be erected, ensuring the front and back displacement of the steel box girder in the horizontal direction, and then completing installation.
Description
[technical field]
The present invention relates to solve a kind of job practices that is used for the large-scale steel bridge beam of Fast Installation under the big construction environment of Traffic Flow of Major Road of City amount, particularly relate to a kind of job practices of using the big shaped steel case of simple and easy brief summary member Fast Installation beam.
[background technology]
At present; The mounting method of large-scale steel bridge beam generally adopts artificial commander, and manpower draws the artificial method of adjustment of establishing cable wind rope, and the steel bridge beam that needs are installed is set up on predetermined bridge pier or support; This method construction precision is low; Operating speed is slow, and steel case beam very easily misplaces in lifting case beam process, adjusts long with regard to bit time.If under the big environment of Traffic Flow of Major Road of City amount; For obstruction not, require operating efficiency high especially, construction finishes as early as possible; So existing conventional construction method can not satisfy the demands, a kind of method that large-scale bridge girder steel is installed fast and accurately of market demand.
[summary of the invention]
The objective of the invention is to above technical deficiency; A kind of job practices that is used at the large-scale steel bridge beam of major urban arterial highway Fast Installation is provided; The present invention is directed to the defective of existing conventional construction method; Can carry out installing and locating to large-scale steel bridge beam fast, accurately, improve operating efficiency, implement convenient and practical.
Technical scheme of the present invention is described below: a kind of job practices that is used at the large-scale steel bridge beam of major urban arterial highway Fast Installation is characterized in that it comprises following construction sequence:
1), in falsework one side of waiting to set up the steel bridge beam 2-3 spare location i iron or channel-section steel are installed, effect is a control steel case beam left and right displacement in the horizontal direction;
2), at the falsework two ends of waiting to set up the steel bridge beam two location i iron or channel-section steel are installed, effect is the upper and lower displacement of control steel case beam in vertical direction, with the jack fine setting, reaches steel case beam design elevation at last;
3), in welding fixing steel plate in steel case beam bottom to be set up, the front and back displacement in the horizontal direction of assurance steel case beam;
4), when steel case beam is installed, the crane steel case beam of slinging, steel case beam both sides pull-up cable wind rope; Steel case beam is during near on-station position; The artificial tension of cable wind rope, steel case beam leans against on described location i iron or the channel-section steel, and effect is a control steel case beam left and right displacement in the horizontal direction;
5), steel case beam is during near on-station position, steel case beam is placed on location i iron or the channel-section steel, effect is the upper and lower displacement of control steel case beam in vertical direction, accomplishes the installation of steel bridge beam at last.
According to above-mentioned technical scheme, its characteristic is that also the location i iron model of control steel case beam left and right displacement in the horizontal direction is I20-I24, and perhaps the channel-section steel model is that [20-[24.
According to above-mentioned technical scheme, its characteristic is that also the i iron model is I20-I24 to control steel case beam in the location of the upper and lower displacement of vertical direction, and perhaps the channel-section steel model is that [20-[24.
According to above-mentioned technical scheme, its characteristic also is, control steel case beam in the length of the location of the upper and lower displacement of vertical direction i iron or channel-section steel greater than 30 millimeters-50 millimeters of jack height.
According to the present invention of above-mentioned technical characterstic, installation accuracy is high, and speed is fast, and the workman is easy to control in hoisting process, can practice thrift artificial and material and mechanical one-shift, not limited by the place, and security performance is high.
Below in conjunction with accompanying drawing and implementation process this method is described further.
[description of drawings]
Accompanying drawing 1 is that steel case beam of the present invention is provided with level and the structural representation of vertically locating i iron.
Accompanying drawing 2 is structural representations of steel case beam of the present invention bottom welding fixing steel plate.
Steel bridge beam in the drawings, 1; 2, bridge pier or support; 3, vertically locate i iron or channel-section steel; 4, jack; 5, horizontal location i iron or channel-section steel; 6, fixing steel plate.
[specific embodiment]
Like Fig. 1, shown in 2, a kind of job practices that is used at the large-scale steel bridge beam of major urban arterial highway Fast Installation is characterized in that, it comprises following construction sequence:
1), in falsework one side of waiting to set up the steel bridge beam 2-3 spare location i iron or channel-section steel are installed, effect is a control steel case beam left and right displacement in the horizontal direction;
2), at the falsework two ends of waiting to set up the steel bridge beam two location i iron or channel-section steel are installed, effect is the upper and lower displacement of control steel case beam in vertical direction, with the jack fine setting, reaches steel case beam design elevation at last;
3), in welding fixing steel plate in steel case beam bottom to be set up, the front and back displacement in the horizontal direction of assurance steel case beam;
4), when steel case beam is installed, the crane steel case beam of slinging, steel case beam both sides pull-up cable wind rope; Steel case beam is during near on-station position; The artificial tension of cable wind rope, steel case beam leans against on described location i iron or the channel-section steel, and effect is a control steel case beam left and right displacement in the horizontal direction;
5), steel case beam is during near on-station position, steel case beam is placed on location i iron or the channel-section steel, effect is the upper and lower displacement of control steel case beam in vertical direction, accomplishes the installation of steel bridge beam at last.
According to above-mentioned technical scheme, its characteristic is that also the location i iron model of control steel case beam left and right displacement in the horizontal direction is I20-I24, and perhaps the channel-section steel model is that [20-[24.
According to above-mentioned technical scheme, its characteristic is that also the i iron model is I20-I24 to control steel case beam in the location of the upper and lower displacement of vertical direction, and perhaps the channel-section steel model is that [20-[24.
According to above-mentioned technical scheme, its characteristic also is, control steel case beam in the length of the location of the upper and lower displacement of vertical direction i iron or channel-section steel greater than 30 millimeters-50 millimeters of jack height.
In the 3rd above-mentioned step, for the front and back displacement in the horizontal direction of control cabinet beam, at case beam bottom welding fixing steel plate, steel case beam is during near on-station position, and fixing steel plate abuts against on the falsework, the swing in the horizontal direction of control cabinet beam.
Shown in the enforcement and accompanying drawing of this method, be merely the part of the better case study on implementation of this method, can not limit to this method with this.Under the condition that does not break away from this method, any change that those skilled in the art did all belongs within the protection of this method.
Claims (4)
1. a job practices that is used at the large-scale steel bridge beam of major urban arterial highway Fast Installation is characterized in that, it comprises following construction sequence:
1), in falsework one side of waiting to set up the steel bridge beam 2-3 spare location i iron or channel-section steel are installed, effect is a control steel case beam left and right displacement in the horizontal direction;
2), at the falsework two ends of waiting to set up the steel bridge beam two location i iron or channel-section steel are installed, effect is the upper and lower displacement of control steel case beam in vertical direction, with the jack fine setting, reaches steel case beam design elevation at last;
3), in welding fixing steel plate in steel case beam bottom to be set up, the front and back displacement in the horizontal direction of assurance steel case beam;
4), when steel case beam is installed, the crane steel case beam of slinging, steel case beam both sides pull-up cable wind rope; Steel case beam is during near on-station position; The artificial tension of cable wind rope, steel case beam leans against on described location i iron or the channel-section steel, and effect is a control steel case beam left and right displacement in the horizontal direction;
5), steel case beam is during near on-station position, steel case beam is placed on location i iron or the channel-section steel, effect is the upper and lower displacement of control steel case beam in vertical direction, accomplishes the installation of steel bridge beam at last.
2. the job practices that is used at the large-scale steel bridge beam of major urban arterial highway Fast Installation according to claim 1, its characteristic are that also the location i iron model of control steel case beam left and right displacement in the horizontal direction is I20-I24, and perhaps the channel-section steel model is that [20-[24.
3. the job practices that is used at the large-scale steel bridge beam of major urban arterial highway Fast Installation according to claim 1, its characteristic are that also the i iron model is I20-I24 to control steel case beam in the location of the upper and lower displacement of vertical direction, and perhaps the channel-section steel model is that [20-[24.
4. the job practices that is used at the large-scale steel bridge beam of major urban arterial highway Fast Installation according to claim 1; Its characteristic also is, control steel case beam in the length of the location of the upper and lower displacement of vertical direction i iron or channel-section steel greater than 30 millimeters-50 millimeters of jack height.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 201110229036 CN102383375B (en) | 2011-08-10 | 2011-08-10 | Construction method for quickly mounting large steel bridge on urban main road |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 201110229036 CN102383375B (en) | 2011-08-10 | 2011-08-10 | Construction method for quickly mounting large steel bridge on urban main road |
Publications (2)
Publication Number | Publication Date |
---|---|
CN102383375A true CN102383375A (en) | 2012-03-21 |
CN102383375B CN102383375B (en) | 2013-08-07 |
Family
ID=45823176
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN 201110229036 Expired - Fee Related CN102383375B (en) | 2011-08-10 | 2011-08-10 | Construction method for quickly mounting large steel bridge on urban main road |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102383375B (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111005322A (en) * | 2019-12-31 | 2020-04-14 | 上海市机械施工集团有限公司 | Temporary support and construction method for bridge |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1800498A (en) * | 2005-07-12 | 2006-07-12 | 上海市第二市政工程有限公司 | Large scale concrete box girder hoisting method |
KR20090017342A (en) * | 2007-08-14 | 2009-02-18 | 고려개발 주식회사 | Duplex bridge type overpass and construction method |
CN101392501A (en) * | 2007-09-17 | 2009-03-25 | 上海远东国际桥梁建设有限公司 | Erection method for wide span steel box bridge |
KR20090068526A (en) * | 2007-12-24 | 2009-06-29 | 재단법인 포항산업과학연구원 | Construction method of bridge structure and steel composite girder bridge using the same |
CN101864729A (en) * | 2010-06-25 | 2010-10-20 | 清华大学 | A cable-stayed bridge corrugated steel web composite box girder deck system and its construction method |
KR101004618B1 (en) * | 2010-08-12 | 2011-01-03 | 이엔이건설주식회사 | Construction method of composite girder bridge using temporary steel transverse ribs and permanent concrete transverse ribs |
-
2011
- 2011-08-10 CN CN 201110229036 patent/CN102383375B/en not_active Expired - Fee Related
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1800498A (en) * | 2005-07-12 | 2006-07-12 | 上海市第二市政工程有限公司 | Large scale concrete box girder hoisting method |
KR20090017342A (en) * | 2007-08-14 | 2009-02-18 | 고려개발 주식회사 | Duplex bridge type overpass and construction method |
CN101392501A (en) * | 2007-09-17 | 2009-03-25 | 上海远东国际桥梁建设有限公司 | Erection method for wide span steel box bridge |
KR20090068526A (en) * | 2007-12-24 | 2009-06-29 | 재단법인 포항산업과학연구원 | Construction method of bridge structure and steel composite girder bridge using the same |
CN101864729A (en) * | 2010-06-25 | 2010-10-20 | 清华大学 | A cable-stayed bridge corrugated steel web composite box girder deck system and its construction method |
KR101004618B1 (en) * | 2010-08-12 | 2011-01-03 | 이엔이건설주식회사 | Construction method of composite girder bridge using temporary steel transverse ribs and permanent concrete transverse ribs |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111005322A (en) * | 2019-12-31 | 2020-04-14 | 上海市机械施工集团有限公司 | Temporary support and construction method for bridge |
Also Published As
Publication number | Publication date |
---|---|
CN102383375B (en) | 2013-08-07 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103982045B (en) | A kind of roofing latticed shell structure is encorbelmented construction method of installation without support | |
CN203284785U (en) | Verticality-adjusting fixing system of reverse steel pipe column | |
CN207775734U (en) | A kind of balance regulator of single-cantilever assembly | |
CN104314009B (en) | Big sections hoisting mechanism and using method | |
CN103437563B (en) | Mounting method for steel skeleton of large steel structure factory building | |
CN203403369U (en) | Bridge installing and positioning support | |
CN205228807U (en) | Wind turbine blades static test device | |
CN105201219A (en) | Structure synchronous unloading device and construction method thereof | |
CN203866831U (en) | Telescopic splicing guide frame for large-diameter steel protecting cylinder | |
CN201770414U (en) | Jig apparatus for installing and lifting shear webs of megawatt wind generator | |
CN203403368U (en) | Bridge installing and locating support with improved structure | |
CN103601078B (en) | Suspension type hanging device | |
CN108978485A (en) | A kind of steel construction cable-stayed bridge anchor tie plate field installation process | |
CN102383375B (en) | Construction method for quickly mounting large steel bridge on urban main road | |
CN105040591A (en) | Positioning device for waveform steel web and positioning method thereof | |
CN102425115A (en) | Control method for actively overcoming self weight and line shape of loose cable saddle buttress concrete | |
CN213328682U (en) | Mounting structure suitable for heavy scattered cable saddle | |
CN202220329U (en) | Bridge installation positioning support | |
CN205419600U (en) | A base steel construction for constructing tower crane base accurate positioning installation | |
CN104120654A (en) | Prefabricated segment beam bridge girder erection machine and segment beam assembly method | |
CN203403367U (en) | Novel bridge installing and locating support | |
CN204455850U (en) | The interim suspension connection device of Large Steel box beam erection | |
CN211420898U (en) | Vertical positioning device for large-span corrugated steel web | |
CN203222810U (en) | Steel column and base structure system | |
CN209211443U (en) | A kind of device for inserting and placing improving long steel pile casting verticality |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20130807 Termination date: 20200810 |
|
CF01 | Termination of patent right due to non-payment of annual fee |