Emergent repairing tower upside-down mounting frame
Technical field
The present invention relates to electrical equipment technical field, is specifically a kind of emergent repairing tower upside-down mounting frame.
Background technology
At present, the bar of transmission line of electricity, the accident of falling the tower form great threat to power system, and it not only causes power equipment to damage, and power failure etc., also had a strong impact on safe operation and the normal safety utilization of electric power of user of electrical network.Emergent repairing tower be for power system transmission line occur bar, fall tower or column foot landslide while causing power outage, the equipment that the tower of replacement accident temporarily restores electricity rapidly.The emergent repairing tower of prior art is to be formed by connecting through flange by a plurality of tower sections, when erectting emergent repairing tower, by the whole emergent repairing tower that connects in advance with the lifting machine installation of slinging, but, when erectting emergent repairing tower, can run into the place spatial constraints of Special geographical position, as hillside, irregular field, ground etc., lifting machine can't enter, and therefore just can't carry out whole tower lifting.
Summary of the invention
The technical problem to be solved in the present invention is, overcomes the defect of above prior art, provides a kind of and takes up an area that space is little, the emergent repairing tower upside-down mounting frame of high efficiency.
Technical solution of the present invention is, a kind of emergent repairing tower upside-down mounting frame with following structure is provided: it comprises upside-down mounting frame body, on described upside-down mounting frame body, lifting appliance is installed, the lifting end of described lifting appliance connects heavy plate, on described lifting plate, be flexibly connected the first pallet that a tower section for emergent repairing tower is placed, described the first pallet is provided with two the first hanging rings, the top of described upside-down mounting frame body is fixedly connected with two hook ropes, the free end of described two hook ropes connect two with the first pallet on two hooks that the first hanging ring matches and articulates; It also comprises the second pallet, and described the second pallet is provided with two the second hanging rings that match and articulate with two hooks of two hook ropes.
After adopting above structure, emergent repairing tower upside-down mounting frame of the present invention compared with prior art, have the following advantages: this emergent repairing tower upside-down mounting frame in use, upside-down mounting frame body can be placed on the column foot of power supply tower, first tower section is placed on to lifting appliance to be promoted on the first pallet of holding the lifting plate, after lifting appliance drives first tower section and rises to correct position, utilize the hook rope hook of upside-down mounting frame bodies top to live two the first hanging rings on the first pallet, the first pallet is fixed on upside-down mounting frame body together with first tower section on the first pallet; Then drive lifting appliance and be displaced downwardly to initial position, on the lifting plate of lifting appliance, place again the second pallet, then second tower section is placed on the second pallet of lifting plate, driving lifting appliance makes second tower section rise to first tower section bottom again, the top of the bottom of first tower section and second tower section is connected and fixed by flange, extract the first pallet of first tower section bottom untie out simultaneously the hook of hook rope, first pallet is used further to the 3rd tower section and places; Restart lifting appliance and make second tower section be promoted to first tower section place, then with the hook rope hook, live the second pallet of second tower section bottom.So by that analogy, repetitive operation, until found emergent repairing tower.This emergent repairing tower upside-down mounting frame construction area is few, high efficiency, and installation quality is good and operation is highly low, easy to operate.
As preferably, described lifting appliance comprises two the first pulleys that are fixed on upside-down mounting frame bodies top both sides, two ropes that are fixed on the second pulley of upside-down mounting frame body two bottom sides and walk around two the first pulleys and two the second pulleys, two free ends of described rope are fixedly connected with the lifting plate, and the force side of rope is enclosed within on drive pulley and is arranged on the outside of upside-down mounting frame body.This lifting appliance adopts assembly pulley to make castering action power little, simple in structure, easy to use.
The accompanying drawing explanation
Fig. 1 is the structural representation of emergent repairing tower upside-down mounting frame of the present invention.
As shown in the figure:
1, upside-down mounting frame body, 2, the tower section, the 3, first pulley, 4, the hook rope, the 5, first pallet, the 6, first hanging ring, 7, the lifting plate, the 8, second pulley, 9, rope, 10, drive pulley, 11, hook, the 12, second pallet, the 13, second hanging ring.
The specific embodiment
The present invention is further detailed explanation below in conjunction with the drawings and specific embodiments.
As shown in Figure 1,
Emergent repairing tower upside-down mounting frame of the present invention, it comprises upside-down mounting frame body 1, on described upside-down mounting frame body 1, lifting appliance is installed, the lifting end of described lifting appliance connects heavy plate 7, on described lifting plate 7, be flexibly connected the first pallet 5 that a tower section for emergent repairing tower 2 is placed, described the first pallet 5 is provided with two the first hanging rings 6, the top of described upside-down mounting frame body 1 is fixedly connected with two hook ropes 4, the free end of described two hook ropes 4 connect two with the first pallet 5 on two hooks 11 that the first hanging ring 6 matches and articulates; It also comprises the second pallet 12, and described the second pallet 12 is provided with two and links up with 11 the second hanging rings 13 that match and articulate with two two of linking up with rope 4.
Described lifting appliance comprises two the first pulleys 3 that are fixed on upside-down mounting frame body 1 both sides, top, two ropes 9 that are fixed on the second pulley 8 of upside-down mounting frame body 1 two bottom sides and walk around two the first pulleys 3 and two the second pulleys 8, two free ends of described rope 9 are fixedly connected with lifting plate 7, and the force side of rope 9 is enclosed within on drive pulley 10 and is arranged on the outside of upside-down mounting frame body 1.
The operating principle of emergent repairing tower upside-down mounting frame of the present invention is: this emergent repairing tower upside-down mounting frame in use, upside-down mounting frame body 1 can be placed on the column foot of power supply tower, first tower section 2 is placed on to lifting appliance to be promoted on the first pallet 5 of holding lifting plate 7, after lifting appliance drives first tower section 2 and rises to correct position, utilize the hook rope 4 at upside-down mounting frame body 1 top to hook two the first hanging rings 6 on the first pallet 5, the first pallet 5 is fixed on upside-down mounting frame body 1 together with first tower section 2 on the first pallet 5; Then drive lifting appliance and be displaced downwardly to initial position, on the lifting plate 7 of lifting appliance, place again the second pallet 12, then second tower section 2 is placed on the second pallet 12 of lifting plate 7, driving lifting appliance makes second tower section 2 rise to first tower section 2 bottoms again, the top of the bottom of first tower section 2 and second tower section 2 is connected and fixed by flange, extract the first pallet 5 of first tower section 2 bottoms untie out simultaneously the hook 11 of hook rope 4, first pallet 5 is used further to the 3rd tower section 2 and places; Restart lifting appliance and make second tower section 2 be promoted to first tower section place, then with hook rope 4, hook the second pallet 12 of second tower section bottom.So by that analogy, repetitive operation, until found emergent repairing tower.