CN203905435U - Multilayer lifting platform for installation of combustor - Google Patents

Multilayer lifting platform for installation of combustor Download PDF

Info

Publication number
CN203905435U
CN203905435U CN201420302498.2U CN201420302498U CN203905435U CN 203905435 U CN203905435 U CN 203905435U CN 201420302498 U CN201420302498 U CN 201420302498U CN 203905435 U CN203905435 U CN 203905435U
Authority
CN
China
Prior art keywords
platform
fixed
movable
fixed platform
lifting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn - After Issue
Application number
CN201420302498.2U
Other languages
Chinese (zh)
Inventor
吕延波
林海
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SEPCO1 Electric Power Construction Co Ltd
Original Assignee
SEPCO1 Electric Power Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SEPCO1 Electric Power Construction Co Ltd filed Critical SEPCO1 Electric Power Construction Co Ltd
Priority to CN201420302498.2U priority Critical patent/CN203905435U/en
Application granted granted Critical
Publication of CN203905435U publication Critical patent/CN203905435U/en
Anticipated expiration legal-status Critical
Withdrawn - After Issue legal-status Critical Current

Links

Landscapes

  • Load-Engaging Elements For Cranes (AREA)

Abstract

The utility model provides a multilayer lifting platform for installation of a combustor. The multilayer lifting platform comprises a fixed platform, a plurality of layers of movable platforms movably fixed under the fixed platform through a locking device, a plurality of lifting lugs fixed to the fixed platform and a winch fixed above the fixed platform. A reel is arranged over the fixed platform. A steel wire rope of the winch is fixed to the lifting lugs after being wound around the reel. In the using process, the winch is started firstly to lift the movable platforms to a proper position, and the fixed platform is fixed to the lower portion of a platform unit through the locking device. According to the combination mode of the fixed platform and the movable platforms, the movable platforms can continue to be combined as needed. After combination of the movable platforms is completed, the winch is started, all the platforms are lifted to the position of a nozzle of the combustor or another proper construction position, and then workers can carry out construction conveniently. When the lifting height of the lifting platform needs changing, the lifting height of the lifting platform can be changed at will by starting the winch.

Description

The multiple layer up-down platform that a kind of burner is installed
Technical field
The utility model relates to a kind of lift platform.
Background technology
Power boiler breeze burner is installed the existing two kinds of modes of inside staging, and a kind of is full hall scaffold operating platform in stove, and another kind is the large lift platform of individual layer in stove, and the first platform labor intensive and putting up platform belong to high-risk work items; The second platform device takies many, and expense is high and use dumbly, can only, in the work of same absolute altitude face, cause the waste of resource.
Summary of the invention
The utility model is in order to overcome the deficiency of above technology, the multiple layer up-down platform that provides a kind of burner flexible for installation, can multiple benches to install.
The utility model overcomes the technical scheme that its technical problem adopts:
The multiple layer up-down platform that this burner is installed, comprise fixed platform, by locking system activity, be fixed on some layers of movable platform of fixed platform below, the hoist engine that is fixed on the some hangers in fixed platform and is arranged at fixed platform top, directly over described fixed platform, be provided with reel, the wire rope of described hoist engine is fixed on each hanger after walking around reel.
Above-mentioned locking system comprise be arranged at fixed platform and movable platform below some fixed covers, be fixed on some inserted links of movable platform top, on described fixed cover, fixed head is installed, on described fixed head, be provided with two down-side tilt slotted holes, two pin slide are arranged in slotted hole and it is positioned at fixed cover, described inserted link two ends are respectively arranged with some draw-in grooves from top to bottom, under Action of Gravity Field, pin slide is during to slotted hole lower end, and described bearing pin is placed in the draw-in groove of inserted link.
For prevent from that platform from rocking, also comprise being arranged at fixed platform and or each movable platform on some hook II.
For convenient construction personnel arrive other layer of platform, also comprise the fixed bar and the cat ladder that are arranged in fixed platform and each movable platform, described cat ladder is placed on the fixed bar of fixed platform and movable platform by hook I.
In order to improve safety, also comprise the manhole excessively that is arranged at close cat ladder place in fixed platform and each movable platform.
The beneficial effects of the utility model are: during use, first start hoist engine movable platform is risen to suitable position, fixed platform is fixed to the bottom of platform unit by locking system.According to the combination of fixed platform and movable platform, can continue as required combined moving platform.After treating platform combination, start hoist engine, all platforms are risen to burner nozzle position or other suitable construction locations, can facilitate staff to carry out constructing operation.While needing the adjustable height of conversion lift platform, starting hoist engine can arbitrarily change.The multiple layer up-down platform that this burner is installed is installed combined and instant, and volume is small and exquisite can multilayer work flexibly simultaneously, has improved operating efficiency, has saved resource.
Accompanying drawing explanation
Fig. 1 is perspective view of the present utility model;
Fig. 2 is fixed platform structural representation of the present utility model;
Fig. 3 is movable platform structure schematic diagram of the present utility model;
Fig. 4 is locking system structural representation of the present utility model;
In figure, 1. hoist engine 2. reel 3. wire rope 4. fixed platform 5. movable platform 6. hanger 7. cat ladder 8. hook I 9. hook II 10. are crossed manhole 11. fixed bar 12. fixed cover 13. inserted link 14. fixed head 15. slotted hole 16. draw-in groove 17. bearing pins.
The specific embodiment
Below in conjunction with accompanying drawing 1 to 4 pairs of the utility model of accompanying drawing, be described further.
As shown in Figure 1, the multiple layer up-down platform that this burner is installed, comprise fixed platform 4, by locking system activity, be fixed on the some layers of movable platform 5 of fixed platform 4 belows, the hoist engine 1 that is fixed on the some hangers 6 in fixed platform 4 and is arranged at fixed platform 4 tops, directly over fixed platform 4, be provided with reel 2, the wire rope 3 of hoist engine 1 is fixed on each hanger 6 after walking around reel 2.During use, first start hoist engine 1 movable platform 5 is risen to suitable position, fixed platform 4 is fixed to the bottom of platform unit 1 by locking system.Combination according to fixed platform 4 with movable platform 5, can continue combined moving platform 5 as required.After treating platform combination, start hoist engine 3, all platforms are risen to burner nozzle position or other suitable construction locations, can facilitate staff to carry out constructing operation.While needing the adjustable height of conversion lift platform, starting hoist engine 1 can arbitrarily change.The multiple layer up-down platform that this burner is installed is installed combined and instant, and volume is small and exquisite can multilayer work flexibly simultaneously, has improved operating efficiency, has saved resource.
As shown in accompanying drawing 2, accompanying drawing 3 and accompanying drawing 4, above-mentioned locking system comprise be arranged at fixed platform 4 and movable platform 5 belows some fixed covers 12, be fixed on some inserted links 13 of movable platform 12 tops, fixed head 14 is installed on fixed cover 12, on fixed head 14, be provided with two down-side tilt slotted holes 15, two bearing pins 17 slide and are arranged in slotted hole 15 and it is positioned at fixed cover 12, inserted link 13 two ends are respectively arranged with some draw-in grooves from top to bottom, under Action of Gravity Field, when bearing pin 17 slides into slotted hole 15 lower end, bearing pin 17 is placed in the draw-in groove 16 of inserted link 13.When needs carry out Fast Installation by each platform, inserted link 13 is inserted in the endoporus of fixed cover 12, inserted link 13 can be pushed along slotted hole 15 bearing pin 17 open when inserting to both sides, can conveniently adjust upper and lower both sides platform to suitable position.After adjusting to the right place, bearing pin 17 glides and drops down onto slotted hole 15 bottom in the effect of gravity, and now inserted link 13 draw-in groove on it under Action of Gravity Field is stuck on bearing pin 17, therefore realizes the Fast Installation of levels and fixes.When needs are dismantled, by bearing pin 17 is manually pulled to both sides along slotted hole 15, inserted link 13 can be taken out from fixed cover 12.
Can also comprise be arranged at fixed platform 4 and or each movable platform 5 on some hook II 9.That this platform rise to after construction location, can by rope utilization hook II 9, be suspended to the firm position of building nearby, can effectively prevent that multiple layer up-down platform that this burner is installed from producing in use the situation of rocking and occurring.
As shown in Figure 2, also comprise the fixed bar 11 and the cat ladder 7 that are arranged in fixed platform 4 and each movable platform 5, cat ladder 7 is placed on the fixed bar 11 of fixed platform 4 and movable platform 5 by hook I 8.Therefore constructor can utilize cat ladder to arrive up and down on interlayer platform, convenient construction.Also comprise the manhole 10 excessively that is arranged at close cat ladder 7 places in fixed platform 4 and each movable platform 5.Constructor can pass through manhole 10 and be facilitated and arrive other layer of platform at any time by cat ladder 7 from the inside of the multiple layer up-down platform of this burner installation.Owing to climbing up and climbing down from inside, therefore improved greatly safety.

Claims (5)

1. the multiple layer up-down platform that a burner is installed, it is characterized in that: comprise fixed platform (4), by locking system activity, be fixed on the some layers of movable platform (5) of fixed platform (4) below, the hoist engine (1) that is fixed on the some hangers (6) in fixed platform (4) and is arranged at fixed platform (4) top, directly over described fixed platform (4), be provided with reel (2), the wire rope (3) of described hoist engine (1) is fixed on each hanger (6) after walking around reel (2).
2. the multiple layer up-down platform that burner according to claim 1 is installed, it is characterized in that: described locking system comprises the some fixed covers (12) that are arranged at fixed platform (4) and movable platform (5) below, be fixed on some inserted links (13) of movable platform (12) top, fixed head (14) is installed on described fixed cover (12), on described fixed head (14), be provided with two down-side tilt slotted holes (15), two bearing pins (17) slide and to be arranged in slotted hole (15) and it is positioned at fixed cover (12), described inserted link (13) two ends are respectively arranged with some draw-in grooves from top to bottom, under Action of Gravity Field, when bearing pin (17) slides into slotted hole (15) lower end, described bearing pin (17) is placed in the draw-in groove (16) of inserted link (13).
3. the multiple layer up-down platform that burner according to claim 1 is installed, is characterized in that: also comprise be arranged at fixed platform (4) and or each movable platform (5) on some hook II (9).
4. the multiple layer up-down platform of installing according to the burner described in claim 1 or 2 or 3, it is characterized in that: also comprise the fixed bar (11) and the cat ladder (7) that are arranged in fixed platform (4) and each movable platform (5), described cat ladder (7) is placed on the fixed bar (11) of fixed platform (4) and movable platform (5) by hook I (8).
5. the multiple layer up-down platform that burner according to claim 4 is installed, is characterized in that: also comprise and be arranged at the manhole (10) excessively of locating near cat ladder (7) in fixed platform (4) and each movable platform (5).
CN201420302498.2U 2014-06-09 2014-06-09 Multilayer lifting platform for installation of combustor Withdrawn - After Issue CN203905435U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420302498.2U CN203905435U (en) 2014-06-09 2014-06-09 Multilayer lifting platform for installation of combustor

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420302498.2U CN203905435U (en) 2014-06-09 2014-06-09 Multilayer lifting platform for installation of combustor

Publications (1)

Publication Number Publication Date
CN203905435U true CN203905435U (en) 2014-10-29

Family

ID=51779723

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420302498.2U Withdrawn - After Issue CN203905435U (en) 2014-06-09 2014-06-09 Multilayer lifting platform for installation of combustor

Country Status (1)

Country Link
CN (1) CN203905435U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104005549A (en) * 2014-06-09 2014-08-27 山东电力建设第一工程公司 Multi-layer lift platform mounted on combustor
CN112096048A (en) * 2020-09-14 2020-12-18 中国建筑第八工程局有限公司 Double-layer integral lifting operation platform for high-rise building construction

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104005549A (en) * 2014-06-09 2014-08-27 山东电力建设第一工程公司 Multi-layer lift platform mounted on combustor
CN104005549B (en) * 2014-06-09 2015-12-23 山东电力建设第一工程公司 The multiple layer up-down platform that a kind of burner is installed
CN112096048A (en) * 2020-09-14 2020-12-18 中国建筑第八工程局有限公司 Double-layer integral lifting operation platform for high-rise building construction

Similar Documents

Publication Publication Date Title
KR101553966B1 (en) Wall-mounted Tower Crane Climbing Device
CN201268937Y (en) Double-layer hanging cradle for working aloft
EP3077666B1 (en) An internal tower structure for a wind turbine generator
US10753110B2 (en) Rack structure for an in-field 3D construction printer
CN204057851U (en) Performance stage booth lifting mechanism
CN105226560B (en) A kind of crossing frame and its construction method
CN104358336A (en) Unit type curtain wall installation system and installation method thereof
CN106136561A (en) Electrician can backpack Self-unlocking lifting tool bag
KR20120131710A (en) Cage rail climbing system
CN205429566U (en) Crossing structure
CN106150057B (en) A kind of split blade type hydraulic pressure lift climbing frame
CN203905435U (en) Multilayer lifting platform for installation of combustor
CN103422662A (en) Integral mobile construction platform for cast-in-place of elevator shaft and method for using same
CN207647152U (en) Tower lifts constructing device certainly
CN104016243B (en) Boiler cable shaft hanging apparatus
CN201541085U (en) Lifting device for rotary insulated platform
CN104005549B (en) The multiple layer up-down platform that a kind of burner is installed
CN104150393A (en) Micro power electric equipment rotating and hoisting device
CN107487423B (en) Marine suspension scaffold and construction method thereof
CN206784958U (en) A kind of encorbelmented across metal greatly decorates prefabricated roof and air translation splicing structure
CN105544957A (en) Mobile scaffold for horizontal overhead pipeline construction and construction method thereof
CN202731270U (en) Movable platform for high-altitude installation operation of space steel structure
JP6554610B2 (en) Assembly method for a DC converter valve
CN107060347A (en) A kind of big encorbelmented across metal decorates prefabricated roof and air translation splicing structure
CN103121629B (en) Hoisting method of large support equipment for basement

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
AV01 Patent right actively abandoned

Granted publication date: 20141029

Effective date of abandoning: 20151223

C25 Abandonment of patent right or utility model to avoid double patenting