Emergent repairing tower upside-down mounting frame
Technical field
The present invention relates to electrical equipment technical field, specifically is a kind of emergent repairing tower upside-down mounting frame.
Background technology
At present, the bar of transmission line of electricity, the accident of falling the tower constitute great threat to power system, and it not only causes power equipment to damage, and power failure etc. have also had a strong impact on the safe operation and the normal safety utilization of electric power of user of electrical network.Emergent repairing tower be used for power system transmission line take place bar, fall tower or column foot landslide when causing power outage, the equipment that the tower of replacement accident temporarily restores electricity rapidly.The emergent repairing tower of prior art is to be formed by connecting through flange a plurality of tower sections; When erectting emergent repairing tower, with the whole emergent repairing tower that connects in advance with the lifting machine installation of slinging, still; When erectting emergent repairing tower, can run into the place spatial constraints in special geographical position; Like hillside, irregular field, ground etc., lifting machine can't get into, and therefore just can't put in order the tower lifting.
Summary of the invention
The technical problem that the present invention will solve is, overcomes the defective of above prior art, provides a kind of and takes up an area of that the space is little, the emergent repairing tower upside-down mounting frame of high efficiency.
Technical solution of the present invention is; A kind of emergent repairing tower upside-down mounting frame with following structure is provided: it comprises upside-down mounting frame body; On the said upside-down mounting frame body lifting appliance is installed; The lifting end of said lifting appliance connects heavy plate, flexibly connects one on the said lifting plate and supplies first pallet of the tower section placement of emergent repairing tower, and said first pallet is provided with two first hanging rings; Said upside-down mounting frame upper part of body is fixedly connected two hook ropes, the free end of said two hook ropes connect two with first pallet on two first hooks that hanging ring matches and articulates; It also comprises second pallet, and said second pallet is provided with two second hanging rings that match and articulate with two hooks of two hook ropes.
After adopting above structure; Emergent repairing tower upside-down mounting frame of the present invention compared with prior art; Have the following advantages: this emergent repairing tower upside-down mounting frame in use; Can upside-down mounting frame body be placed on the column foot of power supply tower, first tower section be placed on lifting appliance promote on first pallet of end lifting plate, after first tower section of lifting appliance drive rises to correct position; Utilize the hook rope hook of upside-down mounting frame bodies top to live two first hanging rings on first pallet, first pallet is fixed on the upside-down mounting frame body together with first tower section on first pallet; Drive lifting appliance then and be displaced downwardly to initial position; On the lifting plate of lifting appliance, place second pallet again; Then second tower section is placed on second pallet of lifting plate, drives lifting appliance again and make second tower section rise to first tower section bottom, the bottom of first tower section and the top of second tower section are connected and fixed through flange; Simultaneously first pallet of first tower section bottom is extracted and untied out the hook of hook rope, first pallet is used further to the 3rd tower section and places; Restart lifting appliance and make second tower section be promoted to first tower section place, live second pallet of second tower section bottom again with the hook rope hook.So by that analogy, repetitive operation is until emergent repairing tower is stood.This emergent repairing tower upside-down mounting frame construction area is few, high efficiency, and installation quality is good and operation is highly low, easy to operate.
As preferably; Described lifting appliance comprises two first pulleys that are fixed on upside-down mounting frame bodies top both sides; Two second pulleys and the rope of walking around two first pulleys and two second pulleys that are fixed on upside-down mounting frame body two bottom sides; Two free ends of said rope are fixedly connected with the lifting plate, and the force side of rope is enclosed within on the drive pulley and is arranged on the outside of upside-down mounting frame body.This lifting appliance adopts assembly pulley to make castering action power little, simple in structure, easy to use.
Description of drawings
Fig. 1 is the structural representation of emergent repairing tower upside-down mounting frame of the present invention.
As shown in the figure:
1, upside-down mounting frame body, 2, the tower section, 3, first pulley, 4, the hook rope, 5, first pallet, 6, first hanging ring, 7, the lifting plate, 8, second pulley, 9, rope, 10, drive pulley, 11, hook, 12, second pallet, 13, second hanging ring.
The specific embodiment
Below in conjunction with the accompanying drawing and the specific embodiment the present invention is done further detailed explanation.
It is as shown in Figure 1,
Emergent repairing tower upside-down mounting frame of the present invention; It comprises upside-down mounting frame body 1; On the said upside-down mounting frame body 1 lifting appliance is installed; The lifting end of said lifting appliance connects heavy plate 7, flexibly connects one on the said lifting plate 7 and supplies first pallet 5 of tower section 2 placements of emergent repairing tower, and said first pallet 5 is provided with two first hanging rings 6; The top of said upside-down mounting frame body 1 is fixedly connected two hook ropes 4, the free end of said two hook ropes 4 connect two with first pallet 5 on two first hanging rings 6 hook 11 that matches and articulate; It also comprises second pallet 12, and said second pallet 12 is provided with two two second hanging rings 13 that hook 11 matches and articulates with two hook ropes 4.
Described lifting appliance comprises two first pulleys 3 that are fixed on both sides, upside-down mounting frame body 1 top; Two second pulleys 8 and the rope 9 of walking around two first pulleys 3 and two second pulleys 8 that are fixed on upside-down mounting frame body 1 two bottom sides; Two free ends of said rope 9 are fixedly connected with lifting plate 7, and the force side of rope 9 is enclosed within on the drive pulley 10 and is arranged on the outside of upside-down mounting frame body 1.
The operating principle of emergent repairing tower upside-down mounting frame of the present invention is: this emergent repairing tower upside-down mounting frame in use; Can upside-down mounting frame body 1 be placed on the column foot of power supply tower; First tower section 2 is placed on lifting appliance to be promoted on first pallet 5 of end lifting plate 7; After first tower section 2 of lifting appliance drive rises to correct position; Two first hanging rings 6 that utilize the hook rope 4 at upside-down mounting frame body 1 top to hook on first pallet 5 make first pallet 5 be fixed on the upside-down mounting frame body 1 together with first tower section 2 on first pallet 5; Drive lifting appliance then and be displaced downwardly to initial position; On the lifting plate 7 of lifting appliance, place second pallet 12 again; Then second tower section 2 is placed on second pallet 12 of lifting plate 7; Driving lifting appliance again makes second tower section 2 rise to first tower section 2 bottoms; The bottom of first tower section 2 and the top of second tower section 2 are connected and fixed through flange, simultaneously first pallet 5 of first tower section 2 bottoms are extracted and untied out the hook 11 of hook rope 4, first pallet 5 is used further to the 3rd tower section 2 and places; Restart lifting appliance and make second tower section 2 be promoted to first tower section place, hook second pallet 12 of second tower section bottom again with hook rope 4.So by that analogy, repetitive operation is until emergent repairing tower is stood.