CN102251781A - 散粒体围岩隧道导向水平旋喷桩预支护施工方法 - Google Patents

散粒体围岩隧道导向水平旋喷桩预支护施工方法 Download PDF

Info

Publication number
CN102251781A
CN102251781A CN2011101060595A CN201110106059A CN102251781A CN 102251781 A CN102251781 A CN 102251781A CN 2011101060595 A CN2011101060595 A CN 2011101060595A CN 201110106059 A CN201110106059 A CN 201110106059A CN 102251781 A CN102251781 A CN 102251781A
Authority
CN
China
Prior art keywords
drilling
churning
jet grouting
orifice tube
guide hole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2011101060595A
Other languages
English (en)
Other versions
CN102251781B (zh
Inventor
何复生
朱家稳
蔡爽
杨勇
王声扬
吴文彪
石伟
张琳
王国炜
罗飚
胡光全
陈艳林
杨兴林
杨全勇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway No 2 Engineering Group Co Ltd
China Railway Erju 1st Engineering Co Ltd
Original Assignee
China Railway Erju Co Ltd
China Railway Erju 1st Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Erju Co Ltd, China Railway Erju 1st Engineering Co Ltd filed Critical China Railway Erju Co Ltd
Priority to CN 201110106059 priority Critical patent/CN102251781B/zh
Publication of CN102251781A publication Critical patent/CN102251781A/zh
Application granted granted Critical
Publication of CN102251781B publication Critical patent/CN102251781B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

本发明公开了一种散粒体围岩隧道导向水平旋喷桩预支护施工方法,通过采用水平定向钻机先打设精度高于5‰的导孔,导孔打设到设计长度后旋转回撤钻杆,在回撤钻杆的同时,用35~40MPa的压力,将配制好的水泥浆液通过钻杆喷射到土体中。喷射流以巨大的冲击力切削土体,强制土体颗粒与水泥浆液搅拌混合,在胶结硬化后,形成水平圆柱状水泥土固结体,即水平旋喷桩。当旋喷桩相互咬合后,便以同心圆形式在隧道拱部外侧形成封闭的水平旋喷帷幕体形成超预支护,有效防止了漏沙引起坍塌问题;而且成本低,在保证安全的同时大大加快施工速度。

Description

散粒体围岩隧道导向水平旋喷桩预支护施工方法
技术领域
本发明涉及一种散粒体围岩隧道工程的施工方法,特别涉及一种适用于沙层、风积沙层等松散软弱不稳定地质中隧道开挖前的超前预支护施工方法。
背景技术
对于长距离、超浅埋、大断面、散粒体围岩隧道,由于隧道洞身穿越处风积沙粒径属特细沙的散粒体,具有粒径均匀、透水性强、几无粘聚性、堆放致密、注浆渗透性差等特征。对于这类不良地质规模的隧道,国内外尚无系统、完整和规范的超前预支护施工方法可以借鉴。
发明内容
本发明的发明目的在于:提供了一种散粒体围岩隧道导向水平旋喷桩预支护施工方法,在风积沙地层中施工方便,有效解决了传统超前预支护存在的漏沙引起坍塌的技术问题。
为了解决上述技术问题,本发明所采用的技术方案如下:一种散粒体围岩隧道导向水平旋喷桩预支护施工方法,包括如下步骤:
第一步、施工准备:检查钻机、注浆泵运行是否正常,钻具、工具是否齐全;设置工作室;测量放线定桩位;平整工作平台,铺设轨道、安装机架,钻机就位,调整钻机角度、方位,安装钻头;
第二步、打设导孔:采用?130mm钻头钻进,钻进深度为1.60m,初始开孔角度为0.5%;退出钻具,将一根直径为?127mm、长0.8m的孔口管埋入已开好的孔内,孔口管外露0.30m;在掌子面植?12mm钢筋4根,钢筋用锚固剂固结,将钢筋与孔口管焊接牢固;安装法兰盘和球阀;预导孔施工采用水平定向钻进打设,利用导向定位系统跟踪监测预导孔打设角度和方位变化,发现钻进角度偏差需及时进行纠偏;打设导孔;检查确定孔口管安装牢固后,调整钻机,对好孔位;将旋喷钻头及第一根钻杆送入孔口管内;安装密封装置;打开循环液排出口;开始钻进,每钻进4m使用水平导向仪测量一次,并做好测量记录,一旦发现偏斜需及时进行纠偏,直到钻至设计深度;钻进过程中保持循环液压力为1.0~2.0Mpa;
第三步、喷浆:按1:1的重量比将水和水泥配制成水泥浆;在制浆过程中随时测量浆液比重,浆液用搅拌机搅制,搅拌浆液需连续均匀,搅拌时间大于等于5min,一次搅拌用量的使用时间控制在4h以内;当钻进到设计深度时开始旋喷,喷浆至孔口掌子面0.50m时停止喷浆;卸下孔口管最外端的密封装置,关闭循环液排出口;拔出钻杆和钻头,关闭大球阀;旋喷注浆完成后在循环液排出口处安装压力表,然后用注浆泵补注浆,注浆压力控制在0.8-1.0MPa;补注浆完成48h后卸下大球阀。
所述工作室的长度为8m、高度为钻机高度加二分之一桩径进行设置。
所述测量放线定桩位包括在掌子面测量标出隧道开挖轮廓线,测量定出桩位,用钢筋作好桩位标志,并编好每个桩号。
在所述铺设轨道、安装机架时,需满足:H型钢轨找平误差≤3mm;底盘对角线误差≤3mm;斜拉筋需绷紧,交叉拉力相等;四柱对角误差≤5mm。
在旋喷时,先旋喷30min后再开始后退,旋喷前5m时,后退速度保持在15~18cm/min,以后升到20cm/min;喷浆压力控制在35~40MPa之间。
与现有技术相比,本发明的有益效果是:通过采用水平定向钻机先打设精度高于5‰的导孔,导孔打设到设计长度后旋转回撤钻杆,在回撤钻杆的同时,用35~40MPa的压力,将配制好的水泥浆液通过钻杆喷射到土体中。喷射流以巨大的冲击力切削土体,强制土体颗粒与水泥浆液搅拌混合,在胶结硬化后,形成水平圆柱状水泥土固结体,即水平旋喷桩。当旋喷桩相互咬合后,便以同心圆形式在隧道拱部外侧形成封闭的水平旋喷帷幕体形成超预支护,有效防止了漏沙引起坍塌问题,提供了一种在风积沙地层中施工方便、结构合理的水平旋喷桩全新预支护体系,成本低,在保证安全的同时大大加快施工速度。
具体实施方式
一种散粒体围岩隧道导向水平旋喷桩预支护施工方法,包括如下步骤:
第一步、施工准备:
1、检查钻机、高压注浆泵运行是否正常,钻具、工具是否齐全。
2、设置工作室:工作室的长度和高度根据水平旋喷桩桩机的长度和高度进行确定。现场水平旋喷桩钻机长度是7.5m,工作室的长度采用8m;钻机高度是0.5m,工作室的高度为钻机高度加二分之一桩径进行设置。其作用是为水平旋喷桩钻机提供作业空间。
3、测量放线定桩位:在掌子面测量标出隧道开挖轮廓线,测量定出桩位,用钢筋作好桩位标志,并编好每个桩号。
4、设备安装:A、平整工作平台;B、铺设轨道、安装机架;C、钻机就位;D、调整钻机角度、方位;E、安装钻头。在铺设轨道和安装立柱时,需满足:H型钢轨找平误差≤3mm;底盘对角线误差≤3mm;斜拉筋需绷紧,交叉拉力相等;四柱对角误差≤5mm。
第二步、打设导孔:
1、开孔器开孔:
采用?130mm钻头钻进,钻进深度为1.60m;初始开孔角度为0.5%;
退出钻具,准备安装孔口管;
将一根直径为?127mm、长0.8m的孔口管埋入已开好的孔内,作为孔口管,孔口管外露0.30m;
在掌子面植?12mm钢筋4根,钢筋用锚固剂固结,将钢筋与孔口管焊接牢固,以加固孔口管;
安装法兰盘和球阀。
2、预导孔的导向定位:
预导孔施工采用水平定向钻进打设,利用导向定位系统跟踪监测预导孔打设角度和方位变化,发现钻进角度偏差应及时进行纠偏。导向定位系统包括导向钻头及导向定位探棒。
钻头内装有传感器,传感器由15V直流供电。导向定位系统的显示屏显示钻头的倾角(水平角度)、面向角(导向板的方向:导向板朝上即为12点,如同钟面)。打设角度如果偏下,可以把钻头调到12点,即导向板朝上,直接顶进,此时由于导向板底板斜面面积大。受到一个向上的力,钻头轨迹就会朝上运动。同理在6点纠偏可以使钻头轨迹朝下,9点、3点分别是为左、右纠偏方向。如果角度合适,钻机会匀速旋转钻进,此时钻杆轨迹一般是平直的。
3、打设导孔:
打设导孔的目的:一是根据地质条件,调整钻机钻进、回撤动力及速度;二是掌握成孔精度,为后续旋喷桩施工提供技术依据。
4、钻进:
检查确定孔口管安装牢固后,调整钻机,对好孔位;将旋喷钻头及第一根钻杆送入孔口管内;安装密封装置(即在预埋孔口管外端埋设密封装置,目的是将孔口管与钻杆间的间隙进行密封;其作用是稳定钻机钻进过程中的循环液压力);打开循环液排出口;
开始钻进,每钻进4m要使用水平导向仪测量一次,并做好测量记录,一旦发现偏斜要及时进行纠偏,直到钻至设计深度。
钻进过程中要保持循环液压力1.0~2.0MPa,但不得超过2.0MPa。
第三步、喷浆:
(1)配制浆液:
根据配比配制水泥浆,要求水:水泥为1:1,在制浆过程中应随时测量浆液比重,浆液用高速搅拌机搅制,搅拌浆液必须连续均匀,搅拌时间大于等于5min,一次搅拌用量的使用时间亦控制在4h以内,并要求对浆液进行试块试验。
在制浆过程中应随时测量浆液比重,每孔高压喷浆结束后要统计该孔的材料用量。
(2)拔杆喷浆:
当钻进到设计深度时开始旋喷,为了保证端头旋喷质量,先旋喷30min后再开始后退,旋喷前5m时,后退速度保持在15~18cm/min,以后可升到20cm/min;喷浆压力控制在35~40MPa之间。
(3)封孔:
喷浆至孔口掌子面0.50m时,应停止喷浆;卸下孔口管最外端的密封装置,关闭循环液排出口;快速拔出钻杆和钻头,关闭大球阀;高压旋喷注浆完成后应在循环液排出口处安装压力表,然后用注浆泵补注浆,注浆压力控制在0.8-1.0MPa;补注浆完成48h后方能卸下大球阀结束封孔。

Claims (5)

1.一种散粒体围岩隧道导向水平旋喷桩预支护施工方法,其特征在于:包括如下步骤:
第一步、施工准备:检查钻机、注浆泵运行是否正常,钻具、工具是否齐全;设置工作室;测量放线定桩位;平整工作平台,铺设轨道、安装机架,钻机就位,调整钻机角度、方位,安装钻头;
第二步、打设导孔:采用?130mm钻头钻进,钻进深度为1.60m,初始开孔角度为0.5%;退出钻具,将一根直径为?127mm、长0.8m的孔口管埋入已开好的孔内,孔口管外露0.30m;在掌子面植?12mm钢筋4根,钢筋用锚固剂固结,将钢筋与孔口管焊接牢固;安装法兰盘和球阀;预导孔施工采用水平定向钻进打设,利用导向定位系统跟踪监测预导孔打设角度和方位变化,发现钻进角度偏差需及时进行纠偏;打设导孔;检查确定孔口管安装牢固后,调整钻机,对好孔位;将旋喷钻头及第一根钻杆送入孔口管内;安装密封装置;打开循环液排出口;开始钻进,每钻进4m使用水平导向仪测量一次,并做好测量记录,一旦发现偏斜需及时进行纠偏,直到钻至设计深度;钻进过程中保持循环液压力为1.0~2.0Mpa;
第三步、喷浆:按1:1的重量比将水和水泥配制成水泥浆;在制浆过程中随时测量浆液比重,浆液用搅拌机搅制,搅拌浆液需连续均匀,搅拌时间大于等于5min,一次搅拌用量的使用时间控制在4h以内;当钻进到设计深度时开始旋喷,喷浆至孔口掌子面0.50m时停止喷浆;卸下孔口管最外端的密封装置,关闭循环液排出口;拔出钻杆和钻头,关闭大球阀;旋喷注浆完成后在循环液排出口处安装压力表,然后用注浆泵补注浆,注浆压力控制在0.8-1.0MPa;补注浆完成48h后卸下大球阀。
2.根据权利要求1所述的散粒体围岩隧道导向水平旋喷桩预支护施工方法,其特征在于:所述工作室的长度为8m、高度为钻机高度加二分之一桩径进行设置。
3.根据权利要求1所述的散粒体围岩隧道导向水平旋喷桩预支护施工方法,其特征在于:所述测量放线定桩位包括在掌子面测量标出隧道开挖轮廓线,测量定出桩位,用钢筋作好桩位标志,并编好每个桩号。
4.根据权利要求1所述的散粒体围岩隧道导向水平旋喷桩预支护施工方法,其特征在于:在所述铺设轨道、安装机架时,需满足:H型钢轨找平误差≤3mm;底盘对角线误差≤3mm;斜拉筋需绷紧,交叉拉力相等;四柱对角误差≤5mm。
5.根据权利要求1所述的散粒体围岩隧道导向水平旋喷桩预支护施工方法,其特征在于:在第三步所述旋喷时,先旋喷30min后再开始后退,旋喷前5m时,后退速度保持在15~18cm/min,以后升到20cm/min;喷浆压力控制在35~40MPa之间。
CN 201110106059 2011-04-27 2011-04-27 散粒体围岩隧道导向水平旋喷桩预支护施工方法 Active CN102251781B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201110106059 CN102251781B (zh) 2011-04-27 2011-04-27 散粒体围岩隧道导向水平旋喷桩预支护施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201110106059 CN102251781B (zh) 2011-04-27 2011-04-27 散粒体围岩隧道导向水平旋喷桩预支护施工方法

Publications (2)

Publication Number Publication Date
CN102251781A true CN102251781A (zh) 2011-11-23
CN102251781B CN102251781B (zh) 2013-07-17

Family

ID=44979318

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201110106059 Active CN102251781B (zh) 2011-04-27 2011-04-27 散粒体围岩隧道导向水平旋喷桩预支护施工方法

Country Status (1)

Country Link
CN (1) CN102251781B (zh)

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102650210A (zh) * 2012-05-11 2012-08-29 中铁十二局集团有限公司 下半断面为干燥粉细砂层隧道的施工方法
CN102720505A (zh) * 2012-06-20 2012-10-10 中铁十二局集团有限公司 上半断面为干燥粉细砂层隧道的开挖方法
CN102748036A (zh) * 2012-07-03 2012-10-24 中铁十二局集团有限公司 加固干燥粉细砂层隧道的浆液配比及施工方法
CN103291326A (zh) * 2013-07-05 2013-09-11 河南理工大学 一种大变形巷道围岩再造承载层控制技术
CN103306687A (zh) * 2012-10-31 2013-09-18 王卓 软岩隧道长悬臂水平旋喷变形控制施工方法
CN103883332A (zh) * 2014-02-28 2014-06-25 北京市市政工程研究院 粉细砂地层加固方法及装置
CN105019917A (zh) * 2015-08-13 2015-11-04 青岛业高建设工程有限公司 冲击钻进式超前旋喷管棚施工装置及施工方法
CN105525619A (zh) * 2016-01-20 2016-04-27 中铁隆工程集团有限公司 一种富水地层暗挖隧道咬合管幕及其施工方法
CN105909263A (zh) * 2016-06-13 2016-08-31 中交第公路勘察设计研究院有限公司 风积沙地层公路隧道结构及其施工方法
CN110989001A (zh) * 2019-12-24 2020-04-10 山东大学 一种运用hdd技术的桩基三维钻孔ct探测方法
CN111236951A (zh) * 2020-02-22 2020-06-05 中铁十九局集团第六工程有限公司 风积砂地层隧道洞口段咬合桩加固方法
CN115262605A (zh) * 2022-06-30 2022-11-01 中煤科工集团西安研究院有限公司 一种矿山超深侧向截水帷幕构筑方法

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH04108910A (ja) * 1990-08-28 1992-04-09 Daido Concrete Kogyo Kk 沈設コンクリート杭の杭頭処理方法
CN1657711A (zh) * 2005-03-21 2005-08-24 严平 旋喷锚杆桩施工工艺
CN1710213A (zh) * 2005-07-04 2005-12-21 雷玉华 带高压旋喷桩尖的同步组合桩的施工方法
CN101255693A (zh) * 2008-04-17 2008-09-03 徐玉杰 地基加固的水泥砂浆旋喷桩及施工方法

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4108910B2 (ja) * 2000-09-01 2008-06-25 株式会社リコー 画像処理装置、画像処理方法および記録媒体

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH04108910A (ja) * 1990-08-28 1992-04-09 Daido Concrete Kogyo Kk 沈設コンクリート杭の杭頭処理方法
CN1657711A (zh) * 2005-03-21 2005-08-24 严平 旋喷锚杆桩施工工艺
CN1710213A (zh) * 2005-07-04 2005-12-21 雷玉华 带高压旋喷桩尖的同步组合桩的施工方法
CN101255693A (zh) * 2008-04-17 2008-09-03 徐玉杰 地基加固的水泥砂浆旋喷桩及施工方法

Cited By (19)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102650210A (zh) * 2012-05-11 2012-08-29 中铁十二局集团有限公司 下半断面为干燥粉细砂层隧道的施工方法
CN102650210B (zh) * 2012-05-11 2014-07-09 中铁十二局集团有限公司 下半断面为干燥粉细砂层隧道的施工方法
CN102720505A (zh) * 2012-06-20 2012-10-10 中铁十二局集团有限公司 上半断面为干燥粉细砂层隧道的开挖方法
CN102748036B (zh) * 2012-07-03 2015-04-22 中铁十二局集团有限公司 加固干燥粉细砂层隧道的浆液配比及施工方法
CN102748036A (zh) * 2012-07-03 2012-10-24 中铁十二局集团有限公司 加固干燥粉细砂层隧道的浆液配比及施工方法
CN103306687B (zh) * 2012-10-31 2015-09-16 北京中铁瑞威基础工程有限公司 软岩隧道长悬臂水平旋喷变形控制施工方法
CN103306687A (zh) * 2012-10-31 2013-09-18 王卓 软岩隧道长悬臂水平旋喷变形控制施工方法
CN103291326B (zh) * 2013-07-05 2015-08-19 河南理工大学 一种大变形巷道围岩再造承载层控制技术
CN103291326A (zh) * 2013-07-05 2013-09-11 河南理工大学 一种大变形巷道围岩再造承载层控制技术
CN103883332A (zh) * 2014-02-28 2014-06-25 北京市市政工程研究院 粉细砂地层加固方法及装置
CN103883332B (zh) * 2014-02-28 2016-08-17 北京市市政工程研究院 粉细砂地层加固方法及装置
CN105019917A (zh) * 2015-08-13 2015-11-04 青岛业高建设工程有限公司 冲击钻进式超前旋喷管棚施工装置及施工方法
CN105525619A (zh) * 2016-01-20 2016-04-27 中铁隆工程集团有限公司 一种富水地层暗挖隧道咬合管幕及其施工方法
CN105525619B (zh) * 2016-01-20 2018-10-02 中铁隆工程集团有限公司 一种富水地层暗挖隧道咬合管幕
CN105909263A (zh) * 2016-06-13 2016-08-31 中交第公路勘察设计研究院有限公司 风积沙地层公路隧道结构及其施工方法
CN110989001A (zh) * 2019-12-24 2020-04-10 山东大学 一种运用hdd技术的桩基三维钻孔ct探测方法
CN111236951A (zh) * 2020-02-22 2020-06-05 中铁十九局集团第六工程有限公司 风积砂地层隧道洞口段咬合桩加固方法
CN115262605A (zh) * 2022-06-30 2022-11-01 中煤科工集团西安研究院有限公司 一种矿山超深侧向截水帷幕构筑方法
CN115262605B (zh) * 2022-06-30 2023-07-18 中煤科工集团西安研究院有限公司 一种矿山超深侧向截水帷幕构筑方法

Also Published As

Publication number Publication date
CN102251781B (zh) 2013-07-17

Similar Documents

Publication Publication Date Title
CN102251781B (zh) 散粒体围岩隧道导向水平旋喷桩预支护施工方法
CN104453946B (zh) 一种软弱围岩隧道修建的超前加固施工方法
CN102277898B (zh) 排水管顶进施工方法
CN104929114A (zh) 一种高压旋喷桩止水帷幕施工装置及其方法
CN101245600B (zh) 用高压双液旋喷技术生成水平加固体的施工方法
CN108951612A (zh) 一种地铁隧道盾构端头加固方法
CN204753574U (zh) 一种高压旋喷桩止水帷幕施工装置
CN103015519A (zh) 排水管顶管施工
CN104674798A (zh) 一种无置换上下转换喷浆的五轴水泥土搅拌桩施工工法
CN102182199A (zh) 高压摆喷止水帷幕施工方法
CN108755671B (zh) 一种富水砾砂层三轴搅拌桩施工方法
CN103388338A (zh) 一种新型快速止水及土体改良的方法
CN110259466A (zh) 一种地铁车站富水砂层大断面盾构施工工艺
CN102953374A (zh) 一种输电线路铁塔桩基施工用高压旋喷桩施工方法
CN107653889A (zh) 一种型钢压灌水泥土帷幕支护桩的施工方法
CN111636455A (zh) 一种trd与旋挖引孔深度止水帷幕的综合建造方法
CN110306531A (zh) 高水位漂石地层连续墙施工工艺
CN110777775A (zh) 一种基坑结构及其施工方法
CN113293773A (zh) 一种基坑支护体系及其施工方法
CN110005456A (zh) 一种软岩大变形隧道台阶法锚杆快速施工方法
CN103850261A (zh) 入岩深基坑嵌岩止水帷幕施工方法
CN112252310A (zh) 采用高压旋喷桩机进行深基坑止水帷幕施工的方法
CN103015435A (zh) 长螺旋潜孔锤振动旋喷水泥土型钢桩基坑止水支护方法
CN108590668B (zh) 一种暗挖车站超长管棚拉管法
CN107604907A (zh) 一种深基坑支护工程锚索防渗漏施工工法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20160108

Address after: Jinniu District Kam Tong Road Chengdu city Sichuan province 610031 No. 16

Patentee after: CHINA RAILWAY NO.2 BUREAU ENGINEERING Co.,Ltd.

Address before: 610041, No. nine, No. 156, building B, high building, Xing Xing Road, Chengdu hi tech Zone, Sichuan

Patentee before: CHINA RAILWAY ERJU Co.,Ltd.

Patentee before: CHINA RAILWAY ERJU 1ST ENGINEERING Co.,Ltd.

CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: No. 16, Jinniu District Road, Jinniu District Road, Chengdu, Sichuan

Patentee after: CHINA RAILWAY NO.2 ENGINEERING GROUP Co.,Ltd.

Address before: No. 16, Jinniu District Road, Jinniu District Road, Chengdu, Sichuan

Patentee before: CHINA RAILWAY NO.2 BUREAU ENGINEERING Co.,Ltd.

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20190122

Address after: No. 16, Jinniu District Road, Jinniu District Road, Chengdu, Sichuan

Co-patentee after: CHINA RAILWAY ERJU 1ST ENGINEERING Co.,Ltd.

Patentee after: CHINA RAILWAY NO.2 ENGINEERING GROUP Co.,Ltd.

Address before: No. 16, Jinniu District Road, Jinniu District Road, Chengdu, Sichuan

Patentee before: CHINA RAILWAY NO.2 ENGINEERING GROUP Co.,Ltd.