CN102251669B - Construction method for cylindrical thin-walled concrete wall template - Google Patents

Construction method for cylindrical thin-walled concrete wall template Download PDF

Info

Publication number
CN102251669B
CN102251669B CN201110137405A CN201110137405A CN102251669B CN 102251669 B CN102251669 B CN 102251669B CN 201110137405 A CN201110137405 A CN 201110137405A CN 201110137405 A CN201110137405 A CN 201110137405A CN 102251669 B CN102251669 B CN 102251669B
Authority
CN
China
Prior art keywords
template
outside
support
construction
hoop
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201110137405A
Other languages
Chinese (zh)
Other versions
CN102251669A (en
Inventor
万海滨
胡应洪
姚江涛
李洪生
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Ge Zhou Ba group is second project Co., Ltd.
Original Assignee
China Gezhouba Group No 2 Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Gezhouba Group No 2 Engineering Co Ltd filed Critical China Gezhouba Group No 2 Engineering Co Ltd
Priority to CN201110137405A priority Critical patent/CN102251669B/en
Publication of CN102251669A publication Critical patent/CN102251669A/en
Application granted granted Critical
Publication of CN102251669B publication Critical patent/CN102251669B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention discloses a construction method for a cylindrical thin-walled concrete wall template. The method comprises the following steps of: placing an inner support in an inner ring of an inner template to reinforce and adjust the inner template, arranging an outer hoop at the periphery of an outer template, arranging a limiting support between the inner and outer templates to control the relative size and position of the inner and outer templates, and controlling the steadiness of the templates under the combined action of the inner support, the outer hoop and the limiting support. The construction method is simple, low in cost, convenient in construction and good in template stability, and improves the labor condition of construction personnel. The method is particularly suitable for concrete cylindrical machine piers of hydraulic generators of hydropower stations, air cover walls, and cylindrical thin-walled concrete buildings with inside diameter of less than 10M and the like.

Description

The job practices of drum type brake thin wall concrete wall form
Technical field:
The present invention relates to the job practices of the realm of building construction drum type brake thin wall concrete wall form, be particularly useful for power station hydrogenerator concrete cylinder machine pier and fan housing wall, cylindrical shape building.
Background technology:
At present, the most frequently used reinforcement means of drum type brake thin wall concrete wall form construction is the mode that adopts symmetrical tie rod to reinforce.The tie rod contraposition difficulty of the inside and outside template of this kind job practices, the constructor need get into the position operation that reinforcing bar is intensive, built-in fitting is many, the space is narrow and small, operating difficulties, template correction reinforcement amount is big.
Summary of the invention:
The objective of the invention is in order to overcome the deficiency of existing drum type brake thin wall concrete wall construction technology; Provide that a kind of job practices is simple, form stable property is good, with low cost, construction is convenient, improved the job practices of the cylinder thin wall concrete wall form of constructor's condition of labor.
The objective of the invention is to realize like this:
The job practices of drum type brake thin wall concrete wall form of the present invention; This method is that interior support is placed ring reinforcing and adjusting inner formword in the inner formword; Hoop outside on the exterior sheathing neighboring, being provided with; Limited support is set between inside and outside template controls relative size position between inside and outside template, interior support, hoop and limited support synergy control template is firm outward.
Job practices of the present invention specifically comprises the steps:
1) preparation of construction: the inside and outside circular arc of making inside and outside template is respectively enclosed purlin, and every inside and outside panel is separately fixed at inside and outside enclosing on the purlin, forms the inside and outside template of distinguish; Make outer hoop with reinforcing bar and flower basket bolt;
2) construction lofting: emit earlier the end mouth structure line of inside and outside template with total powerstation, every 2-3m spacing is put a point, the fixing end mouth limited support in the bottom of body of wall, and the two ends of limited support flush with the inside and outside structure line of template;
3) inner formword is installed: the first segment inner formword of distinguish is set up in the template after in place support.
4) exterior sheathing is installed: the first segment exterior sheathing of distinguish is in place, vertical steel pipe is installed outside template, hoop outside install in the steel pipe outside is installed the limited support suitable for reading of first segment template;
5) formwork reinforcement and adjustment: support in the adjusting of symmetry simultaneously and outer hoop, accomplish the reinforcing and the adjustment of template, repeat above-mentioned 3) and 4) step, the second joint template is connected with the first segment template, up to the construction of accomplishing whole template;
6) form removal: after concreting is accomplished, loosening interior support and flower basket bolt, promptly dismountable inside and outside template.
Advantage of the present invention: inner formword and exterior sheathing installation and removal are easy, and construction is disturbed few; Exterior sheathing can put in place under the effect of limited support in disposable adjustment reinforcing.The interior support with outer bound round adjusting easily, and be easy to operate; Job practices of the present invention is simple, with low cost, form stable property is good, the distortion is little, has improved constructor's condition of labor.The present invention is specially adapted to power station hydrogenerator concrete cylinder machine pier and fan housing wall, the following drum type brake thin wall concrete of internal diameter 10M works etc.
Description of drawings:
Fig. 1 is the construction process figure of drum type brake thin wall concrete wall of the present invention
Fig. 2 is a drum type brake thin wall concrete wall form structure vertical view of the present invention.
Fig. 3 is that exterior sheathing of the present invention binds round the reinforcing expanded view outward.
The specific embodiment:
Referring to Fig. 1~Fig. 3, the construction method step of present embodiment drum type brake thin wall concrete wall is following:
1) preparation of construction: preparation of construction mainly be support in making 2 with outer hoop 6, inner formword 1, exterior sheathing 4: make inside and outside circular arc respectively and enclose purlin, every inside and outside panel is separately fixed at inside and outside enclosing on the purlin, inner formword 1, the exterior sheathing 4 of formation distinguish.The size of inner formword 1, exterior sheathing 4 will be convenient to transportation and constructor's operation.Template is earlier in factory's group circle inspection; With the outer hoop 6 of the long 2-3m of Φ 8-Φ 12 reinforcement fabrications, bind round 6 two ends outward and respectively process an annulus, be beneficial to flower basket bolt 5 and be connected.Interior 2 general channel-section steel or the steel pipe manufacturings of adopting that support, an end or two ends are provided with the bolt of adjustable length.
2) construction lofting: earlier emit the inside and outside end mouth structure line of body of wall with total powerstation, per 2-3m spacing is put a point, can be with the arc plate external and internal compositions sideline of drawing by layout point.The fixing end mouth limited support 7 in the bottom of body of wall, the two ends of limited support 7 flush with body of wall external and internal compositions sideline.Inspection end mouth elevation, mouth at the bottom of the employing cement mortar screeding.
3) inner formword is installed: the first segment inner formword 1 of distinguish is round with regard to hyte, support 2 in setting up.
4) exterior sheathing is installed: the first segment exterior sheathing 4 of distinguish is round with regard to hyte, vertical Ф 48 steel pipes 3, the spacing 1-2m of steel pipe 3 are installed outside exterior sheathing 4; In steel pipe 3 outsides outer hoop 6 is installed, is bound round the 6 formation closed loops that link to each other with flower basket bolt 5 outward, the limited support 7 that mounting template is suitable for reading; Limited support 7 is direction towards the center of circle; But progressively adjust the outer hoop 6 of flower basket bolt 5 degrees of tightness, support 2 screw rod simultaneously in the adjustment, until inner formword 1, exterior sheathing 4 passed examinations.Downward slippage when preventing that outer hoop 6 is fastening is welded a U type ring at the sidewall of steel pipe 3, will bind round outward to be put in the U type ring.
5) repeat above-mentioned 3) and 4) construction sequence, with second the joint template be connected with the first segment template, with same way up to the completion whole template construction.
6) form removal: after concreting is accomplished, support in loosening 2 with the dismountable inner formword in flower basket bolt 5 backs 1, exterior sheathing 4.
According to the construction needs, interior support can be adopted meter font or intersecting parallels and stable bent structure.
The foregoing description is that foregoing of the present invention is further described, but should this scope that is interpreted as the above-mentioned theme of the present invention only not limited to the foregoing description.All technology that realizes based on foregoing all belong to scope of the present invention.

Claims (1)

1. the job practices of drum type brake thin wall concrete wall form; This method is that interior support is placed ring reinforcing and adjusting inner formword in the inner formword; Hoop outside on the exterior sheathing neighboring, being provided with; Limited support is set between inside and outside template controls relative size position between inside and outside template, interior support, hoop and limited support synergy control template is firm outward, and described job practices specifically comprises the steps:
1) preparation of construction: the inside and outside circular arc of making inside and outside template is enclosed purlin, and every panel is separately fixed at inside and outside enclosing on the purlin, forms the inside and outside template of distinguish, makes outer hoop with reinforcing bar and flower basket bolt;
2) construction lofting: emit earlier the end mouth structure line of inside and outside template with total powerstation, every 2-3m spacing is put a point, the fixing end mouth limited support in the bottom of body of wall, and the two ends of limited support flush with the inside and outside structure line of template;
3) inner formword is installed: the first segment inner formword of distinguish is set up in the template after in place support;
4) exterior sheathing is installed: the first segment exterior sheathing of distinguish is in place, vertical steel pipe is installed outside template, hoop outside install in the steel pipe outside is installed the limited support suitable for reading of first segment template;
5) formwork reinforcement and adjustment: support in the adjusting of symmetry simultaneously and outer hoop, accomplish the reinforcing and the adjustment of template, repeat above-mentioned 3) and 4) step, the second joint template is connected with the first segment template, up to the construction of accomplishing whole template;
6) form removal: after concreting is accomplished, loosening interior support and flower basket bolt, promptly dismountable inside and outside template.
CN201110137405A 2011-05-26 2011-05-26 Construction method for cylindrical thin-walled concrete wall template Active CN102251669B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201110137405A CN102251669B (en) 2011-05-26 2011-05-26 Construction method for cylindrical thin-walled concrete wall template

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201110137405A CN102251669B (en) 2011-05-26 2011-05-26 Construction method for cylindrical thin-walled concrete wall template

Publications (2)

Publication Number Publication Date
CN102251669A CN102251669A (en) 2011-11-23
CN102251669B true CN102251669B (en) 2012-09-12

Family

ID=44979209

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201110137405A Active CN102251669B (en) 2011-05-26 2011-05-26 Construction method for cylindrical thin-walled concrete wall template

Country Status (1)

Country Link
CN (1) CN102251669B (en)

Families Citing this family (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102635230B (en) * 2012-05-17 2015-12-16 福建莆田鸿达牧业有限公司 The formwork for placing of large methane tank body and casting method
CN105525749B (en) * 2015-12-24 2017-11-17 国家电网公司 Substation accident oil sump large form pouring construction method
CN106337368B (en) * 2016-08-25 2018-06-29 中国十七冶集团有限公司 A kind of hypervelocity Thin-Wall Piers template construction stent
CN109424503B (en) * 2017-09-01 2020-07-14 赵晓军 Installation method of center tower and construction method of tower barrel
CN109424243B (en) * 2017-09-01 2022-01-07 赵晓军 Tower drum construction method using enclosing purlin
CN109424504B (en) * 2017-09-01 2020-04-14 赵晓军 Construction method of tower barrel
CN109707073A (en) * 2017-10-26 2019-05-03 孙阳 The assemble method of the interior purlin component of tower
CN109707157A (en) * 2017-10-26 2019-05-03 孙阳 The assemble method of the outer purlin component of tower
CN108978718A (en) * 2018-07-23 2018-12-11 中国水利水电第五工程局有限公司 A kind of inspection shaft gang form
CN109386128A (en) * 2018-11-20 2019-02-26 东莞市太龙湾建设工程有限公司 A kind of mold and construction method for casting concrete pond body
CN110630009B (en) * 2019-09-17 2021-07-02 中国化学工程第六建设有限公司 Arc concrete structure formwork reinforcing construction method
CN111910915A (en) * 2020-07-16 2020-11-10 中国二十冶集团有限公司 Cast-in-place concrete cylinder structure internal mold reinforcing device and construction method thereof
CN112459485B (en) * 2020-10-29 2022-01-25 中国一冶集团有限公司 Circular concrete awl is fought inboard template reinforcing support frame device

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5216863A (en) * 1988-08-15 1993-06-08 Nils Nessa Formwork comprising a plurality of interconnectable formwork elements
CN101824878A (en) * 2010-04-16 2010-09-08 北京工业大学 Multi-cavity steel tube concrete superposed column and preparation method thereof
CN101845850A (en) * 2010-06-22 2010-09-29 中国建筑第二工程局有限公司 Strengthening concrete frame structure and construction method thereof
CN101858143A (en) * 2010-07-09 2010-10-13 徐学文 Mold pipe building construction technology

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5216863A (en) * 1988-08-15 1993-06-08 Nils Nessa Formwork comprising a plurality of interconnectable formwork elements
CN101824878A (en) * 2010-04-16 2010-09-08 北京工业大学 Multi-cavity steel tube concrete superposed column and preparation method thereof
CN101845850A (en) * 2010-06-22 2010-09-29 中国建筑第二工程局有限公司 Strengthening concrete frame structure and construction method thereof
CN101858143A (en) * 2010-07-09 2010-10-13 徐学文 Mold pipe building construction technology

Also Published As

Publication number Publication date
CN102251669A (en) 2011-11-23

Similar Documents

Publication Publication Date Title
CN102251669B (en) Construction method for cylindrical thin-walled concrete wall template
CN103806546B (en) A kind of method of attachment of precast concrete plank
CN109736353A (en) Construction method of composite single-side formwork deep foundation pit basement outer wall
CN102877646B (en) Grouted overlapping assembly type reinforced concrete shear wall structure and method for building grouted overlapping assembly type reinforced concrete shear wall structure
CN207499455U (en) A kind of shaping tool fixture for the anti-bank construction of secondary structure masonry
CN203639005U (en) Reinforcing device of tower crane
CN103334356A (en) Bridge type precast reinforced concrete hidden beam slab pavement system and construction method thereof
CN103334359B (en) Prefabricated reinforced concrete pavement plate and pavement construction method
CN103255866B (en) Roof circular arc-shaped dome structure and manufacturing method
CN201891133U (en) Manual assembled type self-waterproof late poured band prefabricated slab of basement outer wall
CN103046788B (en) Steel funnel of coal blending bin and installation method of traditional steel funnel of coal blending bin
CN203229972U (en) Basement external wall post-pouring-band prefabricated blocking hanging plate
CN109853625A (en) Hybrid mode is linked and packed integral concrete pipe gallery
CN204940652U (en) Large-span prestressed site prefabrication arch bar
CN202180515U (en) Window frame precasting mould for buildings
CN202925975U (en) Steel funnel for coal blending bunker
CN205330156U (en) Cast -in -place template reinforcing apparatus at position is connected to assembly outer wall and cast -in -place interior wall T type
CN212836713U (en) Simple coke oven flue arching construction supporting system
CN204662739U (en) A kind of steel bar truss floor support plate and light-steel light-concrete combining structure
CN103924614B (en) A kind of shaft tower split raft foundation fast-assembling basis
CN203373631U (en) Prefabricated reinforced concrete pavement slab
CN103924714B (en) A kind of steel wire entirety building of skeleton construction body of wall and manufacture craft thereof
CN206815366U (en) A kind of prefabricated assembled basis
KR20070095695A (en) Half assembly-typed construction system and method of common duct
CN111321844A (en) Hollow sandwich steel pipe concrete beam with eccentrically placed inner pipe

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C56 Change in the name or address of the patentee

Owner name: CHINA GE ZHOU BA GROUP IS SECOND PROJECT CO., LTD.

Free format text: FORMER NAME: GEZHOUBA GROUP NO.2 ENGINEERING CO.,LTD.

CP03 Change of name, title or address

Address after: 610091 Sichuan Province, Chengdu District of Qingyang City Industrial Development Zone (East) with the road No. 8 Building 10

Patentee after: China Ge Zhou Ba group is second project Co., Ltd.

Address before: 610091 Sichuan Province, Chengdu District of Qingyang City Industrial Development Zone (East) Road No. 8 Building 10 Gezhouba Dam Tongcheng Group Second Engineering Co Ltd

Patentee before: Gezhouba Group No.2 Engineering Co., Ltd.