CN102182867A - 矿浆管道在流沙层地段的敷设方法 - Google Patents

矿浆管道在流沙层地段的敷设方法 Download PDF

Info

Publication number
CN102182867A
CN102182867A CN 201110093817 CN201110093817A CN102182867A CN 102182867 A CN102182867 A CN 102182867A CN 201110093817 CN201110093817 CN 201110093817 CN 201110093817 A CN201110093817 A CN 201110093817A CN 102182867 A CN102182867 A CN 102182867A
Authority
CN
China
Prior art keywords
pipe trench
ditches
pipelines
pipeline
excavation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN 201110093817
Other languages
English (en)
Other versions
CN102182867B (zh
Inventor
董荔苇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China 19th Metallurgical Corp
Original Assignee
China 19th Metallurgical Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China 19th Metallurgical Corp filed Critical China 19th Metallurgical Corp
Priority to CN 201110093817 priority Critical patent/CN102182867B/zh
Publication of CN102182867A publication Critical patent/CN102182867A/zh
Application granted granted Critical
Publication of CN102182867B publication Critical patent/CN102182867B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Sewage (AREA)

Abstract

本发明涉及浆体的大口径、长距离输送管道敷设,提供了一种矿浆管道在流沙层地段的敷设方法,管沟分段开挖,包括步骤:1)、设置封闭结构隔断已开挖完成的管沟同待开挖段管沟;2)、开挖待开挖段管沟,同时向开挖形成的沟槽内注水,直至完成;3)、将管道两端封闭后移至管沟中,使管道漂浮在水面上;4)、向管道内注水或通过配重将管道压至管沟沟底;5)、回填。利用水的渗透压阻止流沙涌入沟内,通过渗透压挤压、紧实周围沙层,避免沟槽壁的塌方、管沟边缘的地陷,方便管沟成型。回填后,注入的水大部分浸入地下,其余因回填挤出地面。因此施工方便、快速且施工成本低。适用于矿浆管道在流沙层地段的敷设。

Description

矿浆管道在流沙层地段的敷设方法
技术领域
本发明涉及浆体的大口径、长距离输送管道敷设,尤其是一种矿浆管道在流沙层地段的敷设方法。
背景技术
大口径、长距离的浆体管道广泛运用于矿石输送,尤其是位置偏远的矿山。浆体管道线路根据地形、地势进行布置,力求顺直以减少线路长度和避免转弯过多,线路选择应避免经过地形起伏过大地区,尽量减少泵站数量和加速流的产生;线路应尽可能避开滑坡、崩塌、沉陷、泥石流、沼泽、流沙层等地质不良地区,地震烈度大于七度地区的活动断裂带及人口稠密区。但无论是采用地上明敷穿越地质不良地区,还是改线绕过地质不良地区,均会导致成本的急剧上升。
流沙层地段,一般地表地耐力能满足重型机械行走,挖开表层后,表层以下均为流沙层。开挖管沟时,大量流沙涌入沟槽内,沟槽壁塌方严重,沟槽开口能达到几米甚至更多,管沟边缘几米范围内易出现地陷,使管沟成型困难。针对在流沙层地段的施工,目前仅公开了某市政工程流沙层地基的处理工艺,即深层搅拌桩和高压旋喷桩,28天后再对成桩进行检测。但针对大口径长距离矿浆管道在流沙层地段的敷设,还未发现相关的文献报道。由于大口径长距离管矿浆道地域广阔,采用上述深层搅拌桩和高压旋喷桩的处理工艺,成本太高。
发明内容
本发明所要解决的技术问题是提供一种施工方便、快速且施工成本低的矿浆管道在流沙层地段的敷设方法。
本发明解决其技术问题所采用的技术方案是:矿浆管道在流沙层地段的敷设方法,在整个流沙层地段管沟分段开挖,并包括如下步骤:1)、设置封闭结构隔断已开挖完成的管沟同待开挖段管沟;2)、开挖待开挖段管沟,同时向开挖形成的沟槽内注水,直至完成待开挖段管沟的开挖;3)、将管道两端封闭后移至管沟中,使管道漂浮在水面上;4)、向管道内注水或通过配重将管道压至管沟沟底;5)、回填。
进一步的,在所述步骤2)中,控制开挖速度并保证水位始终保持与地表相平。
进一步的,在所述步骤3)中,向管沟内补水并保证水位始终保持与地表相平。
进一步的,所述封闭结构是夯土坝。
进一步的,在所述步骤1)中,在已开挖完成的管沟同待开挖段管沟相邻的一端端头设置封闭结构。
进一步的,所述每段管沟的长度为300~500m。
本发明的有益效果是:通过注水,在整个开挖和埋管过程中,利用水的重力产生的渗透压阻止流沙涌入沟槽内,并通过渗透压对管沟周围沙层的挤压,紧实沙层,水能起到很好的护壁作用,避免了沟槽壁的塌方、管沟边缘的地陷,方便管沟成型。埋管及回填时,注入的水绝大部分浸入地下,极少部分因回填挤出地面。因此施工方便、快速且施工成本低。
具体实施方式
下面结合实施例对本发明进一步说明。
本发明的矿浆管道在流沙层地段的敷设方法,在整个流沙层地段管沟分段开挖,并包括如下步骤:1)、设置封闭结构隔断已开挖完成的管沟同待开挖段管沟;2)、开挖待开挖段管沟,同时向开挖形成的沟槽内注水,直至完成待开挖段管沟的开挖;3)、将管道两端封闭后移至管沟中,使管道漂浮在水面上;4)、向管道内注水或通过配重将管道压至管沟沟底;5)、回填。其中,在所述步骤4)中,为方便操作,保护管道,最好的,采用鞍型配重将管道压至管沟沟底。
为了保证在开挖过程中,整个沟槽壁均受渗透压的作用,在所述步骤2)中,控制开挖速度并保证水位始终保持与地表相平。为了保证在埋管过程中,整个沟槽壁均受渗透压的作用,在所述步骤3)中,向管沟内补水并保证水位始终保持与地表相平。
当开挖沟槽呈V型并坡度较为平缓时,水位也可以低于地表。但水位始终保持与地表相平,除了可以使得整个沟槽壁均受渗透压的作用外,还可以通过漫出的水渗透入管沟边缘的沙层,进一步紧实周围的沙层,避免管沟边缘的地陷。
为了方便施工,所述封闭结构是夯土坝。进一步的,在起始的第一段,可以在相邻的非流沙层留2~3m不开挖,夯实后直接作为夯土坝。
为了在敷设完成后,浆体管道在使用过程中的位置稳定性,回填料应避免使用有机物、骨灰、垃圾、盐碱土、石头、易氧化矿物质等松散、易变形的回填物料。最好采用粘土、拌合土等夯实填充。
上述封闭结构可以在开挖一小段后设置在待开挖段管沟内,但最好的,在所述步骤1)中,在已开挖完成的管沟同待开挖段管沟相邻的一端端头设置封闭结构,能利用上述夯土坝直接构成部分的回填夯土层,进一步加快施工进度。
由于需要设置封闭结构,因此每段管沟的长度越短,施工效率越低;同时,考虑到水的渗透量,每段管沟的长度越长,注水量越大、开挖速度越低,施工越困难。因此,最好的,所述每段管沟的长度为300~500m。

Claims (6)

1.矿浆管道在流沙层地段的敷设方法,在整个流沙层地段管沟分段开挖,并包括如下步骤:
1)、设置封闭结构隔断已开挖完成的管沟同待开挖段管沟;
2)、开挖待开挖段管沟,同时向开挖形成的沟槽内注水,直至完成待开挖段管沟的开挖;
3)、将管道两端封闭后移至管沟中,使管道漂浮在水面上;
4)、向管道内注水或通过配重将管道压至管沟沟底;
5)、回填。
2.如权利要求1所述的矿浆管道在流沙层地段的敷设方法,其特征在于:在所述步骤2)中,控制开挖速度并保证水位始终保持与地表相平。
3.如权利要求1所述的矿浆管道在流沙层地段的敷设方法,其特征在于:在所述步骤3)中,向管沟内补水并保证水位始终保持与地表相平。
4.如权利要求1、2或3所述的矿浆管道在流沙层地段的敷设方法,其特征在于:所述封闭结构是夯土坝。
5.如权利要求4所述的矿浆管道在流沙层地段的敷设方法,其特征在于:在所述步骤1)中,在已开挖完成的管沟同待开挖段管沟相邻的一端端头设置封闭结构。
6.如权利要求1、2或3所述的矿浆管道在流沙层地段的敷设方法,其特征在于:所述每段管沟的长度为300~500m。
CN 201110093817 2011-04-14 2011-04-14 矿浆管道在流沙层地段的敷设方法 Active CN102182867B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201110093817 CN102182867B (zh) 2011-04-14 2011-04-14 矿浆管道在流沙层地段的敷设方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201110093817 CN102182867B (zh) 2011-04-14 2011-04-14 矿浆管道在流沙层地段的敷设方法

Publications (2)

Publication Number Publication Date
CN102182867A true CN102182867A (zh) 2011-09-14
CN102182867B CN102182867B (zh) 2012-12-05

Family

ID=44569130

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201110093817 Active CN102182867B (zh) 2011-04-14 2011-04-14 矿浆管道在流沙层地段的敷设方法

Country Status (1)

Country Link
CN (1) CN102182867B (zh)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102518944A (zh) * 2011-12-15 2012-06-27 攀钢集团工程技术有限公司 原矿输送方法
CN106838464A (zh) * 2017-04-01 2017-06-13 中国十七冶集团有限公司 一种长距离输送管道及π型补偿器水上漂浮安装方法

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4486124A (en) * 1983-10-12 1984-12-04 Kabushiki Kaisha Komatsu Seisakusho Pipe laying method and apparatus
CN1197902A (zh) * 1998-01-21 1998-11-04 袁根木 输水排污管铺设方法
CN1558130A (zh) * 2004-01-30 2004-12-29 胜利油田胜利石油化工建设有限责任公 铺设大口径管道下沟施工方法
CN101315139A (zh) * 2008-06-20 2008-12-03 广州市自来水工程公司 一种过河管沉管施工工艺
JP2010124639A (ja) * 2008-11-21 2010-06-03 Kyuken:Kk 電力用鞘管内充填工法
CN101775826A (zh) * 2010-01-26 2010-07-14 济南金鼎信息技术有限公司 一种铺设输水管道的施工方法

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4486124A (en) * 1983-10-12 1984-12-04 Kabushiki Kaisha Komatsu Seisakusho Pipe laying method and apparatus
CN1197902A (zh) * 1998-01-21 1998-11-04 袁根木 输水排污管铺设方法
CN1558130A (zh) * 2004-01-30 2004-12-29 胜利油田胜利石油化工建设有限责任公 铺设大口径管道下沟施工方法
CN101315139A (zh) * 2008-06-20 2008-12-03 广州市自来水工程公司 一种过河管沉管施工工艺
JP2010124639A (ja) * 2008-11-21 2010-06-03 Kyuken:Kk 電力用鞘管内充填工法
CN101775826A (zh) * 2010-01-26 2010-07-14 济南金鼎信息技术有限公司 一种铺设输水管道的施工方法

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102518944A (zh) * 2011-12-15 2012-06-27 攀钢集团工程技术有限公司 原矿输送方法
CN106838464A (zh) * 2017-04-01 2017-06-13 中国十七冶集团有限公司 一种长距离输送管道及π型补偿器水上漂浮安装方法

Also Published As

Publication number Publication date
CN102182867B (zh) 2012-12-05

Similar Documents

Publication Publication Date Title
CN106759473B (zh) 地下综合管廊和道路的施工结构及其施工方法
CN204059124U (zh) 一种砂桩排水强夯后注浆地基加固结构
CN104131575B (zh) 一种岩溶高度发育地层坝基的堵漏排水方法
CN105672348A (zh) 一种深水区砂卵石地层截除桥梁桩基的施工方法
CN104499479A (zh) 一种穿越砂砾石回填层的挖孔桩施工方法
CN105201001B (zh) 一种岩溶地区大型溶洞的复合防渗结构及其施工方法
CN102966072B (zh) 软弱土地基上堤防加宽加高工程结合面处治的施工方法
CN103032097A (zh) 适用于偏压富水地层的隧道排水结构及其施工方法
CN103981876A (zh) 用于深厚软基河道与傍河路堤共建的组合构件及施工方法
CN108166518A (zh) 地下管线基坑与软土地基同步处理的结构及其加固方法
CN103696416A (zh) 一种地基处理新方法
CN105200973A (zh) 一种软弱地基综合处理方法
CN105971638A (zh) Wss工法在富水砂层盾构换刀加固中的应用
CN108824412B (zh) 基于石笼墙加筋土以及强夯联合的软基处理方法
CN114575355A (zh) 一种土护降施工方法
CN207646754U (zh) 一种桩体贯入式填土体加筋承载结构
CN102425179B (zh) 一种微型钢管灌注桩支撑加筋土渗沟结构
CN103276717B (zh) 复合土工合成材料加筋垫层处理软土地基的方法
CN106869153B (zh) 一种井点降水快速处理软地基的方法
CN108277815A (zh) 用于河流中取水头结构施工的围堰结构及其施工方法
CN110804994B (zh) 一种水库大坝施工方法
CN203050779U (zh) 适用于偏压富水地层的隧道排水结构
CN102182867B (zh) 矿浆管道在流沙层地段的敷设方法
CN107881987A (zh) 深厚覆盖层上面板堆石坝坝基防渗结构
CN215976663U (zh) 一种横穿高压线下的挖方区复合地基处理结构

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant