CN102162250A - 流沙承压水土层大面积深基坑开挖围护施工方法 - Google Patents
流沙承压水土层大面积深基坑开挖围护施工方法 Download PDFInfo
- Publication number
- CN102162250A CN102162250A CN 201010113059 CN201010113059A CN102162250A CN 102162250 A CN102162250 A CN 102162250A CN 201010113059 CN201010113059 CN 201010113059 CN 201010113059 A CN201010113059 A CN 201010113059A CN 102162250 A CN102162250 A CN 102162250A
- Authority
- CN
- China
- Prior art keywords
- deep foundation
- foundation pit
- layer
- soil
- excavation
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Landscapes
- Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
Abstract
本发明公开了一种流沙承压水土层大面积深基坑开挖围护施工方法,其首先控制深基坑开挖的降水深度在开挖面以下500-1000毫米内,深基坑外侧周围设置一圈无砂管井,无砂管井距深基坑边2米、深度大于深基坑底部6-10米、排布间距为15-20米,深基坑内侧边坡铺设钢筋网片并设置一圈轻型井点,然后深基坑开挖后在粉质粘土夹粉土层和粉细沙层的边坡上设置土钉墙进行锚固,土钉墙上设置排水孔;本方法在不增大开挖面积的前提下,确保流沙承压水土层大面积深基坑的开挖,降低了施工难度和成本,减少了施工周期。
Description
技术领域
本发明涉及一种流沙承压水土层大面积深基坑开挖围护施工方法。
背景技术
深基坑开挖围护是深基坑开挖过程中的重要工序,围护不当将造成开挖过程中的各类故障,严重的导致深基坑的坍塌;针对流沙承压水土层,其围护工作尤为重要,如开挖处土层结构为第一层耕填土层、第二层粘土层、第三层粉质粘土夹粉土层、第四层为粉细沙层;粉细沙层为承压含水层,水头高度为6-7米,并位于深基坑开挖层中;如果该部位基坑围护措施不得当,土方开挖至粉细沙层后会造成基坑内粉细沙层在压力作用下涌入基坑内,致使基坑边坡与周围土体大面积坍塌,造成严重的后果。因基坑第三层、第四层土质为粉质粘土夹粉土层和粉细沙层,稳定性很差,且基坑边坡坡度按设计有一定要求,不宜太大,因此基坑开挖后由于基坑边坡比较小容易造成该部位塌落,特别是遇到雨水天气塌落现象会更加严重。
按以往的施工方法,遇到类似地质条件的大面积深基坑,必须进行基坑大范围卸压降水与疏干降水后进行大放坡开挖,该基坑的深度必须按1∶2放坡才能进行开挖,而且还必须在有特殊要求的部位进行局部加固。采用此开挖方法基坑因放坡开挖面积会增加很多,对周围环境影响比较大,如遇开挖空间限制或周边建筑影响时,甚至无法开挖施工,在遇到较大的雨水天气时,因雨水冲刷粉细沙层边坡的土方会大面积塌落,对基坑的整体施工带来严重影响。
如果基坑开挖对基坑坡度有限制,则需对基坑采取重力档墙整体围护,基坑外围进行卸压降水,基坑内部进行疏干降水后才可以进行土方施工。采用此方法工期、造价增加幅度比较大,粉细沙层进行地基加固处理施工质量较难保证。
发明内容
本发明所要解决的技术问题是提供一种流沙承压水土层大面积深基坑开挖围护施工方法,利用本方法在不增大开挖面积的前提下,确保流沙承压水土层大面积深基坑的开挖,降低了施工难度和成本,减少了施工周期。
为解决上述技术问题,本发明流沙承压水土层大面积深基坑开挖围护施工方法,流沙承压水土层为第一层耕填土层、第二层粘土层、第三层粉质粘土夹粉土层、第四层粉细沙层,本方法包括如下步骤:
步骤一、深基坑开挖的降水深度控制在开挖面以下500-1000毫米内,减少对深基坑周围环境的影响;
步骤二、在深基坑外侧周围设置一圈无砂管井,用于降低第四层粉细沙层中承压水头高度,无砂管井距深基坑边2米、深度大于深基坑底部6-10米,无砂管井的排布间距为15-20米;
步骤三、在深基坑内侧的边坡上铺设钢筋网片并设置一圈轻型井点,封堵地下水向基坑内渗入,保持深基坑边坡的基本稳定;
步骤四、深基坑开挖后在粉质粘土夹粉土层和粉细沙层的边坡上设置土钉墙进行锚固,土钉墙上设置排水孔。
进一步,上述土钉墙的土钉采用注浆锚杆,注浆锚杆沿深基坑底部向下倾斜10度,锚杆间距1.5米呈网格状排布,并与深基坑边坡铺设的钢筋网片焊接后喷射混凝土形成锚固土钉墙体。
进一步,上述排水孔采用UPVC管,其长度为300毫米并一端用滤水细纱包裹并同深基坑边坡钢筋网片绑扎设置于土钉墙体内,UPVC管沿土钉墙按2米间距成网格状排布。
由于本发明流沙承压水土层大面积深基坑开挖围护施工方法采用了上述技术方案,即控制深基坑开挖的降水深度在开挖面以下500-1000毫米内,深基坑外侧周围设置一圈无砂管井,无砂管井距深基坑边2米、深度大于深基坑底部6-10米、排布间距为15-20米,深基坑内侧边坡铺设钢筋网片并设置一圈轻型井点,深基坑开挖后在粉质粘土夹粉土层和粉细沙层的边坡上设置土钉墙进行锚固,土钉墙上设置排水孔;本方法在不增大开挖面积的前提下,确保流沙承压水土层大面积深基坑的开挖,降低了施工难度和成本,减少了施工周期。
附图说明
下面结合附图和实施方式对本发明作进一步的详细说明:
图1为本发明施工方法中深基坑的示意图。
具体实施方式
如图1所示,本发明流沙承压水土层大面积深基坑开挖围护施工方法,流沙承压水土层为第一层耕填土层1、第二层粘土层2、第三层粉质粘土夹粉土层3、第四层粉细沙层4,本方法包括如下步骤:
步骤一、深基坑开挖的降水深度控制在开挖面以下500-1000毫米内,减少对深基坑周围环境的影响;
步骤二、在深基坑外侧周围设置一圈无砂管井5,用于降低第四层粉细沙层4中承压水头高度,无砂管井5距深基坑边2米、深度大于深基坑底部6-10米,无砂管井的排布间距为15-20米;
步骤三、在深基坑内侧的边坡上铺设钢筋网片并设置一圈轻型井点6,封堵地下水向基坑内渗入,保持深基坑边坡的基本稳定;轻型井点6的设置有效封堵地下水向深基坑内渗入,保持了深基坑边坡的稳定性;
步骤四、深基坑开挖后在粉质粘土夹粉土层3和粉细沙层4的边坡上设置土钉墙进行锚固,为防止深基坑内水位上升时承压水对土钉墙造成的压力使土钉墙失稳,同时在土钉墙上设置排水孔,排水孔能够及时将土钉墙内部承压水排除,保证了土钉墙的稳定性。
进一步,上述土钉墙的土钉采用注浆锚杆7,注浆锚杆7沿深基坑底部向下倾斜10度,锚杆间距1.5米呈网格状排布,并与深基坑边坡铺设的钢筋网片焊接后喷射混凝土形成锚固土钉墙体。
进一步,上述排水孔采用UPVC管,其长度为300毫米并一端用滤水细纱包裹并同深基坑边坡钢筋网片绑扎设置于土钉墙体内,UPVC管沿土钉墙按2米间距成网格状排布。UPVC管一端采用滤水细纱包裹使其具有良好的虑水性,在喷射混凝土后使UPVC管固定于土钉墙体内。
采用本施工方法,流沙承压水土层大面积的深基坑可顺利开挖,开挖后深基坑内无明水,基坑边坡稳定,即使经过暴雨深基坑内积水都会很快渗入到基底沙层内并通过管井与轻型井点排除,土钉墙内的少量积水能够通过排水孔顺利排除,保证了墙体的整体稳定性。本方法在不增大开挖面积的前提下,可以大幅度减少基坑开挖面积,有效控制基坑边坡稳定性及降水水位高度,确保流沙承压水土层大面积深基坑的开挖,降低了施工难度和成本,减少了施工周期,施工工艺与工序控制简单,采用无砂管井、轻型井点、土钉墙综合施工,保证了基坑开挖与边坡稳定,减少了对周围环境的影响。
Claims (3)
1.一种流沙承压水土层大面积深基坑开挖围护施工方法,流沙承压水土层为第一层耕填土层、第二层为粘土层、第三层为粉质粘土夹粉土层、第四层为粉细沙层,其特征在于:本方法包括如下步骤:
步骤一、深基坑开挖的降水深度控制在开挖面以下500-1000毫米内,减少对深基坑周围环境的影响;
步骤二、在深基坑外侧周围设置一圈无砂管井,用于降低第四层粉细沙层中承压水头高度,无砂管井距深基坑边2米、深度大于深基坑底部6-10米,无砂管井的排布间距为15-20米;
步骤三、在深基坑内侧的边坡上铺设钢筋网片并设置一圈轻型井点,封堵地下水向深基坑内渗入,保持深基坑边坡的基本稳定;
步骤四、深基坑开挖后在粉质粘土夹粉土层和粉细沙层的边坡上设置土钉墙进行锚固,土钉墙上设置排水孔。
2.根据权利要求所述的流沙承压水土层大面积深基坑开挖围护施工方法,其特征在于:所述土钉墙的土钉采用注浆锚杆,注浆锚杆沿深基坑底部向下倾斜10度,锚杆间距1.5米呈网格状排布,并与深基坑边坡铺设的钢筋网片焊接后喷射混凝土形成锚固土钉墙体。
3.根据权利要求所述的流沙承压水土层大面积深基坑开挖围护施工方法,其特征在于:所述排水孔采用UPVC管,其长度为300毫米并一端用滤水细纱包裹并同深基坑边坡钢筋网片绑扎设置于土钉墙体内,UPVC管沿土钉墙按2米间距成网格状排布。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201010113059A CN102162250B (zh) | 2010-02-24 | 2010-02-24 | 流沙承压水土层大面积深基坑开挖围护施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201010113059A CN102162250B (zh) | 2010-02-24 | 2010-02-24 | 流沙承压水土层大面积深基坑开挖围护施工方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN102162250A true CN102162250A (zh) | 2011-08-24 |
CN102162250B CN102162250B (zh) | 2012-10-10 |
Family
ID=44463680
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201010113059A Active CN102162250B (zh) | 2010-02-24 | 2010-02-24 | 流沙承压水土层大面积深基坑开挖围护施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102162250B (zh) |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103835296A (zh) * | 2012-11-22 | 2014-06-04 | 浙江海洋学院 | 滩涂围垦区深基坑支护的防护结构及其施工方法 |
CN104831737A (zh) * | 2015-04-29 | 2015-08-12 | 孔志坚 | 地铁车站地下室支护施工方法 |
CN104947677A (zh) * | 2014-03-28 | 2015-09-30 | 中国二十冶集团有限公司 | 坑中坑快速围堰填充施工方法 |
CN105113511A (zh) * | 2015-07-20 | 2015-12-02 | 河北二十冶建设有限公司 | 砂岩结合土层的基坑综合支护施工方法 |
CN105350552A (zh) * | 2015-09-25 | 2016-02-24 | 中国二十冶集团有限公司 | 回填夹渣土层的地下水控制方法 |
CN110029673A (zh) * | 2019-04-16 | 2019-07-19 | 潮峰钢构集团有限公司 | 适用于深基坑围护的锚索钻孔桩结构及其围护方法 |
CN110438999A (zh) * | 2019-07-30 | 2019-11-12 | 中国葛洲坝集团第一工程有限公司 | 一种地下水丰富的深基坑放坡开挖施工方法 |
CN111749247A (zh) * | 2020-06-30 | 2020-10-09 | 中国二冶集团有限公司 | 管道深基坑支护施工方法 |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108824466A (zh) * | 2018-06-02 | 2018-11-16 | 北京泽通水务建设有限公司 | 一种基坑侧壁涌水涌沙的处理方法 |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2331703Y (zh) * | 1998-06-10 | 1999-08-04 | 上海宝钢冶金建设公司第五工程公司 | 微型井点降水装置 |
JP3872094B2 (ja) * | 2006-01-18 | 2007-01-24 | Jfe建材株式会社 | ライナープレート立坑の形成方法 |
-
2010
- 2010-02-24 CN CN201010113059A patent/CN102162250B/zh active Active
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2331703Y (zh) * | 1998-06-10 | 1999-08-04 | 上海宝钢冶金建设公司第五工程公司 | 微型井点降水装置 |
JP3872094B2 (ja) * | 2006-01-18 | 2007-01-24 | Jfe建材株式会社 | ライナープレート立坑の形成方法 |
Cited By (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103835296A (zh) * | 2012-11-22 | 2014-06-04 | 浙江海洋学院 | 滩涂围垦区深基坑支护的防护结构及其施工方法 |
CN103835296B (zh) * | 2012-11-22 | 2015-10-28 | 浙江海洋学院 | 滩涂围垦区深基坑支护的防护结构及其施工方法 |
CN104947677A (zh) * | 2014-03-28 | 2015-09-30 | 中国二十冶集团有限公司 | 坑中坑快速围堰填充施工方法 |
CN104831737A (zh) * | 2015-04-29 | 2015-08-12 | 孔志坚 | 地铁车站地下室支护施工方法 |
CN105113511A (zh) * | 2015-07-20 | 2015-12-02 | 河北二十冶建设有限公司 | 砂岩结合土层的基坑综合支护施工方法 |
CN105350552A (zh) * | 2015-09-25 | 2016-02-24 | 中国二十冶集团有限公司 | 回填夹渣土层的地下水控制方法 |
CN110029673A (zh) * | 2019-04-16 | 2019-07-19 | 潮峰钢构集团有限公司 | 适用于深基坑围护的锚索钻孔桩结构及其围护方法 |
CN110029673B (zh) * | 2019-04-16 | 2023-10-13 | 潮峰钢构集团有限公司 | 适用于深基坑围护的锚索钻孔桩结构及其围护方法 |
CN110438999A (zh) * | 2019-07-30 | 2019-11-12 | 中国葛洲坝集团第一工程有限公司 | 一种地下水丰富的深基坑放坡开挖施工方法 |
CN111749247A (zh) * | 2020-06-30 | 2020-10-09 | 中国二冶集团有限公司 | 管道深基坑支护施工方法 |
Also Published As
Publication number | Publication date |
---|---|
CN102162250B (zh) | 2012-10-10 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102162250B (zh) | 流沙承压水土层大面积深基坑开挖围护施工方法 | |
CN108442382B (zh) | 横穿深基坑的压力管线原位保护及围护挡土结构及施工方法 | |
CN103321230B (zh) | 在运行浅埋地铁长距离穿越场地中的深大基坑开挖方法 | |
CN102966108B (zh) | 紧临既有建筑物以地下结构为内支撑的深基坑施工方法 | |
CN103967504B (zh) | 一种电厂循环水系统隧洞口的支护结构及施工方法 | |
CN106703044B (zh) | 一种流塑状冲填土软弱地层放坡组合支护方法 | |
CN107083771B (zh) | 一种人工挖孔桩的成孔施工方法 | |
CN207109475U (zh) | 傍山高填路堤稳定与变形控制结构 | |
CN103410152B (zh) | 一种用于狭长深基坑土方开挖的施工方法 | |
CN106640096A (zh) | 穿越回填土段及过渡段隧道的施工方法 | |
CN109457709A (zh) | 一种双排桩结合大角度锚索的支护结构及施工方法 | |
CN105887757A (zh) | 生态护坡复合挡土墙结构及施工方法 | |
CN102808627A (zh) | 钢管棚暗挖施工方法 | |
CN106013178B (zh) | 一种浅埋型岩溶地区岩溶地面塌陷的充填方法 | |
CN102425179B (zh) | 一种微型钢管灌注桩支撑加筋土渗沟结构 | |
CN104453915A (zh) | 大断面竖井预注浆加固快速开挖方法 | |
CN206873466U (zh) | 一种用于平硐明槽段防护结构 | |
CN102094419A (zh) | 地基中存在粉质沙层的钻孔桩成型方法 | |
CN211950500U (zh) | 一种偏压进洞结构 | |
CN213088018U (zh) | 一种盾构下穿建筑物防沉降控制的支护结构 | |
CN203925514U (zh) | 一种电厂循环水系统隧洞口的支护结构 | |
CN107447794A (zh) | 一种地铁保护区域内开挖基坑的抗浮起施工方法 | |
CN209780906U (zh) | 一种隧道进洞的结构 | |
CN107130610A (zh) | 一种深基坑支护的施工方法 | |
CN105113511A (zh) | 砂岩结合土层的基坑综合支护施工方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |