CN102116051A - 一种逐层悬挑结构的吊装方法 - Google Patents

一种逐层悬挑结构的吊装方法 Download PDF

Info

Publication number
CN102116051A
CN102116051A CN2009102477368A CN200910247736A CN102116051A CN 102116051 A CN102116051 A CN 102116051A CN 2009102477368 A CN2009102477368 A CN 2009102477368A CN 200910247736 A CN200910247736 A CN 200910247736A CN 102116051 A CN102116051 A CN 102116051A
Authority
CN
China
Prior art keywords
layer
lifting
overhanging structure
construction
overhanging
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2009102477368A
Other languages
English (en)
Other versions
CN102116051B (zh
Inventor
罗魏凌
项海龙
郑立忠
郑双
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Mechanized Construction Co Ltd
Original Assignee
Shanghai Mechanized Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Mechanized Construction Co Ltd filed Critical Shanghai Mechanized Construction Co Ltd
Priority to CN200910247736.8A priority Critical patent/CN102116051B/zh
Publication of CN102116051A publication Critical patent/CN102116051A/zh
Application granted granted Critical
Publication of CN102116051B publication Critical patent/CN102116051B/zh
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

本发明经济高效解决了一种在悬挑投影范围内上下均有建筑物需同步施工的大悬挑结构施工难题。其特征在于根据结构特点组成和起重机械性能,将整个大悬挑结构逐段分解,再将逐段分解的悬挑分段结构最低段与相关拉结楼层钢梁在采取稳定加固措施后组合成若干个吊装单元体,吊装单元体起吊安装到位后可利用自身结构的受力进行稳定,不需要在下部设置大型支撑。这样的吊装方法可节约大量施工支撑,降低成本,且悬挑结构施工时不影响其下部建筑物的工作,这样可创造出施工作业面,加快施工进度。

Description

一种逐层悬挑结构的吊装方法
技术领域:
本发明涉及悬挑结构施工方法,为一种逐层悬挑结构的吊装方法。
背景技术:
随着社会的发展,各种异型结构越来越多,同时业主对工程施工的工期和组织要求也越来越高,工程施工的环境变得更加苛刻和复杂。目前有的建筑设计比较时尚超前,非常规形式的建筑物大量出现,如2010年上海世博会中国馆就是一个逐层悬挑的大悬挑结构,在高度33.15米的楼层处开始外挑,最远外挑距离达35米,如采用常规的施工方法,是采取在大悬挑结构的投影下方设置临时支撑,然后将外挑结构吊装到设计位置后临时搁置在下部设置的临时支撑上进行稳定,待与建筑物相关连接结构安装到位且节点终固连接后再将临时支撑拆除卸载。然而由于工期的要求,大悬挑结构施工的同时其大悬挑结构投影下部的地面上也有建筑需要同时施工,如果采取设置临时支撑安装大悬挑结构的话,势必影响下部投影区域内结构的同步施工。此外,即使可以进行临时支撑的设置,也需耗费大量的支撑用钢,费工费时,因此如何采取一种新的施工工艺是经济高效解决上下均有结构需同步施工的大悬挑结构的施工关键。
发明内容:
针对现有施工技术中对悬挑结构施工时采取在悬挑结构下设支撑所存在的上述问题,本发明提供了一种新的无支撑悬挑结构的吊装方法并解决了常规方法所存在的施工问题。本发明设计一种逐层悬挑结构的吊装方法,其特征在于:将整个大悬挑结构按照结构特点逐层分解,再将逐层分解的悬挑分段结构与相关拉结楼层钢梁分解成若干个吊装单元,在每个吊装单元体上安装临时杆件进行加固连接,吊装采取从下往上逐层吊装的办法进行,先对最底层悬挑分段结构的吊装单元进行吊装,并与建筑物进行固定连接,待最底层悬挑分段结构安装完毕后,再对次最底层悬挑分结构的吊装单元进行吊装,并与最底层悬挑分结构和相关楼层结构钢梁固定连接,循环上述步骤,直到最高层的悬挑分结构安装完毕,最后拆除临时加固杆件。其特征在于:首节悬挑结构的吊装采取与相应楼层钢梁组合安装形成可依靠自身稳定的结构体系(不需要在悬挑结构下部设置支撑);上一层悬挑分结构的吊装单元吊装到位时采取从已吊装完毕的下层悬挑结构上设置小型支撑临时固定。本发明的优点是解决了无法采取从下部设置临时支撑条件下的大悬挑结构安装难题,可以将悬挑结构分解后利用自身的结构拉接稳定安装到位,不需在大悬挑结构下部设支撑,而只需在吊装完毕下部悬挑结构上设置小型支撑临时固定上部楼层钢梁的办法,节省了工时、少占了施工场地并降低了施工成本。
附图说明:
图1为本发明的一个典型吊装单元的结构示意图,图2为最底层悬挑分结构的吊装单元的安装连接示意图,图3为次最底层悬挑分结构的吊装单元的安装示意图。
图中1为结构水平钢梁,2为悬挑巨型斜撑,3为临时杆件,4为路基箱(用于拼装、起吊时的放置),5为吊头,6为建筑物核心筒,7为吊车,8为最底层悬挑分段结构,9为次最底层悬挑分结构,10相关楼层结构钢梁。
下面结合附图和施工实例对本发明作详细使用说明。
具体实施方式:
将整个大悬挑结构按照结构特点逐层分解,再将逐层分解的悬挑分段结构与相关拉结楼层钢梁组合成若干个吊装单元,在每个吊装单元体上安装临时杆件进行加固连接,吊装采取从下往上逐层吊装的办法进行,先对最底层悬挑分段结构的吊装单元进行吊装,并与建筑物进行固定连接,待最底层悬挑分段结构安装完毕后,再对次最底层悬挑分结构的吊装单元进行吊装,并与最底层悬挑分结构和相关楼层结构钢梁固定连接,循环上述步骤,直到最高层的悬挑分结构安装完毕,最后拆除临时加固杆件。其特征在于首节悬挑结构的吊装采取与相应楼层钢梁组合安装形成可依靠自身稳定的结构体系(不需要在悬挑结构下部设置支撑);上一层悬挑分结构的吊装单元吊装到位时采取从已吊装完毕的下层悬挑结构上设置小型支撑临时固定。
一个具体实施例,如中国馆的施工,实施过程主要分两步,首先要做好结构分析计算,将原来整个外挑结构进行分解,先根据结构特点和吊机性能逐层分解分段,将每根支撑分解成可以实现无支撑吊装的吊装单元,采用悬挑结构中原有结构的水平钢梁与悬挑斜撑组合成稳定三角体系,即一个水平钢梁与悬挑斜撑加上一个临时稳定工字钢组成的三角形,计算组装成三角体系后的一个吊装单元在施工过程中是否稳定、变形是否在可控制范围内。在稳定三角体系上设置吊耳,然后用钢丝绳穿过吊耳,并将吊装单元吊装到位后,将斜撑的根部与核心筒内预先留出的钢牛腿连接固定,同时将相关楼层结构钢梁根部也和核心筒内伸出的牛腿连接固定,解决悬挑结构的临时稳定问题,重复上述步骤,全部完成最底层悬挑分段结构的吊装及与建筑物的固定连接。然后再从已经吊装固定到位的首节悬挑结构上设置小型临时支撑将上部相关楼层结构钢梁安装到位(也可根据实际情况不加小型支撑,直接采取将上部分段斜撑和相关楼层结构钢梁组装在一起的办法进行吊装),再进行次最底层的悬挑分结构的吊装与最底层悬挑分结构的固定连接并和已利用临时小型支撑稳定吊装到位的相关楼层结构钢梁拉结稳定,依此步骤,直到安装完最高层的悬挑分结构,最后拆除临时加固杆件。因此是一种创造性的节约施工工期和成本的悬挑结构安装方法。

Claims (2)

1.一种逐层悬挑结构的吊装方法,其特征在于:将整个大悬挑结构按照结构特点逐层分解,再将逐层分解的悬挑分段结构与相关拉结楼层钢梁组合成若干个吊装单元,在每个吊装单元体上安装临时杆件进行加固连接,吊装采取从下往上逐层吊装的办法进行,先对最底层悬挑分段结构的吊装单元进行吊装,并与建筑物进行固定连接,待最底层悬挑分段结构安装完毕后,再对次最底层悬挑分结构的吊装单元进行吊装,并与最底层悬挑分结构和相关楼层结构钢梁固定连接,循环上述步骤,直到最高层的悬挑分结构安装完毕,最后拆除临时加固杆件。
2.按权利要求1所述的一种逐层悬挑结构的吊装方法,其特征在于:上一层悬挑分结构的吊装单元吊装到位,从已吊装完毕的下层稳定悬挑结构上设置小型支撑临时固定。
CN200910247736.8A 2009-12-30 2009-12-30 一种逐层悬挑结构的吊装方法 Expired - Fee Related CN102116051B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN200910247736.8A CN102116051B (zh) 2009-12-30 2009-12-30 一种逐层悬挑结构的吊装方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN200910247736.8A CN102116051B (zh) 2009-12-30 2009-12-30 一种逐层悬挑结构的吊装方法

Publications (2)

Publication Number Publication Date
CN102116051A true CN102116051A (zh) 2011-07-06
CN102116051B CN102116051B (zh) 2014-08-06

Family

ID=44214963

Family Applications (1)

Application Number Title Priority Date Filing Date
CN200910247736.8A Expired - Fee Related CN102116051B (zh) 2009-12-30 2009-12-30 一种逐层悬挑结构的吊装方法

Country Status (1)

Country Link
CN (1) CN102116051B (zh)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102409864A (zh) * 2011-11-14 2012-04-11 中建钢构有限公司 一种钢桁架的施工方法及其吊装时使用的临时加固装置
CN102777038A (zh) * 2011-12-06 2012-11-14 中建四局第三建筑工程有限公司 一种高层建筑u形槽卸料施工方法
CN102953557A (zh) * 2012-11-14 2013-03-06 中冶天工集团有限公司 一种用于蜂窝型网壳提升点的加固方法
CN107190995A (zh) * 2017-07-06 2017-09-22 中建三局集团有限公司 多层弧形吊柱高空无胎架支撑
CN109750845A (zh) * 2017-11-08 2019-05-14 上海宝冶集团有限公司 用于开口型平面桁架的地面拼装方法
CN111749456A (zh) * 2020-07-16 2020-10-09 江苏省江建集团有限公司 瞭望塔悬挑结构与塔身主体的同步施工方法
CN113513161A (zh) * 2021-03-30 2021-10-19 中建四局第六建设有限公司 一种用于悬挑钢斜柱免支撑吊装的三角机构及施工方法
CN114108996A (zh) * 2021-11-26 2022-03-01 中煤西安设计工程有限责任公司 一种无楼板砖砌填充墙的施工装置及方法
CN114673366A (zh) * 2022-05-10 2022-06-28 陕西建工机械施工集团有限公司 一种型钢梁高空无支架分段对接安装方法

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN100366854C (zh) * 2004-07-29 2008-02-06 华东建筑设计研究院有限公司 用h型钢结构构成观光塔的方法及h型钢结构制作方法
CN101177956B (zh) * 2007-11-29 2010-11-03 浙江精工钢结构有限公司 柔性轨道分离式顶推滑移施工方法及其设备
CN101446110B (zh) * 2008-12-31 2011-01-26 中国京冶工程技术有限公司 高空悬挑钢结构及其旋转施工方法

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102409864A (zh) * 2011-11-14 2012-04-11 中建钢构有限公司 一种钢桁架的施工方法及其吊装时使用的临时加固装置
CN102409864B (zh) * 2011-11-14 2014-04-09 中建钢构有限公司 一种钢桁架的施工方法及其吊装时使用的临时加固装置
CN102777038A (zh) * 2011-12-06 2012-11-14 中建四局第三建筑工程有限公司 一种高层建筑u形槽卸料施工方法
CN102777038B (zh) * 2011-12-06 2014-10-15 中建四局第三建筑工程有限公司 一种高层建筑u形槽卸料施工方法
CN102953557A (zh) * 2012-11-14 2013-03-06 中冶天工集团有限公司 一种用于蜂窝型网壳提升点的加固方法
CN107190995A (zh) * 2017-07-06 2017-09-22 中建三局集团有限公司 多层弧形吊柱高空无胎架支撑
CN109750845A (zh) * 2017-11-08 2019-05-14 上海宝冶集团有限公司 用于开口型平面桁架的地面拼装方法
CN111749456A (zh) * 2020-07-16 2020-10-09 江苏省江建集团有限公司 瞭望塔悬挑结构与塔身主体的同步施工方法
CN111749456B (zh) * 2020-07-16 2021-11-12 江苏省江建集团有限公司 瞭望塔悬挑结构与塔身主体的同步施工方法
CN113513161A (zh) * 2021-03-30 2021-10-19 中建四局第六建设有限公司 一种用于悬挑钢斜柱免支撑吊装的三角机构及施工方法
CN114108996A (zh) * 2021-11-26 2022-03-01 中煤西安设计工程有限责任公司 一种无楼板砖砌填充墙的施工装置及方法
CN114673366A (zh) * 2022-05-10 2022-06-28 陕西建工机械施工集团有限公司 一种型钢梁高空无支架分段对接安装方法

Also Published As

Publication number Publication date
CN102116051B (zh) 2014-08-06

Similar Documents

Publication Publication Date Title
CN102116051B (zh) 一种逐层悬挑结构的吊装方法
CN201176598Y (zh) 地铁隧道正上方基础底板钢筋笼
CN106869489A (zh) 超高层核心筒水平与竖向同步施工顶模系统及施工方法
CN103935911B (zh) 塔吊附墙支撑结构及其施工方法
CN101413341B (zh) 电梯井内模板施工方法及电梯井内模板施工支架
CN102877649B (zh) 装配式混凝土结构隔层浇筑施工方法
CN101418571B (zh) 宽大基坑逆作法施工的中板施工方法
CN101881005A (zh) 一种双曲拱桥的加固方法
CN107476583A (zh) 一种混凝土装配式楼房建造施工方法
CN108582466A (zh) 一种预制箱梁钢筋笼胎具
CN111335611B (zh) 一种大跨度悬挑构件施工系统及其施工方法
CN109162437B (zh) 用于多筒钢板剪力墙的整体钢平台及其施工方法
CN205348761U (zh) 地下室无梁顶板上安装无基础升降机的加固结构
CN102912989B (zh) 一种钢网壳与索穹顶组合结构的安装方法
CN102733608A (zh) 一种造粒塔喷头层施工方法
CN206956979U (zh) 一种带顶柱的一字型剪力墙
CN109629714A (zh) 一种带安装凸台的楼梯间预制隔墙及其安装方法
CN102352690A (zh) 现浇混凝土空心楼板钢管的抗浮定位系统的施工方法
CN102936953A (zh) “大”字型劲钢结构模板施工方法
CN105625732A (zh) 超高悬挑钢结构桁架无支撑施工方法
CN214219929U (zh) 一种地下室外墙单边支模加固结构
CN209799320U (zh) 用于多筒钢板剪力墙的整体钢平台
JP4476096B2 (ja) 大型高層風力発電所の建設方法
CN210530314U (zh) 钢砼组合剪力墙t型节点浇筑模板架
CN210827907U (zh) 一种pcf局部叠合窗间墙构造

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C53 Correction of patent for invention or patent application
CB02 Change of applicant information

Address after: 201802 Shanghai City, Jiading District Nanxiang Town, Shanghai Yi Road No. 1255

Applicant after: Shanghai Mechanized Construction Group Co., Ltd.

Address before: 201802 Shanghai City, Jiading District Nanxiang Town, Shanghai Yi Road No. 1255

Applicant before: Shanghai Mechanized Construction Co., Ltd.

COR Change of bibliographic data

Free format text: CORRECT: APPLICANT; FROM: SHANGHAI CITY MACHINERY CONSTRUCTION CO., LTD. TO: SHANGHAI MECHANIZED CONSTRUCTION CO., LTD.

C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20140806

Termination date: 20201230