CN102061695A - Treatment method of drainage pipe pile composite foundation - Google Patents
Treatment method of drainage pipe pile composite foundation Download PDFInfo
- Publication number
- CN102061695A CN102061695A CN 201010580533 CN201010580533A CN102061695A CN 102061695 A CN102061695 A CN 102061695A CN 201010580533 CN201010580533 CN 201010580533 CN 201010580533 A CN201010580533 A CN 201010580533A CN 102061695 A CN102061695 A CN 102061695A
- Authority
- CN
- China
- Prior art keywords
- pile
- tube
- draining
- soil
- drainage
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Landscapes
- Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)
Abstract
The invention relates to a treatment method of a drainage pipe pile composite foundation. The treatment method comprises the following steps: arranging drainage pipe piles according to a certain distance in a soft clay foundation; arranging drainage cushion layers on the top surfaces of the drainage pipe piles or pile caps; when the pile caps are arranged on the top of the drainage pipe piles, arranging preformed holes on the pile caps so as to ensure that the pipe pile holes are communicated with the drainage cushion layers; and arranging a certain number of small holes penetrating through pipe walls on the pipe walls of the drainage pipe piles so that underground water in soil among the piles can flow into the pipe pile holes via the small holes and then is drained via the preformed holes and the drainage cushion layers on the pile caps. Therefore, by means of the treatment method of the drainage pipe pile composite foundation, the dissipation of excess pore water pressure in the soil among the piles can be enhanced, the soil compacting effect generated by pipe pile construction can be reduced, and the load carried by the soil among the piles or post-construction settlement caused by self weight of foundation soil can be reduced.
Description
Technical field
The present invention relates to a kind of method for processing foundation, be specifically related to a kind of method for processing foundation that can accelerate excess pore water pressure dissipation in the ground, belong to the foundation treatment technology field.
Background technology
Along with construction periods such as speedway, railway ground constantly shortens, allow that settlement after construction is more and more littler, but the construction pile tube can produce excess pore water pressure in ground in the cohesive soil ground, cause lateral displacement or earth heaving, just may cause engineering accidents such as broken pile, pile body inclining, engineering construction is produced adverse influence, in addition, prefabricated tubular pile pile composite foundation inter-pile soil is born load when big or foundation soil when being underconsolidated soil, there is excess pore water pressure in inter-pile soil, if vertical drainage body is not set between stake, the ground settlement after construction may be just bigger.
For fear of or reduce above-mentioned adverse effect, need in ground, be provided with earlier vertical drainage body usually, and adopt measures such as jumping pile constructing process, so just make the construction technology complexity, the construction costs height, the construction period is elongated.
Summary of the invention
The purpose of this invention is to provide a kind of excess pore water pressure of can accelerating in the ground and dissipate, reduce the treatment process of composite foundation of soil compaction effect and settlement after construction, adopt this ground processing method, can effectively shorten the construction period, reduce construction costs.
The object of the present invention is achieved like this:
A kind of gutter pile composite foundation processing method comprises the steps:
(1) aperture that runs through tube wall of some at first is set on draining pile tube tube wall;
(2) the draining pile tube that will be provided with aperture is then arranged according to a determining deviation in the soft clay ground;
(3) at draining pile tube end face drainage blanket is set at last, load application on drainage blanket, underground water flows in the draining pile tube stake hole by the aperture on the draining pile tube tube wall in the inter-pile soil, drains by drainage blanket.
Purpose of the present invention can also realize like this:
A kind of gutter pile composite foundation processing method comprises the steps:
(1) aperture that runs through tube wall of some at first is set on draining pile tube tube wall;
(2) the draining pile tube that will be provided with aperture is then arranged according to a determining deviation in the soft clay ground;
(3) at draining pile tube top pile cover is set at last, preformed hole is set on the pile cover, end face at pile cover is provided with drainage blanket, load application on the plumbing bed course, underground water flows in the draining pile tube stake hole by the aperture on the draining pile tube tube wall in the inter-pile soil, drains by the preformed hole on the pile cover, drainage blanket.
Gutter pile composite foundation processing method can promote the dissipation of the ultra-clean pore water pressure that tube pile construction, ground load, ground deadweight etc. produce in ground, thereby reduces soil compaction effect and reduce settlement after construction, improves workmanship.
Advantage of the present invention is:
(1) adopt the aperture that runs through tube wall is set on draining pile tube tube wall, underground water is drained, the ultra-clean pore water pressure is dissipated, thereby has reduced soil compaction effect and reduced settlement after construction, has improved workmanship.
(2) adopt in gutter pile composite foundation processing method, easy construction, easy to operate, reduced construction costs.
Description of drawings
Fig. 1 band pile cover gutter pile composite foundation schematic diagram;
Fig. 2 is for being gutter pile composite foundation schematic diagram;
Among the figure, 1 is preformed hole on the pile cover, and 2 is pile cover, and 3 is drainage blanket, and 4 is ground, and 5 are the draining pile tube, and 6 is aperture, and 7 is the pile tube pile lining, and 8 is inter-pile soil.
The specific embodiment
Below by embodiment the present invention is described in further details, these embodiment only are used for illustrating the present invention, do not limit the scope of the invention.
Embodiment 1
A kind of gutter pile composite foundation processing method comprises the steps:
(1) aperture that runs through tube wall of some at first is set on draining pile tube tube wall;
(2) the draining pile tube that will be provided with aperture is then arranged according to a determining deviation in the soft clay ground;
(3) at draining pile tube top pile cover is set at last, preformed hole is set on the pile cover, end face at pile cover is provided with drainage blanket, load application on the plumbing bed course, underground water flows in the draining pile tube stake hole by the aperture on the draining pile tube tube wall in the inter-pile soil, drains by the preformed hole on the pile cover, drainage blanket.
Embodiment 2
A kind of gutter pile composite foundation processing method comprises the steps:
(1) aperture that runs through tube wall of some at first is set on draining pile tube tube wall;
(2) the draining pile tube that will be provided with aperture is then arranged according to a determining deviation in the soft clay ground;
(3) at draining pile tube end face drainage blanket is set at last, load application on drainage blanket, underground water flows in the draining pile tube stake hole by the aperture on the draining pile tube tube wall in the inter-pile soil, drains by drainage blanket.
Claims (2)
1. a gutter pile composite foundation processing method is characterized in that this method comprises the steps:
(1) aperture that runs through tube wall of some at first is set on draining pile tube tube wall;
(2) the draining pile tube that will be provided with aperture is then arranged according to a determining deviation in the soft clay ground;
(3) at draining pile tube end face drainage blanket is set at last, load application on drainage blanket, underground water flows in the draining pile tube stake hole by the aperture on the draining pile tube tube wall in the inter-pile soil, drains by drainage blanket.
2. a gutter pile composite foundation processing method is characterized in that this method comprises the steps:
(1) aperture that runs through tube wall of some at first is set on draining pile tube tube wall;
(2) the draining pile tube that will be provided with aperture is then arranged according to a determining deviation in the soft clay ground;
(3) at draining pile tube top pile cover is set at last, preformed hole is set on the pile cover, end face at pile cover is provided with drainage blanket, load application on the plumbing bed course, underground water flows in the draining pile tube stake hole by the aperture on the draining pile tube tube wall in the inter-pile soil, drains by the preformed hole on the pile cover, drainage blanket.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 201010580533 CN102061695A (en) | 2010-12-09 | 2010-12-09 | Treatment method of drainage pipe pile composite foundation |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 201010580533 CN102061695A (en) | 2010-12-09 | 2010-12-09 | Treatment method of drainage pipe pile composite foundation |
Publications (1)
Publication Number | Publication Date |
---|---|
CN102061695A true CN102061695A (en) | 2011-05-18 |
Family
ID=43997177
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN 201010580533 Pending CN102061695A (en) | 2010-12-09 | 2010-12-09 | Treatment method of drainage pipe pile composite foundation |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102061695A (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102392445A (en) * | 2011-10-21 | 2012-03-28 | 中铁十七局集团第六工程有限公司 | Construction method of prestressed pipe pile with vertical water discharge grooves |
CN102444125A (en) * | 2011-10-21 | 2012-05-09 | 中铁十七局集团第六工程有限公司 | Construction method for improving penetrating speed and bearing capacity of prestressed pipe pile |
CN108999178A (en) * | 2018-08-06 | 2018-12-14 | 宁波市交通规划设计研究院有限公司 | A kind of Soft Soil Subgrade Treatment Method of soil body hardening form compound foundation |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1958967A (en) * | 2006-11-22 | 2007-05-09 | 天津鸿海科技开发有限责任公司 | Quick dewatering method of positive and negative pressure for drainage piles in rigid body |
CN101824817A (en) * | 2010-05-06 | 2010-09-08 | 任再永 | Drainage consolidation construction method for treating soft soil foundation by container stacking loading |
-
2010
- 2010-12-09 CN CN 201010580533 patent/CN102061695A/en active Pending
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1958967A (en) * | 2006-11-22 | 2007-05-09 | 天津鸿海科技开发有限责任公司 | Quick dewatering method of positive and negative pressure for drainage piles in rigid body |
CN101824817A (en) * | 2010-05-06 | 2010-09-08 | 任再永 | Drainage consolidation construction method for treating soft soil foundation by container stacking loading |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102392445A (en) * | 2011-10-21 | 2012-03-28 | 中铁十七局集团第六工程有限公司 | Construction method of prestressed pipe pile with vertical water discharge grooves |
CN102444125A (en) * | 2011-10-21 | 2012-05-09 | 中铁十七局集团第六工程有限公司 | Construction method for improving penetrating speed and bearing capacity of prestressed pipe pile |
CN102392445B (en) * | 2011-10-21 | 2013-10-30 | 中铁十七局集团第六工程有限公司 | Construction method of prestressed pipe pile with vertical water discharge grooves |
CN108999178A (en) * | 2018-08-06 | 2018-12-14 | 宁波市交通规划设计研究院有限公司 | A kind of Soft Soil Subgrade Treatment Method of soil body hardening form compound foundation |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103437371B (en) | Construction method of water drainage uplift pile | |
CN103510528A (en) | Blind trench water discharging structure used for underground structure up-floating prevention | |
CN103321231A (en) | Construction method of foundation pit support | |
CN102433876A (en) | Multi-compartment casing composite pile and construction method thereof | |
CN203174619U (en) | Reverse raft concrete terrace | |
CN102359096A (en) | Method for strengthening deep soft soil foundation by sealing | |
CN103195085A (en) | Downward story-adding basement and construction method thereof | |
CN103290850A (en) | Arch combination foundation pit retaining and protection system and construction method thereof | |
CN103938634A (en) | Deep foundation pit supporting structure and construction method | |
CN103741706B (en) | A kind of deep water open type combination foundation harbour and construction method thereof | |
CN202865828U (en) | Fast-draining pipe pile | |
CN203654309U (en) | Pile-caisson hydraulic structure | |
CN103572770B (en) | A kind of stake case hydraulic structures and construction method thereof | |
CN104652444A (en) | Construction method for overall reverse operation of ultra-large type deep foundation pit center island type alternative earth excavation | |
CN104074197B (en) | The construction method of large diameter thin wall cylinder stake compound anchor rod-type foundation pit enclosure structure | |
CN103122642B (en) | Construction method of vertical post support change | |
CN102061695A (en) | Treatment method of drainage pipe pile composite foundation | |
CN202730785U (en) | Anti-floating blind ditch water drainage structure for underground structure | |
CN104074183A (en) | Drilling and concrete injected root composite pile implanting pile structure and construction method | |
CN204282399U (en) | A kind of subway space enclosing structure | |
CN204212177U (en) | A kind of double doing in the hole of stand column pile cheats diaphragm wall structure | |
CN206157594U (en) | Campshed box culvert structure | |
CN103741690B (en) | A kind of soil plug compensates pile tube and extracts construction method and soil plug used compensation pile tube pile pulling device thereof | |
CN205591212U (en) | Multi -functional precast tubular pile | |
CN205501983U (en) | Decompression drainage tubular pile |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C12 | Rejection of a patent application after its publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20110518 |