CN103122642B - Construction method of vertical post support change - Google Patents
Construction method of vertical post support change Download PDFInfo
- Publication number
- CN103122642B CN103122642B CN201310035279.2A CN201310035279A CN103122642B CN 103122642 B CN103122642 B CN 103122642B CN 201310035279 A CN201310035279 A CN 201310035279A CN 103122642 B CN103122642 B CN 103122642B
- Authority
- CN
- China
- Prior art keywords
- support
- immersed tube
- vertical
- construction method
- horizontal support
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Bulkheads Adapted To Foundation Construction (AREA)
- Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)
Abstract
Description
技术领域 technical field
本发明属于沉管隧道建设领域,具体涉及一种用于预制沉管管节的干坞基坑支护结构中采用的竖向支柱换撑的施工方法。 The invention belongs to the field of immersed tube tunnel construction, and in particular relates to a construction method for replacing vertical pillars used in a dry dock foundation pit support structure for prefabricated immersed tube joints.
背景技术 Background technique
水下隧道已成为交通设施规划网络的重要节点工程,世界各地已经修建近数百座水下交通隧道,其中一百多座隧道采用沉管工法修建而成。在沉管隧道建设中,其干坞、管段、基槽、管段基础等,均是沉管隧道的主要分项工程。而干坞承担着沉管管节预制与起浮任务,在沉管隧道中的作用是举足轻重的。 Underwater tunnels have become an important node project in the planning network of transportation facilities. Nearly hundreds of underwater transportation tunnels have been built all over the world, and more than 100 tunnels are built using the immersed tube method. In the construction of immersed tube tunnels, its dry dock, pipe section, foundation trench, pipe section foundation, etc. are the main sub-projects of immersed tube tunnels. The dry dock is responsible for the prefabrication and floating tasks of immersed tube sections, and plays an important role in immersed tube tunnels.
在场地狭小情况下,干坞施工常见的方法如下:设置悬臂式“Π”型或格构型地下连续墙,为考虑沉管管节起浮出坞,一般不设水平支撑。该方法对沉管管节制作及起浮出坞较为方便,但悬臂式“Π”型或格构型地下连续墙为满足承载基坑外水土压力所需截面较大,造成围护墙体量过大,干坞造价较高,占地面积增加。 In the case of a small site, the common method of dry dock construction is as follows: set up a cantilever type "Π" type or lattice structure underground diaphragm wall, and generally do not set horizontal supports in order to consider the floating of immersed tube joints. This method is more convenient for the fabrication of immersed tube joints and lifting and undocking, but the section required for the cantilevered “Π” type or lattice underground diaphragm wall to meet the water and soil pressure outside the foundation pit is relatively large, resulting in the volume of the surrounding wall. If it is too large, the cost of the dry dock will be higher and the floor space will increase.
发明内容 Contents of the invention
本发明的目的是根据上述现有技术的不足之处,提供一种竖向支柱换撑的施工方法,该施工方法通过在干坞基坑的地下连续墙上设置水平支撑,并先后通过竖向格构柱和竖向支柱换撑来作为其支撑结构,以达到减小地下连续墙支护结构的截面和体量空间尺寸。 The purpose of the present invention is to provide a construction method for vertical pillar replacement according to the deficiencies of the above-mentioned prior art. Lattice columns and vertical pillars are replaced as the supporting structure to reduce the section and volume space dimensions of the underground diaphragm wall support structure.
本发明目的实现由以下技术方案完成: The object of the present invention is realized by the following technical solutions:
一种竖向支柱换撑的施工方法,涉及干坞基坑、在所述干坞基坑内建造的沉管管节以及作为所述干坞基坑支护结构的“Π”型地下连续墙,其特征在于所述施工方法至少包括如下步骤:在所述“Π”型地下连续墙顶部设置水平支撑,在靠近所述水平支撑的中部设置竖向格构柱,所述竖向格构柱的底部深入至所述干坞基坑底部土体,用以作为所述水平支撑的临时支撑结构;制作所述沉管管节;之后在所述沉管管节的顶部设置竖向支柱换撑,所述竖向支柱换撑的两端部分别支撑连接于所述水平支撑和所述沉管管节,用以作为所述水平支撑的竖向支撑结构;之后割除所述竖向格构柱位于所述干坞基坑底板以上部分;在所述沉管管节内设置水箱并加水压重,打开所述干坞基坑的坞口以向所述干坞基坑内灌水;待所述干坞基坑内水位达到起浮标高时,拆除所述水平支撑以及竖向支柱换撑,抽排所述水箱内的水体,使所述沉管管节起浮。 A construction method for vertical pillar replacement, involving a dry dock foundation pit, immersed tube joints built in the dry dock foundation pit, and a "Π" type underground diaphragm wall as the support structure of the dry dock foundation pit, It is characterized in that the construction method includes at least the following steps: setting a horizontal support on the top of the "Π" type underground diaphragm wall, setting a vertical lattice column near the middle of the horizontal support, and the vertical lattice column The bottom goes deep into the soil at the bottom of the dry dock foundation pit, which is used as a temporary support structure for the horizontal support; the immersed tube joint is made; and then vertical pillars are set on the top of the immersed tube joint for support, The two ends of the vertical support support are respectively supported and connected to the horizontal support and the immersed tube joint, which are used as the vertical support structure of the horizontal support; after that, the vertical lattice column is cut off The part above the bottom plate of the dry dock foundation pit; set a water tank in the immersed pipe joint and add water pressure to open the dock mouth of the dry dock foundation pit to pour water into the dry dock foundation pit; When the water level in the dock foundation pit reaches the height of the buoy, remove the horizontal support and replace the vertical support, drain the water in the water tank, and float the immersed tube joint.
所述的支撑连接是:在所述水平支撑的支撑位置处预埋钢筋笼,所述钢筋笼外凸于所述水平支撑的下表面;在一护筒内预设钢筋笼,之后将所述护筒设置于所述支撑连接处;连接所述预埋钢筋笼和预设钢筋笼,最后完成钢筋笼的灌注注浆,以构成所述竖向支柱换撑的所述支撑连接。 The support connection is: pre-embed a reinforcement cage at the support position of the horizontal support, and the reinforcement cage is protruding from the lower surface of the horizontal support; a reinforcement cage is preset in a casing, and then the The casing is arranged at the support connection; the pre-embedded reinforcement cage and the preset reinforcement cage are connected, and finally the filling and grouting of the reinforcement cage is completed to form the support connection for the replacement of the vertical pillar.
所述竖向支柱换撑底部设置有扩大基础,并在所述扩大基础与所述沉管管节的顶板之间设置一隔离层。 An enlarged foundation is provided at the bottom of the vertical support brace, and an isolation layer is arranged between the enlarged foundation and the top plate of the immersed tube joint.
所述竖向支柱换撑为一钢构件,其底部通过采用螺栓与所述沉管管节的顶部连接,其顶部通过采用抱箍与所述水平支撑连接。 The vertical support is a steel member, the bottom of which is connected to the top of the immersed tube joint by bolts, and the top is connected to the horizontal support by hoops.
本发明的优点是,通过在干坞基坑的地下连续墙上设置水平支撑,并先后通过竖向格构柱和竖向支柱换撑来作为其支撑结构,减小了地下连续墙构件体量尺寸,既降低了工程造价并有效控制了地下连续墙的占地范围,又对沉管管节的施工质量以及起浮出坞无任何影响,特别适用于场地狭小条件下建造干坞基坑。 The advantage of the present invention is that by setting the horizontal support on the underground continuous wall of the foundation pit of the dry dock, and successively replacing the vertical lattice column and the vertical support as its supporting structure, the volume of the underground continuous wall component is reduced The size not only reduces the project cost and effectively controls the area occupied by the underground diaphragm wall, but also has no impact on the construction quality of the immersed tube joints and the lifting and undocking. It is especially suitable for the construction of dry dock foundation pits under narrow conditions.
附图说明 Description of drawings
图1为本发明中的施工步骤一即设置水平支撑及竖向格构柱的示意图; Fig. 1 is the schematic diagram that horizontal support and vertical lattice column are set for construction step one among the present invention;
图2为本发明中的施工步骤二、三即在沉管管节顶部设置竖向支柱换撑的示意图; Fig. 2 is the construction steps 2 and 3 in the present invention, promptly arranges the schematic diagram of the vertical pillar changing support at the top of the immersed tube joint;
图3为本发明中的施工步骤四即割除竖向格构柱的示意图; Fig. 3 is the schematic diagram that the construction step 4 among the present invention cuts off the vertical lattice column;
图4为本发明中的施工步骤五即在沉管管节内设置水箱的示意图; Fig. 4 is the construction step five in the present invention namely the schematic diagram that water tank is set in the immersed tube section;
图5为本发明中的施工步骤五即先在水箱内加水压重后在干坞基坑内灌水的示意图; Fig. 5 is the schematic diagram of pouring water in the dry dock foundation pit after first adding water pressure in the water tank in construction step five among the present invention;
图6为本发明中的施工步骤六即拆除水平支撑和竖向支柱换撑的示意图; Fig. 6 is the schematic diagram that the construction step 6 among the present invention promptly dismantles horizontal support and vertical pillar and changes support;
图7为本发明中施工步骤六即抽排水箱内水体以使沉管管节起浮的示意图; Fig. 7 is a schematic diagram of pumping the water body in the drainage tank to float the immersed tube joint in the sixth construction step of the present invention;
图8为本发明中竖向支柱换撑的局部放大图B; Fig. 8 is a partially enlarged view B of vertical pillar replacement in the present invention;
图9为本发明中“Π”型地下连续墙平面图A-A。 Fig. 9 is the plane view A-A of the "Π" type underground diaphragm wall in the present invention.
具体实施方式 Detailed ways
以下结合附图通过实施例对本发明的特征及其它相关特征作进一步详细说明,以便于同行业技术人员的理解: The features of the present invention and other relevant features are described in further detail below in conjunction with the accompanying drawings through the embodiments, so as to facilitate the understanding of those skilled in the art:
如图1-9,图中标记1-7分别为:水平支撑1、钢筋笼1-1、振捣孔1-2、地下连续墙2、竖向格构柱3、竖向格构柱桩基3-1、沉管管节4、预留孔洞4-1、竖向支柱换撑5、护筒5-1、钢筋笼5-2、扩大基础5-3、水箱6、隔离层7。 As shown in Figure 1-9, the marks 1-7 in the figure are: horizontal support 1, steel cage 1-1, vibrating hole 1-2, underground diaphragm wall 2, vertical lattice column 3, vertical lattice column pile Foundation 3-1, immersed tube joint 4, reserved hole 4-1, vertical pillar support 5, casing 5-1, steel cage 5-2, enlarged foundation 5-3, water tank 6, isolation layer 7.
实施例一:本实施例涉及一种沉管隧道干坞基坑中采用竖向支柱换撑的施工方法,通过采用水平支撑及竖向立柱换撑作为干坞基坑的支护构件,来减小干坞基坑内支护结构(即地下连续墙)的体量尺寸和工程造价,该施工方法包括如下步骤: Embodiment 1: This embodiment relates to a construction method using vertical pillar replacement in the dry dock foundation pit of an immersed tube tunnel. By using horizontal support and vertical pillar replacement as the supporting components of the dry dock foundation pit, the The volume size and engineering cost of the support structure (i.e. the underground diaphragm wall) in the foundation pit of the small dry dock, the construction method includes the following steps:
①如图1、8和9所示,在干坞基坑中设置“Π”型地下连续墙2,在地下连续墙2的顶部设置有水平支撑1,该水平支撑1用以对地下连续墙2提供侧向支档力,同时在水平支撑1的中心处附近设置一竖向格构柱3,竖向格构柱3的底部深入至干坞基坑的底部土体内(即为竖向格构柱桩基3-1),该竖向格构柱3用以作为水平支撑1的临时支撑结构;其中在水平支撑1的支撑连接处预埋有钢筋笼1-1,钢筋笼1-1外凸于水平支撑1的下表面,并在其中心处预留有用于浇捣混凝土浆的振捣孔1-2; ①As shown in Figures 1, 8 and 9, a "Π" type underground diaphragm wall 2 is set in the dry dock foundation pit, and a horizontal support 1 is arranged on the top of the underground diaphragm wall 2, and the horizontal support 1 is used to support the underground diaphragm wall. 2 provide lateral supporting force, and at the same time, set a vertical lattice column 3 near the center of the horizontal support 1, and the bottom of the vertical lattice column 3 goes deep into the bottom soil of the dry dock foundation pit (that is, the vertical lattice column pile foundation 3-1), the vertical lattice column 3 is used as a temporary support structure for the horizontal support 1; a reinforcement cage 1-1 is pre-embedded at the support connection of the horizontal support 1, and the reinforcement cage 1-1 It protrudes outward from the lower surface of the horizontal support 1, and a vibrating hole 1-2 for pouring concrete slurry is reserved at the center thereof;
②如图1所示,之后制作沉管管节4,并在其底板上设置预留孔洞4-1,以供竖向格构柱3贯穿通过; ②As shown in Figure 1, the immersed tube joint 4 is made afterwards, and a reserved hole 4-1 is set on its bottom plate for the vertical lattice column 3 to pass through;
③如图2和8所示,在沉管管节4的顶板上施作钢筋砼竖向支柱换撑5,施作步骤为:在一圆形护筒5-1内预设钢筋笼5-2,之后将圆形护筒5-1的顶端与水平支撑1内的钢筋笼1-1对接,在圆形护筒5-1的底部设置有扩大基础5-3,同时在沉管管节4顶板与扩大基础5-3之间设置隔离层,其后通过水平支撑1中预留的振捣孔1-2向圆形护筒内灌注混凝土浆,以构成上述的钢筋砼竖向支柱换撑5; ③As shown in Figures 2 and 8, the reinforced concrete vertical pillar replacement support 5 is applied on the top plate of the immersed tube joint 4, and the construction steps are as follows: a reinforcement cage 5-1 is preset in a circular casing 5-1 2. After that, connect the top of the circular casing 5-1 with the reinforcement cage 1-1 in the horizontal support 1, set an enlarged foundation 5-3 at the bottom of the circular casing 5-1, and at the same time place the immersed tube joint 4 An isolation layer is set between the top plate and the enlarged foundation 5-3, and then concrete slurry is poured into the circular casing through the vibrating holes 1-2 reserved in the horizontal support 1 to form the above-mentioned reinforced concrete vertical pillar replacement. support 5;
④如图3所示,待竖向支柱换撑5的强度养护达到要求之后,割除竖向格构柱3的上半部分,即割除位于干坞基坑底板以上的部分,只保留其位于土体以下的竖向格构柱桩基3-1;之后清理并恢复干坞基坑基础和底板,而后绑扎钢筋灌注混凝土封填沉管管节4底板上的预留孔洞4-1; ④ As shown in Fig. 3, after the strength maintenance of the vertical column support 5 meets the requirements, the upper half of the vertical lattice column 3 is cut off, that is, the part above the bottom of the foundation pit of the dry dock is cut off, and only the part located in the soil is kept. The vertical lattice column pile foundation 3-1 below the body; then clean up and restore the dry dock foundation pit foundation and floor, and then bind the steel bars and pour concrete to seal and fill the reserved hole 4-1 on the bottom plate of the immersed pipe joint 4;
⑤如图4、5所示,在沉管管节4内两侧设置水箱6并加水压重,其后打开干坞基坑的坞口以向干坞基坑内灌水; ⑤ As shown in Figures 4 and 5, set water tanks 6 on both sides of the immersed tube joint 4 and add water pressure, and then open the dock mouth of the dry dock foundation pit to pour water into the dry dock foundation pit;
⑥如图6、7所示,待干坞基坑内的水位达到沉管管节4的起浮标高时,拆除水平支撑1及用于支撑水平支撑1的竖向支柱换撑5,此时利用水体对地下连续墙2产生的压力替换拆除的水平支撑1对地下连续墙2的支档力,之后抽排水箱6内水体,使干坞基坑内工况满足沉管管节4起浮出坞等施工条件。 ⑥ As shown in Figures 6 and 7, when the water level in the foundation pit of the dry dock reaches the buoyancy height of the immersed tube joint 4, the horizontal support 1 and the vertical support 5 used to support the horizontal support 1 are removed and the support 5 is replaced. The pressure generated by the water body on the underground diaphragm wall 2 replaces the support force of the dismantled horizontal support 1 on the underground diaphragm wall 2, and then the water body in the drainage tank 6 is pumped to make the working conditions in the foundation pit of the dry dock meet the requirements of the immersed pipe joint 4 to float out of the dock and other construction conditions.
实施例二:本实施例中竖向支柱换撑的具体施工方法与实施例一中相同,但是在本实施例中竖向支柱换撑5采用钢构件,其下部通过采用螺栓与沉管管节4顶板连接,其上部通过采用钢抱箍与水平支撑1连接,采用螺栓与钢抱箍这两种连接件可利于快速施工,避免实施例一中采用钢筋砼结构存在养护期的缺点,该竖向支柱换撑5可在干坞基坑内灌水后拆除。 Embodiment 2: The specific construction method of the vertical pillar replacement in this embodiment is the same as that in Embodiment 1, but in this embodiment, the vertical pillar replacement 5 adopts steel members, and its lower part adopts bolts and immersed tube joints 4. The top plate is connected, and its upper part is connected with the horizontal support 1 by using steel hoops. The use of bolts and steel hoops can facilitate rapid construction and avoid the disadvantages of the maintenance period of the reinforced concrete structure in Embodiment 1. The vertical Changing support 5 to pillar can be removed after pouring water in the dry dock foundation pit.
Claims (4)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201310035279.2A CN103122642B (en) | 2013-01-30 | 2013-01-30 | Construction method of vertical post support change |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201310035279.2A CN103122642B (en) | 2013-01-30 | 2013-01-30 | Construction method of vertical post support change |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN103122642A CN103122642A (en) | 2013-05-29 |
| CN103122642B true CN103122642B (en) | 2014-10-29 |
Family
ID=48453767
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201310035279.2A Expired - Fee Related CN103122642B (en) | 2013-01-30 | 2013-01-30 | Construction method of vertical post support change |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN103122642B (en) |
Families Citing this family (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN105134250B (en) * | 2015-10-16 | 2017-06-20 | 中铁十局集团第一工程有限公司 | Exempt to tear the method for supporting direct lining cutting open in a kind of weak surrounding rock subway station |
| CN108457300B (en) * | 2018-01-19 | 2021-01-22 | 中国建筑第八工程局有限公司 | Construction method for replacing support of underground large-span structure by cover-excavation method |
| CN111236250A (en) * | 2020-01-17 | 2020-06-05 | 中铁第六勘察设计院集团有限公司 | Method for quickly removing foundation pit support at onshore section joint of immersed tube tunnel |
| CN111206585A (en) * | 2020-02-24 | 2020-05-29 | 中铁第六勘察设计院集团有限公司 | A structural system for prefabricated modular transportation of large-scale immersed tunnel sections on flat ground |
| CN112609701B (en) * | 2020-11-30 | 2022-12-02 | 中国建筑第八工程局有限公司 | Method for dismantling inner support of deep foundation pit |
| CN114837226A (en) * | 2022-05-06 | 2022-08-02 | 中铁第六勘察设计院集团有限公司 | Dry dock arrangement method based on immersed tunnel passing through Jiangxian continents |
Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| RU2114251C1 (en) * | 1995-07-12 | 1998-06-27 | Акционерное общество закрытого типа - Нефтегазогорная компания "Нефтегазгор" | Method for driving underwater mine working or tunnel |
| JPH11323977A (en) * | 1998-05-18 | 1999-11-26 | Taisei Corp | Waterproof structure of underwater tunnel |
| CN1696415A (en) * | 2004-05-12 | 2005-11-16 | 布伊古公共工程公司 | Process and apparatus for producing an immersed tunnel on subsea ground |
| CN1884723A (en) * | 2006-06-12 | 2006-12-27 | 中铁隧道勘测设计院有限公司 | Construction method for prefabricating immersed tube tunnel tubulation adopting mobile dry dock |
| CN102345299A (en) * | 2011-11-11 | 2012-02-08 | 上海市隧道工程轨道交通设计研究院 | Reusable fabricated end seal method for immersed tube tunnel |
-
2013
- 2013-01-30 CN CN201310035279.2A patent/CN103122642B/en not_active Expired - Fee Related
Patent Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| RU2114251C1 (en) * | 1995-07-12 | 1998-06-27 | Акционерное общество закрытого типа - Нефтегазогорная компания "Нефтегазгор" | Method for driving underwater mine working or tunnel |
| JPH11323977A (en) * | 1998-05-18 | 1999-11-26 | Taisei Corp | Waterproof structure of underwater tunnel |
| CN1696415A (en) * | 2004-05-12 | 2005-11-16 | 布伊古公共工程公司 | Process and apparatus for producing an immersed tunnel on subsea ground |
| CN1884723A (en) * | 2006-06-12 | 2006-12-27 | 中铁隧道勘测设计院有限公司 | Construction method for prefabricating immersed tube tunnel tubulation adopting mobile dry dock |
| CN102345299A (en) * | 2011-11-11 | 2012-02-08 | 上海市隧道工程轨道交通设计研究院 | Reusable fabricated end seal method for immersed tube tunnel |
Also Published As
| Publication number | Publication date |
|---|---|
| CN103122642A (en) | 2013-05-29 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN103195085B (en) | Downward story-adding basement and construction method thereof | |
| CN205742213U (en) | Foundation pit supporting construction | |
| CN103122642B (en) | Construction method of vertical post support change | |
| CN104805854B (en) | A kind of Deep Water Ultra-long steel sheet pile cofferdam construction method under tide environment | |
| CN101503882B (en) | Underground continuous wall with connected reinforcement cage constructed by reverse construction method and construction method thereof | |
| CN105544575B (en) | A kind of bottom concrete construction method under water of use steel truss reinforcement | |
| CN101358453A (en) | Composite casing cofferdam and its construction method | |
| CN108505805B (en) | Large cast-in-situ water pool with expansion reinforcing belt for crack control and construction method thereof | |
| CN101117800A (en) | One pile three-purpose method in underground engineering | |
| CN105089061A (en) | Ultra-deep foundation pit supporting method | |
| CN103806464B (en) | Large-scale high ferro station and subway cross top-down construction method up and down | |
| CN103132537A (en) | Steel latticed column homocentric-square-shaped concrete bearing platform combination type tower crane base structure and construction method | |
| CN104895324B (en) | A kind of construction method of the huge plug-in type suspension column structure of reinforced concrete composite structure | |
| CN103422510A (en) | Steel pipe frame type cofferdam structure and construction method | |
| AU2012313196B2 (en) | Partially floating marine platform for offshore wind-power, bridges and marine buildings, and construction method | |
| CN113774936A (en) | Floating transportation, positioning and sinking construction method for double-wall steel cofferdam with pile foundation firstly and cofferdam secondly | |
| CN104532957A (en) | Inversed construction method for adding basement in existing building | |
| CN104234082A (en) | Jump-layer reversed construction method for deep foundation pit | |
| CN100535264C (en) | Steel boxed cofferdam and recovery method thereof | |
| CN106894420B (en) | Basement construction method for supporting | |
| CN201972155U (en) | Topdown-construction-method foundation pit supporting structure of steel plate pile | |
| CN104711931B (en) | Temporary underwater pier manufacturing, assembling and disassembling method suitable for bridge erection | |
| CN207405730U (en) | A kind of discharge structure of basement | |
| CN108035379B (en) | Comprehensive pipe gallery and construction method thereof | |
| CN107326932B (en) | A quasi-semi-reverse construction method for an underground garage |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C06 | Publication | ||
| PB01 | Publication | ||
| C10 | Entry into substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant | ||
| CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20141029 |
|
| CF01 | Termination of patent right due to non-payment of annual fee |