CN102011369A - 跨各种道路的桥梁合拢段钢壳施工方法 - Google Patents

跨各种道路的桥梁合拢段钢壳施工方法 Download PDF

Info

Publication number
CN102011369A
CN102011369A CN 201010542422 CN201010542422A CN102011369A CN 102011369 A CN102011369 A CN 102011369A CN 201010542422 CN201010542422 CN 201010542422 CN 201010542422 A CN201010542422 A CN 201010542422A CN 102011369 A CN102011369 A CN 102011369A
Authority
CN
China
Prior art keywords
box hat
welding
bellows
reinforcing bar
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN 201010542422
Other languages
English (en)
Other versions
CN102011369B (zh
Inventor
李晓超
雷军
王克勤
周高峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Second Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd
Original Assignee
Second Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Second Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd filed Critical Second Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd
Priority to CN 201010542422 priority Critical patent/CN102011369B/zh
Publication of CN102011369A publication Critical patent/CN102011369A/zh
Application granted granted Critical
Publication of CN102011369B publication Critical patent/CN102011369B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

本发明公开了一种跨各种道路的桥梁合拢段钢壳施工方法,该方法首先完成两部分钢壳的设计、加工、成型;将两部分钢壳分别吊装至合拢段两端头位置并焊接起来,待钢筋及预应力管道安装结束后,向钢壳内浇注混凝土。合拢之后钢壳作为砼一部分,不用拆除,这样就大大减少了工作量,该方法会安全可靠、操作简洁、实施快速、降低造价,在桥梁建设中将发挥越来越大的作用,产生越来越好的社会和经济效益。

Description

跨各种道路的桥梁合拢段钢壳施工方法 
技术领域
本发明涉及一种道路桥梁的施工方法,具体涉及桥梁合拢段的施工方法。 
背景技术
现有技术中,道路桥梁合拢段的施工采用吊架施工方法,即采用直径32精轧螺纹钢吊住横梁的施工方法(如图1所示),合拢段吊模支架在箱梁转体前安装在两端不影响转体施工的位置,待转体施工结束后,再调整吊架到准确位置。 
这种桥梁吊架施工方法存在的问题包括: 
(1)施工所需的机具设备多,而且施工安全危险极大。 
(2)施工程序复杂,施工干扰极大。 
(3)一般也能克服上跨构造物或交通密集公路,铁路的困难,尤其是对修建处于交通运输繁忙的城市立交桥和铁路跨线桥,其劣势更加明显。 
(4)施工周期长、施工速度慢、工程造价高。 
发明内容
本发明的目的为了克服桥梁吊架施工方法中存在的问题,提供一种施工安全、方便,速度较快的跨各种道路的桥梁合拢段钢壳施工方法。 
为解决以上问题,本发明所述的一种跨各种道路的桥梁合拢段钢壳施工方法,首先完成两部分钢壳的设计、加工、成型;将两部分钢壳分别吊装至合拢段两端头位置并焊接起来,待钢筋及预应力管道安装结束后,向钢壳内浇注混凝土。本发明合拢梁段采用钢壳施工,为了便于钢壳的吊装,钢壳共分三部分制造,分别为底板,腹板和翼缘板。钢壳的焊接均采用I级熔透焊(除了加强肋板焊接),钢壳内侧需要焊接钢板作为肋板来加强钢壳整体性能,钢壳外侧焊缝要打磨平整,并涂上防护漆,用吊车吊装钢壳,两个钢壳在箱梁转体前分别安装在合拢段两端头位置,待转体施工结束后,并在劲性骨架锁定之前,钢壳挂在两端混凝土上,待梁体标高、平面位置调整完毕后,及时锁定劲性骨架,将钢壳模板焊接,待底板、腹板钢筋绑扎结束,预应力管道预埋结束后,绑扎顶板钢筋、安装预应力管道及各类预埋件。安装钢筋和预应力管道,然后加固钢壳,最后用汽车泵浇筑合拢段的砼,该部位在既有铁路上方,钢壳不需要拆除,不影响外观。 
本发明所述的钢壳施工法是一种新型施工方法,合拢之后钢壳作为砼一部分,不用拆除,钢壳施工法的关键技术问题是钢壳施工工艺技术研究。钢壳施工的焊接均采用I级熔透焊,钢壳之间设置3道横肋板和多道纵肋板来保持钢壳的结构稳定,同是也保证了钢壳的强度。钢壳作为砼的一部分,不用拆除,这样就大大减少了工作量。随着新技术、新工艺的不断出现以及在工程中的应用,该方法会更加安全可靠、操作简洁、实施快速、降低造价,在桥梁建设中将发挥越来越大的作用,产生越来越好的社会和经济效益。 
附图说明
图1为传统合拢段施工吊架模板横纵断面图。 
图2为传统的合拢段施工吊架模板横断。 
图3为本发明的总体施工工艺流程。 
图4为本发明合拢段施工钢壳模板示意图。 
图5为本发明两个钢壳连接图。 
具体实施方式
以下结合附图对本发明做具体说明。 
本发明所述的一种跨各种道路的桥梁合拢段钢壳施工方法,首先完成两部分钢壳的设计、加工、成型;将两部分钢壳分别吊装至合拢段两端头位置并焊接起来(如图5),待钢筋及预应力管道安装结束后,向钢壳内浇注混凝土。总体施工工艺流程如图3所示。 
(一)钢壳施工 
1、钢壳材料下料 
(1)、钢壳设计及要求 
设计要求: 
(1)钢壳面板采用采用Q235钢板,钢板的化学成分及机械性能应符合GB/T700-1988的有关规定。 
(2)钢壳为焊接后加工结构,钢壳对接焊接焊缝要求I级熔透焊,平整度要求在2mm之内。 
(3)钢壳外层表面按《铁路涂装保护涂装》(TB1527-2004)第五套体系进行涂装保护。 
(2)、钢壳加工及要求 
主要工序如下: 
(1)原材料采购,下料。 
(2)预成型:钢壳部分焊接预成型。 
(3)拼焊:对预成型好的钢壳进行拼焊,拼焊时进行定位,焊缝坡口采用坡口焊接,焊接方式为手工电弧焊,焊缝经过超声波探伤达到JB4730-1994II级。焊接完毕打磨掉焊缝余高。 
(4)加强肋板的组焊:点焊定位后进行焊接,注意防止钢壳面板的变形 
(5)底板、腹板和翼缘板之间的整体组装。 
钢壳加工要求如下: 
(1)钢壳各部件的外形尺寸及公差符合设计图纸要求。 
(2)各部件焊接时按焊接工艺要求操作,严格控制焊接变形。焊缝应光滑平整,无咬边、气孔、夹渣等缺陷。 
(3)两个钢壳截面尺寸都应误差在5mm之内。 
(4)钢壳边缘各点高程误差不大于3mm,不得有挠曲变形。 
(5)两个钢壳的中心轴线和标高应误差不大于2mm。 
(3)、钢壳检查验收 
钢壳加工完成后,邀请设计、监理单位进行现场验收,进行外观、局部尺寸等检查,结果均符合图纸要求。 
(二)合拢梁段施工 
(1)钢壳、模板 
合拢梁段采用钢壳施工,合拢段钢壳分两部分,在箱梁转体前分别安装在6#段端头位置,待转体施工结束后,再将两部分连接起来。如图4所示。在劲性骨架锁定之前,钢壳预埋在两端混凝土上,但不能马上连接,待梁体标高、平面位置调整完毕后,及时锁定劲性骨架,待底板、腹板钢筋绑扎结束,预应力管道预埋结束后,加固钢壳模板,绑扎顶板钢筋、安装预应力管道及各类预埋件 
(2)钢筋及预应力管道安装 
①、钢筋施工 
箱梁钢筋根据施工图进行配料,在钢筋加工场地加工成型后运至现场绑扎, 钢筋的绑扎顺序为:底板钢筋→腹板竖向、水平钢筋→顶板钢筋。钢筋长度、间距、接头等均严格按设计及相应规范执行。同时施工时注意为下道工序预埋钢筋、栏杆、泄水管、通讯电缆等预埋件,并确保位置准确。 
②、波纹管埋设 
箱梁预应力管道通过埋设波纹管的方法进行预留。波纹管使用前除进行外观质量检查外,还必须进行密封性能的检验,检查合格后,才可施工。 
波纹管安装工艺:波纹管安装时通过定位网片定位,预应力管道定位筋应设置准确,管道弯曲部分间距每50cm设一处,在弯道部分要适当加密布置,直线部分间距每100cm设一处。用接头套管接长波纹管,在波纹管接头处将波纹管接口用小锤整平,以防在穿束时引起波纹管翻卷。波纹管的安装精度按设计要求进行控制。 
浇注砼之前,仔细复查波纹管有无破损、接头是否密实。 
(3)混凝土浇注 
合拢段混凝土浇注过程中,按新浇注混凝土的重量分级卸去平衡重,保证平衡施工。合拢段混凝土选择在一天中气温较低的时段进行浇注。 
箱梁合拢段混凝土浇筑时,混凝土用汽车泵输送,混凝土浇筑整个施工过程处于封闭状态; 
(4)预应力施工 
待混凝土强度和弹性模量均达到设计值时,张拉预应力钢束。张拉顺序:先张拉底板预应力束,再张拉顶板预应力束。 
(三)劳动组织 
施工人员经培训合格后上岗,特殊工种应持证上岗,一个钢壳施工一般需要13人,并保持相对稳定,人员分配和调整应按不同工种配齐、配足。一个球铰施工作业人员配备见表1,可根据施工现场情况及时调整。 
表1一个钢壳施工作业人员配备表 
Figure BDA0000031996360000041
Figure BDA0000031996360000051
(四)机具设备 
施工机具应根据实施性施工组织设计要求,配备污染低、能耗小、效率高的机具,单个球铰施工机具配备参见表2,可根据施工现场情况及时调整。 
表2单个钢壳作业面施工机具配备表 
Figure BDA0000031996360000052

Claims (3)

1.一种跨各种道路的桥梁合拢段钢壳施工方法,其特征在于:首先完成两部分钢壳的设计、加工、成型;将两部分钢壳分别吊装至合拢段两端头位置并焊接起来,待钢筋及预应力管道安装结束后,向钢壳内浇注混凝土。
2.根据权利要求1所述的一种跨各种道路的桥梁合拢段钢壳施工方法,其特征在于钢壳的设计、加工、成型过程包括:
原材料采购,下料;
预成型:钢壳部分焊接预成型;
拼焊:对预成型好的钢壳进行拼焊,拼焊时进行定位,焊缝坡口采用坡口焊接,焊接方式为手工电弧焊,焊缝经过超声波探伤达到JB4730—1994Ⅱ级,焊接完毕打磨掉焊缝余高;
加强肋板的组焊:点焊定位后进行焊接,注意防止钢壳面板的变形;
底板,腹板和翼缘板之间的整体组装。
3.根据权利要求1所述的一种跨各种道路的桥梁合拢段钢壳施工方法,其特征在于钢筋及预应力管道安装过程包括:
(1)钢筋施工
箱梁钢筋根据施工图进行配料,在钢筋加工场地加工成型后运至现场绑扎,钢筋的绑扎顺序为:底板钢筋→腹板竖向、水平钢筋→顶板钢筋,钢筋长度、间距、接头等均严格按设计及相应规范执行,同时施工时注意为下道工序预埋钢筋、栏杆、泄水管、通讯电缆等预埋件,并确保位置准确;
(2)波纹管埋设
箱梁预应力管道通过埋设波纹管的方法进行预留,波纹管使用前除进行外观质量检查外,还必须进行密封性能的检验,检查合格后,才可施工,波纹管安装工艺:波纹管安装时通过定位网片定位,预应力管道定位筋应设置准确,管道弯曲部分间距每50㎝设一处,在弯道部分要适当加密布置,直线部分间距每100cm设一处,用接头套管接长波纹管,在波纹管接头处将波纹管接口用小锤整平,以防在穿束时引起波纹管翻卷,每节梁段在预应力管道较高处安装一到两个压浆出气孔。
CN 201010542422 2010-11-12 2010-11-12 跨各种道路的桥梁合拢段钢壳施工方法 Active CN102011369B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201010542422 CN102011369B (zh) 2010-11-12 2010-11-12 跨各种道路的桥梁合拢段钢壳施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201010542422 CN102011369B (zh) 2010-11-12 2010-11-12 跨各种道路的桥梁合拢段钢壳施工方法

Publications (2)

Publication Number Publication Date
CN102011369A true CN102011369A (zh) 2011-04-13
CN102011369B CN102011369B (zh) 2013-01-23

Family

ID=43841682

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201010542422 Active CN102011369B (zh) 2010-11-12 2010-11-12 跨各种道路的桥梁合拢段钢壳施工方法

Country Status (1)

Country Link
CN (1) CN102011369B (zh)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105239499A (zh) * 2015-11-10 2016-01-13 中国建筑第六工程局有限公司 一种钢混结合段后压浆结构
CN108396651A (zh) * 2018-02-06 2018-08-14 中铁二院昆明勘察设计研究院有限责任公司 一种钢壳滑道系统及施工方法
CN108411767A (zh) * 2018-02-06 2018-08-17 中铁二院昆明勘察设计研究院有限责任公司 一种自闭合式合拢钢壳系统及施工方法
CN108589556A (zh) * 2018-05-04 2018-09-28 中铁二十三局集团有限公司 跨运营线低净空转体桥施工工法
CN108755413A (zh) * 2018-04-18 2018-11-06 广东省交通规划设计研究院股份有限公司 桥梁建设方法及桥梁
CN108978497A (zh) * 2018-06-27 2018-12-11 中铁十二局集团有限公司 连续梁预埋钢壳分区加工及分体安装方法
CN111979929A (zh) * 2020-08-27 2020-11-24 中铁二十局集团有限公司 转体桥合龙装置及施工方法
CN112222775A (zh) * 2020-09-28 2021-01-15 中船黄埔文冲船舶有限公司 一种端钢壳结构的翼缘板的制作方法

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004324164A (ja) * 2003-04-23 2004-11-18 Ps Mitsubishi Construction Co Ltd 波形鋼板ウエブpc橋閉合部の施工方法
JP2007262654A (ja) * 2006-03-27 2007-10-11 Taisei Corp アーチ橋及びアーチ橋の架設方法
JP2008045370A (ja) * 2006-08-21 2008-02-28 Ihi Corp 鋼製橋脚と杭の定着方法及び装置
CN101195987A (zh) * 2007-12-27 2008-06-11 中交第二航务工程局有限公司 斜拉桥中跨顶推辅助合龙工艺及梁段拉移组合装置
CN101435182A (zh) * 2008-12-30 2009-05-20 中铁大桥局股份有限公司 刚构桥合拢临时锁定方法
JP2009144410A (ja) * 2007-12-13 2009-07-02 Central Nippon Expressway Co Ltd Pc橋の閉合方法
CN101575840A (zh) * 2009-06-02 2009-11-11 重庆交通大学 悬臂拼装钢箱节段的钢-砼组合连续刚构桥施工方法
CN101838968A (zh) * 2010-05-19 2010-09-22 中铁二十局集团有限公司 跨越既有铁路运营线的双线桥施工工艺

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004324164A (ja) * 2003-04-23 2004-11-18 Ps Mitsubishi Construction Co Ltd 波形鋼板ウエブpc橋閉合部の施工方法
JP2007262654A (ja) * 2006-03-27 2007-10-11 Taisei Corp アーチ橋及びアーチ橋の架設方法
JP2008045370A (ja) * 2006-08-21 2008-02-28 Ihi Corp 鋼製橋脚と杭の定着方法及び装置
JP2009144410A (ja) * 2007-12-13 2009-07-02 Central Nippon Expressway Co Ltd Pc橋の閉合方法
CN101195987A (zh) * 2007-12-27 2008-06-11 中交第二航务工程局有限公司 斜拉桥中跨顶推辅助合龙工艺及梁段拉移组合装置
CN101435182A (zh) * 2008-12-30 2009-05-20 中铁大桥局股份有限公司 刚构桥合拢临时锁定方法
CN101575840A (zh) * 2009-06-02 2009-11-11 重庆交通大学 悬臂拼装钢箱节段的钢-砼组合连续刚构桥施工方法
CN101838968A (zh) * 2010-05-19 2010-09-22 中铁二十局集团有限公司 跨越既有铁路运营线的双线桥施工工艺

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
《科协论坛(下半月)》 20070225 高峰立 连续刚构桥合拢段施工技术 , 第02期 2 *
《第十七届全国桥梁学术会议论文集(下册)》 20061231 向中富 等 石板坡大桥结构体系及施工控制特点 , 1 *
《铁道建筑》 20070120 吴必刚 预应力混凝土连续刚构桥的合龙工艺 , 第01期 2 *

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105239499A (zh) * 2015-11-10 2016-01-13 中国建筑第六工程局有限公司 一种钢混结合段后压浆结构
CN108396651A (zh) * 2018-02-06 2018-08-14 中铁二院昆明勘察设计研究院有限责任公司 一种钢壳滑道系统及施工方法
CN108411767A (zh) * 2018-02-06 2018-08-17 中铁二院昆明勘察设计研究院有限责任公司 一种自闭合式合拢钢壳系统及施工方法
CN108396651B (zh) * 2018-02-06 2023-05-16 中铁二院昆明勘察设计研究院有限责任公司 一种钢壳滑道系统及施工方法
CN108755413A (zh) * 2018-04-18 2018-11-06 广东省交通规划设计研究院股份有限公司 桥梁建设方法及桥梁
CN108755413B (zh) * 2018-04-18 2020-07-07 广东省交通规划设计研究院股份有限公司 桥梁建设方法及桥梁
CN108589556A (zh) * 2018-05-04 2018-09-28 中铁二十三局集团有限公司 跨运营线低净空转体桥施工工法
CN108978497A (zh) * 2018-06-27 2018-12-11 中铁十二局集团有限公司 连续梁预埋钢壳分区加工及分体安装方法
CN111979929A (zh) * 2020-08-27 2020-11-24 中铁二十局集团有限公司 转体桥合龙装置及施工方法
CN112222775A (zh) * 2020-09-28 2021-01-15 中船黄埔文冲船舶有限公司 一种端钢壳结构的翼缘板的制作方法

Also Published As

Publication number Publication date
CN102011369B (zh) 2013-01-23

Similar Documents

Publication Publication Date Title
CN102011369B (zh) 跨各种道路的桥梁合拢段钢壳施工方法
CN101852031B (zh) 覆土罐施工方法
CN101781879B (zh) 独塔无背索斜拉桥施工方法
CN205711743U (zh) 一种干湿接缝的钢‑混凝土组合桥面板
CN102493603B (zh) 暗柱式全装配抗震建筑物和工法
CN106703834A (zh) 超大断面隧道二次衬砌整体模筑施工方法
CN104988844B (zh) 二次张拉预应力装配式波形钢腹板组合梁
CN103215894B (zh) 移动式临时预应力张拉锚块
CN103924525B (zh) 城市立交桥工业化短线预制拼装施工方法
CN105625188A (zh) 基于BIM技术的客运专线48m节段梁施工方法
CN101100902A (zh) 斜拉钢桁架高支模结构体系及其施工方法
CN103758348B (zh) 型钢框架结构混凝土楼板悬模浇筑施工方法
CN102966037A (zh) 桥梁伸缩缝安装施工工艺
CN106760110A (zh) 基于bim压型钢板‑钢筋混凝土空腹夹层楼盖施工工法
CN102220741B (zh) 跨越现有线路且与既有线并行的钢混结合梁施工工艺
CN103233424A (zh) 吊篮法无支架防撞墙施工方法及施工吊篮和施工用模板
CN109972655A (zh) 一种预制管廊机械与液压组合型整体安拆钢模板及安装方法
CN203174510U (zh) 桥梁防撞护栏施工用移动装配式吊篮和施工用模板
CN101994292A (zh) 桥梁高墩高效组合快速施工
CN109914666A (zh) 压型钢板混凝土组合楼面大面积浇筑施工方法
CN103952979A (zh) 一种钢砼叠合梁顶板无支架施工装置及施工方法
CN206538685U (zh) 双柱墩和中系梁桁架整体移动系统
CN109869153A (zh) 快速施工竖井衬砌的整体提升悬臂模板装置及施工方法
CN202000692U (zh) 轻型卫生间单元
CN105672113B (zh) 一种波形钢腹板下翼缘钢混结合部构造及施工方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant