CN102011368B - One-time molding construction method for vase-shaped columnar pier of viaduct - Google Patents
One-time molding construction method for vase-shaped columnar pier of viaduct Download PDFInfo
- Publication number
- CN102011368B CN102011368B CN2010105388458A CN201010538845A CN102011368B CN 102011368 B CN102011368 B CN 102011368B CN 2010105388458 A CN2010105388458 A CN 2010105388458A CN 201010538845 A CN201010538845 A CN 201010538845A CN 102011368 B CN102011368 B CN 102011368B
- Authority
- CN
- China
- Prior art keywords
- shaped steel
- vase
- steel formwork
- pier
- set shaped
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Abstract
The invention relates to a one-time molding construction method for a vase-shaped columnar pier of a viaduct. The method comprises the following steps of: early-stage preparation work; assembling shaping steel molding templates, namely finishing binding reinforcing steel bars of the vase-shaped columnar pier of the viaduct according a design drawing; transporting the bond reinforcing steel bars to a scene and assembling into a vase-shaped columnar steel reinforcement cage; placing the vase-shaped columnar steel reinforcement cage on a foundation platform through a wood block; splicing every four machined and fabricated shaping steel molding templates, supporting the spliced shaping steel molding templates on the wood block and positioning the spliced shaping steel molding templates outside the steel reinforcement cage, wherein each shaping steel molding template is 2 to 3 meters long; arranging a plurality of shaping steel molding templates in the height direction of the pier, wherein two back-to-back channel steel belts are arranged on each shaping steel molding template transversely, liner plates are arranged at the two ends of each channel steel belt, opposite pulling holes are reserved on the liner plates, two adjacent molding templates in a transverse direction are locked through opposite pulling lead screws, and a jack used for adjusting the elevation of the shaping steel molding templates is arranged on the upper part of the wood block; and casting concrete. The one-time molding construction method for the vase-shaped columnar pier of the viaduct is convenient to construct.
Description
Technical field
The present invention relates to a kind of viaduct pier construction field, particularly relate to the vase-shaped columnar pier one-shot forming of a kind of viaduct job practices.
Background technology
Present vase-shaped columnar pier for urban viaduct bridges molding construction at twice, opposite joint is always uneven between template, and the centre always has the slit one, pass through processing, so both wasting manpower and material resources, Forming Quality is low, and simultaneously, its outward appearance is also not too attractive in appearance.
Summary of the invention
The present invention is in order to overcome the deficiency of prior art, and the vase-shaped columnar pier one-shot forming of the viaduct of a kind of easy construction that provides job practices, the viaduct pier quality of moulding is high by this method, and outward appearance is beautiful.
The technical scheme that the present invention adopts:
It comprises the steps:
(1) preliminary preparation: foundation platform is cleaned out; The axis and the sideline of the good pier stud of bullet; The good peripheral ground of compacting is put up support scaffolding and is gone up people's cat ladder, configures required concrete; Simultaneously, with the used flitch piece of construction, set shaped steel formwork, channel-section steel band, backing plate, prepare to put in place to drawing lead screw, bolt, jack;
(2) assembling set shaped steel formwork: at first, the reinforcing bar of the vase-shaped columnar pier of viaduct is finished by the design drawing colligation, and transport to on-the-spot spelling and become vase-shaped pillar reinforcing cage; And be placed on the foundation platform through the flitch piece, four one of the set shaped steel formworks that processing and fabricating is good are pieced together to be located at and are positioned at the reinforcing cage outside, the every block length 2-3 of set shaped steel formwork rice on the flitch piece; The polylith set shaped steel formwork is set on the bridge pier short transverse, is horizontally arranged with two back-to-back channel-section steel bands on the every set shaped steel formwork, channel-section steel band two ends are provided with backing plate; Backing plate is provided with pulling eye; Laterally adjacent two templates are through to drawing lead screw locking, and the every horizontal and vertical edge of set shaped steel formwork all is provided with bolt hole, connects locking through bolt in the time of assembling; And adjacent two set shaped steel formwork edge tongue and grooves match; Paste with double faced adhesive tape between set shaped steel formwork tongue and the groove, prevent to mix the earth slurry and run off, flitch piece top also is provided with the absolute altitude that jack is used to adjust set shaped steel formwork;
(3) concreting: it is inner that the concrete slurry that configures is injected the set shaped steel formwork that assembles, but just one-time-concreting moulding after the maintenance.
Be vertically arranged with the channel-section steel stiffener on the above-mentioned set shaped steel formwork.
The technique effect that the present invention obtains:
1. the present invention's vase-shaped columnar pier one-shot forming of viaduct of constructing, easy construction, workable; Do not receive the restriction of fabricating yard condition, applied widely, can reduce cost; Solved scene molding construction at twice effectively; Opposite joint is always uneven between template, the middle construction difficult problem that one slit always arranged, and have comprehensive technology economic benefit preferably.
Description of drawings
Fig. 1 is a set shaped steel formwork scheme of installation of the present invention;
Fig. 2 is the cutaway view Amplified image at the A-A place of Fig. 1;
Fig. 3 is the cutaway view Amplified image that shows set shaped steel formwork tongue 11 at the B-B place of Fig. 2;
Fig. 4 is the cutaway view Amplified image that shows set shaped steel formwork groove 12 at the B-B place of Fig. 2.
Among the figure: 1-foundation platform, 2-flitch, 3-set shaped steel formwork, 4-channel-section steel band, 5-backing plate, 6-to pulling eye, 7-to drawing lead screw, 8-stiffener, 9-jack, 10-bolt hole, 11-tongue, 12-groove, 13-double faced adhesive tape.
The specific embodiment
Below in conjunction with accompanying drawing embodiment of the present invention is done further explanation.
Referring to Fig. 1-4, the vase-shaped columnar pier one-shot forming of a kind of viaduct job practices, it comprises the steps:
(1) preliminary preparation: foundation platform 1 is cleaned out; The axis and the sideline of the good pier stud of bullet; The good peripheral ground of compacting is put up support scaffolding and is gone up people's cat ladder, configures required concrete; Simultaneously, with the used flitch piece 2 of construction, set shaped steel formwork 3, channel-section steel band 4, backing plate 5, prepare to put in place to drawing lead screw 7, bolt, jack 9;
(2) assembling set shaped steel formwork: at first, the reinforcing bar of the vase-shaped columnar pier of viaduct is finished by the design drawing colligation, and transport to on-the-spot spelling and become vase-shaped pillar reinforcing cage; And be placed on the foundation platform 1 through 100x100mm flitch piece 2, the concrete size of flitch piece can specifically be set according to the bridge pier size, and 3 four one of the set shaped steel formworks that processing and fabricating is good are pieced together to be located at and are positioned at the reinforcing cage outside on the flitch piece; The every block length 2-3 of set shaped steel formwork rice is provided with the polylith set shaped steel formwork on the bridge pier short transverse, connect each other to form the bridge pier shape; Be horizontally arranged with two back-to-back channel-section steel bands 4 on the every set shaped steel formwork, channel-section steel band two ends are provided with backing plate 5, and backing plate is provided with pulling eye 6; Laterally adjacent two templates are through to drawing lead screw 7 lockings; The every horizontal and vertical edge of set shaped steel formwork all is provided with bolt hole 10, connect locking through bolt in the time of assembling, and adjacent two set shaped steel formwork edge tongue and grooves matches; Paste with double faced adhesive tape 13 between set shaped steel formwork tongue 11 and the groove 12; Prevent to mix the earth slurry and run off, be vertically arranged with channel-section steel stiffener 8 on the set shaped steel formwork 3, flitch piece top also is provided with the absolute altitude that jack 9 is used to adjust set shaped steel formwork; Used device in the above-mentioned assembling process; Specifically can select for use: like the channel-section steel band is [16 channel-section steels; Backing plate is
equal leg angle; To drawing lead screw is that Φ 12 draws lead screw; Double faced adhesive tape is that 3-5mm is thick; Emboss pit plays 5-10mm, and stiffener is
equal leg angle.
(3) concreting: it is inner that the concrete slurry that configures is injected the set shaped steel formwork that assembles, but just one-time-concreting moulding after the maintenance.
Protection scope of the present invention is not limited to the above embodiments, and obviously, those skilled in the art can carry out various changes and distortion and do not depart from the scope of the present invention and spirit the present invention.If these changes and distortion belong in the scope of claim of the present invention and equivalent technologies thereof, then the intent of the present invention also comprises these changes and is out of shape interior.
Claims (2)
1. the vase-shaped columnar pier one-shot forming of viaduct job practices, it is characterized in that: it comprises the steps:
(1) preliminary preparation: foundation platform (1) is cleaned out; The axis and the sideline of the good pier stud of bullet; The good peripheral ground of compacting is put up support scaffolding and is gone up people's cat ladder, configures required concrete; Simultaneously, with the used flitch piece (2) of construction, set shaped steel formwork (3), channel-section steel band (4), backing plate (5), prepare to put in place to drawing lead screw (7), bolt, jack (9);
(2) assembling set shaped steel formwork: at first the reinforcing bar with the vase-shaped columnar pier of viaduct finishes by the design drawing colligation, and transports to on-the-spot spelling and become vase-shaped pillar reinforcing cage, and is placed on the foundation platform (1) through flitch piece (2); (3) four one assemblies of the set shaped steel formwork that processing and fabricating is good are propped up to be located at and are positioned at the reinforcing cage outside on the flitch piece; The every block length 2-3 of set shaped steel formwork rice is provided with the polylith set shaped steel formwork on the bridge pier short transverse, connect each other to form the bridge pier shape; Be horizontally arranged with two back-to-back channel-section steel bands (4) on the every set shaped steel formwork; Channel-section steel band two ends are provided with backing plate (5), and backing plate is provided with pulling eye (6), and laterally adjacent two templates are through to drawing lead screw (7) locking; The every horizontal and vertical edge of set shaped steel formwork all is provided with bolt hole (10); Connect locking through bolt in the time of assembling, and adjacent two set shaped steel formwork edge tongue and grooves match, paste with double faced adhesive tape (13) between set shaped steel formwork tongue (11) and the groove (12); Prevent that concrete grout runs off, flitch piece top also is provided with the absolute altitude that jack (9) is used to adjust set shaped steel formwork;
(3) concreting: it is inner that the concrete grout that configures is injected the set shaped steel formwork that assembles, but just one-time-concreting moulding after the maintenance.
2. the vase-shaped columnar pier one-shot forming of viaduct according to claim 1 job practices is characterized in that: be vertically arranged with channel-section steel stiffener (8) on the described set shaped steel formwork.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2010105388458A CN102011368B (en) | 2010-11-10 | 2010-11-10 | One-time molding construction method for vase-shaped columnar pier of viaduct |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2010105388458A CN102011368B (en) | 2010-11-10 | 2010-11-10 | One-time molding construction method for vase-shaped columnar pier of viaduct |
Publications (2)
Publication Number | Publication Date |
---|---|
CN102011368A CN102011368A (en) | 2011-04-13 |
CN102011368B true CN102011368B (en) | 2012-02-29 |
Family
ID=43841681
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2010105388458A Expired - Fee Related CN102011368B (en) | 2010-11-10 | 2010-11-10 | One-time molding construction method for vase-shaped columnar pier of viaduct |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102011368B (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107217596A (en) * | 2017-06-07 | 2017-09-29 | 中铁十六局集团第四工程有限公司 | It is a kind of to collect construction method that is prefabricated and installing urban viaduct baffle plate |
Families Citing this family (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106677069B (en) * | 2016-12-28 | 2018-04-06 | 杭州江润科技有限公司 | A kind of construction method of bridge pier integral formwork support one-shot forming structure |
CN107460829B (en) * | 2017-09-05 | 2023-06-30 | 方菱桥隧模架(福州)有限公司 | Bridge pier steel mould installation protection device and installation method thereof |
CN108018782A (en) * | 2017-12-20 | 2018-05-11 | 上海市机械施工集团有限公司 | The construction method of overhead box beam concrete column |
CN110512524A (en) * | 2019-08-16 | 2019-11-29 | 中交一公局第五工程有限公司 | A kind of bridge pier column safe construction method |
Family Cites Families (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
FR2662719B1 (en) * | 1990-05-30 | 1992-10-23 | Scetauroute | CENTRAL DOCK STATION ON A RAILWAY LINE OR OTHER VIADUC CONSTRUCTION. |
CN100432339C (en) * | 2006-11-13 | 2008-11-12 | 北京建工华创工程技术有限公司 | Low temperature construction method for bridge support grouting |
CN100513696C (en) * | 2007-10-16 | 2009-07-15 | 中铁大桥局集团第四工程有限公司 | Pier body cap cracking body outside stress reinforcing method |
CN101845797A (en) * | 2010-05-18 | 2010-09-29 | 武汉一冶交通工程有限责任公司 | One-step molding method of vase-shaped columnar pier for urban viaduct bridges |
-
2010
- 2010-11-10 CN CN2010105388458A patent/CN102011368B/en not_active Expired - Fee Related
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107217596A (en) * | 2017-06-07 | 2017-09-29 | 中铁十六局集团第四工程有限公司 | It is a kind of to collect construction method that is prefabricated and installing urban viaduct baffle plate |
Also Published As
Publication number | Publication date |
---|---|
CN102011368A (en) | 2011-04-13 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102011368B (en) | One-time molding construction method for vase-shaped columnar pier of viaduct | |
CN105220808B (en) | Large-span prestressed arch bar in-situ precast construction method of installation | |
CN106592426A (en) | Prefabricated template system for transverse pre-stress overall width reinforced concrete bridge deck and construction method | |
CN210712751U (en) | Aqueduct trough body post-cast strip concrete formwork mounting structure | |
CN109972837A (en) | A kind of wooden frame template and its application method | |
CN108222347A (en) | A kind of big module welding overlapping beam slab of the assembled with plane girder temporary support | |
CN104831932A (en) | Construction technology for high-grade concrete column base | |
CN104863296A (en) | Integrally modular steel bar truss floor plate and construction method thereof | |
CN204983649U (en) | Big inclination cylinder steel form | |
CN203961099U (en) | A kind of high strength hollow constructional column template brick and the constructional column of building thereof | |
CN210597794U (en) | Connecting device of prefabricated plate | |
CN110219232B (en) | Concrete pouring method for deck type arch bridge | |
CN202023154U (en) | Trestle vase-shaped column-type pier forming mold | |
CN106978898B (en) | Turnover combined die for cast-in-situ molding of reinforced concrete structure and construction method thereof | |
EP3403798B1 (en) | Mobile structure and procedure for the prefabrication of desirably prestressed concrete bars | |
CN106638617A (en) | Pouring method of concrete without template in lattice beam type slope support | |
CN202970006U (en) | L-shaped prefabricated clear water bleacher plate installation construction structure | |
CN201857579U (en) | Vase-shaped column pier forming mould for viaducts | |
CN212835512U (en) | Circular inspection shaft template | |
WO2022012566A1 (en) | Method for installing zippered wall part | |
CN107268755A (en) | A kind of construction method of inlet for stom water | |
CN108978957B (en) | Integrally formed wall body free of dismantling formwork and construction process | |
CN208396295U (en) | A kind of open-cut station construction stair formwork erecting structure | |
CN203684654U (en) | Template assembly structure | |
CN112663943A (en) | Building structure wall construction method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20120229 Termination date: 20211110 |