CN101967986A - Lining trolley for internal model of walking vault of steel support structure of guard post section - Google Patents

Lining trolley for internal model of walking vault of steel support structure of guard post section Download PDF

Info

Publication number
CN101967986A
CN101967986A CN 201010278169 CN201010278169A CN101967986A CN 101967986 A CN101967986 A CN 101967986A CN 201010278169 CN201010278169 CN 201010278169 CN 201010278169 A CN201010278169 A CN 201010278169A CN 101967986 A CN101967986 A CN 101967986A
Authority
CN
China
Prior art keywords
chassis
trolley
lining trolley
guard
support
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN 201010278169
Other languages
Chinese (zh)
Other versions
CN101967986B (en
Inventor
谢玉军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chengdu Ruihe Machinery Manufacturing Co., Ltd.
Chian Railway Shisiju Group Corporation Tunnel Engineering Co., Ltd.
Original Assignee
SICHUAN PROVINCE RUILONG ROAD AND BRIDGE MACHINERY EQUIPMENT CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SICHUAN PROVINCE RUILONG ROAD AND BRIDGE MACHINERY EQUIPMENT CO Ltd filed Critical SICHUAN PROVINCE RUILONG ROAD AND BRIDGE MACHINERY EQUIPMENT CO Ltd
Priority to CN2010102781695A priority Critical patent/CN101967986B/en
Publication of CN101967986A publication Critical patent/CN101967986A/en
Application granted granted Critical
Publication of CN101967986B publication Critical patent/CN101967986B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The invention discloses a lining trolley for an internal model of a walking vault of a steel support structure of a guard post section, which belongs to the technical field of lining trolleys, and comprises a vertical lifting device; the vertical lifting device comprises at least two vertical support cylinders which are arranged at the front end of the trolley and used for supporting a top lower girder, at least two vertical support cylinders which are arranged at the rear end of the trolley and used for supporting the top lower girder, and a jacking strut which is arranged at the middle part of the trolley and used for supporting the top lower girder, wherein the lower ends of the vertical support cylinders and the jacking strut are connected to the lower girder. When carrying out vault lining on the guard post section, the trolley can pass through the temporary steel support structure conveniently and quickly; and the trolley has the advantages of strong reliability and low construction cost.

Description

Go along with sb. to guard him the pile cutoff steel and support step type vault internal mold lining trolley
Technical field
The present invention relates to a kind of lining trolley, especially relate to a kind of pile cutoff steel of going along with sb. to guard him and support step type vault internal mold lining trolley.
Background technology
Go along with sb. to guard him pile cutoff steel support step type vault internal mold lining trolley and be used to go along with sb. to guard him the lining cutting that pile cutoff has the temporary steel support section, the abutment wall owing to construct earlier, there is temporary steel support to prop up after the construction in the side wall both sides, when the lining cutting of construction arch, described temporary steel support can not be removed again, therefore chassis must pass through temporary steel support when walking, chassis is to adopt chassis levels separated structures form by the method for temporary steel support at present, also promptly be embedded with sleeve bolt in the side wall both sides, by sleeve bolt bracket is installed, interim rail is housed on the bracket, chassis upper strata running gear is walked on rail, the arch lining construction finishes, and bracket is removed again.This chassis structure not only causes construction very complicated, because in order to guarantee interim rail security of operation, the installation site required precision of bracket is very high, thereby construction cost height, and the weight on chassis upper strata is all supported by bracket, side wall is stressed bigger so, causes the chassis reliability of operation relatively poor, has potential safety hazard.
Summary of the invention
The objective of the invention is to: provide a kind of do not need chassis levels lock out operation also can be easily the pile cutoff steel of going along with sb. to guard him by temporary steel support support step type vault internal mold lining trolley.
Technical scheme of the present invention is: a kind of pile cutoff steel of going along with sb. to guard him supports step type vault internal mold lining trolley, comprise vertical lifting gear, described vertical lifting gear comprises at least two at least two vertical support cylinders that are used to support longeron under the upper strata that are used to support the vertical support cylinder of longeron under the upper strata and are positioned at the chassis rear end that are positioned at the chassis front end, and the fore-set that is used to support longeron under the upper strata that is positioned at the chassis middle part, the lower end of described vertical support cylinder and fore-set is connected in down on the longeron; Wherein, described vertical support cylinder comprises the oil cylinder that has piston rod, and described oil cylinder is socketed with casing outward, is connected with fairlead on the described piston rod, and described fairlead is socketed in the casing; Described fore-set comprises fixed leg, and the upper end of fixed leg is provided with jack, and described jack side is provided with hangers, and described hangers is articulated on the connecting rod of fixed leg upper side.
The top of described fairlead is connected in the top of piston rod.
Described connecting rod is removably connected to the fixed leg upper side.
Described fixed leg upper side is provided with two supporting legs, and described connecting rod is riveted on two supporting legs.
Using method of the present invention: when chassis will pass through temporary steel support, be positioned at of the piston rod contraction of chassis front end near the vertical support cylinder of temporary steel support, be contracted to the position that is lower than temporary steel support, temporary steel support is by this vertical support cylinder top then, when temporary steel support was passed through this vertical support cylinder, the piston rod of described vertical support cylinder stretched out and supports longeron under the upper strata; In like manner, adopt with the quadrat method chassis through adjacent vertical support cylinder; When the chassis fore-set will pass through temporary steel support, regulate the jack of the upper end of fixed leg, it is reduced highly slightly, promptly reduce to make it swing to a side time when jack, jack is fallen to hangers one thruster, the height of chassis fore-set becomes the height of fixed leg, and this moment, the chassis fore-set can pass temporary steel support smoothly; In like manner, adopt with the chassis fore-set of quadrat method chassis through other; When temporary steel support will be passed through in the chassis rear end, be positioned at of the piston rod contraction of chassis rear end near the vertical support cylinder of temporary steel support, be contracted to the position that is lower than temporary steel support, temporary steel support is by this vertical support cylinder top then, when temporary steel support was passed through this vertical support cylinder, the piston rod of described vertical support cylinder stretched out and supports longeron under the upper strata; In like manner, adopt with the quadrat method chassis through adjacent vertical support cylinder.
Need to prove, a kind of pile cutoff steel of going along with sb. to guard him of the present invention supports step type vault internal mold lining trolley, for the existing stake section of going along with sb. to guard him vault internal mold lining trolley, its innovation part is, the present invention has adopted vertical lifting gear, and the structure that other of chassis do not relate to vertical lifting gear still adopts prior art.
The invention has the beneficial effects as follows: when the lining cutting of the stake section of going along with sb. to guard him construction arch, chassis can pass through temporary steel support quickly and easily; And good reliability, construction cost is low.
The present invention is further described below in conjunction with the drawings and specific embodiments.
Description of drawings
Fig. 1 is the structural representation of user mode of the present invention;
Fig. 2 is the lateral view of Fig. 1;
Fig. 3 is the structural representation of vertical support cylinder among Fig. 1;
Fig. 4 is the structural representation of fore-set among Fig. 1;
Fig. 5 is the structural representation that jack described in Fig. 4 is swung to fixed leg one side;
Reference numeral is, 1 is longeron under the upper strata, and 2 is vertical support cylinder, and 2-1 is a piston rod, 2-2 is an oil cylinder, and 2-3 is a fairlead, and 2-4 is a casing, and 3 is fore-set, 3-1 is a jack, and 3-2 is a fixed leg, and 3-3 is a hangers, 3-4 is a connecting rod, and 3-5 is a supporting leg, and 4 are following longeron, 5 is running gear, and 6 is the door frame crossbeam, and 7 is temporary steel support, 8 is the door frame lower transverse beam, and 9 is door frame transverse truss pull bar, and 10 is that vertical screw mandrel is very heavy.
The specific embodiment
Preferred embodiment
Extremely shown in Figure 5 as Fig. 1, a kind of pile cutoff steel of going along with sb. to guard him supports step type vault internal mold lining trolley, comprise vertical lifting gear, described vertical lifting gear comprises and is positioned at vertical support cylinder 2 in the left and right sides and fore-set 3, wherein every side is positioned at two two vertical support cylinders 2 that are used to support longeron 1 under the upper strata that are used to support the vertical support cylinder 2 of longeron 1 under the upper strata and are positioned at the chassis rear end of chassis front end, and the fore-set that is used to support longeron 1 under the upper strata 3 that is positioned at the chassis middle part, the lower end of described vertical support cylinder 2 and fore-set 3 is connected in down on the longeron 4.Described vertical support cylinder comprises the oil cylinder 2-2 that has piston rod 2-1, described oil cylinder 2-2 is socketed with casing 2-4 outward, be connected with fairlead 2-3 on the described piston rod 2-1, described fairlead 2-3 is socketed among the casing 2-4, and the top of described fairlead 2-3 is connected in the top of piston rod 2-1.When oil cylinder is subjected to time spent of doing of lateral force, lateral force passes to fairlead by casing, thereby protection piston rod 2-1 avoids the effect of lateral force, can also prevent that foreign material from entering piston simultaneously.Described fore-set 3, comprise fixed leg 3-2, the upper end of fixed leg is provided with jack 3-1, described jack 3-1 side is provided with hangers 3-3, described hangers 3-3 is articulated on the connecting rod 3-4 of fixed leg 3-2 upper side, described fixed leg 3-2 upper side is provided with two supporting leg 3-5, and described connecting rod 3-4 is riveted on two supporting leg 3-5, and described hangers 3 is articulated on the connecting rod 3 between two supporting legs 5.Prop up on side wall 8 at the two ends of temporary steel support 7 among the figure.
In the present embodiment, except above-mentioned vertical lifting gear, the running gear 5 that also comprises longeron 4 belows under being loaded on that has chassis now, door frame crossbeam 6 is installed on the longeron 1 under the described upper strata, and the rack system of adorning on the door frame crossbeam, door frame crossbeam 6 is connected with door frame lower transverse beam 8 with door frame transverse truss pull bar 9 by vertical screw mandrel very heavy 10.Need to prove that when passing through temporary steel support, the vertical screw mandrel very heavy 9 and the door frame transverse truss pull bar 10 of chassis all need fall, when vault was constructed, vertical screw mandrel very heavy 9 and door frame transverse truss pull bar 10 were in place and support door frame crossbeam 6.
Disclosed all features in this manual, or the step in disclosed all methods or the process except mutually exclusive feature and/or step, all can make up by any way.
Disclosed arbitrary feature in this manual (comprising any accessory claim, summary and accompanying drawing) is unless special narration all can be replaced by other equivalences or the alternative features with similar purpose.That is, unless special narration, each feature is an example in a series of equivalences or the similar characteristics.
The above only is preferred embodiment of the present invention, not in order to restriction the present invention, all any modifications of being done within the spirit and principles in the present invention, is equal to and replaces and improvement etc., all should be included within protection scope of the present invention.

Claims (4)

1. go along with sb. to guard him pile cutoff steel support step type vault internal mold lining trolley for one kind, comprise vertical lifting gear, it is characterized in that, described vertical lifting gear comprises that every side is positioned at least two at least two vertical support cylinders (2) that are used to support longeron under the upper strata (1) that are used to support the vertical support cylinder (2) of longeron under the upper strata (1) and are positioned at the chassis rear end of chassis front end, and the fore-set that is used to support longeron under the upper strata (1) (3) that is positioned at the chassis middle part, the lower end of described vertical support cylinder (2) and fore-set (3) is connected in down on the longeron (4); Wherein, described vertical support cylinder comprises the oil cylinder (2-2) that has piston rod (2-1), described oil cylinder (2-2) is outer to be socketed with casing (2-4), is connected with fairlead (2-3) on the described piston rod (2-1), and described fairlead (2-3) is socketed in the casing (2-4); Described fore-set (3) comprises fixed leg (3-2), and the upper end of fixed leg is provided with jack (3-1), and described jack (3-1) side is provided with hangers (3-3), and described hangers (3-3) is articulated on the connecting rod (3-4) of fixed leg (3-2) upper side.
2. the pile cutoff steel of going along with sb. to guard him according to claim 1 supports step type vault internal mold lining trolley, it is characterized in that the top of described fairlead (2-3) is connected in the top of piston rod (2-1).
3. the pile cutoff steel of going along with sb. to guard him according to claim 1 supports step type vault internal mold lining trolley, and it is characterized in that: described connecting rod (3-4) is removably connected to fixed leg (3-2) upper side.
4. the pile cutoff steel of going along with sb. to guard him according to claim 3 supports step type vault internal mold lining trolley, and it is characterized in that: described fixed leg (3-2) upper side is provided with two supporting legs (3-5), and described connecting rod (3-4) is riveted on two supporting legs (3-5).
CN2010102781695A 2010-09-10 2010-09-10 Lining trolley for internal model of walking vault of steel support structure of guard post section Active CN101967986B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2010102781695A CN101967986B (en) 2010-09-10 2010-09-10 Lining trolley for internal model of walking vault of steel support structure of guard post section

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2010102781695A CN101967986B (en) 2010-09-10 2010-09-10 Lining trolley for internal model of walking vault of steel support structure of guard post section

Publications (2)

Publication Number Publication Date
CN101967986A true CN101967986A (en) 2011-02-09
CN101967986B CN101967986B (en) 2012-07-25

Family

ID=43547196

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2010102781695A Active CN101967986B (en) 2010-09-10 2010-09-10 Lining trolley for internal model of walking vault of steel support structure of guard post section

Country Status (1)

Country Link
CN (1) CN101967986B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104533460A (en) * 2014-12-31 2015-04-22 上海市机械施工集团有限公司 Construction method for concrete pouring of support-changing type formwork trolley and underground channel

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2131978Y (en) * 1992-08-08 1993-05-05 铁道部第五工程局第四工程处 Lining-building platform car for tunnel construction
JP2005048382A (en) * 2003-07-30 2005-02-24 Sumitomo Mitsui Construction Co Ltd Work truck, and tunnel excavator equipped with the work truck
CN1851233A (en) * 2006-05-24 2006-10-25 杨秋利 Tunnel lining trolley
EP2090744A1 (en) * 2008-02-13 2009-08-19 Jörimann Stahl AG Conveyor trolley
JP2009209525A (en) * 2008-02-29 2009-09-17 Taisei Corp Self-propelled segment assembling equipment and self-propelled segment assembling method
CN201778823U (en) * 2010-09-10 2011-03-30 四川省锐隆路桥机械设备有限公司 Enclosure pile section steel support walking arch crown internal mold lining trolley

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2131978Y (en) * 1992-08-08 1993-05-05 铁道部第五工程局第四工程处 Lining-building platform car for tunnel construction
JP2005048382A (en) * 2003-07-30 2005-02-24 Sumitomo Mitsui Construction Co Ltd Work truck, and tunnel excavator equipped with the work truck
CN1851233A (en) * 2006-05-24 2006-10-25 杨秋利 Tunnel lining trolley
EP2090744A1 (en) * 2008-02-13 2009-08-19 Jörimann Stahl AG Conveyor trolley
JP2009209525A (en) * 2008-02-29 2009-09-17 Taisei Corp Self-propelled segment assembling equipment and self-propelled segment assembling method
CN201778823U (en) * 2010-09-10 2011-03-30 四川省锐隆路桥机械设备有限公司 Enclosure pile section steel support walking arch crown internal mold lining trolley

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
《河南水利与南水北调》 20071213 马进元 燕山水库泄洪洞边顶拱钢模台车施工技术 50-51 1-4 , 第8期 *
《铁道建筑技术》 20011231 李新航 秦岭隧道钢模台车的作业方式 30-31 1-4 , 第1期 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104533460A (en) * 2014-12-31 2015-04-22 上海市机械施工集团有限公司 Construction method for concrete pouring of support-changing type formwork trolley and underground channel
CN104533460B (en) * 2014-12-31 2016-10-05 上海市机械施工集团有限公司 Support replacement formula formwork jumbo and the construction method of underpass concreting

Also Published As

Publication number Publication date
CN101967986B (en) 2012-07-25

Similar Documents

Publication Publication Date Title
CN102002913B (en) Prefabricated T beam transferring trolley
CN206070393U (en) A kind of asynchronous construction hanging basket of Wavelike steel webplate composite beam bridge
CN206233543U (en) A kind of climbing device for jacking construction platform
CN202544854U (en) Lining trolley for subway station
CN106522112A (en) Cable-stayed bridge side span beam section erecting system and method thereof
CN205711757U (en) Section assembling truss double beam girder erecting machine
CN103835195B (en) Cross-device and the method for the quick traversing change of a kind of track-laying machine low level jacking
CN203530851U (en) Basket device for combined basket working vehicle
CN101570959B (en) Cross-over bridge fabrication machine with up mobile formwork and cross-over construction method thereof
CN103993849A (en) Wellhead stabilizer
CN201778823U (en) Enclosure pile section steel support walking arch crown internal mold lining trolley
CN101864731A (en) Mobile framework equipment
CN101967986B (en) Lining trolley for internal model of walking vault of steel support structure of guard post section
CN204282803U (en) To encorbelment formwork structure for mounting platform
CN204126655U (en) The anti-electric lining trolley of double track tunnel newly-built hangar tunnel lining construction
CN206538687U (en) Cable-stayed bridge end bay beam section construction system
CN108086169A (en) The installation method for improving of bridge construction mobile formwork
CN202611340U (en) Self-propelled road bed protective barrier transportation and installation all-in-one machine
CN102225580B (en) Method for longitudinally moving box girder internal mold
CN209039992U (en) Bracket is packed in high-speed rail Bridge Erector transition
CN201420239Y (en) Hydraulic locking mechanism
CN205935727U (en) Elevartor shaft automatic crawl robot and safety protection stage mechanism
CN203729163U (en) Track laying machine low-position jacking fast shifting span-changing device
CN203175575U (en) Concrete lining steel mould trolley side mould plate supporting device
CN108775016B (en) Concrete support horizontal movement adjustable hanging basket

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
ASS Succession or assignment of patent right

Owner name: CHENGDU RUILONG MACHINERY MANUFACTURING CO., LTD.

Free format text: FORMER OWNER: SICHUAN RUILONG ROAD + BRIDGE MACHINERY EQUIPMENT CO., LTD.

Effective date: 20110715

C41 Transfer of patent application or patent right or utility model
COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 610300 FUXING AVENUE (INSIDE OF DACHENG INDUSTRIAL PARK), DATONG INDUSTRIALPARK, QINGBAIJIANG DISTRICT, CHENGDU CITY, SICHUAN PROVINCE TO: 610300 BEIXIN ECONOMIC DEVELOPMENT ZONE, QINGBAIJIANG DISTRICT, CHENGDU CITY, SICHUAN PROVINCE

TA01 Transfer of patent application right

Effective date of registration: 20110715

Address after: 610300 New Economic Development Zone, Qingbaijiang District, Sichuan, Chengdu

Applicant after: Chengdu Ruihe Machinery Manufacturing Co., Ltd.

Address before: 610300, Fuxing Road, Dacheng Industrial Zone, Qingbaijiang District, Sichuan, Chengdu province (Dacheng Industrial Park)

Applicant before: Sichuan Province Ruilong Road and Bridge Machinery Equipment Co., Ltd.

C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: CHINA RAILWAY SHISIJU GROUP TUNNEL ENGINEERING CO.

Effective date: 20130717

C41 Transfer of patent application or patent right or utility model
C53 Correction of patent for invention or patent application
CB03 Change of inventor or designer information

Inventor after: Xie Yujun

Inventor after: Yang Liangang

Inventor after: Wang Jianwei

Inventor after: Li Zhong

Inventor before: Xie Yujun

COR Change of bibliographic data

Free format text: CORRECT: INVENTOR; FROM: XIE YUJUN TO: XIE YUJUN YANG LIANGANG WANG JIANWEI LI ZHONG

TR01 Transfer of patent right

Effective date of registration: 20130717

Address after: 610300 New Economic Development Zone, Qingbaijiang District, Sichuan, Chengdu

Patentee after: Chengdu Ruihe Machinery Manufacturing Co., Ltd.

Patentee after: Chian Railway Shisiju Group Corporation Tunnel Engineering Co., Ltd.

Address before: 610300 New Economic Development Zone, Qingbaijiang District, Sichuan, Chengdu

Patentee before: Chengdu Ruihe Machinery Manufacturing Co., Ltd.