CN101876253A - 大倾角煤层开采工作面布置方法 - Google Patents

大倾角煤层开采工作面布置方法 Download PDF

Info

Publication number
CN101876253A
CN101876253A CN2009102523722A CN200910252372A CN101876253A CN 101876253 A CN101876253 A CN 101876253A CN 2009102523722 A CN2009102523722 A CN 2009102523722A CN 200910252372 A CN200910252372 A CN 200910252372A CN 101876253 A CN101876253 A CN 101876253A
Authority
CN
China
Prior art keywords
section
coal seam
working surface
active section
back production
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2009102523722A
Other languages
English (en)
Inventor
黄国春
伍永平
廖由俊
周强文
李明
周登辉
唐宗良
毛新红
解盘石
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Baosteel Group Xinjiang Bayi Iron and Steel Co Ltd
Original Assignee
Baosteel Group Xinjiang Bayi Iron and Steel Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Baosteel Group Xinjiang Bayi Iron and Steel Co Ltd filed Critical Baosteel Group Xinjiang Bayi Iron and Steel Co Ltd
Priority to CN2009102523722A priority Critical patent/CN101876253A/zh
Publication of CN101876253A publication Critical patent/CN101876253A/zh
Pending legal-status Critical Current

Links

Images

Landscapes

  • Devices Affording Protection Of Roads Or Walls For Sound Insulation (AREA)

Abstract

本发明公开了一种大倾角煤层开采工作面布置方法,该工作面采用由顶板-煤层-底板的折线形布置方式,工作面沿所要开采的煤层倾斜方向自下而上布置为沿顶回采段、变坡段和沿底回采段,变坡段角度按照小于煤层倾角布置,保证开采过程中支架的稳定性。

Description

大倾角煤层开采工作面布置方法
技术领域
本发明涉及一种煤矿开采工作面布置方式,特别是大倾角煤层开采工作面布置方法。
背景技术
大倾角煤层走向长壁开采工作面布置优化技术是大倾角煤层长壁综放开采的核心技术,也是确保项目实施并取得成功的基础和关键。合理的巷道布置,不仅能改善大倾角煤层条件下支架受力状态和设备运行条件,从根本上解决大倾角煤层综采长壁工作面上下端头行人、通风、运料不畅问题,而且还能减少煤层长壁综放工作面基本支架对端头支架斜面侧向推力,有效地防止基本支架倾倒下滑和控制工作面前后部运输机的上窜下滑,顺利实现大倾角煤层开采。
发明内容
本发明的目的在于提供一种大倾角煤层开采工作面布置方法,该方法能够克服开采设备的整体下滑和支架倾倒现象,提高支架的稳定性,解决由于煤层底板太软带来的不利影响,确保开采工作正常进行。
本发明解决其技术问题所采用的技术方案是:一种大倾角煤层开采工作面布置方法,在煤层内的运输顺槽与回风顺槽之间由下到上倾斜开挖设置工作面,工作面由下、中、上三个工作段连接呈折线形,下工作段为沿顶回采段,该回采段沿着所要开采煤层的顶板平行布置,上工作段为沿底回采段,该回采段沿着所要开采煤层的底板平行布置,上工作段与下工作段之间通过所说的中工作段相连,中工作段为变坡段,该变坡段与水平面之间的夹角小于25度,上工作段的长度大于下工作段的长度,工作面内间隔均布设置着液压支架。
本发明的有益效果是,一方面通过变坡段缓解了上段工作面中上段支架失稳(倾倒、下滑)对下段支架的冲力或挤压,提高了支护的稳定性;另一方面减少了工作面下部采空区冒落空间,使冒落矸石充填段上移,有利于工作面支护的稳定,特别是强制放顶时,冒落矸石下滑冲击力减弱,对支架冲击力减缓。本发明方法简单易行,能够克服开采设备的整体下滑和支架倾倒现象,提高支架的稳定性,解决由于煤层底板太软带来的不利影响,确保开采工作正常进行。
附图说明
下面结合附图和实施例对本发明进一步说明。
附图为本发明的工作面布置结构示意图。
具体实施方式
新疆焦煤集团艾维尔沟煤矿25112工作面1主采5#煤层,煤层平均厚度5.1m,平均倾角39°,工作面1长95m,采用走向长壁综放开采方法,采高2.3m,放煤高度2.8m。工作面1采用了本发明工作面布置方式。
如附图所示,在煤层内的运输顺槽2与回风顺槽3之间由下到上倾斜开挖设置工作面1,工作面1由下、中、上三个工作段连接呈折线形,下工作段6为沿顶回采段,长19米,该回采段沿着所要开采煤层5的顶板10平行布置,所要开采煤层5为底煤层。
上工作段8为沿底回采段,长度为57米,该回采段沿着所要开采煤层4的底板11平行布置,所要开采煤层4为顶煤层,上工作段8与下工作段6之间通过所说的中工作段7相连。
中工作段7为变坡段,长度为20米,该变坡段与水平面之间的夹角9为24度。
上工作段8的长度大于下工作段6的长度,沿底回采段长度占整个工作面1长度的60%~75%。
工作面内间隔均布设置着液压支架12。如附图所示,液压支架12的布置形式为:在沿顶回采段6内布置1-10#液压支架,在变坡段7内布置11-22#液压支架,在沿底回采段8内布置23#~60#液压支架。

Claims (3)

1.一种大倾角煤层开采工作面布置方法,其特征在于:在煤层内的运输顺槽与回风顺槽之间由下到上倾斜开挖设置工作面,工作面由下、中、上三个工作段连接呈折线形,下工作段为沿顶回采段,该回采段沿着所要开采煤层的顶板平行布置,上工作段为沿底回采段,该回采段沿着所要开采煤层的底板平行布置,上工作段与下工作段之间通过所说的中工作段相连,中工作段为变坡段,该变坡段与水平面之间的夹角小于25度,上工作段的长度大于下工作段的长度,工作面内间隔均布设置着液压支架。
2.根据权利要求1所述的大倾角煤层开采工作面布置方法,其特征在于:沿底回采段长度占整个工作面长度的60%~75%。
3.根据权利要求1所述的大倾角煤层开采工作面布置方法,其特征在于:变坡段与水平面之间的夹角为24°。
CN2009102523722A 2009-04-29 2009-11-27 大倾角煤层开采工作面布置方法 Pending CN101876253A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2009102523722A CN101876253A (zh) 2009-04-29 2009-11-27 大倾角煤层开采工作面布置方法

Applications Claiming Priority (3)

Application Number Priority Date Filing Date Title
CN200910113305.2 2009-04-29
CN200910113305 2009-04-29
CN2009102523722A CN101876253A (zh) 2009-04-29 2009-11-27 大倾角煤层开采工作面布置方法

Publications (1)

Publication Number Publication Date
CN101876253A true CN101876253A (zh) 2010-11-03

Family

ID=43018912

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2009102523722A Pending CN101876253A (zh) 2009-04-29 2009-11-27 大倾角煤层开采工作面布置方法

Country Status (1)

Country Link
CN (1) CN101876253A (zh)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102392681A (zh) * 2011-10-14 2012-03-28 中国矿业大学 厚煤层临空区回采巷道的防冲布置方法
CN102536238A (zh) * 2012-01-09 2012-07-04 中国矿业大学 一种大倾角层状非煤固体矿床采矿方法
CN102852523A (zh) * 2012-09-12 2013-01-02 华亭煤业集团有限责任公司 急倾斜综放工作面反s形切眼的布置方法
CN103485786A (zh) * 2013-09-11 2014-01-01 太原理工大学 一种急倾斜煤层走向长壁机械化开采方法
CN103953348A (zh) * 2014-05-13 2014-07-30 中国矿业大学 一种大倾角/急倾斜煤层采空区矸石协同利用控制顶板方法
CN104088639A (zh) * 2014-06-25 2014-10-08 西安科技大学 一种大倾角厚煤层走向长壁工作面大采高开采方法
CN105484783A (zh) * 2015-12-04 2016-04-13 西安科技大学 适用于大倾角煤层长壁伪俯斜工作面的平行四边形液压支架
CN108915687A (zh) * 2018-07-03 2018-11-30 河南理工大学 急倾斜分段采掘一体化放顶煤采煤方法
CN109763822A (zh) * 2019-01-21 2019-05-17 西安科技大学 大倾角厚煤层多区段无煤柱错层护巷及段间煤柱充填方法
CN109915144A (zh) * 2019-04-17 2019-06-21 中国矿业大学 一种大倾角分叉煤层综放转综采连续推进开采方法

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1190693A (zh) * 1998-02-18 1998-08-19 中国矿业大学(北京校区) 厚煤层错层位巷道布置采全厚采煤法
RU2147682C1 (ru) * 1998-09-24 2000-04-20 Российский Университет Дружбы Народов Способ разработки мощного пологого пласта короткими забоями в диагональных слоях
CN2610087Y (zh) * 2003-06-28 2004-04-07 靖远煤业有限责任公司 临界大倾角特厚煤层综放工作面下段设计
CN1558090A (zh) * 2004-02-10 2004-12-29 中国矿业大学(北京校区) 厚煤层全高开采的三段式回采工艺

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1190693A (zh) * 1998-02-18 1998-08-19 中国矿业大学(北京校区) 厚煤层错层位巷道布置采全厚采煤法
RU2147682C1 (ru) * 1998-09-24 2000-04-20 Российский Университет Дружбы Народов Способ разработки мощного пологого пласта короткими забоями в диагональных слоях
CN2610087Y (zh) * 2003-06-28 2004-04-07 靖远煤业有限责任公司 临界大倾角特厚煤层综放工作面下段设计
CN1558090A (zh) * 2004-02-10 2004-12-29 中国矿业大学(北京校区) 厚煤层全高开采的三段式回采工艺

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
唐军华: "高瓦斯区松软煤层沿顶布巷综放回采", 《煤》 *
谢俊文: "急倾斜厚煤层走向长壁综放开采技术", 《煤炭学报》 *

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102392681A (zh) * 2011-10-14 2012-03-28 中国矿业大学 厚煤层临空区回采巷道的防冲布置方法
CN102536238A (zh) * 2012-01-09 2012-07-04 中国矿业大学 一种大倾角层状非煤固体矿床采矿方法
CN102852523A (zh) * 2012-09-12 2013-01-02 华亭煤业集团有限责任公司 急倾斜综放工作面反s形切眼的布置方法
CN103485786A (zh) * 2013-09-11 2014-01-01 太原理工大学 一种急倾斜煤层走向长壁机械化开采方法
CN103485786B (zh) * 2013-09-11 2016-01-20 太原理工大学 一种急倾斜煤层走向长壁机械化开采方法
CN103953348A (zh) * 2014-05-13 2014-07-30 中国矿业大学 一种大倾角/急倾斜煤层采空区矸石协同利用控制顶板方法
CN104088639A (zh) * 2014-06-25 2014-10-08 西安科技大学 一种大倾角厚煤层走向长壁工作面大采高开采方法
CN105484783A (zh) * 2015-12-04 2016-04-13 西安科技大学 适用于大倾角煤层长壁伪俯斜工作面的平行四边形液压支架
CN108915687A (zh) * 2018-07-03 2018-11-30 河南理工大学 急倾斜分段采掘一体化放顶煤采煤方法
CN109763822A (zh) * 2019-01-21 2019-05-17 西安科技大学 大倾角厚煤层多区段无煤柱错层护巷及段间煤柱充填方法
CN109915144A (zh) * 2019-04-17 2019-06-21 中国矿业大学 一种大倾角分叉煤层综放转综采连续推进开采方法
CN109915144B (zh) * 2019-04-17 2020-04-28 中国矿业大学 一种大倾角分叉煤层综放转综采连续推进开采方法

Similar Documents

Publication Publication Date Title
CN101876253A (zh) 大倾角煤层开采工作面布置方法
CN101915101B (zh) 一种急倾斜厚煤层采煤方法
CN102061921B (zh) 大倾角煤层走向长壁工作面异形液压支架俯斜开采方法
CN201460729U (zh) 掘进机机载锚杆钻机
CN101514633A (zh) 无巷旁支护的沿空留巷工艺
CN103407737A (zh) 快速掘进用迈步式自移胶带机机尾
CN104088639A (zh) 一种大倾角厚煤层走向长壁工作面大采高开采方法
CN205638519U (zh) 一种薄煤层固体充填支架
CN103939135B (zh) 一种综采工作面撤架通道快速施工方法
CN202483604U (zh) 一种用于斜顶巷道超前支护的液压支架
CN104265291A (zh) 急倾斜特厚煤层刨运机综合机械化采煤方法
CN203962014U (zh) 综采充填两用工作面液压支架
CN102418525A (zh) 软煤层长壁大采高综合机械化采煤末采方法
CN101265808B (zh) 煤矿联体异步支架充填挡墙
CN201090231Y (zh) 采煤工作面支护联合液压支架
CN201747392U (zh) 一种煤矿用联顶梁滑移液压支架系统
CN101906984B (zh) 一种煤矿用联顶梁滑移液压支架系统
CN105370282B (zh) 大倾斜特厚煤层高段走向壁式综放采煤法
CN201209457Y (zh) 斜顶巷道超前支护横向前移支架
CN103362511B (zh) 急倾斜中厚煤层台阶式无煤柱采煤法
CN205172581U (zh) 大倾斜特厚煤层高段走向壁式综放开采结构
CN104832177A (zh) 一种大倾角煤层合层分岔连续开采的方法
CN104265344A (zh) 输送机卸载部后置式端头液压支架
CN203428405U (zh) 快速掘进用迈步式自移胶带机机尾
CN203570351U (zh) 薄煤层综合机械化沿空留巷支护装置

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20101103