CN101871347A - 采矿环境再造分层分条中深孔落矿采矿法 - Google Patents

采矿环境再造分层分条中深孔落矿采矿法 Download PDF

Info

Publication number
CN101871347A
CN101871347A CN 201010221547 CN201010221547A CN101871347A CN 101871347 A CN101871347 A CN 101871347A CN 201010221547 CN201010221547 CN 201010221547 CN 201010221547 A CN201010221547 A CN 201010221547A CN 101871347 A CN101871347 A CN 101871347A
Authority
CN
China
Prior art keywords
ore
bar shaped
filling
layering
circulation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN 201010221547
Other languages
English (en)
Other versions
CN101871347B (zh
Inventor
周科平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Central South University
Original Assignee
Central South University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Central South University filed Critical Central South University
Priority to CN2010102215476A priority Critical patent/CN101871347B/zh
Publication of CN101871347A publication Critical patent/CN101871347A/zh
Application granted granted Critical
Publication of CN101871347B publication Critical patent/CN101871347B/zh
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Drilling And Exploitation, And Mining Machines And Methods (AREA)

Abstract

本发明公开了一种采矿环境再造分层分条中深孔落矿采矿法,首先将急倾斜中厚以上不稳固富矿体划分阶段,阶段内划分数个小分层,分层内划分若干条形矿柱,以条形矿柱为回采单元,分两个循环进行开采;在第一循环各条形矿柱内开凿凿岩道,条形矿柱末端设置通风天井,将通风天井扩展形成切割槽,中深孔凿岩,侧向崩矿,后退式回采,装矿运至阶段矿石溜井,矿石运至地表选厂,高标号充填料充填至各条形采空区;分层内条形矿柱采取隔一采一的协调有序回采方式;第二循环内在充填工艺时,先在各条形采空区底部充填一定厚度的高标号充填料,剩余空间采取低标号充填料充填。本发明具有开采环境安全可靠,矿石回收率和生产率高,贫化损失低等特点。

Description

采矿环境再造分层分条中深孔落矿采矿法
技术领域
本发明涉及一种金属矿床地下开采的采矿方法,主要适用于回采矿体不稳固、围岩不稳固至稳固、矿石价值较高(品位高)的急倾斜中厚以上矿体。
背景技术
矿体不稳固、价值较高的急倾斜中厚以上金属矿床,通常采用分层充填采矿法、上向进路充填采矿法进行回采。
传统的分层充填法可分为“上向分层充填采矿法”和“下向分层充填采矿法”两种,其分层高度约为2.5-4.0m,它们分布以上向和下向的方式逐层进行矿房回采。“上向分层充填采矿法”的特点是:自下而上一层一层地往上回采,每采完一个分层,随机用充填材料充填分层空区,然后再回采上一分层;充填体作用于上、下盘围岩,并作为上一分层回采作业的工作平台。采用这种方法回采时,人员、设备在空顶高达5-7m的顶板暴露面下工作,生产安全性差。“下向分层充填采矿法”与上述采矿法的回采方向正相反,它是自上而下一层一层地往下回采,每采完一个分层就用混凝土进行分层胶结充填,充填体作为下一分层回采的人工顶板;用混凝土作充填料时,需要布设钢筋,工艺复杂,充填成本很高,采矿效率低。
传统的分层充填采矿法的作业循环包括:凿岩爆破、出矿、充填和护顶,完成一个作业循环后,转入另一分层的回采。因此,这种采矿方法的回采工艺十分复杂、安全条件不好、工作面劳动生产率较低、作业成本高、矿块生产能力也受到很大限制,为了完成产量,同时回采的矿块数多,井下工作线长,生产组织管理复杂。
上向进路充填采矿法是一种由下而上,以巷道进路方式回采并充填的采矿方法,主要适用于矿岩均不稳固,但矿体基本能保证回采进路稳定的高价值金属矿床。其特点是:进路顶板暴露面积与采场比较相对较小,能保证回采作业的安全;进路断面较大,凿岩、出矿、支护、充填等工艺可实现机械化作业,为不破坏矿石原有稳定性和保证接顶的质量,进路回采采用光面爆破。
上向进路充填采矿法凿岩、出矿、支护、充填等工艺机械化程度低于其它方法,单个进路生产能力较低,断面较大时虽然能提高部分生产能力,但对于比较破碎矿体存在生产安全隐患,如采取顶板支护措施,将使得生产成本大幅度提高,且支护结构的装拆工艺复杂,无法保障生产效率。
发明内容
本发明所要解决的技术问题是提供一种开采环境安全可靠,矿石回收率和生产率高,损失贫化得到有效控制,特别适用于急倾斜中厚以上、品位较高、矿石不稳固的金属矿床回采的采矿环境再造分层分条中深孔落矿采矿法。
为了解决上述技术问题,本发明提供的采矿环境再造分层分条中深孔落矿采矿法,先将急倾斜中厚以上不稳固富矿体划分阶段,阶段内划分数个小分层,分层内划分若干条形矿柱,以条形矿柱为回采单元,分两个循环进行开采;在第一循环各条形矿柱内开凿凿岩道,条形矿柱末端设置通风天井,将通风天井扩展形成切割槽,在凿岩道内钻凿上向扇形中深炮孔,以切割槽为初始自由面,采取后退式侧向崩矿的方式回采矿石,通风完毕后,采用遥控铲运机装矿运至阶段矿石溜井,矿石经溜井下放至阶段运输平巷后由无轨设备运至地表选厂;充填时,高标号充填料充填至各条形采空区,形成高强度人工矿柱;分层内条形矿柱采取隔一采一的协调有序回采方式;第二循环内各条形矿柱回采工艺与第一循环相同,不同的是在充填工艺时,先在各条形采空区底部充填一定厚度的高标号充填料,剩余空间采取低标号充填料充填。
先将急倾斜中厚以上不稳固富矿体划分阶段,阶段内划分3个10m厚的分层,分层内划分若干条形矿柱,所述的条形矿柱宽6m,高10m,长度据矿体客观实际而定,以所述的条形矿柱为基本回采单元,分两个循环进行开采;在第一循环条形矿柱内采用气腿式凿岩机机开凿凿岩道,所述的条形矿柱末端设置通风天井,将所述的通风天井扩展形成切割槽,在所述的凿岩道内钻凿上向扇形中深炮孔,所述的炮孔直径为110mm,排距1.8m,以所述的切割槽为初始自由面,每次爆破1~3排所述的炮孔,依次采取后退式侧向崩矿的方式回采矿石,通风完毕后,崩落矿石采用1.5m3小型遥控铲运机装矿经凿岩道、出矿进路和分层运输道运至矿石溜井,所述的崩落矿石经所述的矿石溜井下放至阶段运输平巷,由无轨设备运至地表选厂,分层内所述的条形矿柱采取隔一采一的协调有序回采方式;充填时,高标号充填料经回风充填井、通风充填联络道、通风充填道充填至各条形采空区,形成高强度人工矿柱;第二循环内各所述的条形矿柱回采工艺与第一循环相同,不同的是在充填时,先在各条形采空区充填3m厚度的所述的高标号充填料,剩余7m高度的空间采取低标号充填料充填;经第一循环和第二循环后,高标号充填体形成了新的开采环境结构,低标号充填体强化了人工矿柱的承载能力。
第一循环高配比胶结充填料与第二循环各个采空区底部高配比胶结充填料一起形成了包含人工矿柱和下一分层人工顶板的人工采场结构,实现安全开采新环境的再造。第二循环中部分充填采用了低配比的水泥砂浆充填料,不但降低了充填成本,而且将人工矿柱二向受力状态转变为三向受力状态,改善了人工矿柱受力条件,强化了采场结构的承载能力。应用该采矿方法使得开采环境更加安全可靠,降低了开采成本,并使矿石回收率和生产率大幅提高,贫化损失得到了有效控制。
采用遥控铲运机出矿,避免了工作人员直接暴露在隐患环境中,提高了出矿能力,促进安全生产。
如上盘围岩不稳固时,可在矿体内预先用浅孔落矿法回采一个小分层,用混凝土充填,形成阶段人工顶板,然后在人工顶板下进行分层、条形矿柱划分与回采工艺,后续工艺过程同前所述。
其具体的步骤如下:
1、将矿体划分为阶段,阶段内划分分层,分层内划分若干条形矿柱,分两个循环进行回采;
2、第一循环条形矿柱内开凿凿岩道、切割通风天井,形成切割槽;
3、将第一循环各个条形矿柱进行隔一采一,崩落矿石由遥控铲运机装运至阶段溜井;
4、对第一循环采空区进行较高配比的水泥砂浆胶结充填,形成高强度人工矿柱;
5、将第二循环条形矿柱进行隔一采一地回采,崩落矿石由遥控铲运机装运至阶段溜井;
6、在第二循环形成的采空区底部先进行小部分高配比胶结充填,形成下一分层人工顶板;
7、对第二循环剩余采空区空间进行低配比的水泥砂浆充填,强化人工矿柱的承载能力;
8、回采工作转至下一分层。
采用本发明,将阶段分成数个小分层,分层内划分若干条形矿柱,实行两个循环回采,第一循环隔一采一后形成高强度充填体,第二循环隔一采一后在采空区底部形成一定厚度的高强度充填体,两个回采循环后的高强度充填体构成了一个安全开采环境,提高了矿石的回收率,降低了矿石贫化率。部分采空区进行低强度充填,降低了开采成本。
附图说明
图1是本发明第一循环开采工艺流程示意图;
图2是沿图1中A-A线剖面图;
图3是沿图1中B-B线剖面图;
图4是本发明第二循环开采工艺流程示意图;
图5是沿图1中D-D线剖面图;
图6是沿图1中E-E线剖面图。
图中:
1-矿石溜井,2-分层运输道,3-出矿进路,4-凿岩道,5-切割通风天井,6-切割槽,7-通风充填道,8-通风充填联络道,9-回风充填井,10-条形矿柱,11-矿块边界,12-高标号充填料,13-低高标号充填料,14-炮孔,15-崩落矿石。
具体实施方式
下面结合附图和具体实施方式对本发明作进一步说明。
参见图1、图2、图3、图4、图5和图6,先将急倾斜中厚以上不稳固富矿体划分阶段,阶段内划分3个小分层,分层内划分若干条形矿柱10,条形矿柱10宽6m,高10m,长度据矿体客观实际而定,以条形矿柱10为回采单元,分两个循环进行开采;在第一循环各条形矿柱10内采用气腿式凿岩机机开凿规格为2.5m×2.5m的凿岩道4,条形矿柱10的末端设置规格为2.0m×2.0m的通风天井5,将通风天井5扩展形成6.0m×10.0m×2.0m的切割槽6,在凿岩道4内采用CS-100高气压环形潜孔凿岩钻机钻凿上向扇形中深炮孔14,炮孔14直径为110mm,排距1.8m,以切割槽6为初始自由面,每次爆破1~3排炮孔14,依次采取后退式侧向崩矿的方式回采矿石,通风完毕后,崩落矿石15采用1.5m3小型遥控铲运机装矿经凿岩道4、出矿进路3和分层运输道2运至阶段矿石溜井1,矿石经溜井1下放至阶段运输平巷,由无轨设备运至地表选厂。分层内条形矿柱10采取隔一采一的协调有序回采方式。充填时,高标号充填料12经回风充填井9、通风充填联络道8、通风充填道7充填至各条形采空区,形成高强度人工矿柱;第二循环内各条形矿柱10回采工艺与第一循环相同,不同的是在充填时,先在各条形采空区充填3m厚度的高标号充填料12,剩余7m高度的空间采取低标号充填料13充填。经第一循环和第二循环后,高标号充填体形成了新的开采环境结构,低标号充填体强化了人工矿柱的承载能力。
回风充填井9、通风充填联络道8、通风充填道7底板高于本分层底板标高10m,断面规格为2.0m×2.0m,为提高接顶质量,充填至最后环节时采取加压注浆、膨胀济等技术措施强化接顶。爆破后的矿石,通过平底结构受矿,利用遥控铲运机装矿,运至阶段溜井。避免了工人直接暴露在破碎矿体下,作业安全,采场生产能力和劳动生产率高。
本发明在国内一个地下矿山得到了实际应用,该矿山为急倾斜厚大矿体,围岩稳固,矿体不稳固、节理裂隙极度发育,属于碎裂结构资源,应用本专利方法,构建了安全性高的开采环境结构,提高了劳动生产率和资源回收率,降低矿石贫化率,收到了很好的经济效益。

Claims (2)

1.一种采矿环境再造分层分条中深孔落矿采矿法,其特征是:先将急倾斜中厚以上不稳固富矿体划分阶段,阶段内划分数个小分层,分层内划分若干条形矿柱,以条形矿柱为回采单元,分两个循环进行开采;在第一循环各条形矿柱内开凿凿岩道,条形矿柱末端设置通风天井,将通风天井扩展形成切割槽,在凿岩道内钻凿上向扇形中深炮孔,以切割槽为初始自由面,采取后退式侧向崩矿的方式回采矿石,通风完毕后,采用遥控铲运机装矿运至阶段矿石溜井,矿石经溜井下放至阶段运输平巷后由无轨设备运至地表选厂;充填时,高标号充填料充填至各条形采空区,形成高强度人工矿柱;分层内条形矿柱采取隔一采一的协调有序回采方式;第二循环内各条形矿柱回采工艺与第一循环相同,不同的是在充填工艺时,先在各条形采空区底部充填一定厚度的高标号充填料,剩余空间采取低标号充填料充填。
2.根据权利要求1所述的采矿环境再造分层分条中深孔落矿采矿法,其特征是:先将急倾斜中厚以上不稳固富矿体划分阶段,阶段内划分3个10m厚的分层,分层内划分若干条形矿柱(10),所述的条形矿柱(10)宽6m,高10m,长度据矿体客观实际而定,以所述的条形矿柱(10)为基本回采单元,分两个循环进行开采;在第一循环条形矿柱(10)内采用气腿式凿岩机机开凿凿岩道(4),所述的条形矿柱(10)末端设置通风天井(5),将所述的通风天井(5)扩展形成切割槽(6),在所述的凿岩道(4)内钻凿上向扇形中深炮孔(14),所述的炮孔(14)直径为110mm,排距1.8m,以所述的切割槽(6)为初始自由面,每次爆破1~3排所述的炮孔(14),依次采取后退式侧向崩矿的方式回采矿石,通风完毕后,崩落矿石(15)采用1.5m3小型遥控铲运机装矿经凿岩道(4)、出矿进路(3)和分层运输道(2)运至矿石溜井(1),所述的崩落矿石(15)经所述的矿石溜井(1)下放至阶段运输平巷,由无轨设备运至地表选厂,分层内所述的条形矿柱(10)采取隔一采一的协调有序回采方式;充填时,高标号充填料(12)经回风充填井(9)、通风充填联络道(8)、通风充填道(7)充填至各条形采空区,形成高强度人工矿柱;第二循环内各所述的条形矿柱(10)回采工艺与第一循环相同,不同的是在充填时,先在各条形采空区充填3m厚度的所述的高标号充填料(12),剩余7m高度的空间采取低标号充填料(13)充填;经第一循环和第二循环后,高标号充填体形成了新的开采环境结构,低标号充填体强化了人工矿柱的承载能力。
CN2010102215476A 2010-07-08 2010-07-08 采矿环境再造分层分条中深孔落矿采矿法 Expired - Fee Related CN101871347B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2010102215476A CN101871347B (zh) 2010-07-08 2010-07-08 采矿环境再造分层分条中深孔落矿采矿法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2010102215476A CN101871347B (zh) 2010-07-08 2010-07-08 采矿环境再造分层分条中深孔落矿采矿法

Publications (2)

Publication Number Publication Date
CN101871347A true CN101871347A (zh) 2010-10-27
CN101871347B CN101871347B (zh) 2011-12-14

Family

ID=42996414

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2010102215476A Expired - Fee Related CN101871347B (zh) 2010-07-08 2010-07-08 采矿环境再造分层分条中深孔落矿采矿法

Country Status (1)

Country Link
CN (1) CN101871347B (zh)

Cited By (23)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102155228A (zh) * 2011-02-21 2011-08-17 中南大学 全分段预裂挤压一次爆破采矿法
CN102226396A (zh) * 2011-05-19 2011-10-26 中南大学 非爆破开挖再造人工群柱深孔崩矿嗣后充填采矿法
CN102337892A (zh) * 2011-08-25 2012-02-01 长沙矿山研究院 一种上向进路充填法
CN102392641A (zh) * 2011-08-02 2012-03-28 中钢矿业开发有限公司 一种点柱式全矿床不分中段上向高分层连续推进充填采矿方法
CN102619513A (zh) * 2012-03-26 2012-08-01 中南大学 同在原岩中布置底部出矿结构的房柱式中深孔充填采矿法
CN102808621A (zh) * 2011-06-03 2012-12-05 中国华冶科工集团有限公司 急倾斜厚矿体的爆破方法
CN102926776A (zh) * 2012-11-17 2013-02-13 山东黄金矿业(莱州)有限公司三山岛金矿 下向短锚索连续、多层预支护方法
CN103114854A (zh) * 2013-02-18 2013-05-22 中南大学 一种再造人工间柱回采矿柱的方法
CN103206215A (zh) * 2013-04-11 2013-07-17 中南大学 一种预控顶上向进路充填采矿法
CN103527197A (zh) * 2013-10-28 2014-01-22 中国矿业大学 一种特厚煤层固体胶结充填巷式开采方法
CN103615250A (zh) * 2013-12-09 2014-03-05 中南大学 分条间柱全空场开采嗣后充填协同采矿法
CN104153782A (zh) * 2014-07-29 2014-11-19 长沙矿山研究院有限责任公司 连续崩落采矿方法
CN104594903A (zh) * 2014-11-19 2015-05-06 攀钢集团工程技术有限公司 用于全段高组合凿岩爆破的落矿方法
CN104863592A (zh) * 2015-06-18 2015-08-26 长沙矿山研究院有限责任公司 一种大结构分段凿岩阶段出矿嗣后充填采矿法
CN106884658A (zh) * 2017-03-09 2017-06-23 昆明理工大学 一种采场人工底部结构构筑方法
CN107035371A (zh) * 2017-05-15 2017-08-11 赵丽华 巨厚钾盐矿床竖向深槽底卸式开采方法
CN107130962A (zh) * 2017-05-23 2017-09-05 西北矿冶研究院 一种用于厚大矿体的分段崩矿嗣后胶结充填采矿方法
CN107237635A (zh) * 2017-07-06 2017-10-10 中国煤炭科工集团太原研究院有限公司 一种一次采全厚的特厚固体钾盐矿开采方法
CN107339104A (zh) * 2017-08-03 2017-11-10 长沙矿山研究院有限责任公司 保安隔离矿柱回收方法
CN107939399A (zh) * 2017-11-25 2018-04-20 彝良驰宏矿业有限公司 一种多中段同时开采模式下水平矿柱回收方法及进路结构
CN109236295A (zh) * 2018-11-14 2019-01-18 中南大学 一种适用于深部厚大矿床的三步骤回采方法
CN109469485A (zh) * 2019-01-17 2019-03-15 福州大学 上向凹凸无筋镶嵌与中深孔崩矿两步骤协同充填采矿法
CN114165235A (zh) * 2021-11-23 2022-03-11 湖南柿竹园有色金属有限责任公司 一种大直径深孔连续装药侧向崩矿采矿方法

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1162690A (zh) * 1996-04-12 1997-10-22 崔正洙 地下矿山采矿新工艺
CN1373286A (zh) * 2002-03-05 2002-10-09 殷惠钧 切割落矿干式充填人工矿柱采矿方法
US6474745B2 (en) * 2000-06-26 2002-11-05 Cutting Edge Technology Pty Ltd. Method of mining
CN1423032A (zh) * 2001-12-03 2003-06-11 中南大学 地下金属矿山多层矿体的采矿方法
US6688702B1 (en) * 2002-12-16 2004-02-10 Grigori A. Abramov Borehole mining method
CN1260461C (zh) * 2003-08-08 2006-06-21 中南大学 阶梯式分段挤压崩矿跟随充填连续采矿法

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1162690A (zh) * 1996-04-12 1997-10-22 崔正洙 地下矿山采矿新工艺
US6474745B2 (en) * 2000-06-26 2002-11-05 Cutting Edge Technology Pty Ltd. Method of mining
CN1423032A (zh) * 2001-12-03 2003-06-11 中南大学 地下金属矿山多层矿体的采矿方法
CN1373286A (zh) * 2002-03-05 2002-10-09 殷惠钧 切割落矿干式充填人工矿柱采矿方法
US6688702B1 (en) * 2002-12-16 2004-02-10 Grigori A. Abramov Borehole mining method
CN1260461C (zh) * 2003-08-08 2006-06-21 中南大学 阶梯式分段挤压崩矿跟随充填连续采矿法

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
《中国矿业》 20070531 张世超等 高分段中深孔崩矿顶板诱导崩落连续采矿法在铜坑矿的应用 第16卷, 第5期 2 *
《湖南科技大学学报(自然科学版)》 20080930 周科平等 基于开采环境再造深孔诱导崩矿方案优化研究 第23卷, 第3期 2 *

Cited By (33)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102155228A (zh) * 2011-02-21 2011-08-17 中南大学 全分段预裂挤压一次爆破采矿法
CN102226396A (zh) * 2011-05-19 2011-10-26 中南大学 非爆破开挖再造人工群柱深孔崩矿嗣后充填采矿法
CN102808621A (zh) * 2011-06-03 2012-12-05 中国华冶科工集团有限公司 急倾斜厚矿体的爆破方法
CN102808621B (zh) * 2011-06-03 2014-11-12 中国华冶科工集团有限公司 急倾斜厚矿体的爆破方法
CN102392641B (zh) * 2011-08-02 2013-09-11 中钢矿业开发有限公司 一种点柱式全矿床不分中段上向高分层连续推进充填采矿方法
CN102392641A (zh) * 2011-08-02 2012-03-28 中钢矿业开发有限公司 一种点柱式全矿床不分中段上向高分层连续推进充填采矿方法
CN102337892B (zh) * 2011-08-25 2014-06-25 长沙矿山研究院 一种上向进路充填法
CN102337892A (zh) * 2011-08-25 2012-02-01 长沙矿山研究院 一种上向进路充填法
CN102619513A (zh) * 2012-03-26 2012-08-01 中南大学 同在原岩中布置底部出矿结构的房柱式中深孔充填采矿法
CN102619513B (zh) * 2012-03-26 2013-12-25 中南大学 同在原岩中布置底部出矿结构的房柱式中深孔充填采矿法
CN102926776A (zh) * 2012-11-17 2013-02-13 山东黄金矿业(莱州)有限公司三山岛金矿 下向短锚索连续、多层预支护方法
CN102926776B (zh) * 2012-11-17 2014-10-08 山东黄金矿业(莱州)有限公司三山岛金矿 下向短锚索连续、多层预支护方法
CN103114854A (zh) * 2013-02-18 2013-05-22 中南大学 一种再造人工间柱回采矿柱的方法
CN103206215A (zh) * 2013-04-11 2013-07-17 中南大学 一种预控顶上向进路充填采矿法
CN103206215B (zh) * 2013-04-11 2015-03-11 中南大学 一种预控顶上向进路充填采矿法
CN103527197A (zh) * 2013-10-28 2014-01-22 中国矿业大学 一种特厚煤层固体胶结充填巷式开采方法
CN103615250A (zh) * 2013-12-09 2014-03-05 中南大学 分条间柱全空场开采嗣后充填协同采矿法
CN104153782A (zh) * 2014-07-29 2014-11-19 长沙矿山研究院有限责任公司 连续崩落采矿方法
CN104153782B (zh) * 2014-07-29 2016-03-23 长沙矿山研究院有限责任公司 连续崩落采矿方法
CN104594903A (zh) * 2014-11-19 2015-05-06 攀钢集团工程技术有限公司 用于全段高组合凿岩爆破的落矿方法
CN104863592A (zh) * 2015-06-18 2015-08-26 长沙矿山研究院有限责任公司 一种大结构分段凿岩阶段出矿嗣后充填采矿法
CN106884658A (zh) * 2017-03-09 2017-06-23 昆明理工大学 一种采场人工底部结构构筑方法
CN106884658B (zh) * 2017-03-09 2018-11-27 昆明理工大学 一种采场人工底部结构构筑方法
CN107035371B (zh) * 2017-05-15 2018-09-14 赵丽华 巨厚钾盐矿床竖向深槽底卸式开采方法
CN107035371A (zh) * 2017-05-15 2017-08-11 赵丽华 巨厚钾盐矿床竖向深槽底卸式开采方法
CN107130962A (zh) * 2017-05-23 2017-09-05 西北矿冶研究院 一种用于厚大矿体的分段崩矿嗣后胶结充填采矿方法
CN107237635A (zh) * 2017-07-06 2017-10-10 中国煤炭科工集团太原研究院有限公司 一种一次采全厚的特厚固体钾盐矿开采方法
CN107339104A (zh) * 2017-08-03 2017-11-10 长沙矿山研究院有限责任公司 保安隔离矿柱回收方法
CN107339104B (zh) * 2017-08-03 2019-11-19 长沙矿山研究院有限责任公司 保安隔离矿柱回收方法
CN107939399A (zh) * 2017-11-25 2018-04-20 彝良驰宏矿业有限公司 一种多中段同时开采模式下水平矿柱回收方法及进路结构
CN109236295A (zh) * 2018-11-14 2019-01-18 中南大学 一种适用于深部厚大矿床的三步骤回采方法
CN109469485A (zh) * 2019-01-17 2019-03-15 福州大学 上向凹凸无筋镶嵌与中深孔崩矿两步骤协同充填采矿法
CN114165235A (zh) * 2021-11-23 2022-03-11 湖南柿竹园有色金属有限责任公司 一种大直径深孔连续装药侧向崩矿采矿方法

Also Published As

Publication number Publication date
CN101871347B (zh) 2011-12-14

Similar Documents

Publication Publication Date Title
CN101871347B (zh) 采矿环境再造分层分条中深孔落矿采矿法
CN101105129B (zh) 采矿环境再造连续采矿嗣后充填采矿法
CN108612530B (zh) 一种上盘围岩破碎倾斜中厚矿体的采矿方法
CN110259451B (zh) 一种缓倾斜中厚矿体预控顶高效采矿方法
CN104895566B (zh) 一种残矿回收采矿法
CN106761912B (zh) 一种适合于不稳定岩层的高效上向进路分层充填采矿方法
CN107829742B (zh) 一种崩落-充填-空场-崩落采矿方法
CN110331978B (zh) 一种环境再造分段中深孔嗣后充填采矿法
CN111828007B (zh) 一种地下矿山采空区遗留间柱的回采方法
CN101858217A (zh) 房柱变换式盘区上向分层充填采矿法
CN108868771A (zh) 一种水平中深孔回采倾斜中厚矿体的采矿方法
CN109630115B (zh) 用于缓倾斜中厚矿体的分段空场嗣后充填采矿法
CN105909247A (zh) 无底柱分段胶结充填采矿方法
CN105626071A (zh) 一种缓倾斜薄矿体采矿方法
CN210134930U (zh) 一种适用于缓倾斜破碎矿床开采的分区预控顶结构
CN105019902A (zh) 一种脉内斜巷上向分层充填采矿法
CN111706328B (zh) 一种用于充填法处理采空区遗留间柱的开采方法
CN101368482A (zh) 缓倾斜矿体全面采矿法的新工艺
CN109723441A (zh) 控制地压房柱两步骤机械化协同高分段无固废开采工艺
CN110219650B (zh) 一种环境再造阶段深孔嗣后充填采矿法
CN106593447A (zh) 一种地下采矿缓倾斜中厚矿体采矿方法
CN109026005A (zh) 一种综合机械化落矿分层崩落采矿方法
CN112727463A (zh) 一种软弱岩层条件下急倾斜薄矿脉的机械化充填采矿方法
CN115559744A (zh) 一种适于倾斜、急倾斜薄矿体开采的底部结构布置方式
CN115075820A (zh) 一种无切割井急倾斜薄矿体开采方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
EE01 Entry into force of recordation of patent licensing contract

Application publication date: 20101027

Assignee: HUNAN ANHUA XIANG AN TUNGSTEN INDUSTRY Co.,Ltd.

Assignor: Central South University

Contract record no.: 2012430000214

Denomination of invention: Mining environment reconstruction layering and striping medium-length hole ore removal mining method

Granted publication date: 20111214

License type: Exclusive License

Record date: 20120831

CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20111214