CN102619513A - 同在原岩中布置底部出矿结构的房柱式中深孔充填采矿法 - Google Patents

同在原岩中布置底部出矿结构的房柱式中深孔充填采矿法 Download PDF

Info

Publication number
CN102619513A
CN102619513A CN2012100827797A CN201210082779A CN102619513A CN 102619513 A CN102619513 A CN 102619513A CN 2012100827797 A CN2012100827797 A CN 2012100827797A CN 201210082779 A CN201210082779 A CN 201210082779A CN 102619513 A CN102619513 A CN 102619513A
Authority
CN
China
Prior art keywords
ore
pillars
house
filling
pillar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2012100827797A
Other languages
English (en)
Other versions
CN102619513B (zh
Inventor
赵国彦
李夕兵
郭子源
董金奎
范作鹏
刘志祥
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Central South University
Original Assignee
Central South University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Central South University filed Critical Central South University
Priority to CN 201210082779 priority Critical patent/CN102619513B/zh
Publication of CN102619513A publication Critical patent/CN102619513A/zh
Application granted granted Critical
Publication of CN102619513B publication Critical patent/CN102619513B/zh
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Earth Drilling (AREA)

Abstract

本发明公开了一种同在原岩中布置底部出矿结构的房柱式中深孔充填采矿法,将矿体沿走向划分为间隔布置的矿房和矿柱,多个房柱采场构成一个盘区;采用脉外无轨采准系统;盘区房柱回采顺序是先采矿房,后采矿柱;矿房回采时从第二分段开始后退式逐排回采;矿房出矿后采空区先用高灰砂比水泥尾砂充填一分段,然后用低灰砂比水泥尾砂充填并接顶;矿柱回采时从第一分段开始,用矿房回采相同方法回采矿柱;矿柱出矿后采空区用高灰砂比水泥尾砂充填一分段,然后用素尾砂充填并接顶;待整个矿块回采结束后,用进路法进行回收;本发明具有采场生产能力大、采矿工效高、回收率高、作业安全、生产成本低等显著优点。

Description

同在原岩中布置底部出矿结构的房柱式中深孔充填采矿法
技术领域
本发明涉及一种分段凿岩阶段出矿嗣后充填的复合采矿法,特别是涉及一种同在原岩中布置底部出矿结构的房柱式中深孔充填采矿法。
技术背景
中深孔分段凿岩阶段出矿嗣后充填采矿法是目前常用的一种高效、回采工艺简单、作业安全性好的采矿方法,但该方法仅适应于回采矿房。若矿房矿柱均采用该矿法,则存在着出矿底部结构难以形成,需要在充填体内预先构筑混凝土假底假巷,导致作业不安全,效率低,成本高等问题。
对于厚大矿体的矿柱回采,多数矿山采用效率较低的上向分层充填采矿法或上向进路采矿法。由于矿柱受到矿房回采时中深孔爆破的损伤与切割影响,岩体的稳固性大幅下降,矿柱回采条件极度恶化,长条状矿柱处于二侧充填体包围,采用自下而上的开采顺序,当矿柱底部揭露后,矿柱完全依赖二侧充填体粘结力、岩层自身拉应力和上下盘岩层悬臂梁的共同作用得以支承,当矿柱稳固性较差时,上部矿柱有可能整体下沉或大面积塌落,造成重大安全事故。另外,采用上向分层充填采矿法或进路法开采,其回采工艺复杂,工人施工劳动强度大,劳动组织复杂,采场生产能力小,开采成本高,且贫损率较高。
发明内容
本发明要解决的技术问题是提供一种安全性好、机械化程度高、回采工艺简单、劳动强度低、效率高、生产能力大的同在原岩中布置底部出矿结构的房柱式中深孔充填采矿法。
为了解决上述技术问题,本发明提供的同在原岩中布置底部出矿结构的房柱式中深孔充填采矿法,其步骤如下:
①、将矿体沿走向划分为间隔布置的矿房和矿柱,6~10个房柱采场构成一个盘区,中段高40~120m,分段高8~15m,矿房宽8~12m,矿柱宽10~15m,顶柱高8~10m;
②、采用脉外无轨采准系统,由阶段运输巷道、脉外分段平巷、斜坡道、出矿联络道、凿岩联络道和溜矿井构成,分段凿岩巷布置在房柱各分段底部中央;
③、盘区房柱回采顺序是先采矿房,后采矿柱,盘区房柱采充结束后再采顶柱,房柱内各分段自上而下同时回采,上分段超前下分段2~3m;
④、矿房回采时预留第一分段不采,从第二分段开始用中深孔钻机或凿岩台车打眼,用微差爆破方法从矿房上盘一端后退式逐排爆破至整个矿房;铲运机以位于同高度的矿柱凿岩巷作为出矿巷,通过出矿进路,将矿房崩落矿石铲出;矿房出矿后采空区先用1∶4~1∶6的水泥尾砂充填,充填高度8~15m,然后用1∶8~1∶15的水泥尾砂充填并接顶;
⑤、矿柱回采时从第一分段开始用矿房回采相同的方法采完整个矿柱;铲运机以矿房预留的第一分段凿岩巷作为出矿巷,通过出矿进路,将矿柱崩落矿石铲出;矿柱出矿后采空区先用1∶4~1∶6的水泥尾砂充填8~10m,然后用素尾砂充填并接顶;
⑥、房柱开采形成的交错连接的顶柱结构,由于有高配比水泥尾砂胶结充填层保护,待整个矿块回采结束后,再用进路法回收。
所述的步骤①中所述的间隔布置的矿房和矿柱,以中段运输巷为起点,将阶段内房柱垂高上划分为分段;每分段垂直矿体走向布置分段凿岩巷,在房柱中靠矿体上盘位置分别布置切割天井,以切割天井为自由面,用中深孔凿岩机或凿岩台车打眼爆破形成切割槽,以切割槽为自由空间,从房柱上盘一端后退式自上而下分段回采,扇形中深孔分排逐次爆破并用电动或柴油铲运机铲出部分矿石,提供下次爆破自由空间,直至房柱回采结束。
所述的步骤②中房柱底部出矿结构利用房柱内的分段凿岩巷,沿房柱分段凿岩巷每隔8~10m以60°倾角布置出矿进路;受矿堑沟左右二翼的出矿进路交错布置;矿房出矿底部结构布置在矿柱中,以矿柱的第二分段凿岩巷为出矿巷;矿柱出矿底部结构通过矿房预留的第一分段凿岩巷作为出矿巷。
所述的步骤④中矿房预留的第一分段在下一中段回采时采出;矿房矿柱最后一分段回采时减少炮孔长度,形成2~3m的顶柱,出矿完后用1∶4或1∶6水泥尾矿充填,充填体强度3~4MPa;顶柱或V形堑沟用进路法回收。
采用上述技术方案的同在原岩中布置底部出矿结构的房柱式中深孔充填采矿法,其有益效果是:
①安全性增高
本发明针对厚大较稳固型金属矿床,通过实现人员在巷道内作业,避免人员暴露在空场内,大幅度提高了作业安全性,从而有效地保证了矿体开采安全。
②采矿效率增大
本发明可实现多个矿房或矿柱同步回采,可充分利用无轨设备作业,并实现多个采场凿岩、出矿、充填平行作业,生产相对集中,避免了单个房柱开采人员分散、设备利用率低、劳动组织烦琐等不足,矿块开采效率增高。
③出矿结构简单
本发明通过改变房柱回采高度,矿房矿柱底部出矿结构均布置在原岩中,即矿房出矿底部结构布置在矿柱中,矿柱出矿底部结构布置在矿房中,避免了房柱底部出矿结构不可能同在原岩中的矛盾,省去构造人工假巷等工序,出矿灵活、劳动强度低、出矿效率高。
④资源回收率高
形成交错连接的顶柱结构,采用高配比水泥尾砂胶结充填,待整个矿块回采结束后,用进路法进行回收,实现顶底柱回采;另外,因为采用分段凿岩阶段出矿嗣后充填采矿法,避免了用分层充填法开采一次采高低,矿石易混入充填体中,矿石贫化损失大等问题。
其主要技术经济指标为:
①采场生产能力:605t/d;
②采矿工效:127.3t/工班;
③采矿损失率:7.0%;
④采矿贫化率:6.5%;
⑤采切比:10.99标准m/kt;
⑥采矿直接成本:80.29元/t。
附图说明
图1为本发明采矿方法结构示意图。
图2为图1的B-B剖面图。
图3为图1的C-C剖面图。
图4为图1的D-D剖面图。
具体实施方式
本发明提供的同在原岩中布置底部出矿结构的房柱式中深孔充填采矿法,其步骤如下:
①、将矿体沿走向划分为间隔布置的矿房和矿柱,6~10个房柱采场构成一个盘区,中段高40~120m,分段高8~15m,矿房宽8~12m,矿柱宽10~15m,顶柱高8~10m;
②、采用下盘脉外无轨采准系统,其技术要点是:平行矿体下盘边界布置分段平巷14,各分段平巷通过斜坡道20与阶段运输巷16相通,凿岩联络道13联接分段凿岩巷道12与分段平巷14,出矿联络道17联接受矿横巷19和阶段运输平巷16,从而构成盘区下盘脉外无轨采准系统;
③、盘区房柱回采顺序是先采矿房,后采矿柱,盘区房柱采充结束后再采顶柱,房柱内各分段自上而下同时回采,上分段超前下分段2~3m;
④、矿房回采时预留第一分段不采,从第二分段开始用中深孔钻机或凿岩台车打眼,用微差爆破方法从矿房上盘一端后退式逐排爆破至整个矿房;铲运机以位于同高度的矿柱凿岩巷作为出矿巷,通过出矿进路,将矿房崩落矿石铲出;矿房出矿后采空区先用1∶4~1∶6的水泥尾砂充填,充填高度8~15m,然后用1∶8~1∶15的水泥尾砂充填并接顶;
⑤、矿柱回采时从第一分段开始用矿房回采相同的方法采完整个矿柱;铲运机以矿房预留的第一分段凿岩巷作为出矿巷,通过出矿进路,将矿柱崩落矿石铲出;矿柱出矿后采空区先用1∶4~1∶6的水泥尾砂充填8~10m,然后用素尾砂充填并接顶;
⑥、房柱开采形成的交错连接的顶柱结构,由于有高配比水泥尾砂胶结充填层保护,待整个矿块回采结束后,再用进路法回收。
步骤①中所述的间隔布置的矿房和矿柱,以中段运输巷为起点,将阶段内房柱垂高上划分为分段;每分段垂直矿体走向布置分段凿岩巷,在房柱中靠矿体上盘位置分别布置切割天井,以切割天井为自由面,用中深孔凿岩机或凿岩台车打眼爆破形成切割槽,以切割槽为自由空间,从房柱上盘一端后退式自上而下分段回采,扇形中深孔分排逐次爆破并用电动或柴油铲运机铲出部分矿石,提供下次爆破自由空间,直至房柱回采结束。
步骤②中房柱底部出矿结构利用房柱内的分段凿岩巷,沿房柱分段凿岩巷每隔8~10m以60°倾角布置出矿进路;受矿堑沟左右二翼的出矿进路交错布置;矿房出矿底部结构布置在矿柱中,以矿柱的第二分段凿岩巷为出矿巷;矿柱出矿底部结构通过矿房预留的第一分段凿岩巷作为出矿巷。
步骤④中矿房预留的第一分段在下一中段回采时采出;矿房矿柱最后一分段回采时减少炮孔长度,形成2~3m的顶柱,出矿完后用1∶4或1∶6水泥尾矿充填,充填体强度3~4MPa;顶柱或V形堑沟用进路法回收。
以下结合附图和具体实施例对本发明做进一步详细说明。
山东黄金矿业(莱州)有限公司焦家金矿寺庄矿区主要回采7-2号矿体,矿岩较坚硬,f=10~12,矿体倾角62°。-250m~-190m中段矿体平均水平厚61m,走向长184m,金矿平均品位2.36g/t。
具体实施步骤是:
①、选择-250m~-190m中段矿体采用同在原岩中布置底部出矿结构的房柱式中深孔充填采矿法,沿矿体走向划分间隔布置的矿房和矿柱,矿房宽10m,矿柱宽12.5m,4个矿房4个矿柱构成一个盘区,盘区长90m,中段高60m,分段高10m。
②、采用无轨采准方式,在矿体下盘布置中段运输巷道、脉外分段平巷,用中段斜坡道将各分段平巷联通,分段平巷一侧布置有出矿联络道和脉外集中出矿溜井,如图1、图2、图3和图4所示,图中:1-高灰砂比水泥尾砂,2-素尾砂,3-矿房顶柱,4-低灰砂比水泥尾砂5-矿柱顶柱,6-矿体,7-矿石,8-扇形中深孔,9-矿房回采,10-回风联络道,11-回风平巷,12-分段凿岩巷,13-凿岩联络道,14-分段平巷,15-溜矿井,16-阶段运输巷,17-出矿联络道,18-出矿进路,19-受矿横巷,20-斜坡道,21-泄水井,22-充填隔墙,23-切割回风天井,24-切割槽。
③、从分段平巷中垂直矿体走向掘进凿岩联络道13和分段凿岩巷12。从矿柱第二分段凿岩巷每隔10m向二侧矿房掘进出矿进路18。矿柱回采时,从矿房第一分段凿岩巷沿巷道每隔10m向二侧矿柱掘进出矿进路19。
④、盘区房柱回采顺序是先采矿房I,后采矿柱II,盘区房柱采充结束后再采顶柱。房柱内各分段同时回采,上分段超前下分段2~3m。矿房内第一分段不采,留在下一中段回采时再采。
⑤、矿房矿柱在矿体上盘预先掘进切割上山,以切割上山为自由面,用中深孔拉切割槽。房柱回采时从分段凿岩巷内用凿岩台车或YGZ-90钻机凿扇形中深孔,用毫秒差非电导爆管微差爆破,崩落矿石由铲运机铲出。房柱采完后,采空区先用1∶4~1∶6的水泥尾砂胶结充填,充填高度10m,然后矿房用灰砂比1∶8~1∶15的水泥尾砂胶结充填并接顶,矿柱用素尾砂充填并接顶。充填前作好充填准备,所有房柱与外隔相通的出入口构筑充填隔离墙,然后架设充填管。
⑥、盘区采完后,其顶柱用进路法进行回收。
为确保同在原岩中布置底部出矿结构的房柱式中深孔充填采矿法安全可靠,验证其高效性、低贫损性,在矿体上盘埋设了多种应力位移测试装置,对岩层进行了长期观测,并对盘区采场结构参数进行了必要的调整。

Claims (4)

1.一种同在原岩中布置底部出矿结构的房柱式中深孔充填采矿法,其特征在于:步骤如下:
①、将矿体沿走向划分为间隔布置的矿房和矿柱,6~10个房柱采场构成一个盘区,中段高40~120m,分段高8~15m,矿房宽8~12m,矿柱宽10~15m,顶柱高8~10m;
②、采用脉外无轨采准系统,由阶段运输巷道、脉外分段平巷、斜坡道、出矿联络道、凿岩联络道和溜矿井构成,分段凿岩巷布置在房柱各分段底部中央;
③、盘区房柱回采顺序是先采矿房,后采矿柱,盘区房柱采充结束后再采顶柱,房柱内各分段自上而下同时回采,上分段超前下分段2~3m;
④、矿房回采时预留第一分段不采,从第二分段开始用中深孔钻机或凿岩台车打眼,用微差爆破方法从矿房上盘一端后退式逐排爆破至整个矿房;铲运机以位于同高度的矿柱凿岩巷作为出矿巷,通过出矿进路,将矿房崩落矿石铲出;矿房出矿后采空区先用1∶4~1∶6的水泥尾砂充填,充填高度8~15m,然后用1∶8~1∶15的水泥尾砂充填并接顶;
⑤、矿柱回采时从第一分段开始用矿房回采相同的方法采完整个矿柱;铲运机以矿房预留的第一分段凿岩巷作为出矿巷,通过出矿进路,将矿柱崩落矿石铲出;矿柱出矿后采空区先用1∶4~1∶6的水泥尾砂充填18~20m,然后用素尾砂充填并接顶;
⑥、房柱开采形成的交错连接的顶柱结构,待整个矿块回采结束后,用进路法回收。
2.根据权利要求1所述的同在原岩中布置底部出矿结构的房柱式中深孔充填采矿法,其特征在于:所述的步骤①中所述的间隔布置的矿房和矿柱,以中段运输巷为起点,将阶段内房柱垂高上划分为分段;每分段垂直矿体走向布置分段凿岩巷,在房柱中靠矿体上盘位置分别布置切割天井,以切割天井为自由面,用中深孔凿岩机或凿岩台车打眼爆破形成切割槽,以切割槽为自由空间,从房柱上盘一端后退式自上而下分段回采,扇形中深孔分排逐次爆破并用电动或柴油铲运机铲出部分矿石,提供下次爆破自由空间,直至房柱回采结束。
3.根据权利要求1或2所述的同在原岩中布置底部出矿结构的房柱式中深孔充填采矿法,其特征在于:所述的步骤②中房柱底部出矿结构利用房柱内的分段凿岩巷,沿房柱分段凿岩巷每隔8~10m以60°倾角布置出矿进路;受矿堑沟左右二翼的出矿进路交错布置;矿房出矿底部结构布置在矿柱中,以矿柱的第二分段凿岩巷为出矿巷;矿柱出矿底部结构通过矿房预留的第一分段凿岩巷作为出矿巷。
4.根据权利要求1或2所述的同在原岩中布置底部出矿结构的房柱式中深孔充填采矿法,其特征在于:所述的步骤④中矿房预留的第一分段在下一中段回采时采出;矿房矿柱最后一分段回采时减少炮孔长度,形成2~3m的顶柱,出矿完后用1∶4或1∶6水泥尾矿充填,充填体强度3~4MPa;顶柱或V形堑沟用进路法回收。
CN 201210082779 2012-03-26 2012-03-26 同在原岩中布置底部出矿结构的房柱式中深孔充填采矿法 Expired - Fee Related CN102619513B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201210082779 CN102619513B (zh) 2012-03-26 2012-03-26 同在原岩中布置底部出矿结构的房柱式中深孔充填采矿法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201210082779 CN102619513B (zh) 2012-03-26 2012-03-26 同在原岩中布置底部出矿结构的房柱式中深孔充填采矿法

Publications (2)

Publication Number Publication Date
CN102619513A true CN102619513A (zh) 2012-08-01
CN102619513B CN102619513B (zh) 2013-12-25

Family

ID=46559694

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201210082779 Expired - Fee Related CN102619513B (zh) 2012-03-26 2012-03-26 同在原岩中布置底部出矿结构的房柱式中深孔充填采矿法

Country Status (1)

Country Link
CN (1) CN102619513B (zh)

Cited By (26)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103590832A (zh) * 2013-11-27 2014-02-19 山东盛大矿业有限公司 矿柱预隔离分段条块充填采矿法及适用于该采矿法的矿体
CN103643992A (zh) * 2013-12-10 2014-03-19 中国恩菲工程技术有限公司 采矿充填方法
CN103967493A (zh) * 2014-05-23 2014-08-06 山东黄金矿业(莱州)有限公司三山岛金矿 一种缓倾斜薄矿体矿柱采矿法
RU2558841C1 (ru) * 2014-01-23 2015-08-10 Открытое акционерное общество "Научно-исследовательский и проектный институт обогащения и механической обработки полезных ископаемых "Уралмеханобр" (ОАО "Уралмеханобр") Способ разработки мощных крутопадающих рудных тел
CN104863592A (zh) * 2015-06-18 2015-08-26 长沙矿山研究院有限责任公司 一种大结构分段凿岩阶段出矿嗣后充填采矿法
CN105041314A (zh) * 2015-06-13 2015-11-11 招金矿业股份有限公司大尹格庄金矿 一种深部嗣后回采矿房—分层回采矿柱的联合采矿法
CN105888668A (zh) * 2016-06-15 2016-08-24 山东华联矿业股份有限公司 预控顶上向高分段中深孔嗣后充填采矿方法
CN105927228A (zh) * 2016-05-23 2016-09-07 中国矿业大学(北京) 直立破碎矿体自动沉落式采矿方法
CN105927227A (zh) * 2016-04-21 2016-09-07 西北矿冶研究院 一种底部结构堑沟角度的确定方法
CN106121647A (zh) * 2016-08-04 2016-11-16 西北矿冶研究院 一种分次爆破集中回收滞后矿柱的方法
CN106246182A (zh) * 2016-08-04 2016-12-21 西北矿冶研究院 一种同步形成间隔矿柱的中深孔房柱法
CN106437838A (zh) * 2016-12-05 2017-02-22 广西大学 底部结构下卡车直接出矿后期放矿充填同步水平深孔留矿法
CN106837332A (zh) * 2017-03-03 2017-06-13 长沙矿山研究院有限责任公司 机械化台阶式房柱采矿法
CN108398067A (zh) * 2018-03-16 2018-08-14 长春黄金研究院有限公司 一种中深孔上向打孔下向装药的孔内微差爆破方法
CN109707441A (zh) * 2018-12-20 2019-05-03 新巴尔虎右旗荣达矿业有限责任公司 一种采空区干式充填矿柱回收方法
CN110792439A (zh) * 2019-12-04 2020-02-14 福建海峡科化富兴建设工程有限公司 阶段矿房采矿法回采后的水平矿柱的崩落方法
CN110905516A (zh) * 2019-11-29 2020-03-24 金川集团股份有限公司 一种下向分层水平进路高分段充填采矿法
CN112031770A (zh) * 2020-09-11 2020-12-04 中钢集团马鞍山矿山研究总院股份有限公司 一种适于厚大矿体多采场同步开采的采矿新方法
CN112502704A (zh) * 2020-11-10 2021-03-16 西北矿冶研究院 一种大结构空场嗣后充填开采方法
CN112879084A (zh) * 2021-01-18 2021-06-01 长沙矿山研究院有限责任公司 一种尾砂井下存储系统形成方法
CN113047835A (zh) * 2021-02-24 2021-06-29 中南大学 集空、崩、充一体的深井厚大矿体采矿方法
CN113202472A (zh) * 2021-05-21 2021-08-03 中煤第七十一工程处有限责任公司 一种地下矿山分段分层分条向上分层采矿法
CN114086959A (zh) * 2021-11-16 2022-02-25 铜陵有色金属集团股份有限公司 一种大直径高颈漏斗底部结构、施工方法及回采方法
CN114109387A (zh) * 2021-11-30 2022-03-01 湖南柿竹园有色金属有限责任公司 一种适应于智能装备作业特点的高效采矿工艺
CN114183142A (zh) * 2021-12-08 2022-03-15 西北矿冶研究院 一种开采倾斜及急倾斜薄矿体的方法
CN117662150A (zh) * 2024-02-01 2024-03-08 矿冶科技集团有限公司 一种深部矿体全生命周期卸荷采矿方法

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101105129A (zh) * 2007-07-16 2008-01-16 中南大学 采矿环境再造连续采矿嗣后充填采矿法
RU2350750C1 (ru) * 2007-11-20 2009-03-27 Государственное образовательное учреждение высшего профессионального образования "Санкт-Петербургский государственный горный институт имени Г.В. Плеханова (технический университет)" Способ разработки крутых рудных тел
CN101858217A (zh) * 2010-05-18 2010-10-13 中南大学 房柱变换式盘区上向分层充填采矿法
CN101871347A (zh) * 2010-07-08 2010-10-27 中南大学 采矿环境再造分层分条中深孔落矿采矿法
CN102003185A (zh) * 2010-11-05 2011-04-06 中蓝连海设计研究院 分段条带回采尾盐干式充填采矿法
RU2010124708A (ru) * 2010-06-16 2011-12-27 Георгий Михайлович Еремин (RU) Способ разработки месторождений полезных ископаемых

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101105129A (zh) * 2007-07-16 2008-01-16 中南大学 采矿环境再造连续采矿嗣后充填采矿法
RU2350750C1 (ru) * 2007-11-20 2009-03-27 Государственное образовательное учреждение высшего профессионального образования "Санкт-Петербургский государственный горный институт имени Г.В. Плеханова (технический университет)" Способ разработки крутых рудных тел
CN101858217A (zh) * 2010-05-18 2010-10-13 中南大学 房柱变换式盘区上向分层充填采矿法
RU2010124708A (ru) * 2010-06-16 2011-12-27 Георгий Михайлович Еремин (RU) Способ разработки месторождений полезных ископаемых
CN101871347A (zh) * 2010-07-08 2010-10-27 中南大学 采矿环境再造分层分条中深孔落矿采矿法
CN102003185A (zh) * 2010-11-05 2011-04-06 中蓝连海设计研究院 分段条带回采尾盐干式充填采矿法

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
韦章能: "安庆铜矿缓倾斜薄矿体采矿工艺研究", 《有色金属(矿山部分)》 *

Cited By (36)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103590832B (zh) * 2013-11-27 2016-05-18 山东盛大矿业有限公司 矿柱预隔离分段条块充填采矿法及适用于该采矿法的矿体
CN103590832A (zh) * 2013-11-27 2014-02-19 山东盛大矿业有限公司 矿柱预隔离分段条块充填采矿法及适用于该采矿法的矿体
CN103643992A (zh) * 2013-12-10 2014-03-19 中国恩菲工程技术有限公司 采矿充填方法
CN103643992B (zh) * 2013-12-10 2016-04-13 中国恩菲工程技术有限公司 采矿充填方法
RU2558841C1 (ru) * 2014-01-23 2015-08-10 Открытое акционерное общество "Научно-исследовательский и проектный институт обогащения и механической обработки полезных ископаемых "Уралмеханобр" (ОАО "Уралмеханобр") Способ разработки мощных крутопадающих рудных тел
CN103967493A (zh) * 2014-05-23 2014-08-06 山东黄金矿业(莱州)有限公司三山岛金矿 一种缓倾斜薄矿体矿柱采矿法
CN103967493B (zh) * 2014-05-23 2015-12-02 山东黄金矿业(莱州)有限公司三山岛金矿 一种缓倾斜薄矿体矿柱采矿法
CN105041314A (zh) * 2015-06-13 2015-11-11 招金矿业股份有限公司大尹格庄金矿 一种深部嗣后回采矿房—分层回采矿柱的联合采矿法
CN104863592A (zh) * 2015-06-18 2015-08-26 长沙矿山研究院有限责任公司 一种大结构分段凿岩阶段出矿嗣后充填采矿法
CN104863592B (zh) * 2015-06-18 2017-03-01 长沙矿山研究院有限责任公司 一种大结构分段凿岩阶段出矿嗣后充填采矿法
CN105927227A (zh) * 2016-04-21 2016-09-07 西北矿冶研究院 一种底部结构堑沟角度的确定方法
CN105927228A (zh) * 2016-05-23 2016-09-07 中国矿业大学(北京) 直立破碎矿体自动沉落式采矿方法
CN105927228B (zh) * 2016-05-23 2018-01-05 中国矿业大学(北京) 直立破碎矿体自动沉落式采矿方法
CN105888668A (zh) * 2016-06-15 2016-08-24 山东华联矿业股份有限公司 预控顶上向高分段中深孔嗣后充填采矿方法
CN106121647A (zh) * 2016-08-04 2016-11-16 西北矿冶研究院 一种分次爆破集中回收滞后矿柱的方法
CN106246182A (zh) * 2016-08-04 2016-12-21 西北矿冶研究院 一种同步形成间隔矿柱的中深孔房柱法
CN106437838A (zh) * 2016-12-05 2017-02-22 广西大学 底部结构下卡车直接出矿后期放矿充填同步水平深孔留矿法
CN106837332A (zh) * 2017-03-03 2017-06-13 长沙矿山研究院有限责任公司 机械化台阶式房柱采矿法
CN108398067A (zh) * 2018-03-16 2018-08-14 长春黄金研究院有限公司 一种中深孔上向打孔下向装药的孔内微差爆破方法
CN109707441A (zh) * 2018-12-20 2019-05-03 新巴尔虎右旗荣达矿业有限责任公司 一种采空区干式充填矿柱回收方法
CN110905516A (zh) * 2019-11-29 2020-03-24 金川集团股份有限公司 一种下向分层水平进路高分段充填采矿法
CN110905516B (zh) * 2019-11-29 2021-05-11 金川集团股份有限公司 一种下向分层水平进路高分段充填采矿法
CN110792439A (zh) * 2019-12-04 2020-02-14 福建海峡科化富兴建设工程有限公司 阶段矿房采矿法回采后的水平矿柱的崩落方法
CN112031770A (zh) * 2020-09-11 2020-12-04 中钢集团马鞍山矿山研究总院股份有限公司 一种适于厚大矿体多采场同步开采的采矿新方法
CN112502704A (zh) * 2020-11-10 2021-03-16 西北矿冶研究院 一种大结构空场嗣后充填开采方法
CN112879084A (zh) * 2021-01-18 2021-06-01 长沙矿山研究院有限责任公司 一种尾砂井下存储系统形成方法
CN113047835B (zh) * 2021-02-24 2022-04-15 中南大学 集空、崩、充一体的深井厚大矿体采矿方法
CN113047835A (zh) * 2021-02-24 2021-06-29 中南大学 集空、崩、充一体的深井厚大矿体采矿方法
CN113202472A (zh) * 2021-05-21 2021-08-03 中煤第七十一工程处有限责任公司 一种地下矿山分段分层分条向上分层采矿法
CN113202472B (zh) * 2021-05-21 2024-01-23 中煤第七十一工程处有限责任公司 一种地下矿山分段分层分条向上分层采矿法
CN114086959A (zh) * 2021-11-16 2022-02-25 铜陵有色金属集团股份有限公司 一种大直径高颈漏斗底部结构、施工方法及回采方法
CN114109387A (zh) * 2021-11-30 2022-03-01 湖南柿竹园有色金属有限责任公司 一种适应于智能装备作业特点的高效采矿工艺
CN114183142A (zh) * 2021-12-08 2022-03-15 西北矿冶研究院 一种开采倾斜及急倾斜薄矿体的方法
CN114183142B (zh) * 2021-12-08 2023-10-13 西北矿冶研究院 一种开采倾斜及急倾斜薄矿体的方法
CN117662150A (zh) * 2024-02-01 2024-03-08 矿冶科技集团有限公司 一种深部矿体全生命周期卸荷采矿方法
CN117662150B (zh) * 2024-02-01 2024-05-14 矿冶科技集团有限公司 一种深部矿体全生命周期卸荷采矿方法

Also Published As

Publication number Publication date
CN102619513B (zh) 2013-12-25

Similar Documents

Publication Publication Date Title
CN102619513B (zh) 同在原岩中布置底部出矿结构的房柱式中深孔充填采矿法
CN101858217B (zh) 房柱变换式盘区上向分层充填采矿法
CN103557002B (zh) 一种盘区机械化集中溜井上向水平分层充填采矿法
CN101105129B (zh) 采矿环境再造连续采矿嗣后充填采矿法
CN108661646B (zh) 一种假顶房柱式留矿嗣后充填采矿法
CN1260461C (zh) 阶梯式分段挤压崩矿跟随充填连续采矿法
CN102678121B (zh) 无盘区中深孔留矿分层控顶嗣后充填采矿法
CN106121643B (zh) 预留护壁矿两步骤嵌套组合充填采矿法
CN103032070A (zh) 一种控界房柱式分段空场嗣后阶段充填采矿法
CN104018836B (zh) 一种有不稳固假顶倾斜中厚矿体的分采方法
CN108612530A (zh) 一种上盘围岩破碎倾斜中厚矿体的采矿方法
CN103437769B (zh) 组合再造结构体中深孔落矿协同锚索支护嗣后充填采矿法
CN102251773B (zh) 适合于极复杂矿体开采的进路式上向水平分层充填采矿法
CN102953733A (zh) 中央脉外房柱式联合横巷两端脉内连续分段充填采矿法
CN102953732A (zh) 房柱式大直径深孔倒台阶状分段侧向崩矿嗣后充填采矿法
CN102168579A (zh) 中厚倾斜破碎矿体脉内采准无间柱连续分段充填法
CN105587318A (zh) 一种缓倾斜平行中厚矿体群连续回采的充填采矿法
CN103628878B (zh) 破碎围岩矿体下向进路分层无分段巷道充填采矿方法
CN110259451A (zh) 一种缓倾斜中厚矿体预控顶高效采矿方法
CN109184694A (zh) 一种上盘预锚分段凿岩阶段空场嗣后充填采矿法
CN1982649A (zh) 一种采矿方法
CN106761756A (zh) 一种用于上向分层全尾砂胶结充填法的采场结构
CN100441831C (zh) 联合支柱支撑顶板、采场分区、阶梯式回采采矿方法
CN101509377A (zh) 急倾斜矿体房柱采矿方法
CN102979526B (zh) 中深孔分段采矿出矿堑沟充填法构筑工艺

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20131225

Termination date: 20210326