CN101852479B - 管道的分段错序安装方法 - Google Patents

管道的分段错序安装方法 Download PDF

Info

Publication number
CN101852479B
CN101852479B CN2009100487581A CN200910048758A CN101852479B CN 101852479 B CN101852479 B CN 101852479B CN 2009100487581 A CN2009100487581 A CN 2009100487581A CN 200910048758 A CN200910048758 A CN 200910048758A CN 101852479 B CN101852479 B CN 101852479B
Authority
CN
China
Prior art keywords
pipeline
place
installation
segmentation
segmental
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN2009100487581A
Other languages
English (en)
Other versions
CN101852479A (zh
Inventor
谢滨
徐晓华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
MCC5 Group Shanghai Corp Ltd
Original Assignee
MCC5 Group Shanghai Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by MCC5 Group Shanghai Corp Ltd filed Critical MCC5 Group Shanghai Corp Ltd
Priority to CN2009100487581A priority Critical patent/CN101852479B/zh
Publication of CN101852479A publication Critical patent/CN101852479A/zh
Application granted granted Critical
Publication of CN101852479B publication Critical patent/CN101852479B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

本发明涉及冶金设备中的管道施工安装领域,具体为一种管道的分段错序安装方法。一种管道的分段错序安装方法,按如下步骤依次进行:管道分段→管道制作→管道预排序→管道支架安装→管道编号并地面就位→管道组对→吊车就位→管道错序安装→精度调整→分段连接,其特征是:管道分段时,在管道变径处和弯头角度较小处分段;根据第一段吊装的管道在空中的稳定性最好和第一段吊装的管道安装后方便水平方向的偏差和竖直方向的高差精度控制的原则确定吊装的先后顺序。本发明的场地占用小、工期利用率高、生产效率高。

Description

管道的分段错序安装方法
技术领域
本发明涉及冶金设备中的管道施工安装领域,具体为一种管道的分段错序安装方法。 
背景技术
在如今的冶金生产厂的建设过程中,工期越来越紧,施工计划制订要非常严谨才能满足工期要求,因此造成建筑结构和安装工期都非常紧张。而在施工过程中却总会出现各种各样的不可预见的因素,从而导致建筑结构工期的拖延,最后工艺管道及设备安装所需要的时间和施工场地都非常紧张,由此造成了很多工程都无法按期交工的尴尬局面。 
发明内容
为了克服现有技术的缺陷,提供一种场地占用小、安装工期短的管道安装方法,本发明公开了一种管道的分段错序安装方法。 
本发明通过如下技术方案达到发明目的: 
一种管道的分段错序安装方法,将管道分成若干段再逐段吊装拼接完成,按如下步骤依次进行:管道分段→管道制作→管道预排序→管道支架安装→管道编号并地面就位→管道组对→吊车就位→管道错序安装→精度调整→分段连接,其特征是: 
管道分段时,在管道变径处和弯头角度较小处分段。 
管道预排序时,在安装处的地面上进行排序,根据第一段吊装的管道在空中的稳定性最好和第一段吊装的管道安装后方便水平方向的偏差和竖直方向的高差精度控制的原则确定吊装的先后顺序。 
管道支架安装时,在管道上安装吊耳,管道的重心落在吊耳连线所构成的范围内。
所述的管道的分段错序安装方法,其特征是:最后安装的管道要求中心线控制误差在-100mm~0mm内。 
本发明的安装方法解决了安装高峰场地紧张、工期紧张的问题,通过分段安装保证安装工作可以见缝插针地进行,通过错序安装保证安装安全可靠并最后确保了工期。本发明的有益效果是场地占用小、工期利用率高、生产效率高。 
附图说明
图1是采用本发明予以吊装的风管的俯视图; 
图2是采用本发明予以吊装的风管的主视图; 
图3是采用本发明予以吊装的风管的分段示意图; 
图4是采用本发明予以吊装的风管中带有两个吊耳的管2的俯视图; 
图5是采用本发明予以吊装的风管中带有两个吊耳的管2的主视图; 
图6是采用本发明予以吊装的风管中在管2上确定第3个吊耳的俯视图; 
图7是采用本发明予以吊装的风管中在管2上确定第3个吊耳的主视图; 
图8是采用本发明予以吊装的风管中确定了3个吊耳的管2的主视图。 
具体实施方式
以下通过具体实施例进一步说明本发明。 
实施例1 
一种管道的分段错序安装方法,现需吊装如图1和图2所示的风管10,其中,a和b分别是风管10中两部分的中心线,其水平偏差为1m,垂直偏差为5m。 
按如下步骤依次进行:管道分段→管道制作→管道预排序→管道支架安装→管道编号并地面就位→管道组对→吊车就位→管道错序安装→精度调整→分段连接。 
先根据在管道变径处和弯头角度较小处分段原则,将风管10如图3所示分成管1、管2、管3和管4这4部分,再根据第一段吊装的管道在空中的稳定性最好并且第一段吊装的管道安装后方便水平方向的偏差和竖直方向的高差的控制原则,以管2为第一段吊装,第2段吊装管3,第3段吊装 管4,最后吊装管1。 
风管在安装之前需在安装处的地面上进行排序,要长时间的占用大面积施工用地,由于场地紧张一般都不能整体就位,可分部进行,只要有空闲场地出现,见缝插针的将相应的短管或弯头倒运到相应的场地,进行顺序组对。 
先确定2个吊耳的位置:按管2两端弯头两个顶点确定风管各部位最高中心线,此线上按整段风管的重心分布确定吊耳21和吊耳22的位置,如图4和图5所示。再计算第3吊耳的位置:根据中心线偏差1米,风管半径为1.2米,计算θ=arctan(1/1.2)=39°48′,如图6和图7所示,从而吊耳23的位置是:吊耳23所在截面半径和吊耳21、吊耳22连线的夹角为39°48′。 
根据计算结果,在管2上依次焊接吊耳21、吊耳22和吊耳23,如图8所示。 
吊装顺序和吊耳位置都确定完毕后,开始逐段吊装并拼接。由于现场环境的限制,导致吊车的工作幅度、起升高度都将变的非常大以及遮挡了吊车司机的视野,所以要求起重指挥员和吊车司机的必须密切配合。 

Claims (2)

1.一种管道的分段错序安装方法,将管道分成若干段再逐段吊装拼接完成,按如下步骤依次进行:管道分段→管道制作→管道预排序→管道支架安装→管道编号并地面就位→管道组对→吊车就位→管道错序安装→精度调整→分段连接,其特征是:
管道分段时,在管道变径处和弯头角度较小处分段;
管道预排序时,在安装处的地面上进行排序,根据第一段吊装的管道在空中的稳定性最好和第一段吊装的管道安装后方便水平方向的偏差和竖直方向的高差精度控制的原则确定吊装的先后顺序;
管道支架安装时,在管道上安装吊耳,管道的重心落在吊耳连线所构成的范围内。
2.如权利要求1所述的管道的分段错序安装方法,其特征是:最后安装的管道要求中心线控制误差在-100mm~0mm内。
CN2009100487581A 2009-04-02 2009-04-02 管道的分段错序安装方法 Active CN101852479B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2009100487581A CN101852479B (zh) 2009-04-02 2009-04-02 管道的分段错序安装方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2009100487581A CN101852479B (zh) 2009-04-02 2009-04-02 管道的分段错序安装方法

Publications (2)

Publication Number Publication Date
CN101852479A CN101852479A (zh) 2010-10-06
CN101852479B true CN101852479B (zh) 2012-07-04

Family

ID=42804083

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2009100487581A Active CN101852479B (zh) 2009-04-02 2009-04-02 管道的分段错序安装方法

Country Status (1)

Country Link
CN (1) CN101852479B (zh)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103692195A (zh) * 2013-12-20 2014-04-02 中国五冶集团有限公司 一种管道安装方法
CN108453132B (zh) * 2017-12-28 2020-10-02 上海二十冶建设有限公司 一种超薄带生产线热箱模块化安装方法
CN110735970A (zh) * 2019-09-12 2020-01-31 中国二冶集团有限公司 长输管线多根连续冷弯管安装施工方法

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5429330A (en) * 1994-02-23 1995-07-04 Refrigeration Specialists, Inc. Duct system and method for assembling same
CN101397596A (zh) * 2008-09-12 2009-04-01 北京首钢建设集团有限公司 高炉热风围管整体安装施工方法

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5429330A (en) * 1994-02-23 1995-07-04 Refrigeration Specialists, Inc. Duct system and method for assembling same
CN101397596A (zh) * 2008-09-12 2009-04-01 北京首钢建设集团有限公司 高炉热风围管整体安装施工方法

Also Published As

Publication number Publication date
CN101852479A (zh) 2010-10-06

Similar Documents

Publication Publication Date Title
CN101852479B (zh) 管道的分段错序安装方法
CN107588233A (zh) 一种超大口径压力钢管在斜井下弯段的安装方法
CN205013938U (zh) 城市自来水管道不停水接管施工结构
CN104594618A (zh) 一种高炉水渣排汽筒体的抱箍式可拆卸操作平台
CN104843357A (zh) 苯加氢工程的槽罐及其制作和安装方法
CN105239775A (zh) 一种用于筒仓滑模施工的钢筋安装质量动态控制方法
CN104776268B (zh) 大口径钢筋混凝土排水管道安装的机械化施工方法
CN101392518B (zh) 一种大型水轮机引水钢管道的快速施工方法
CN203640247U (zh) 一种高炉水渣排汽筒体的抱箍式可拆卸操作平台
CN109724411B (zh) 大型转化炉辐射段模块化组装方法
CN109160676A (zh) 污水处理厂不停运扩能改造施工方法
CN104153451A (zh) 预制托块混凝土管道安装施工方法
CN105065845A (zh) 市政下水道分叉管修复装置及其施工方法
WO2015158074A1 (zh) 一种地下供水玻璃钢夹砂管与钢管连接更换的施工方法
CN110797827A (zh) 一种电缆排管预制混凝土模块
CN202265801U (zh) 一种碾压混凝土坝诱导缝接缝灌浆排气系统
CN102661075B (zh) 分段式单筒混凝土结构烟囱的制造方法
CN114087421A (zh) 一种箱涵内敷设压力管道施工方法
CN209722908U (zh) 钢构体
CN104314311B (zh) 用于施工塔机可升降的水平360°喷淋装置
CN106854931A (zh) 一种承插锁扣式排气道及施工工法
CN202509774U (zh) 一种pccp管承插口外部接缝灌浆装置
CN102400440B (zh) 一种外模板
CN105441614A (zh) 一种高炉五通球组对方法
CN201891250U (zh) 一种地坪找平器

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant