CN101852016B - 地下墙体超长竖筋一次安装脚手架施工方法 - Google Patents
地下墙体超长竖筋一次安装脚手架施工方法 Download PDFInfo
- Publication number
- CN101852016B CN101852016B CN2010101999715A CN201010199971A CN101852016B CN 101852016 B CN101852016 B CN 101852016B CN 2010101999715 A CN2010101999715 A CN 2010101999715A CN 201010199971 A CN201010199971 A CN 201010199971A CN 101852016 B CN101852016 B CN 101852016B
- Authority
- CN
- China
- Prior art keywords
- double
- step frame
- scaffolds
- scaffold
- base plate
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
- Working Measures On Existing Buildindgs (AREA)
Abstract
本发明涉及建筑施工方法,尤其是一种地下墙体超长竖筋一次安装脚手架施工方法。其特点是:设置双排脚手架第一步架短钢管立管为临时立管坐落在混凝土垫层上,此短钢管待底板混凝土初凝时拆除;双排脚手架第一排大横杆高度距结构底板完成标高300mm,为脚手架扫地杆;双排脚手架第二步架钢管立管位于两根双排脚手架第一步架短钢管立管中间,其底部标高高出结构底板设计表面标高一个多层板厚度;逐根拆除双排脚手架第一步架短钢管立管,逐根填补结构底板上形成的管眼,逐根在双排脚手架第二步架钢管立管下垫多层板片,管眼用原浆混凝土灌实,并随大面底板混凝土抹平压光。本发明节约钢材,减少工序,提高效率,降低成本,保证地下结构防水质量。
Description
技术领域
本发明涉及建筑施工方法,尤其是一种地下墙体超长竖筋一次安装脚手架施工方法。
背景技术
在地下结构施工中,为了减少钢筋连接次数,节约钢材,地下墙体可以采用超长钢筋一次施工技术。即,在地下结构底板浇筑混凝土前,将墙体竖筋整根预埋,而不是只预埋够搭接长度的一部分。这样就可以减少钢筋的连接次数,节约钢材。而对墙体竖筋的临时固定则采用双排脚手架。此脚手架可以考虑为下一步墙体支模使用。现有技术中,由于双排脚手架坐落于尚未浇筑混凝土的结构底板上,为避免脚手钢管被埋置到混凝土中,需为其设置钢筋马凳。马凳上焊接直立短钢筋,底板钢筋绑扎完毕搭设双排脚手架时,将脚手架的钢管立管套置于短钢筋之上,混凝土浇筑后,钢筋马凳永久埋置于混凝土中。这种做法,钢筋马凳需要单独制作,单独安装,费工费料。而且在地下结构完成后,需要割除暴露于结构底板表面的钢筋头,对于钢筋头表面进行防锈处理,如结构底板尚设置有柔性防水层,钢筋头的处理更需仔细,否则就为防水质量埋下隐患。
发明内容
本发明旨在解决现有技术存在的上述问题,而提供一种能够节约钢材、节约人工、减少工序、提高效率、更好的保证地下结构防水质量的地下墙体超长竖筋一次安装脚手架施工方法。
本发明解决现有技术问题采用的技术方案是:
一种地下墙体超长竖筋一次安装脚手架施工方法,包括双排脚手架第一步架、第二步架和第三步架的安装,其特征在于:
a、设置双排脚手架第一步架短钢管立管作为临时立管坐落在混凝土垫层上,此短钢管待底板混凝土初凝时拆除;
b、双排脚手架的第一排大横杆的高度为距结构底板完成标高300mm,作为脚手架的扫地杆;
c、双排脚手架第二步架钢管立管位置位于两根双排脚手架第一步架短钢管立管中间,其底部标高高出结构底板设计表面标高一个多层板的厚度;
d逐根拆除双排脚手架第一步架短钢管立管,逐根填补结构底板上形成的管眼,逐根在双排脚手架第二步架钢管立管下垫设150×150mm多层板片,管眼用原浆混凝土灌实,并随大面底板混凝土抹平压光。
与现有方法相比,本发明的突出效果是:能够节约钢材,节约人工,减少工序,提高效率,降低成本;更好的保证地下结构防水质量。
附图说明
图1是底板混凝土浇筑前双排脚手架立面示意图。
图2是底板混凝土浇筑后双排脚手架立面示意图。
图3是底板混凝土浇筑后双排脚手架平面示意图。
图中:双排脚手架第一步架短钢管立管1;大横杆2;小横杆3;双排脚手架第二步架钢管立管4;双排脚手架第二步架小横杆5;双排脚手架第三步架小横杆6;多层板片7;墙体钢筋骨架8。
具体实施方式
以下结合附图及实施例详述本发明。
本实施例所述地下墙体超长竖筋一次安装脚手架施工方法,按下述步骤进行:
1、参见图1、图3。结构底板钢筋绑扎完毕后,按照设计位置搭设双排脚手架第一步架,双排脚手架第一步架短钢管立管1立于混凝土垫层上,高度跨越两道大横杆2,第一道大横杆2位置为结构底板上表面标高以上300mm。比如:结构底板厚度500mm,双排脚手架步距1500mm,则双排脚手架第一步架短钢管立管1高度为500+300+1500+200=2500mm。
2、仍参见图1、图3。搭设第二步架。第二步架可按正常双排脚手架搭设,双排脚手架第二步钢管立管4位置位于两根双排脚手架第一步架短钢管立管1中间,其底部标高高出结构底板设计表面标高一个多层板的厚度,约12mm。
3、仍参见图1、图3。搭设第三步架。第三步架中的大横杆2搭设与正常双排脚手架相同,双排脚手架第三步小横杆6长度稍长,同时承担固定墙体超长立筋的作用,与墙体钢筋骨架8用绑扎丝或10号线绑扎。
4、参见图2、图3。结构底板混凝土浇筑完毕后,混凝土初凝前将双排脚手架第一步架短钢管立管1逐根拆除,拔除该双排脚手架第一步架短钢管立管1后形成的管眼马上用混凝土填实,随同大面混凝土压实抹光。
5、参见图2。拆除双排脚手架第一步架短钢管立管1后的双排脚手架第二步钢管立管4下逐根垫设150×150mm多层板片7,加大接触面积,以防对刚刚初凝的混凝土造成破坏。此步骤紧随步骤4进行。
Claims (1)
1.一种地下墙体超长竖筋一次安装脚手架施工方法,包括双排脚手架第一步架、第二步架和第三步架的安装,其特征在于:
a、设置双排脚手架第一步架短钢管立管作为临时立管坐落在混凝土垫层上,此短钢管待底板混凝土初凝时拆除;
b、双排脚手架的第一排大横杆的高度为距结构底板完成标高300mm,作为脚手架的扫地杆;
c、双排脚手架第二步架钢管立管位置位于两根双排脚手架第一步架短钢管立管中间,其底部标高高出结构底板设计表面标高一个多层板的厚度;
d逐根拆除双排脚手架第一步架短钢管立管,逐根填补结构底板上形成的管眼,逐根在双排脚手架第二步架钢管立管下垫设150×150mm多层板片,管眼用原浆混凝土灌实,并随大面底板混凝土抹平压光。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2010101999715A CN101852016B (zh) | 2010-06-11 | 2010-06-11 | 地下墙体超长竖筋一次安装脚手架施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2010101999715A CN101852016B (zh) | 2010-06-11 | 2010-06-11 | 地下墙体超长竖筋一次安装脚手架施工方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN101852016A CN101852016A (zh) | 2010-10-06 |
CN101852016B true CN101852016B (zh) | 2011-12-14 |
Family
ID=42803684
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2010101999715A Active CN101852016B (zh) | 2010-06-11 | 2010-06-11 | 地下墙体超长竖筋一次安装脚手架施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN101852016B (zh) |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN201268953Y (zh) * | 2008-08-29 | 2009-07-08 | 江苏南通二建集团有限公司 | 单面支模装置 |
CN201395794Y (zh) * | 2008-12-08 | 2010-02-03 | 中国建筑西南勘察设计研究院有限公司 | 具有暗柱和土钉支护的基坑 |
Family Cites Families (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2538498B2 (ja) * | 1993-04-10 | 1996-09-25 | 大和ハウス工業株式会社 | 建築工事足場架設工法 |
KR101140327B1 (ko) * | 2008-09-30 | 2012-05-03 | 김영식 | 지하구조물의 일부를 토압지지체로 활용한 지하구조물 철거방법 |
KR100951097B1 (ko) * | 2009-03-13 | 2010-04-07 | (주)한국건설공법 | 지하구조물의 슬래브 및 합벽 구조물과 시공 방법, 그리고 받침브라켓 |
-
2010
- 2010-06-11 CN CN2010101999715A patent/CN101852016B/zh active Active
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN201268953Y (zh) * | 2008-08-29 | 2009-07-08 | 江苏南通二建集团有限公司 | 单面支模装置 |
CN201395794Y (zh) * | 2008-12-08 | 2010-02-03 | 中国建筑西南勘察设计研究院有限公司 | 具有暗柱和土钉支护的基坑 |
Non-Patent Citations (5)
Title |
---|
JP特开平6-299692A 1994.10.25 |
刘术等.钢管排架单侧支模体系的应用技术.《黑龙江科技信息》.2008,(第21期),171、257. * |
宋栋正等.地下室外墙施工缝处钢筋无连接施工法.《山东建材学院学报》.2000,第14卷(第4期),331-334. * |
应敏红.地下室外墙单面模板施工技术.《建筑技术》.2005,第36卷(第11期),869. * |
徐鸿斌.超高超厚地下室外墙单面模板施工技术.《建筑施工》.2006,第28卷(第2期),124-125. * |
Also Published As
Publication number | Publication date |
---|---|
CN101852016A (zh) | 2010-10-06 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104631512B (zh) | 吊模法后浇带梁板施工方法 | |
CN104746435B (zh) | 一种大角度y型墩柱的施工方法 | |
CN104878766B (zh) | 一种长边坡护坡混凝土连续快速浇筑拉模体系及施工方法 | |
CN104405123B (zh) | 现浇钢筋砼薄壁矩形小截面空心柱用模板组件及其施工方法 | |
CN105350559B (zh) | 一种适用于大型厂房的金刚砂结构地面的施工方法 | |
CN202090605U (zh) | 一种工具式楼面平整度、楼板负筋保护层控制装置 | |
CN102661019B (zh) | 建筑物外墙保温装饰一体化施工方法及专用吊装机 | |
CN207160585U (zh) | 超高地下室外墙贝雷架单侧支模体系结构 | |
CN101818570A (zh) | 高层建筑梁式结构转换层的施工方法 | |
CN101368447B (zh) | 古城墙修复施工方法 | |
CN104060760B (zh) | 高层建筑结构转换层混凝土超大梁分层施工方法 | |
CN104120736A (zh) | 一种钢筋混凝土挡土墙的施工方法 | |
CN105780992A (zh) | 一种正交正放钢筋混凝土空腹夹层板楼盖施工工法 | |
CN108661313A (zh) | 一种工具式混凝土叠合板现浇连接段模板支撑装置 | |
CN104631829A (zh) | 结构楼地面高精度找平工艺 | |
CN202882446U (zh) | 钢筋悬吊马凳 | |
CN204690763U (zh) | 长边坡护坡混凝土连续快速浇筑拉模体系 | |
CN101852016B (zh) | 地下墙体超长竖筋一次安装脚手架施工方法 | |
CN204299179U (zh) | 现浇钢筋砼薄壁矩形小截面空心柱用模板组件 | |
CN101666122B (zh) | 微距离架空大梁底模施工方法 | |
CN102777026A (zh) | 一种贝雷架构建超长后浇板支撑体系的方法 | |
CN104746521B (zh) | 超大断截面斜坡垫层施工结构的应用 | |
CN202970006U (zh) | 一种l形预制清水看台板安装施工结构 | |
CN206438766U (zh) | 一种无支撑梁板后浇带模板体系 | |
CN204552115U (zh) | 用于结构楼地面高精度找平的冲筋件 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |