CN101804667A CN 201010137982 CN201010137982A CN101804667A CN 101804667 A CN101804667 A CN 101804667A CN 201010137982 CN201010137982 CN 201010137982 CN 201010137982 A CN201010137982 A CN 201010137982A CN 101804667 A CN101804667 A CN 101804667A
Authority
CN
China
Prior art keywords
box girder
cooling
cooling water
water pipe
stressed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN 201010137982
Other languages
English (en)
Inventor
朱尔玉
李学民
周勇政
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Jiaotong University
Original Assignee
Beijing Jiaotong University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Jiaotong University filed Critical Beijing Jiaotong University
Priority to CN 201010137982 priority Critical patent/CN101804667A/zh
Publication of CN101804667A publication Critical patent/CN101804667A/zh
Pending legal-status Critical Current

Links

Images

Abstract

本发明公开了一种预应力箱梁梁体混凝土降温方法,适用于预应力混凝土箱梁的加工、制作和养护过程中。该方法包括以下步骤:步骤一,沿预应力箱梁梁体纵向布置冷却水管;步骤二,各冷却水管之间串联连接,其一端为进水口(8),另一端为出水口(12);步骤三,进出水口(8、12)与循环水连通,通过冷却水管回路内部水的流通,快速带走箱梁梁体混凝土产生的水化热;步骤四,在预应力箱梁降温完成后,向冷却水管内进行灌浆,保证箱梁混凝土的承载力。该方法有效地解决了预应力箱梁加工、制作和养护中梁体降温慢的难题,缩短了箱梁的预制周期,有效的防止了预应力箱梁在降温过程中裂缝的产生,提高了工程项目的施工效率与施工质量。

Description

预应力箱梁梁体混凝土降温方法
技术领域
本发明涉及一种预应力箱梁梁体混凝土降温方法,适用于预应力混凝土箱梁加工、制作和养护过程中。
背景技术
目前,中国高速铁路的建设进行的如火如荼,高架桥梁结构在高速铁路建设中所占比例很高,一般线路中所占比例达70%~80%以上,而高架桥梁中使用最多的是预应力混凝土箱梁。因此,预应力混凝土箱梁的施工质量及施工速度直接影响着整个工程项目的社会效益及经济效益。
在预应力混凝土箱梁的施工中,箱梁混凝土的养护是其中一个重要的环节。高速铁路的预制箱梁体积较大,浇注的混凝土较多,这样,混凝土中的水泥在水化凝结过程中,会发生数量可观的水化热,使混凝土温度显著上升。同时,由于施工工期的要求,预应力混凝土箱梁需要采用蒸汽养护来加快混凝土的硬化,以缩短施工周期。在经过蒸汽养护之后,箱梁的温度达到最高值,但因混凝土是一种导热性能极为不良的材料,如果热量任其自然散发,往往需要较长的时间。而且,在降温的过程中,箱梁各个部位降温的速率并不相同。在箱梁梁体表面,温度降低的较快,而在箱梁梁体内部,温度降低的较慢,由此便形成了箱梁梁体的内外温差,当该温差达到一定限值时,就会引起箱梁梁体的开裂,产生裂缝,从而影响预应力混凝土箱梁的耐久性。因此,预应力混凝土箱梁的降温速度便成为缩短施工工期,提高施工质量的瓶颈。采用人工冷却的方法,迫使预应力混凝土箱梁按照规范的规定以及施工进度的要求,快速、有效地降温,成为预应力混凝土箱梁预制施工中急需解决的问题之一。
发明内容
本发明所要解决的技术问题在于克服现有方法存在的上述不足之处,提供一种简单易行、快速有效的预应力箱梁梁体混凝土降温方法,在保证预应力箱梁耐久性的基础上,快速的降低预应力箱梁梁体混凝土的温度,缩短预应力箱梁的预制周期。
为实现上述目的,本发明的技术方案为:
预应力箱梁梁体混凝土降温方法,该方法包括以下步骤:
步骤一,沿预应力箱梁梁体纵向布置冷却水管;
步骤二,各冷却水管之间串联连接,其一端为进水口,另一端为出水口;
步骤三,进出水口与循环水连通,通过冷却水管回路内部水的流通,快速带走箱梁梁体混凝土产生的水化热;
步骤四,在预应力箱梁降温完成后,向冷却水管内进行灌浆,保证箱梁混凝土的承载力。
所述的冷却水管的直径为:20mm~32mm,冷却水管的间距为0.5m~2.0m,呈层或列布置。
所述的沿预应力箱梁梁体纵向布置冷却水管是指在预应力箱梁倒角中心位置处和箱梁腹板位置处纵向布置冷却水管。
预应力箱梁梁体混凝土降温方法是:根据计算机仿真计算及实际测量的结果,在预应力箱梁梁体混凝土尺寸大、水化热高或内外温差大的部位,如:预应力箱梁倒角中心位置处和箱梁腹板位置处等。沿预应力箱梁梁体纵向布置冷却水管,利用在冷却水管中通入冷却水的方法带走梁体混凝土产生的水化热,快速有效的降低预应力箱梁混凝土的温度。
冷却水管内的冷却水水温应根据预应力箱梁梁体的实测温度确定,要保证冷却水与预应力箱梁梁体的温度差不大于规范要求,避免因冷却水温度过低造成冷却水管附近的预应力箱梁梁体因温差应力过大而开裂。如果测温时发现冷却水与预应力箱梁梁体温度差过小,则应采取在水箱中加入冷水并将部分水箱内热水抽走的方法以加大温差,增强冷却效果,降低预应力箱梁梁体混凝土的温度。
本发明的有益效果:该方法利用箱梁梁体混凝土内部布置的冷却水管快速带走梁体混凝土产生的水化热,有效地解决了预应力箱梁养护中梁体降温慢的难题,操作简单、易于控制、成本低,尤其对于采用蒸汽养护的预应力箱梁,能较大幅度的缩短箱梁的预制周期,提高制梁台座的周转速度,降低整个工程项目的生产成本。特别地,本方法有效的防止了预应力箱梁在降温过程中裂缝的产生,为提高预应力箱梁施工质量提供了一个有效的方法方案。
附图说明
图1为1/2箱梁横截面冷却水管布置示意图。其中,1~7为冷却水管的编号。
图2为冷却水管连接示意图。其中:8为入水口,9为橡胶连接管,10为接头,11为冷却水管,12为出水口。
具体实施方式
结合附图通过实施例对本发明作进一步说明:
实施例一
预应力箱梁梁体混凝土降温方法,如图5,具体地说,是一种利用箱梁梁体混凝土内部布置冷却水管快速带走梁体混凝土产生的水化热,以达到预应力箱梁梁体混凝土快速降温目的的方法。
该方法包括以下步骤:
步骤一,沿预应力箱梁梁体纵向布置冷却水管;
箱梁的梁高为300cm,梁顶宽度为1200cm,梁底宽度为550cm,顶板厚度为50cm,腹板厚度为100cm,底板厚度为60cm,根据该箱梁的空间尺寸、混凝土厚度等选择冷却水管的直径、管材、间距与层距,本实施例中,冷却水管的直径选择2.0cm,对于直径为2.0cm~3.2cm的冷却水管,均能实现本方法的目的。管材为无缝钢管,间距与层距都选0.5m,共7根。
在箱梁浇注混凝土之前,预先在箱梁梁体内部尺寸大、水化热高或内外温差大的部位,如箱梁倒角中心位置处、箱梁腹板中心位置处等,沿预应力箱梁梁体纵向布置冷却水管。
步骤二,各冷却水管之间串联连接,其一端为进水口8,另一端为出水口12;
待预应力箱梁混凝土浇注完成之后,在预应力箱梁的端部,各纵向布置的冷却水管采用橡胶连接管进行串联连接,橡胶连接管的两端安装管接头,方便与冷却水管之间的连接,降温完成之后,橡胶连接管可拆卸下来,以重复使用。冷却水管连接的顺序为:2→4→3→1→5→6→7。
步骤三,进出水口与循环水连通,通过冷却水管回路内部水的流通,快速带走箱梁梁体混凝土产生的水化热;
待混凝土达到设计强度之后,从入水口处向冷却水管中通入冷却水,冷却水从出水口处流出。利用水管的导热性能,由冷却水的流动带走预应力箱梁混凝土产生的水化热,降低预应力箱梁梁体混凝土的温度,减小预应力箱梁梁体混凝土芯部与表面、梁体与环境之间的温度差。
步骤四,在预应力箱梁降温完成后,对冷却水管进行灌浆,保证箱梁混凝土的承载力。
预应力箱梁降温完成后,将橡胶连接管及接头拆除,对冷却水管进行灌浆,保证箱梁混凝土的承载力。
实施例二
与实施例一的区别在于:
箱梁的梁高为500cm,梁顶宽度为1800cm,梁底宽度为950cm,顶板厚度为60cm,腹板厚度为140cm,底板厚度为70cm,根据该箱梁的空间尺寸、混凝土厚度等选择冷却水管的直径、管材、间距与层距,本实施例中,冷却水管的直径选择3.2cm,对于直径为2.0cm~3.2cm的冷却水管,均能实现本方法的目的。管材为无缝钢管,间距与层距都选2.0m。

Claims (3)

1.预应力箱梁梁体混凝土降温方法,其特征在于,该方法包括以下步骤:
步骤一,沿预应力箱梁梁体纵向布置冷却水管;
步骤二,各冷却水管之间串联连接,其一端为进水口(8),另一端为出水口(12);
步骤三,进出水口(8、12)与循环水连通,通过冷却水管回路内部水的流通,快速带走箱梁梁体混凝土产生的水化热;
步骤四,在预应力箱梁降温完成后,向冷却水管内进行灌浆,保证箱梁混凝土的承载力。
2.根据权利要求1所述的预应力箱梁梁体混凝土降温方法,其特征在于,冷却水管的直径为:20mm~32mm,冷却水管的间距为0.5m~2.0m,冷却水管呈层或列布置。
3.根据权利要求1所述的预应力箱梁梁体混凝土降温方法,其特征在于,所述的沿预应力箱梁梁体纵向布置冷却水管是指在预应力箱梁倒角中心位置处和箱梁腹板位置处纵向布置冷却水管。
CN 201010137982 2010-03-30 2010-03-30 预应力箱梁梁体混凝土降温方法 Pending CN101804667A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201010137982 CN101804667A (zh) 2010-03-30 2010-03-30 预应力箱梁梁体混凝土降温方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201010137982 CN101804667A (zh) 2010-03-30 2010-03-30 预应力箱梁梁体混凝土降温方法

Publications (1)

Publication Number Publication Date
CN101804667A true CN101804667A (zh) 2010-08-18

Family

ID=42606697

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201010137982 Pending CN101804667A (zh) 2010-03-30 2010-03-30 预应力箱梁梁体混凝土降温方法

Country Status (1)

Country Link
CN (1) CN101804667A (zh)

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102518048A (zh) * 2012-01-17 2012-06-27 广西交通科学研究院 零号块腹板分层浇筑非荷载裂缝预防方法
CN103862561A (zh) * 2012-12-11 2014-06-18 天元建设集团有限公司 用于混凝土构件的换热装置以及水化热的利用方法
CN104085040A (zh) * 2014-06-27 2014-10-08 中国长江三峡集团公司 预制箱梁的制造方法
CN105890251A (zh) * 2016-06-04 2016-08-24 中铁十九局集团第五工程有限公司 大型混凝土预制箱梁降温装置及其降温方法
CN107447670A (zh) * 2017-08-28 2017-12-08 南昌大学 斜拉桥大体积混凝土箱梁配重混凝土结构及施工方法
CN107663833A (zh) * 2017-10-26 2018-02-06 北京科技大学 一种箱梁合龙段混凝土的水冷却施工装置及温度控制方法
CN110281380A (zh) * 2019-07-04 2019-09-27 福建省大地管桩有限公司 定向凝结管桩的制造工艺
CN111719434A (zh) * 2020-07-10 2020-09-29 张飞 一种市政路桥建筑用箱梁模板施工方法
CN111719433A (zh) * 2020-07-10 2020-09-29 张飞 一种市政路桥建筑施工用箱梁模板
CN112324140A (zh) * 2020-11-09 2021-02-05 深圳市罗湖建筑安装工程有限公司 预应力混凝土板施工方法
CN112726422A (zh) * 2021-01-31 2021-04-30 班玉杰 一种市政路桥建筑施工用箱梁模板
CN114043630A (zh) * 2021-11-18 2022-02-15 北新集团建材股份有限公司 一种石膏板生产用自动调温系统及方法

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007303159A (ja) * 2006-05-11 2007-11-22 Hazama Corp コンクリート構造物のひび割れ抑制方法
CN101672106A (zh) * 2009-08-11 2010-03-17 中国建筑第五工程局有限公司东莞分公司 大体积砼降温抗裂运用薄壁波纹管循环水系统的施工方法

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007303159A (ja) * 2006-05-11 2007-11-22 Hazama Corp コンクリート構造物のひび割れ抑制方法
CN101672106A (zh) * 2009-08-11 2010-03-17 中国建筑第五工程局有限公司东莞分公司 大体积砼降温抗裂运用薄壁波纹管循环水系统的施工方法

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
《山西建筑》 20070630 张百东 浅谈某大桥现浇箱梁大体积混凝土的施工 , 2 *
《超大跨径混合梁斜拉桥宽箱梁高性能混凝土防裂技术与耐久性研究》 20090115 查进 1 , 1 *

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102518048A (zh) * 2012-01-17 2012-06-27 广西交通科学研究院 零号块腹板分层浇筑非荷载裂缝预防方法
CN103862561A (zh) * 2012-12-11 2014-06-18 天元建设集团有限公司 用于混凝土构件的换热装置以及水化热的利用方法
CN104085040A (zh) * 2014-06-27 2014-10-08 中国长江三峡集团公司 预制箱梁的制造方法
CN105890251A (zh) * 2016-06-04 2016-08-24 中铁十九局集团第五工程有限公司 大型混凝土预制箱梁降温装置及其降温方法
CN107447670A (zh) * 2017-08-28 2017-12-08 南昌大学 斜拉桥大体积混凝土箱梁配重混凝土结构及施工方法
CN107663833A (zh) * 2017-10-26 2018-02-06 北京科技大学 一种箱梁合龙段混凝土的水冷却施工装置及温度控制方法
CN110281380A (zh) * 2019-07-04 2019-09-27 福建省大地管桩有限公司 定向凝结管桩的制造工艺
CN111719434A (zh) * 2020-07-10 2020-09-29 张飞 一种市政路桥建筑用箱梁模板施工方法
CN111719433A (zh) * 2020-07-10 2020-09-29 张飞 一种市政路桥建筑施工用箱梁模板
CN112324140A (zh) * 2020-11-09 2021-02-05 深圳市罗湖建筑安装工程有限公司 预应力混凝土板施工方法
CN112726422A (zh) * 2021-01-31 2021-04-30 班玉杰 一种市政路桥建筑施工用箱梁模板
CN114043630A (zh) * 2021-11-18 2022-02-15 北新集团建材股份有限公司 一种石膏板生产用自动调温系统及方法

Similar Documents

Publication Publication Date Title
CN101804667A (zh) 预应力箱梁梁体混凝土降温方法
CN202125080U (zh) 混凝土散热装置
CN108858697A (zh) 一种冬季保温加热预制简支箱梁模板
CN104708708A (zh) 一种盾构管片的预制方法
CN103643626A (zh) 一种曲线超高型桥墩墩身温度应力裂缝的控制方法
JP2014113636A (ja) 鋳型及び鋳型の製造方法
CN103862561A (zh) 用于混凝土构件的换热装置以及水化热的利用方法
CN105544583B (zh) 一种桥梁承台的施工方法
CN202440743U (zh) 拌和站沥青加热装置
CN201470827U (zh) 一种悬臂式砂芯结构
CN102808395A (zh) 特高拱坝悬臂高度的个性化控制方法
CN202176111U (zh) 钢管混凝土柱u形管循环水养护系统
CN104453236A (zh) 一种控制大体积混凝土裂缝的循环水自然冷却系统及作法
CN208084640U (zh) 一种预制构件用钢混融合sc结构加热模台
CN102407561B (zh) 高速铁路用轨道板预制工艺
CN103225286B (zh) 一种混凝土重力坝坝体结构及其区域协调降温方法
CN106142316A (zh) 一种组合模具养护系统
CN203768418U (zh) 一种金属构件加热炉
CN105154632A (zh) 一种针对变截面长杆类零件的分层淬火工艺方法
CN202877470U (zh) 铜阳极板砂型铸造双面浇铸模
CN105442735A (zh) 一种长钢筋凳现浇楼板的施工方法
CN109056504A (zh) 一种桥梁预制梁低水化热预制用内衬管及其预制方法
CN203875274U (zh) 一种覆膜砂加热装置
CN103847072B (zh) 带树脂加热流道的rtm模具
CN104399892A (zh) 一种新型扭曲片管熔模

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication

Open date: 20100818