CN101804555A CN 201010161241 CN201010161241A CN101804555A CN 101804555 A CN101804555 A CN 101804555A CN 201010161241 CN201010161241 CN 201010161241 CN 201010161241 A CN201010161241 A CN 201010161241A CN 101804555 A CN101804555 A CN 101804555A
Authority
CN
China
Prior art keywords
coupler
power transmission
transmission shaft
assembling
shaft
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN 201010161241
Other languages
English (en)
Other versions
CN101804555B (zh
Inventor
周勇
徐平
胡燕立
刘金平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China First Metallurgical Group Co Ltd
Original Assignee
Wuhan Yiye Machinery & Electronic Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuhan Yiye Machinery & Electronic Engineering Co Ltd filed Critical Wuhan Yiye Machinery & Electronic Engineering Co Ltd
Priority to CN2010101612416A priority Critical patent/CN101804555B/zh
Publication of CN101804555A publication Critical patent/CN101804555A/zh
Application granted granted Critical
Publication of CN101804555B publication Critical patent/CN101804555B/zh
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Automatic Assembly (AREA)

Abstract

本发明涉及一种大型过盈配合联轴器拆装更换的方法,该方法是先利用履带式电加热器和火焰加热相结合的方法使联轴器膨胀,再对联轴器进行拆除和组装工作。该方法可以在大型轧制设备的整个传动装置的拆除、组装或更换工作中的应用。该方法通过垂直方式对传动轴和联轴器进行拆除、安装,降低了施工难度,尽可能缩短了施工工期,一般只需要24小时,满足了业主对工期的迫切需求,并且能够更好地控制过盈较大的大型传动轴与联轴器之间的配合尺寸和安装过程,确保两者之间的连接面不受损伤,从而确保连接质量。

Description

大型过盈配合联轴器拆装更换的方法
技术领域
本发明涉及一种大型过盈配合联轴器拆装更换的方法。
背景技术
在紧张忙碌的生产过程中,大型轧制设备经常会发生传动装置轴承损坏等设备故障,为节约成本,同时又要确保完成生产任务,生产厂家经常会选择局部更换损坏轴承,这就需要检修单位快速完成整个传动装置的拆除、组装和更换工作。
拆除、组装和更换传动装置的过程中,难度最大和耗时最多的工序就是传动轴与联轴器之间的拆除和组装工作。大部分的大型传动轴与联轴器之间选用过盈配合,而目前国内许多大型压力机都不能满足拆除要求,采用传统的加热方式和横向拆除、组装方法难度较大,耗时较多,且极易损伤传动轴连接面,无法满足生产厂家要求,为此,需要对传统的施工工艺进行改进、创新。
发明内容
本发明所要解决的技术问题是:针对上述现有技术存在的问题,提供一种施工速度快、操作简单、确保施工质量的大型过盈配合联轴器的拆除、安装方法。
本发明解决其技术问题采用以下的技术方案:
本发明提供的大型过盈配合联轴器拆装更换的方法,具体是:先利用履带式电加热器和火焰加热相结合的方法使联轴器膨胀,再进行拆除和组装工作。其包括以下步骤:
1)制作一个拆除用立式拉码支架和一个组装用辅助平台;
2)采用履带式电加热器和保温棉,并准备好6~8把烤枪和1台红外感应测温器;同时将拆除用拉码支架安放到合适位置,并将一台液压千斤顶放入支架内;
3)用行车或吊装设备吊住传动轴另一端中心吊装孔,使传动轴垂直于地面,然后将其缓慢放入拉码支架内,提升传动轴,使半联轴器上部与立式拉码支架上面板均匀接触,之后在半联轴器底部放置支墩和调整平垫片,支托半联轴器;
4)利用履带式电加热器和保温棉包裹住半联轴器外表面,将半联轴器均匀地加热到所需温度的60~75%,断电之后拆除履带式电加热器和保温棉;
5)利用6~8把烤枪同时均匀的加热半联轴器外表面,使其迅速、均匀升温,形成与传动轴之间的较大温差,从而起到膨胀作用;
6)达到需要温度后,缓慢、均匀升起液压千斤顶,逐步顶起传动轴,在千斤顶顶起的过程中,随时调整行车吊钩高度,保持与顶起速度相匹配;拆除过程中,利用烤枪加热,保证半联轴器的温度稳定;
7)传动轴与半联轴器拆除完毕后,将传动轴吊装到其他位置以便对包括轴承和定距套在内的部件进行拆除或更换工作,同时将拆除下来的半联轴器吊装到组装平台的挡圈内,并调整组装平台底部调整斜垫板,使半联轴器处于水平状态;
8)将履带式电加热器和保温棉与半联轴器外表面相连,对半联轴器进行加热,到达需要温度后,测量半联轴器内径,满足安装要求后,与传动轴进行组装;
9)将传动轴垂直吊装到半联轴器上部,调整传动轴与半联轴器的对应位置;当半联轴器内径满足安装要求后,缓慢下降传动轴高度,对准安装部位,利用传动轴自重将传动轴与半联轴器连接成整体;安装过程中,要随时检查传动轴是否处于垂直状态,确保连接的准确性,避免损伤轴和半联轴器连接面;吊钩与传动轴的连接应在半联轴器温度冷却,并与传动轴连接成整体后才能拆除;
经过上述步骤后,完成了大型过盈配合联轴器拆装的更换工作。
本发明提供的上述大型过盈配合联轴器拆装更换的方法,其在大型轧制设备的整个传动装置的拆除、组装或更换工作中的应用。
本发明与传统安装方法相比具有以下的主要有益效果:
1.通过垂直方式对传动轴和联轴器进行拆除、安装,降低了施工难度,尽可能缩短了施工工期,满足了业主对工期的迫切需求。按常规施工方式拆除、更换传动轴需要36~48小时,而采用本发明施工,只需要24小时即可,优质高效,施工速度快。
2.质量效果好。使用本发明立式安装方式,能够更好地控制过盈较大的大型传动轴与联轴器之间的配合尺寸和安装过程,确保两者之间的连接面不受损伤,从而确保连接质量。
附图说明
图1为传动轴与联轴器立式拆除示意图。
图2为传动轴拆除时与拉码支架配合的A向俯视图。
图3为传动轴与联轴器组装示意图。
图中:1.传动轴;2.轴承;3.上面板;4.半联轴器;5.调整平垫片;6.支墩;7.型钢立柱;8.底板;9.辅助支柱;10.液压千斤顶;11.定距套;12.挡圈;13.组装平台;14.调整斜垫板。
具体实施方式
下面结合实施例及附图对本发明做进一步阐述,但不限于下述实施例。
实施例1:邯钢连铸连轧厂轧机传动轴联轴器拆除、安装的方法
如图1、图2和图3所示,该方法包括以下步骤:
1.首先拆除传动轴与轧机、减速机之间的连接螺栓,将传动轴1吊装到合适位置后,进行半联轴器4压盖和内齿圈的拆除工作。
2.根据半联轴器4和传动轴1的连接部位相关尺寸,结合使用的液压千斤顶10(例如500t液压千斤顶)外型尺寸,设计制作一个拆除用立式拉码支架和一个组装用辅助平台。
立式拉码支架的结构如图1所示:由上面板3、型钢立柱7和底板8组成,其中:上面板3安装在型钢立柱7的顶部,底板8装在型钢立柱7的底部,焊接固定。在底板8的上面焊接有支撑半联轴器4的支墩6。上面板3和底板8均由厚度为140mm的钢板制成。上面板3根据半联轴器4和传动轴1相关尺寸开孔,使传动轴1和半联轴器4能够顺利放入立式拉码支架内。支墩6采用型钢H300*300*10*15*20焊接而成,制作尺寸根据立式拉码支架和半联轴器4配合尺寸制作。型钢立柱7可由H300*300*10*15*20的型钢制成。
组装用辅助平台的结构如图3所示:设有底板和四组调整斜垫板14。底板位于组装平台13的上面,在底板中部设有与半联轴器4外形尺寸匹配的挡圈12。所述四组调整斜垫板位于组装平台13的底部,用于调整组装平台13水平。
3.根据半联轴器4外形尺寸,选用合适的履带式电加热器和保温棉,并准备好6~8把烤枪和1台红外感应测温器。
履带式电加热器可以采用10KW/片的履带式电加热器,其规格尺寸、数量根据需拆除联轴器的外型尺寸确定。
4.将拆除用立式拉码支架安放到合适位置,并将一台液压千斤顶10放入所述支架内;
5.用行车或其他吊装设备吊住传动轴1另一端中心吊装孔,使传动轴1垂直于地面,然后将其缓慢放入立式拉码支架内,提升传动轴1,使半联轴器4上部与立式拉码支架的上面板3的底面均匀接触,之后在半联轴器4底部放置在支墩6和调整平垫片5。支墩6可由H型钢制成。
6.利用履带式电加热器和保温棉包裹住半联轴器4外表面,将半联轴器4均匀地加热到所需温度的75%左右,断电之后拆除履带式电加热器和保温棉。
7.利用6~8把烤枪同时均匀的对半联轴器4外表面加热,使其迅速、均匀升温至110~125℃范围,一般为120℃,从而形成与传动轴1之间的较大温差,起到膨胀效果。
上述温度数值是根据半联轴器的外型尺寸、材质通过下述公式精确计算而获得。
计算公式为:T=2*Y/a*d+t1。式中:T为加热所需温度;Y为平均实测过盈=0.32;a为加热线膨胀系数=11*10-6;d为联轴器配合尺寸=598;t为室温=23℃。
由此得到,加热温度=2*0.32/11*10-6*598+23=123℃。
8.达到需要温度后,缓慢、均匀升起液压千斤顶10,逐步顶起传动轴1。由于液压千斤顶10行程有限,顶起过程中,需要往返进行几次,同时在液压千斤顶10顶部根据需要增加适当的辅助支柱9。液压千斤顶10顶起的过程中,随时调整行车吊钩高度,保持与顶起速度相匹配。拆除过程中,利用烤枪适当加热,保证半联轴器4的温度稳定。
9.传动轴1与半联轴器4拆除完毕后,将传动轴1吊装到合适位置进行轴承2和定距套11等其他部件拆除、更换工作,同时将拆除下来的半联轴器4吊装到组装平台13的挡圈12内,并调整位于组装平台13底部的调整斜垫板14,使半联轴器4处于水平状态。
10.将履带式电加热器电加热带和保温棉与半联轴器4外表面相连,对半联轴器4进行加热。到达需要温度后,测量半联轴器4内径,满足安装要求后,可与传动轴1进行组装。
11.将传动轴1垂直吊装到半联轴器4上部,调整传动轴1与半联轴器4的对应位置。当半联轴器4内径满足安装要求后,缓慢下降传动轴1高度,对准安装部位,利用传动轴1自重将传动轴1与半联轴器4连接成整体。安装过程中,要随时检查传动轴1是否处于垂直状态,确保连接的准确性,避免损伤传动轴1和半联轴器4的连接面。吊钩与传动轴1的连接应在半联轴器4温度冷却,并与传动轴1连接成整体后才能拆除。
本发明提供的方法还可以在其它大型轧制设备的整个传动装置的拆除、组装或更换工作中的应用。在应用过程中,其步骤同实施例1。

Claims (8)

1.大型过盈配合联轴器拆装更换的方法,其特征是先利用履带式电加热器和火焰加热相结合的方法使联轴器膨胀,再进行拆除和组装工作,具体是采用包括以下步骤的方法:
1)制作一个拆除用立式拉码支架和一个组装用辅助平台;
2)采用履带式电加热器和保温棉,并准备好6~8把烤枪和1台红外感应测温器;同时将拆除用拉码支架安放到合适位置,并将一台液压千斤顶(10)放入支架内;
3)用行车或吊装设备吊住传动轴(1)另一端中心吊装孔,使传动轴(1)垂直于地面,然后将其缓慢放入拉码支架内,提升传动轴(1),使半联轴器(4)上部与立式拉码支架上面板(3)均匀接触,之后在半联轴器(4)底部放置支墩(6)和调整平垫片(5),支托半联轴器(4);
4)利用履带式电加热器和保温棉包裹住半联轴器(4)外表面,将半联轴器(4)均匀地加热到所需温度的60~75%,断电之后拆除履带式电加热器和保温棉;
5)利用6~8把烤枪同时均匀的加热半联轴器(4)外表面,使其迅速、均匀升温,形成与传动轴(1)之间的较大温差,从而起到膨胀作用;
6)达到需要温度后,缓慢、均匀升起液压千斤顶(10),逐步顶起传动轴(1),在千斤顶(10)顶起的过程中,随时调整行车吊钩高度,保持与顶起速度相匹配;拆除过程中,利用烤枪加热,保证半联轴器(4)的温度稳定;
7)传动轴(1)与半联轴器(4)拆除完毕后,将传动轴(1)吊装到其他位置以便对包括轴承(2)和定距套(11)在内的部件进行拆除或更换工作,同时将拆除下来的半联轴器(4)吊装到组装平台(13)的挡圈(12)内,并调整组装平台底部调整斜垫板(14),使半联轴器(4)处于水平状态;
8)将履带式电加热器和保温棉与半联轴器(4)外表面相连,对半联轴器(4)进行加热,到达需要温度后,测量半联轴器(4)内径,满足安装要求后,与传动轴(1)进行组装;
9)将传动轴(1)垂直吊装到半联轴器(4)上部,调整传动轴(1)与半联轴器(4)的对应位置;当半联轴器(4)内径满足安装要求后,缓慢下降传动轴(1)高度,对准安装部位,利用传动轴(1)自重将传动轴(1)与半联轴器(4)连接成整体;安装过程中,要随时检查传动轴(1)是否处于垂直状态,确保连接的准确性,避免损伤轴(1)和半联轴器(4)连接面;吊钩与传动轴(1)的连接应在半联轴器(4)温度冷却,并与传动轴(1)连接成整体后才能拆除;
经过上述步骤后,完成了大型过盈配合联轴器拆装的更换工作。
2.根据权利要求1所述的大型过盈配合联轴器拆装更换的方法,其特征在于立式拉码支架的结构是:设有焊接成整体的上面板(3)、底板(8)和型钢立柱(7),上面板(3)开有能够将半联轴器(4)和传动轴(1)顺利放入该支架内的孔,在底板(8)的上面焊接有支撑半联轴器(4)的支墩(6)。
3.根据权利要求2所述的大型过盈配合联轴器拆装更换的方法,其特征在于上面板(3)和底板(8)的厚度为140mm。
4.根据权利要求1所述的大型过盈配合联轴器拆装更换的方法,其特征在于组装用辅助
平台的结构是:设有底板和四组调整斜垫板(14);底板位于组装平台(13)的上面,在底板中部设有与半联轴器(4)外形尺寸匹配的挡圈(12);所述调整斜垫板位于组装平台(13)的底部,用于调整组装平台(13)水平。
5.根据权利要求1所述的大型过盈配合联轴器拆装更换的方法,其特征在于挡圈(12)由厚度为100mm的钢板制成。
6.根据权利要求1所述的大型过盈配合联轴器拆装更换的方法,其特征在于采用10KW/片的履带式电加热器。
7.根据权利要求1所述的大型过盈配合联轴器拆装更换的方法,其特征在于步骤(8)中,对联轴器(4)进行加热的温度根据需拆除联轴器外型尺寸和材质通过下述公式得到:
计算公式:T=2*Y/a*d+t1),
式中:T为加热所需温度;Y为平均实测过盈;a为加热线膨胀系数;d为联轴器配合尺寸;t为室温。
8.权利要求1至7中任一权利要求所述方法的用途,其特征是所述方法在大型轧制设备的整个传动装置的拆除、组装或更换工作中的应用。
CN2010101612416A 2010-04-27 2010-04-27 大型过盈配合联轴器拆装更换的方法 Expired - Fee Related CN101804555B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2010101612416A CN101804555B (zh) 2010-04-27 2010-04-27 大型过盈配合联轴器拆装更换的方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2010101612416A CN101804555B (zh) 2010-04-27 2010-04-27 大型过盈配合联轴器拆装更换的方法

Publications (2)

Publication Number Publication Date
CN101804555A true CN101804555A (zh) 2010-08-18
CN101804555B CN101804555B (zh) 2011-11-30

Family

ID=42606593

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2010101612416A Expired - Fee Related CN101804555B (zh) 2010-04-27 2010-04-27 大型过盈配合联轴器拆装更换的方法

Country Status (1)

Country Link
CN (1) CN101804555B (zh)

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102528381A (zh) * 2012-02-28 2012-07-04 绵阳华晨瑞安汽车零部件有限公司 过盈装配方法及设备
CN102962667A (zh) * 2012-04-24 2013-03-13 南车南京浦镇车辆有限公司 机械式联轴器拆卸方法
CN102962668A (zh) * 2012-04-24 2013-03-13 南车南京浦镇车辆有限公司 机械式联轴器退装机构
CN103056593A (zh) * 2012-12-14 2013-04-24 中国一冶集团有限公司 大型联轴器的装配方法
CN103627879A (zh) * 2013-11-25 2014-03-12 太原重工股份有限公司 齿圈与淬火定型工装的脱离装置
CN104227318A (zh) * 2013-06-12 2014-12-24 镇江兴达联轴器有限公司 大型联轴器的更换方法
CN105619315A (zh) * 2016-02-15 2016-06-01 于广平 一种热熔器模头及热熔管金属螺纹维修方法
CN106624737A (zh) * 2016-12-08 2017-05-10 钢城集团凉山瑞海实业有限公司 压球机辊子拆装装置
CN106737383A (zh) * 2016-11-23 2017-05-31 沈阳黎明航空发动机(集团)有限责任公司 一种不可拆卸转子中大过盈量配合盘轴装配方法
CN109531104A (zh) * 2019-01-17 2019-03-29 安徽海螺川崎装备制造有限公司 一种挤压辊辊套热拆装置及使用该装置的拆卸方法
CN110757342A (zh) * 2019-10-16 2020-02-07 南京钢铁股份有限公司 一种快速更换抛头的方法
CN111151991A (zh) * 2020-02-26 2020-05-15 安徽马钢设备检修有限公司 一种高压水泵曲轴连接齿轮的零件拆分装置及拆分方法
CN111360750A (zh) * 2020-03-10 2020-07-03 天津大学 一种柔性装配梅花联轴器的系统
CN113977232A (zh) * 2021-11-25 2022-01-28 哈尔滨汽轮机厂有限责任公司 一种过盈阀座的拆除方法

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU774895A2 (ru) * 1978-12-04 1980-10-30 Украинский Заочный Политехнический Институт Станок дл тепловой сборки и разборки деталей
SU1202776A1 (ru) * 1983-05-23 1986-01-07 Научно-Исследовательский Институт Тяжелого Машиностроения Производственного Объединения "Уралмаш" Стенд дл тепловой сборки внутренних колец подшипников с прокатными валками
CN201082500Y (zh) * 2007-10-12 2008-07-09 中冶京唐建设有限公司 电加热拆卸联轴器的装置
CN101462221A (zh) * 2007-12-21 2009-06-24 广东明阳风电技术有限公司 与长轴配合的调心滚子轴承的拆卸方法

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU774895A2 (ru) * 1978-12-04 1980-10-30 Украинский Заочный Политехнический Институт Станок дл тепловой сборки и разборки деталей
SU1202776A1 (ru) * 1983-05-23 1986-01-07 Научно-Исследовательский Институт Тяжелого Машиностроения Производственного Объединения "Уралмаш" Стенд дл тепловой сборки внутренних колец подшипников с прокатными валками
CN201082500Y (zh) * 2007-10-12 2008-07-09 中冶京唐建设有限公司 电加热拆卸联轴器的装置
CN101462221A (zh) * 2007-12-21 2009-06-24 广东明阳风电技术有限公司 与长轴配合的调心滚子轴承的拆卸方法

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
《矿山机械》 20091231 罗长才 提升机联轴器的现场更换 63 1-8 第37卷, 第24期 *

Cited By (18)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102528381A (zh) * 2012-02-28 2012-07-04 绵阳华晨瑞安汽车零部件有限公司 过盈装配方法及设备
CN102962667A (zh) * 2012-04-24 2013-03-13 南车南京浦镇车辆有限公司 机械式联轴器拆卸方法
CN102962668A (zh) * 2012-04-24 2013-03-13 南车南京浦镇车辆有限公司 机械式联轴器退装机构
CN102962667B (zh) * 2012-04-24 2015-03-04 南车南京浦镇车辆有限公司 机械式联轴器拆卸方法
CN103056593A (zh) * 2012-12-14 2013-04-24 中国一冶集团有限公司 大型联轴器的装配方法
CN103056593B (zh) * 2012-12-14 2015-12-23 中国一冶集团有限公司 大型联轴器的装配方法
CN104227318A (zh) * 2013-06-12 2014-12-24 镇江兴达联轴器有限公司 大型联轴器的更换方法
CN103627879A (zh) * 2013-11-25 2014-03-12 太原重工股份有限公司 齿圈与淬火定型工装的脱离装置
CN105619315A (zh) * 2016-02-15 2016-06-01 于广平 一种热熔器模头及热熔管金属螺纹维修方法
CN106737383A (zh) * 2016-11-23 2017-05-31 沈阳黎明航空发动机(集团)有限责任公司 一种不可拆卸转子中大过盈量配合盘轴装配方法
CN106624737A (zh) * 2016-12-08 2017-05-10 钢城集团凉山瑞海实业有限公司 压球机辊子拆装装置
CN109531104A (zh) * 2019-01-17 2019-03-29 安徽海螺川崎装备制造有限公司 一种挤压辊辊套热拆装置及使用该装置的拆卸方法
CN109531104B (zh) * 2019-01-17 2023-07-25 安徽海螺川崎装备制造有限公司 一种挤压辊辊套热拆装置及使用该装置的拆卸方法
CN110757342A (zh) * 2019-10-16 2020-02-07 南京钢铁股份有限公司 一种快速更换抛头的方法
CN111151991A (zh) * 2020-02-26 2020-05-15 安徽马钢设备检修有限公司 一种高压水泵曲轴连接齿轮的零件拆分装置及拆分方法
CN111360750A (zh) * 2020-03-10 2020-07-03 天津大学 一种柔性装配梅花联轴器的系统
CN111360750B (zh) * 2020-03-10 2023-12-26 天津大学 一种柔性装配梅花联轴器的系统
CN113977232A (zh) * 2021-11-25 2022-01-28 哈尔滨汽轮机厂有限责任公司 一种过盈阀座的拆除方法

Also Published As

Publication number Publication date
CN101804555B (zh) 2011-11-30

Similar Documents

Publication Publication Date Title
CN101804555B (zh) 大型过盈配合联轴器拆装更换的方法
CN107447667A (zh) 一种装配式盖梁模具及施工工艺
JP2010520321A (ja) コークス炉壁を取り換える方法、及び装置
CN105369002A (zh) 一种热风炉热风支管内衬修补工装及其修补方法
CN101900486A (zh) 多层焙烧炉砌筑方法及炉床更换方法
CN202607202U (zh) 一种油膜轴承装配与拆卸器具
CN202655402U (zh) 压力钢管圆度调整及支撑装置
CN202271152U (zh) 一种现场拆卸大型过盈联轴器的压力机
CN206986241U (zh) 一种提高齿轮nvh质量的齿轮热处理工装料架
CN104227318A (zh) 大型联轴器的更换方法
CN102312042B (zh) 一种抢修转炉耳轴轴承的方法
CN206794368U (zh) 四辊炉卷可逆轧机自动厚度控制装置的油缸更换装置
CN109385519B (zh) 铝锭推锭式加热炉的模块化安装方法
CN101608868A (zh) 一种可整体安装的阳极焙烧炉火道墙及其砌筑方法
CN211991688U (zh) 一种高压水泵曲轴连接齿轮的零件拆分装置
CN204265799U (zh) 大型薄壁回转体类铸钢件热处理工装
CN105921937A (zh) 一种重载模块的旋转变位装置
CN103056593A (zh) 大型联轴器的装配方法
CN203266041U (zh) 一种安装或拆卸滑履轴承轴瓦的装置
CN103322799B (zh) 环形炉烧嘴的耐火材料离线浇注方法
CN201313944Y (zh) 整体焙烧炉火道墙
CN219598643U (zh) 一种用于无缝钢管冷轧机环孔型的拆卸装置
CN105066701A (zh) 一种点火炉在线更换的方法
CN202240339U (zh) 双面翻转胎架
CN202963037U (zh) 一种用于更换板式轧机弯辊窜辊液压缸的台架

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
ASS Succession or assignment of patent right

Owner name: CHINA FIRST METALLURGICAL CONSTRUCTION GROUP CORPO

Free format text: FORMER OWNER: WUHAN CFMCGC ELECTRICAL AND MECHANICAL ENGINEERING CO., LTD.

Effective date: 20101210

C41 Transfer of patent application or patent right or utility model
TA01 Transfer of patent application right

Effective date of registration: 20101210

Address after: 430081 Wuhan Industrial Zone, Qingshan District, Hubei, No. 3

Applicant after: China First Metallurgical Group Co., Ltd.

Address before: 430081 Wuhan Industrial Zone, Qingshan District, Hubei, No. 3

Applicant before: Wuhan Yiye Machinery & Electronic Engineering Co., Ltd.

C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20111130

Termination date: 20200427

CF01 Termination of patent right due to non-payment of annual fee