CN101763939A - 干熄焦变压器安装方法 - Google Patents
干熄焦变压器安装方法 Download PDFInfo
- Publication number
- CN101763939A CN101763939A CN200810203329A CN200810203329A CN101763939A CN 101763939 A CN101763939 A CN 101763939A CN 200810203329 A CN200810203329 A CN 200810203329A CN 200810203329 A CN200810203329 A CN 200810203329A CN 101763939 A CN101763939 A CN 101763939A
- Authority
- CN
- China
- Prior art keywords
- transformer
- dry quenching
- coke dry
- installing
- tracks
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Landscapes
- Coke Industry (AREA)
Abstract
本发明涉及冶金电气设备安装领域,具体为一种干熄焦变压器安装方法。一种干熄焦变压器安装方法,其特征是,通过如下步骤依次进行:a.在变压器室(8)前用枕木(3)搭设临时吊装平台;b.在枕木(3)上敷设吊车走行轨道(2);c.在与吊车走行轨道(2)齐平的地方铺设变压器轨道(4);d.启动吊车(1),把变压器(7)吊至变压器轨道(4)上方,在变压器(7)下垫钢管(6);e.用手动葫芦(5)将变压器(7)平稳地沿吊车走行轨道(2)和变压器轨道(4)拉入变压器室(8)内,完成安装。本发明操作简单,安全可靠。
Description
技术领域
本发明涉及冶金电气设备安装领域,具体为一种干熄焦变压器安装方法。
背景技术
干法熄焦是目前世界上新诞生的一项冶炼节能技术,其英文名称为Coke Dry Quenching,简称CDQ。干熄焦是用循环惰性气体为热载体,由循环风机将冷的循环气体输入红焦冷却室冷却高温焦炭至250℃以下排出。吸收焦炭热量后的循环热气导入废热锅炉回收热量,产生蒸汽。循环气体冷却、除尘后,再经风机返回冷却室,如此循环冷却红焦。干熄焦锅炉产生的蒸汽或并入厂内蒸汽管网或送去发电。干熄焦技术是重大节能项目,由于在密闭系统内完成熄焦过程,与通常湿熄焦相比,可基本消除酚、HCN、H2S、NH3的排放,减少焦尘排放,且节省熄焦用水。干熄焦工程包括干熄焦本体、锅炉、除氧给水站、干熄焦除尘、发电系统、循环水泵房、操作室和控制室这几部分,其中变压器是发电系统中的重要一环,变压器的安装包括变压器基础的施工、附件安装和真空注油。但由于干熄焦技术属新兴领域,国内采用此法的单位仅有寥寥数家几家企业,对于干熄焦设备的安装还处在摸索阶段,存在着很多不科学、不合理的地方,安装过程复杂。
发明内容
为了克服现有技术的缺陷,提供一种安全可靠的电气设备安装方法,本发明公开了一种干熄焦变压器安装方法。
本发明通过如下技术方案达到发明目的:
一种干熄焦变压器安装方法,通过如下步骤依次进行:
a.在变压器室前用枕木搭设临时吊装平台;
b.在枕木上敷设吊车走行轨道;
c.在与吊车走行轨道齐平的地方铺设变压器轨道;
d.启动吊车,把变压器吊至变压器轨道上方,在变压器下垫钢管;
e.用手动葫芦将变压器平稳地沿吊车走行轨道和变压器轨道拉入变压器室内,完成安装。
所述的干熄焦变压器安装方法,在安装前,根据变压器的中心及标高,在变压器的基础上定出纵、横向中心线;变压器无锈蚀及机械损伤,密封应良好;油箱箱盖法兰及封板的连接螺栓应齐全,紧固良好;无渗漏。
本发明通过铺设齐平的吊车走行轨道和变压器轨道的方法,吊装时安全可靠,采用本发明的方法吊装干熄焦的变压器,操作简单,安全可靠。
附图说明
图1是本发明作业时的示意图。
具体实施方式
以下通过具体实施例进一步说明本发明。
实施例1
在一变压器室8内吊装变压器7,根据变压器7的中心及标高,在变压器7的基础上定出纵、横向中心线,以便于变压器就位。
检查变压器7的油箱及所有附件应齐全,应保证如下条件:无锈蚀及机械损伤,密封应良好;油箱箱盖法兰及封板的连接螺栓应齐全,紧固良好;无渗漏。需要抽芯检查的变压器,应进行抽芯检查。
安装变压器7,如图1所示,按如下步骤依次进行:
a.在变压器室8前用枕木3搭设临时吊装平台;
b.在枕木3上敷设吊车走行轨道2;
c.在与吊车走行轨道2齐平的地方铺设变压器轨道4;
d.启动吊车1,把变压器7吊至变压器轨道4上方,在变压器7下垫多个钢管6;
e.用手动葫芦5将变压器7平稳地沿吊车走行轨道2和变压器轨道4拉入变压器室8内,完成安装。
Claims (2)
1.一种干熄焦变压器安装方法,其特征是,通过如下步骤依次进行:
a.在变压器室(8)前用枕木(3)搭设临时吊装平台;
b.在枕木(3)上敷设吊车走行轨道(2);
c.在与吊车走行轨道(2)齐平的地方铺设变压器轨道(4);
d.启动吊车(1),把变压器(7)吊至变压器轨道(4)上方,在变压器(7)下垫钢管(6);
e.用手动葫芦(5)将变压器(7)平稳地沿吊车走行轨道(2)和变压器轨道(4)拉入变压器室(8)内,完成安装。
2.如权利要求1所述的干熄焦变压器安装方法,其特征是:在安装前,根据变压器(7)的中心及标高,在变压器(7)的基础上定出纵、横向中心线;变压器(7)无锈蚀及机械损伤,密封应良好;油箱箱盖法兰及封板的连接螺栓应齐全,紧固良好;无渗漏。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN200810203329A CN101763939A (zh) | 2008-11-25 | 2008-11-25 | 干熄焦变压器安装方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN200810203329A CN101763939A (zh) | 2008-11-25 | 2008-11-25 | 干熄焦变压器安装方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN101763939A true CN101763939A (zh) | 2010-06-30 |
Family
ID=42495041
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN200810203329A Pending CN101763939A (zh) | 2008-11-25 | 2008-11-25 | 干熄焦变压器安装方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN101763939A (zh) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102110520A (zh) * | 2010-12-30 | 2011-06-29 | 陕西化建工程有限责任公司 | 大型变压器安装、调试施工工艺 |
CN110428963A (zh) * | 2019-09-16 | 2019-11-08 | 刘敏洁 | 一种大型变压器安装吊搬机械及方法 |
-
2008
- 2008-11-25 CN CN200810203329A patent/CN101763939A/zh active Pending
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102110520A (zh) * | 2010-12-30 | 2011-06-29 | 陕西化建工程有限责任公司 | 大型变压器安装、调试施工工艺 |
CN110428963A (zh) * | 2019-09-16 | 2019-11-08 | 刘敏洁 | 一种大型变压器安装吊搬机械及方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102312024B (zh) | 一种冶金熔渣机械粒化和余热回收方法和系统 | |
CN102628586A (zh) | 一种利用钢渣余热发电的系统 | |
CN101763939A (zh) | 干熄焦变压器安装方法 | |
CN112076624B (zh) | 一种scr脱硝装置入口烟温调节系统及调节方法 | |
CN211199256U (zh) | 一种安全回收炉顶煤气的高炉休风装置 | |
CN204022749U (zh) | 一种在原有熄焦塔上改进的熄焦装置 | |
CN202581246U (zh) | 一种利用钢渣余热发电的系统 | |
CN103923668A (zh) | 一种在原有熄焦塔上改进的熄焦方法及装置 | |
CN108796155A (zh) | 高炉出铁场渣铁水余显热回收节能发电系统及发电方法 | |
CN106088214A (zh) | 一种电厂循环水系统的扩建方法 | |
CN109945291B (zh) | 空压机余热经太阳能再热洗浴和供热系统及其控制方法 | |
CN207210462U (zh) | 高炉出铁场渣铁水余显热回收节能发电系统 | |
CN214842698U (zh) | 钢厂冲砂水余热回收系统 | |
CN206916063U (zh) | 一种jn60型焦炉拦焦车炉门消烟平台装置 | |
CN103602343A (zh) | 一种干法熄焦系统 | |
CN216731619U (zh) | 一种核心机组拆装辅助装置 | |
CN101761701A (zh) | 干熄焦电缆桥架安装方法 | |
CN221005490U (zh) | 一种用于防止焦油池内焦油凝固的加热装置 | |
CN214891254U (zh) | 一种耐高温火力发电厂锅炉吹灰器 | |
CN113319112B (zh) | 一种土壤原位热脱附修复装置 | |
CN220205392U (zh) | 一种蒸汽凝结水伴热煤气排水器系统 | |
CN109504404B (zh) | 一种智能全密闭湿法熄焦及综合回收利用设备 | |
CN208995436U (zh) | 一种熄焦车防护装置 | |
CN204981934U (zh) | 共梯式转炉煤气干法除尘放散烟囱 | |
CN206143093U (zh) | 一种精馏废水回收系统 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C02 | Deemed withdrawal of patent application after publication (patent law 2001) | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20100630 |