CN101761338B - 一种固体充填采煤半断面单腿棚沿空留巷方法 - Google Patents
一种固体充填采煤半断面单腿棚沿空留巷方法 Download PDFInfo
- Publication number
- CN101761338B CN101761338B CN201010126430XA CN201010126430A CN101761338B CN 101761338 B CN101761338 B CN 101761338B CN 201010126430X A CN201010126430X A CN 201010126430XA CN 201010126430 A CN201010126430 A CN 201010126430A CN 101761338 B CN101761338 B CN 101761338B
- Authority
- CN
- China
- Prior art keywords
- filling
- gob
- coal
- coal mining
- mining
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 239000003245 coal Substances 0.000 title claims abstract description 47
- 238000005065 mining Methods 0.000 title claims abstract description 41
- 238000000034 method Methods 0.000 title claims abstract description 13
- 239000007787 solid Substances 0.000 title claims abstract description 9
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 22
- 239000010959 steel Substances 0.000 claims abstract description 22
- XEEYBQQBJWHFJM-UHFFFAOYSA-N Iron Chemical compound [Fe] XEEYBQQBJWHFJM-UHFFFAOYSA-N 0.000 claims description 32
- 229910052742 iron Inorganic materials 0.000 claims description 15
- 238000000605 extraction Methods 0.000 claims description 6
- 230000003014 reinforcing effect Effects 0.000 claims description 4
- 239000002184 metal Substances 0.000 abstract 2
- 238000005516 engineering process Methods 0.000 description 5
- 238000010586 diagram Methods 0.000 description 3
- 238000010276 construction Methods 0.000 description 2
- FGRBYDKOBBBPOI-UHFFFAOYSA-N 10,10-dioxo-2-[4-(N-phenylanilino)phenyl]thioxanthen-9-one Chemical compound O=C1c2ccccc2S(=O)(=O)c2ccc(cc12)-c1ccc(cc1)N(c1ccccc1)c1ccccc1 FGRBYDKOBBBPOI-UHFFFAOYSA-N 0.000 description 1
- 238000013459 approach Methods 0.000 description 1
- 238000009412 basement excavation Methods 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000015572 biosynthetic process Effects 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000005755 formation reaction Methods 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 238000012856 packing Methods 0.000 description 1
- 238000011084 recovery Methods 0.000 description 1
- 238000009423 ventilation Methods 0.000 description 1
- 230000003245 working effect Effects 0.000 description 1
Images
Landscapes
- Devices Affording Protection Of Roads Or Walls For Sound Insulation (AREA)
Abstract
一种固体充填采煤半断面单腿棚沿空留巷方法,包括巷道实体煤侧及顶板支护,在充填采煤工作面后方用采煤充填液压支架和充填开采输送机对采空区进行充填,然后在工作面端头顶板距采空区1/3处沿巷道走向用锚杆和锚索固定一排H型钢;随着采煤充填液压支架前移一个步距,先在采空区外侧铺设金属网并架设侧墙工字钢;同时在顶板距采空区1/3内铺设金属网,然后架设顶梁工字钢,使之形成“Г”形单腿棚钢结构支撑体;随着采煤充填液压支架的前移,在侧墙工字钢之间采用钢筋连接固定,使单腿棚钢结构支撑体连成片,配合巷道实体煤侧及顶板支护实现充填开采工作面回采巷道的沿空留巷。其方法简单,支护强度高,造价低,易实施,效率高。
Description
技术领域
本发明涉及一种固体充填采煤半断面单腿棚沿空留巷方法,尤其适用于充填采煤工作面无煤柱沿空留巷。
背景技术
随着固体充填采煤技术逐渐发展,解放了“三下”压煤,提高矿井资源采出率,实现了矿区资源与环境协调开采的需要。但充填采煤中上下区段两回采工作面间的护巷煤柱留设宽度为20~30m,造成了大量煤炭资源的损失,已成为提高充填采煤技术中煤炭资源回采率的瓶颈。现有沿空留巷方法及相关专利技术大多数是在常规采煤作业的基础上采用巷旁充填技术进行的,施工工艺复杂,需耗费较多的人力物力,且此种方式会造成工序间相互影响非常严重,工作效率低。
发明内容
技术问题:本发明的目的是提供一种方法简单,施工方便,省时省力,工作效率高,并具有较强支撑力的固体充填采煤半断面单腿棚沿空留巷方法。
技术方案:本发明的固体充填采煤半断面单腿棚沿空留巷方法,包括巷道实体煤侧及顶板支护,在充填采煤工作面后方用采煤充填液压支架和充填开采输送机对采空区进行充填,还包括以下步骤:
a、在工作面端头顶板距采空区1/3处沿巷道走向用锚杆和锚索固定一排H型钢;
b、随着采煤充填液压支架前移一个步距,在采空区外侧先铺设金属网,然后架设侧墙工字钢;
c、在顶板距采空区1/3内先铺设金属网,然后架设与H型钢成直角相连的顶梁工字钢,使之形成“Γ”形单腿棚钢结构支撑体;
d、随着采煤充填液压支架的前移,在侧墙工字钢之间采用钢筋连接固定,使单腿棚钢结构支撑体连成片,并配合巷道实体煤侧及顶板支护实现充填开采工作面回采巷道的沿空留巷。
有益效果:本发明解决了“三下”压煤及上下区段两回采工作面间的煤柱损失,大大提高了煤炭资源的回采率,既能为本工作面增加了一条安全通道,又能为下个工作面准备一条回采巷道,既能节省巷道掘进费用,又能缓解矿井采掘失调和接续紧张状况,同时又为高瓦斯工作面提供了“Y”型通风的条件,且在采空区充填的基础上留巷难度低,而且为我国类似条件下“三下”压煤的“规模性”开采开创了一条新的技术途径,其方法简单,操作简便,造价低,易实施,工期短,效率高,具有广泛的实用性。
附图说明
图1是本发明的工作面布置示意图;
图2是图1的A-A结构沿空留巷支护示意图;
图3是图2的沿空留巷支护结构俯视示意图;
图4是图1的B-B结构沿空留巷支护侧视示意图。
图中:1-充填采煤工作面,2-充填液压支架,3-充填开采输送机,4-采空区,5-锚杆,6-锚索,7-H型钢,8-侧墙工字钢,9-顶梁工字钢,10-钢筋,11-金属网,12-支护,13-充填体。
具体实施方式
图1所示为采煤工作面布置示意图,在充填采煤工作面1的后方布置采煤充填液压支架2,并对工作面的实体煤侧及巷道用锚杆实施顶板支护12,随着采煤工作面的推进,通过充填开采输送机3对采空区4进行充填,同时在工作面端头顶板距采空区1/3处沿巷道走向采用间距约为2500mm、Φ22×2200mm的锚杆5和Φ17.8×6500mm的锚索6间插固定一排H型钢7,图2所示,H型钢7的尺寸为100×100mm;随着采煤充填液压支架2前移一个步距,常规的一个步距约为0.6米。先在在采空区外侧铺设一段金属网11,图4所示;然后架设侧墙工字钢8;再在顶板距采空区1/3内铺设金属网11,然后架设与H型钢7成直角相连的顶梁工字钢9,顶梁工字钢9一端固定在侧墙工字钢8上,另一端嵌入H型钢7中,图3所示;侧墙工字钢8与顶梁工字钢9连接形成“Γ”形单腿钢结构;随着采煤充填液压支架2的不断前移,与H型钢7、金属网11共同构成单腿棚钢结构支撑体,为保证侧墙体的坚固性,在布设的侧墙工字钢8之间采用钢筋10将其相互固定连接,根据实际情况,固定连接的钢筋10为是一排、二排或三排。使单腿棚钢结构支撑体连成片,单腿棚钢结构支撑体配合巷道实体煤侧及顶板支护12,共同构成充填采煤沿空留巷的支护系统,实现充填开采工作面回采巷道的沿空留巷,不仅对充填体13构成坚实的防护墙,同时保证沿巷道的安全。
Claims (1)
1.一种固体充填采煤半断面单腿棚沿空留巷方法,包括巷道实体煤侧的支护及顶板支护,在充填采煤工作面(1)后方用采煤充填液压支架(2)和充填开采输送机(3)对采空区(4)进行充填,其特征是还包括以下步骤:
a、在工作面端头顶板距采空区1/3处沿巷道走向用锚杆(5)和锚索(6)固定一排H型钢(7);
b、随着采煤充填液压支架(2)前移一个步距,在采空区外侧先铺设金属网(11),然后架设侧墙工字钢(8);
c、在顶板距采空区1/3内先铺设金属网(11),然后架设与H型钢(7)成直角相连的顶梁工字钢(9),使之形成“Γ”形单腿棚钢结构支撑体;
d、随着采煤充填液压支架(2)的前移,在侧墙工字钢(8)之间采用钢筋(10)连接固定,使单腿棚钢结构支撑体连成片,并配合巷道实体煤侧及顶板支护(12)实现充填开采工作面回采巷道的沿空留巷。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201010126430XA CN101761338B (zh) | 2010-03-13 | 2010-03-13 | 一种固体充填采煤半断面单腿棚沿空留巷方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201010126430XA CN101761338B (zh) | 2010-03-13 | 2010-03-13 | 一种固体充填采煤半断面单腿棚沿空留巷方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN101761338A CN101761338A (zh) | 2010-06-30 |
CN101761338B true CN101761338B (zh) | 2011-09-14 |
Family
ID=42492706
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201010126430XA Expired - Fee Related CN101761338B (zh) | 2010-03-13 | 2010-03-13 | 一种固体充填采煤半断面单腿棚沿空留巷方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN101761338B (zh) |
Families Citing this family (19)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102182482A (zh) * | 2011-04-25 | 2011-09-14 | 义马煤业集团股份有限公司跃进煤矿 | 防冲复合抗压支护系统 |
CN102155260B (zh) * | 2011-05-23 | 2012-11-28 | 中国矿业大学 | 一种急倾斜煤层采空区充填方法 |
CN102383857A (zh) * | 2011-07-05 | 2012-03-21 | 徐州贝壳迈宁矿业科技有限公司 | 一种固体充填采煤垒砌矸石墙沿空留巷工艺 |
CN102425417A (zh) * | 2011-09-23 | 2012-04-25 | 西安建筑科技大学 | 易冒顶板锚索毛石墙联合沿空留巷方法 |
CN102444419A (zh) * | 2011-12-31 | 2012-05-09 | 山东科技大学 | 一种薄煤层破碎顶板拖管式充填系统 |
CN102852550B (zh) * | 2012-04-01 | 2015-03-04 | 中国矿业大学 | 一种无煤柱半原位沿空留巷方法 |
CN102877845B (zh) * | 2012-08-30 | 2014-10-29 | 中国矿业大学 | 一种确定断层区采煤机自动割煤轨迹的方法 |
CN103266903B (zh) * | 2013-05-17 | 2016-04-20 | 安徽理工大学 | 一种防冒顶片帮的支护方法 |
CN103422870B (zh) * | 2013-07-26 | 2015-09-16 | 王绍华 | 特厚煤层采全高顶板支护方法 |
CN103470286A (zh) * | 2013-09-25 | 2013-12-25 | 四川省煤炭产业集团有限责任公司 | 一种采用条带钢筋网拦截自溜矸石支护的沿空留巷方法 |
CN104061001B (zh) * | 2014-06-25 | 2016-09-07 | 枣庄矿业(集团)有限责任公司滨湖煤矿 | 沿空留巷开采支护工艺方法 |
CN104088662B (zh) * | 2014-06-25 | 2016-08-31 | 中国矿业大学 | 一种固体充填采煤沿空留巷支护墙体的施工方法 |
CN104847387A (zh) * | 2015-05-28 | 2015-08-19 | 四川川煤华荣能源股份有限公司大宝顶煤矿 | 巷帮固结留巷的施工方法 |
CN106050283B (zh) * | 2016-05-14 | 2018-02-06 | 西安科技大学 | 一种三软煤层回采巷道支护设计方法及装置 |
CN106121676A (zh) * | 2016-08-26 | 2016-11-16 | 百色百矿集团有限公司 | 一种用于沿空留巷护巷的支护结构及其支护方法 |
CN109812269A (zh) * | 2018-12-27 | 2019-05-28 | 天地科技股份有限公司 | 一种适用于复采工作面的无煤柱开采方法 |
CN113719285B (zh) * | 2021-09-23 | 2023-08-22 | 太原理工大学 | 一种综采放顶煤工作面堆喷混凝土沿空留巷方法 |
CN114263494B (zh) * | 2021-11-10 | 2022-09-06 | 中国矿业大学(北京) | 一种端头充填维护下位巷道顶板稳定结构及其充填方法 |
CN114060069B (zh) * | 2021-12-10 | 2023-09-12 | 国家能源投资集团有限责任公司 | 一种浅埋深煤矿的采空区预支护作业方法 |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB758697A (en) * | 1953-10-17 | 1956-10-10 | Gutehoffnungshuette Sterkrade | Improvements in a yieldable mining support structure |
CN201045298Y (zh) * | 2007-04-05 | 2008-04-09 | 四川华蓥山广能(集团)有限责任公司 | 一种大倾角煤层巷道锚棚支架 |
CN101457651A (zh) * | 2008-11-19 | 2009-06-17 | 淮南矿业(集团)有限责任公司 | 煤气共采y型通风系统中沿空留巷的充填垛超前支护方法 |
-
2010
- 2010-03-13 CN CN201010126430XA patent/CN101761338B/zh not_active Expired - Fee Related
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB758697A (en) * | 1953-10-17 | 1956-10-10 | Gutehoffnungshuette Sterkrade | Improvements in a yieldable mining support structure |
CN201045298Y (zh) * | 2007-04-05 | 2008-04-09 | 四川华蓥山广能(集团)有限责任公司 | 一种大倾角煤层巷道锚棚支架 |
CN101457651A (zh) * | 2008-11-19 | 2009-06-17 | 淮南矿业(集团)有限责任公司 | 煤气共采y型通风系统中沿空留巷的充填垛超前支护方法 |
Non-Patent Citations (4)
Title |
---|
万力.岱河煤矿沿空留巷技术研究.《矿业快报》.2008,(第10期),62-64. * |
张东升,马立强,冯光明,缪协兴.综放巷内充填原位沿空留巷技术.《岩石力学与工程学报》.2005,第24卷(第7期),1164-1168. * |
黄玉海."三软"煤层沿空留巷技术的应用.《华北科技学院学报》.2005,第2卷(第2期),40-41,45. |
黄玉海."三软"煤层沿空留巷技术的应用.《华北科技学院学报》.2005,第2卷(第2期),40-41,45. * |
Also Published As
Publication number | Publication date |
---|---|
CN101761338A (zh) | 2010-06-30 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101761338B (zh) | 一种固体充填采煤半断面单腿棚沿空留巷方法 | |
CN103410515B (zh) | 一种三软煤层往复式无煤柱综采方法 | |
CN101864987B (zh) | 一种大倾角煤层沿空留巷充填墙体的构筑方法 | |
CN101514633B (zh) | 无巷旁支护的沿空留巷工艺 | |
CN102661169B (zh) | 一种用于无煤柱开采的锚栓网矸石袋墙体沿空留巷方法 | |
CN100577986C (zh) | 三软地质条件下采空区留巷围岩支护方法 | |
CN202064981U (zh) | 软煤层巷道支护结构 | |
CN103233751B (zh) | 极软弱顶板煤巷双层锚固平衡拱支护系统 | |
CN104061001B (zh) | 沿空留巷开采支护工艺方法 | |
CN102383857A (zh) | 一种固体充填采煤垒砌矸石墙沿空留巷工艺 | |
CN104533482A (zh) | 一种提高沿空掘巷小煤柱稳定性的加固方法 | |
CN102278140A (zh) | 一种固体充填采煤垒砌矸石墙沿空留巷法 | |
CN103147793B (zh) | 薄煤层巷旁充填无煤柱护巷方法 | |
CN110821537B (zh) | 一种综采工作面预掘单回撤通道支护方法 | |
CN104074534B (zh) | 一种综采/综放工作面的沿空留巷方法 | |
CN103758529A (zh) | 一种煤矿沿空留巷巷旁支护方法 | |
CN206000543U (zh) | 一种用于沿空留巷护巷的支护结构 | |
CN105003288A (zh) | 一种中厚煤层沿空留巷的方法和支护系统 | |
CN104863588A (zh) | 超前预设墩柱沿空留巷方法 | |
CN205172609U (zh) | 一种巷道非对称支护装置 | |
CN101936172A (zh) | 采动期间巷道底鼓治理方法 | |
CN104405392A (zh) | 三软厚煤层巷道托顶留底锚网索主动支护综放开采方法 | |
CN204984458U (zh) | 一种中厚煤层沿空留巷的支护系统 | |
CN203978443U (zh) | 一种沿空留巷的支护装置 | |
CN107939419A (zh) | 一种巷道u型钢套棚支护结构 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20110914 Termination date: 20170313 |
|
CF01 | Termination of patent right due to non-payment of annual fee |