CN101736730A - Mixed reinforcement method of high-fill sand foundation - Google Patents

Mixed reinforcement method of high-fill sand foundation Download PDF

Info

Publication number
CN101736730A
CN101736730A CN200810305374A CN200810305374A CN101736730A CN 101736730 A CN101736730 A CN 101736730A CN 200810305374 A CN200810305374 A CN 200810305374A CN 200810305374 A CN200810305374 A CN 200810305374A CN 101736730 A CN101736730 A CN 101736730A
Authority
CN
China
Prior art keywords
pile
foundation
reinforcement method
sand foundation
jet grouting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN200810305374A
Other languages
Chinese (zh)
Inventor
高晰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guiyang Aluminum Magnesium Design and Research Institute Co Ltd
Original Assignee
Guiyang Aluminum Magnesium Design and Research Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guiyang Aluminum Magnesium Design and Research Institute Co Ltd filed Critical Guiyang Aluminum Magnesium Design and Research Institute Co Ltd
Priority to CN200810305374A priority Critical patent/CN101736730A/en
Publication of CN101736730A publication Critical patent/CN101736730A/en
Pending legal-status Critical Current

Links

Images

Abstract

The invention discloses a mixed reinforcement method of high-fill sand foundation, comprising the following steps: 1. adopting a pounder free-falling body to punch for forming a pore, adding filler into the pore by layers for tamping to form a tamping compacted zone; 2. arranging a high-pressure jet grouting pile in a non-compacted zone to form a rigid cement pile body. The pole distribution space of punching pore forming is as follows: a=3.5-4.5 m; the length of the jet grouting pile is 1/2-2/3 of foundation reinforcing depth; and the diameter of the jet grouting pile is as follows: d=0.6-0.8 m. The invention can improve the bearing capacity of the sand foundation by replacing forced ramming in pores, ensures the stability of the foundation by the jet grouting pile, has convenient construction and saves investment.

Description

Mixed reinforcement method of high-fill sand foundation
Technical field
The present invention relates to a kind of method of reinforcing high-fill sand foundation.
Background technology
China's " building lot treatment technology standard " provides the multiple reinforcement means that is applicable to sand foundation, wherein the sand of indication is natural formation, water content is higher, silt that bearing capacity is lower or fine sand soil layer, and the purpose of reinforcing generally is to improve the bearing capacity of foundation soil and eliminate liquefaction.For the darker high fill foundation of sand backfill, because the water content of backfill sand is little, also looser, the sand-gravel pile of recommending in the general code requirement, lime-soil compaction pile, high-pressure slip-casting and the dynamic compaction reinforced processing of displacement, but the effect that adopts independent a kind of method to handle is all relatively poor, reason is that the water content of backfill sand is low, because its internal friction is big, influenced the compacted effect of soil, and the soil body scope that above-mentioned first three methods can be compacted is very little, so the cloth pitch of holes is also very little, be generally 1m~1.5m, therefore the closeer quantity in cloth hole is many, and construction quality is difficult for guaranteeing that the ground stabilization expense is also higher.If adopt the 4th kind of method to handle separately, then bearing capacity of foundation soil can meet the demands, but the stability of ground can not meet the demands.
Summary of the invention
The technical problem to be solved in the present invention is: a kind of mixed reinforcement method of high-fill sand foundation is provided, this method can improve the bearing capacity of sand foundation, and construction quality that prior art exists is difficult for guaranteeing or the ground stabilization expense is higher, the deficiency of foundation stability difference to overcome.
Basic technical scheme of the present invention is: adopt strong rammer of displacement and high-pressure rotary jet grouting pile reinforcing fill sand foundation in the hole.
Adopt the strong rammer of displacement in the hole, compacted looser sand, form more closely knit compacted district in the hole peripheral extent, because the sand internal friction is bigger, make the compacted effect of soil be obstructed and can outside compacted district, form non-compacted district, this regional sand density is poor, lateral deformation constraint to the compacted district soil body is little, under the outer load effect, lateral deformation can take place in the soil body in compacted district, produces foundation instability and destroys.Therefore in non-encrypted area, adopt high-pressure rotary jet grouting pile, the construction of rotary churning pile has compacted effect to this regional soil body, the more important thing is that the formed concrete stake of rotary churning pile belongs to rigid pile, pile body can play the effect of restriction soil lateral, has prevented the lateral deformation unstability of sand.
The present invention compared with prior art, the present invention guarantees the stability of ground by the strong bearing capacity that rams the raising sand foundation of displacement in the hole by rotary churning pile; Investment is saved in easy construction.
Description of drawings
Fig. 1 is a schematic diagram of the present invention;
Fig. 2 is the A Abandon sectional view among Fig. 1.
The specific embodiment
Embodiments of the invention: it comprises following process:
The first, adopt hammer ram freely falling body impact holing, the filled compacting of layering in the hole forms the closely knit compacted district of compacting; The second, arrange high-pressure rotary jet grouting pile in non-compacted district, form rigidity cement pile body.
The cloth pitch of holes a=3.5m~4.5m of impact holing;
The length H1 of rotary churning pile is the ground stabilization degree of depth (1/2~2/3), i.e. H1=(1/2~2/3) H;
Diameter d=the 0.6m of rotary churning pile~0.8m.
Characteristics of the present invention:
1) owing in the process of impact holing and backfill compacting, periphery soil is had stronger compacted effect, so the foundation bearing capacity after reinforcing is higher, formed compacted district scope is bigger, and the spacing α that therefore impacts the cloth hole is also bigger, is generally 3.5m~4.5m.
2) filler can be gathered materials on the spot in the hole, and plain soil, sand, sandstone and building waste all are good filler, and be cheap, saves investment, and the building waste of particularly may dissolving has good protective effect to environment;
3) quantity of rotary churning pile is few, easy construction, and the pile length H of rotary churning pile1Can be littler than calculating required ground processing depth H, saved investment.

Claims (4)

1. mixed reinforcement method of high-fill sand foundation, it is characterized in that: it comprises following process: the first, adopt hammer ram freely falling body impact holing, the filled compacting of layering in the hole forms the closely knit compacted district of compacting; The second, arrange high-pressure rotary jet grouting pile in non-compacted district, form rigidity cement pile body.
2. mixed reinforcement method of high-fill sand foundation according to claim 1 is characterized in that: the cloth pitch of holes a=3.5m~4.5m of impact holing.
3. mixed reinforcement method of high-fill sand foundation according to claim 1 is characterized in that: the length H1 of rotary churning pile is 1/2~2/3 of a ground stabilization depth H.
4. mixed reinforcement method of high-fill sand foundation according to claim 1 is characterized in that: the diameter d=0.6m of rotary churning pile~0.8m.
CN200810305374A 2008-11-04 2008-11-04 Mixed reinforcement method of high-fill sand foundation Pending CN101736730A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN200810305374A CN101736730A (en) 2008-11-04 2008-11-04 Mixed reinforcement method of high-fill sand foundation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN200810305374A CN101736730A (en) 2008-11-04 2008-11-04 Mixed reinforcement method of high-fill sand foundation

Publications (1)

Publication Number Publication Date
CN101736730A true CN101736730A (en) 2010-06-16

Family

ID=42460716

Family Applications (1)

Application Number Title Priority Date Filing Date
CN200810305374A Pending CN101736730A (en) 2008-11-04 2008-11-04 Mixed reinforcement method of high-fill sand foundation

Country Status (1)

Country Link
CN (1) CN101736730A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102561364A (en) * 2012-01-20 2012-07-11 山西机械化建设集团公司 'Three-step three-layer method' landfill filling construction process of dimension stone high-fill dynamic compaction treatment foundation
CN103758109A (en) * 2014-01-13 2014-04-30 东南大学 Arrangement and processing method for long firm and oil solidated water draining chemical churning pile foundation
CN104929009A (en) * 2015-06-04 2015-09-23 苏州金螳螂园林绿化景观有限公司 Method for preventing ground of square from subsiding
CN105155505A (en) * 2015-08-21 2015-12-16 四川九鼎智远知识产权运营有限公司 Construction method for rigid pile composite foundation
CN112030932A (en) * 2020-09-14 2020-12-04 大地巨人(北京)工程科技有限公司 Dynamic compaction pile composite foundation treatment method

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102561364A (en) * 2012-01-20 2012-07-11 山西机械化建设集团公司 'Three-step three-layer method' landfill filling construction process of dimension stone high-fill dynamic compaction treatment foundation
CN102561364B (en) * 2012-01-20 2014-05-07 山西机械化建设集团公司 'Three-step three-layer method' landfill filling construction process of dimension stone high-fill dynamic compaction treatment foundation
CN103758109A (en) * 2014-01-13 2014-04-30 东南大学 Arrangement and processing method for long firm and oil solidated water draining chemical churning pile foundation
CN103758109B (en) * 2014-01-13 2015-08-26 东南大学 For setting and the processing method of the draining rotary churning pile ground of underconsolidated soil
CN104929009A (en) * 2015-06-04 2015-09-23 苏州金螳螂园林绿化景观有限公司 Method for preventing ground of square from subsiding
CN104929009B (en) * 2015-06-04 2017-05-10 苏州金螳螂园林绿化景观有限公司 Method for preventing ground of square from subsiding
CN105155505A (en) * 2015-08-21 2015-12-16 四川九鼎智远知识产权运营有限公司 Construction method for rigid pile composite foundation
CN112030932A (en) * 2020-09-14 2020-12-04 大地巨人(北京)工程科技有限公司 Dynamic compaction pile composite foundation treatment method

Similar Documents

Publication Publication Date Title
CN101440622B (en) CFG pile, pipe pile embankment reinforcement system and construction method thereof
CN101463599A (en) Bidirectional reinforcing and water drainage reinforcing means for highway soft soil foundation
CN103711114A (en) Foundation treatment method
CN101343874A (en) Wrapping pile
CN210288333U (en) Deep foundation treatment structure
CN101736738A (en) Pressure resistance and pull-out resistance grouted gravel pile
CN103321203B (en) Taper hammer ram brute force develops a method
CN101736730A (en) Mixed reinforcement method of high-fill sand foundation
CN102888834A (en) Construction method of large-diameter crushed stone pile
CN107859041A (en) The construction method of collapsible loess zanjon high roadbed structure
CN101575848A (en) Method for treating foundation by combined hammers
CN112195910A (en) Soft foundation treatment structure and construction method for earth-rock dam reinforced by vibroflotation gravel pile and rockfill
CN202787222U (en) Deep stratum reinforcement rammer
CN102251514A (en) Multi-section type variable cross-section dynamic compaction method
CN213390201U (en) Earth-rock dam soft foundation treatment structure with reinforced vibro-replacement gravel pile and rockfill
CN108824412A (en) Based on gabion wall reinforced earth and strong tamping combined soft base processing method
CN110172980A (en) A kind of coarse grain block stone superelevation fill foundation ruggedized construction and its construction method
CN1740457A (en) Vibration process of eliminating wet foundation falling for CFG pile
CN203007761U (en) Grouting reinforcement structure for steel floral tube of existing railway roadbed under operation condition
CN216075211U (en) Combined pile system for treating deep collapsible loess foundation
CN209760216U (en) reinforcement system based on soft soil foundation drainage consolidation
CN104652407B (en) A kind of band stirrup collapsible geosynthetics abnormity granular pile and construction method thereof
CN201981530U (en) Down hole deep dynamic compaction pile in collapsible loess area
CN1095517C (en) Method for reinforcement of foundation ground
CN102535429A (en) Combined-rammer construction technology for foundation treatment

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20100616