CN108824412A - Based on gabion wall reinforced earth and strong tamping combined soft base processing method - Google Patents
Based on gabion wall reinforced earth and strong tamping combined soft base processing method Download PDFInfo
- Publication number
- CN108824412A CN108824412A CN201810777345.6A CN201810777345A CN108824412A CN 108824412 A CN108824412 A CN 108824412A CN 201810777345 A CN201810777345 A CN 201810777345A CN 108824412 A CN108824412 A CN 108824412A
- Authority
- CN
- China
- Prior art keywords
- gabion
- gabion wall
- processing method
- tamping
- soil
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D3/00—Improving or preserving soil or rock, e.g. preserving permafrost soil
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D3/00—Improving or preserving soil or rock, e.g. preserving permafrost soil
- E02D3/02—Improving by compacting
- E02D3/046—Improving by compacting by tamping or vibrating, e.g. with auxiliary watering of the soil
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D3/00—Improving or preserving soil or rock, e.g. preserving permafrost soil
- E02D3/02—Improving by compacting
- E02D3/08—Improving by compacting by inserting stones or lost bodies, e.g. compaction piles
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D3/00—Improving or preserving soil or rock, e.g. preserving permafrost soil
- E02D3/12—Consolidating by placing solidifying or pore-filling substances in the soil
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- Structural Engineering (AREA)
- Agronomy & Crop Science (AREA)
- Environmental & Geological Engineering (AREA)
- Soil Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)
Abstract
The present invention is a kind of based on gabion wall reinforced earth and strong tamping combined soft base processing method, including:1)Gabion wall guide groove is excavated using excavator;2)It will be put under grid gabion by stone material sold stowing in gabion wall guide groove, and be built into gabion wall;3)With tamping machine compaction in layers by the soil body of the enclosed Soft Soil Area of gabion wall and to designed elevation;4)Leveling compacting treated soil layer surface, is laid with Application of geosynthetics-reinforced bed course;5)In gabion cement injection mortar within the walls;6)After being perfused and completing 6-9 days, consolidation effect is examined using static load test.The present invention provides one kind can improve foundation bearing capacity, reduces settlement of foundation, it is capable of the protuberance deformation in limit levels direction again, be conducive to accelerate to apply the soil body discharging consolidation for ramming place, to improve the gabion wall reinforced earth and strong tamping combined soft base processing method of foundation soil strength.With comprehensive effectivenesses such as carrying, draining, strong rammer, reinforcements, mechanization of building operation degree is high, can be obviously shortened the duration.
Description
Technical field
The invention belongs to Soft Soil Subgrade Treatment Techniques fields, are related to a kind of based on gabion wall reinforced earth and strong tamping combined
Soft base processing method.
Background technique
With the fast development of Chinese national economy, country continues to increase infrastructure construction, China's highway,
Railway construction achieves fast development, and soft soil foundation problem becomes increasingly conspicuous, it has also become influences construction quality, completion time of project and engineering
One of key factor of cost.Traditional large-area soft foundation processing method mainly has by increasing compactive effort come to weak soil
The heavy-tamping method for carrying out the closely knit processing of deep layer is passed the load on top using stake using the preloading method for the discharging consolidation for accelerating weak soil
It is delivered to the pile-making method of supporting course, controls the differential settlement of ground using geosynthetics (TGXG or geotechnical grid)
Reinforcement method, and the method that above method is combined.The topography in mountain area cheuch area is low, impeded drainage, by long-term
Ponding, foundation soil be often have the characteristics that high-compressibility, low bearing capacity, high liquid limit weak soil, being unevenly distributed of weak soil, soil nature
Also complex.Simultaneously as the particularity in cheuch area geographical location, is unfavorable for mechanical disengaging, raw material and electric power
Supply, is unsuitable for carrying out large-scale construction operation.Although there are many methods for being used for Soft Ground, carried out to it
When improvement, using above-mentioned conventional method because of the reasons such as long in time limit, cost is high, depth is limited for processing, settlement after construction is difficult to control,
Effect is not obvious during processing mountain area soft base.
Summary of the invention
In order to solve the above technical problems in background technology, the present invention provides one kind can improve foundation bearing
Power reduces uneven settlement of foundation and sedimentation, but be capable of limit levels direction protuberance deformation based on gabion wall reinforced earth with
And strong tamping combined soft base processing method.
To achieve the goals above, the present invention adopts the following technical scheme that:
It is a kind of based on gabion wall reinforced earth and strong tamping combined soft base processing method, include the following steps:
1) gabion wall guide groove is excavated using excavator;The gabion wall guide groove is arranged in regular quadrangle;
2) it will be put under the grid gabion by stone material sold stowing in the gabion wall guide groove that step 1) is excavated, and be built into stone
Cage wall;
3) with tamping machine compaction in layers by the soil body of the enclosed Soft Soil Area of gabion wall and to designed elevation;
4) leveling compacting treated soil layer surface, is laid with Application of geosynthetics-reinforced bed course, and by geosynthetics
Reinforcement cushion is anchored into gabion within the walls;
5) in gabion, cement injection mortar, composition stabilization zone undertake upper load together with foundation soil within the walls.
Preferably, method provided by the present invention further includes after step 5):
6) after being perfused and completing 6-9 days, consolidation effect is examined using static load test, power to be lifted meets design requirement
Afterwards, upper part work construction is carried out.
Preferably, the specific implementation of step 3) of the present invention is:
In by the enclosed Soft Soil Area of gabion wall, is rammed with tamping machine and extremely controlled by the soil body of the enclosed Soft Soil Area of gabion wall for the first time
It after depth, bankets into tamping pit, is rammed for the second time after tamping pit is filled up;Crater depth to ram for the second time reaches control
After depth, then soil is filled up into tamping pit, then carry out third time and ram, until reaching designed elevation in such a way that this is tamped.
Preferably, Application of geosynthetics-reinforced bed course layering of the present invention is spaced, rubble is two-way to be laid on leveling
Compacting treated soil layer surface, and anchor into gabion within the walls.
Preferably, the thickness of Application of geosynthetics-reinforced bed course of the present invention takes 400~500mm.
Preferably, the specific implementation anchored in step 4) of the present invention is:In geosynthetics plus
At the end anchorage of muscle bed course, by geosynthetics employed in Application of geosynthetics-reinforced bed course with the side of anti-package inflection
Formula is anchored, and anchor bar is laid.
Preferably, the partial size of rubble employed in Application of geosynthetics-reinforced bed course of the present invention is 20-
50mm, clay content is not more than 5% in rubble.
Preferably, cement mortar employed in step 5) of the present invention is M30 mortar.
It is an advantage of the invention that:
Include based on gabion wall reinforced earth and strong tamping combined soft base processing method, this method the present invention provides a kind of
1) gabion wall guide groove is excavated using excavator;Gabion wall guide groove is arranged in regular quadrangle;It 2) will be by the grid of stone material sold stowing
It is put under gabion in the gabion wall guide groove that step 1) is excavated, and is built into gabion wall;3) with tamping machine compaction in layers by gabion wall institute
Enclose the soil body of Soft Soil Area and to designed elevation;4) leveling compacting treated soil layer surface, is laid with Application of geosynthetics-reinforced pad
Layer, and Application of geosynthetics-reinforced bed course is anchored into gabion within the walls, and be built into gabion wall;5) in gabion priming petock silt particle within the walls
Slurry constitutes stabilization zone, upper load is undertaken together with foundation soil.The present invention includes the gabion wall with biggish rigidity, can be incited somebody to action
Top is built, the load of structures is transmitted to supporting course, meanwhile, good row is formed by the discrete material of representative of rubble in gabion
Aquaporin can speed up soft base discharging consolidation, effectively improve foundation bearing capacity;Hammer ram freely falling body generates impingement dynamic load pair
Soil body acting accelerates the discharge of weak soil pore water, reduces the hole in the soil body, the soil body becomes dense, so that it is strong to improve foundation soil
Degree;Geosynthetics is wherein playing the role of similar tension film, tensile strength and non-deformability with higher, raising
Its stability, and have the function of uniformly spreading transmitting and control uneven settlement of foundation to load, to control the sedimentation of ground
And differential settlement, reduce horizontal direction displacement, increases the ultimate bearing capacity of ground;The porous property of gabion wall and outsourcing
Lattice cage cladding, constraint and reinforced action.Generally speaking, the present invention has the comprehensive effectivenesses such as carrying, draining, strong rammer, reinforcement, can
Foundation bearing capacity is improved, uneven settlement of foundation and sedimentation are reduced, and is capable of the protuberance deformation in limit levels direction.Meanwhile stone
Cage wall and geosynthetics (TGXG or geotechnical grid) reinforcement cushion collectively form fairly perfect drainage system, favorably
The soil body discharging consolidation for ramming place is applied in acceleration, effectively improves foundation bearing capacity.And the lattice of well in advance stone material sold stowing
Net gabion, mechanization of building operation degree is high, and labor intensity is small, high-efficient, can shorten the construction period.The present invention is with handling mountain area Deep Thick Soft Ground
Base, have more technology and economic advantages, sedimentation can be efficiently controlled, it is shown that its good application prospect, there is no at present about
Report based on gabion wall reinforced earth and strong tamping combined soft base processing method scheme present invention can be mainly used for controlling sedimentation
More demanding large-area soft foundation is made, such as large oil tank ground, highway, railway, airport Soft Ground.
Detailed description of the invention
Fig. 1 is to be adopted based on provided by the present invention based on gabion wall reinforced earth and strong tamping combined soft base processing method
The schematic diagram of the section structure of gabion wall;
Fig. 2 is to be adopted based on provided by the present invention based on gabion wall reinforced earth and strong tamping combined soft base processing method
The overlooking structure diagram of gabion wall;
Fig. 3 and Fig. 4 is provided by the present invention respectively based on gabion wall reinforced earth and strong tamping combined treatment of soft foundation
The case Specific construction figure of method;
In figure
1- gabion wall, 2- tamp weak soil, 3- rubble reinforcement cushion.
Specific embodiment
Technical solution provided by the present invention is described in detail with reference to the accompanying drawing, but the present invention be not limited in
Under type:
The present invention is a kind of based on gabion wall reinforced earth and strong tamping combined soft base processing method, is meeting effectively control
On the basis of settlement of foundation and differential settlement, and it is capable of the protuberance deformation in limit levels direction.Meanwhile gabion wall and geotechnique close
Fairly perfect drainage system is collectively formed at material (TGXG or geotechnical grid) reinforcement cushion, is conducive to accelerate to apply to ram field
The soil body discharging consolidation on ground, effectively improves foundation bearing capacity.
It is a kind of based on gabion wall reinforced earth and strong tamping combined soft base processing method referring to Fig. 1 and Fig. 2, mainly answer
For to the higher large-area soft foundation of requirement of settlement control, such as large oil tank ground, highway, railway, airport weak soil
Basement process, including:
1) gabion wall guide groove is excavated using excavator, regular quadrangle excavates arrangement;
2) it will be put into guide groove under the grid gabion of stone material sold stowing, and be built into gabion wall;
3) with the enclosed Soft Soil Area soil body of tamping machine compaction in layers gabion wall to designed elevation (as needed, such as hole in weak soil
Water collects in the case where ramming effect in gabion region, is drained in gabion wall guide groove);
4) leveling compacting treated soil layer surface, is laid with geosynthetics (TGXG or geotechnical grid) reinforcement pad
Layer, and anchor into gabion within the walls;
5) the rubble gap cement injection mortar to gabion within the walls constitutes stabilization zone, is used to undertake together with foundation soil
Portion's load;
6) after being perfused and completing 6-9 days, consolidation effect is examined using static load test, power to be lifted meets design requirement
Afterwards, upper part work construction is carried out.
Guide groove excavation width is excavated, generally excavator bucket width using the excavator of suitable bucket model
The modulus of (400mm~800mm) or excavator bucket width.Wherein, channel excavation depth is logical according to ground requirement for bearing capacity
Load test is crossed to determine.Spacing between groove is calculated according to the method for calculating area replacement ratio in theory of composite foundation
And determination.
The grid gabion of stone material sold stowing is fabricated to design size cabinet using metal wire rod, the closely knit dress in cabinet
Plastic of Rockfill, and it is built into gabion wall with the gabion, reinforce the anchoring of connecting portion, anchoring strength is made to reach design requirement.
With the enclosed Soft Soil Area soil body of tamping machine compaction in layers gabion wall to designed elevation, first pass is rammed to controlling depth, and one
It behind fixed discharging consolidation interval, bankets into tamping pit, ram for second time after tamping pit is filled up, it is deep that crater depth reaches control
Degree behind certain discharging consolidation interval, then fills up soil into tamping pit, then carries out third all over ramming, in such a way that this is tamped until
Reach designed elevation.
Leveling compacting treated soil layer surface, before geosynthetics laying, will compacting treated soil layer surface,
Careful leveling is carried out, hollow area carries out gravel backfill in advance and makes up a deficiency, and strict control compactness, complies with compactness
Requirement, to prevent differential settlement.
Geosynthetics (TGXG or geotechnical grid) reinforced gravel cushion, soil layer surface and gabion after leveling
In wall top, two layers of two-way laying of interval rubble of reinforcement material point, it is ensured that laying is smooth, uniform, and reinforced gravel cushion thickness takes 400
~500mm, to enhance the overall stiffness of bed course.
Geosynthetics is anchored into gabion wall, at end anchorage, by geosynthetics in a manner of anti-package inflection
It is anchored, lays anchor bar, its spacing, intensity, anchorage depth should meet design requirement, and check reinforcement at anchoring.
The partial size of rubble is 20-50mm, and stone matter is hard, and weathering is few, and to guarantee drainage effect, clay content is not more than 5%.Water
Cement mortar, using M30 mortar, the match ratio of cement and sand is 1:1, ratio of mud 0.4-0.45.
Embodiment 1
Certain section of Hang Rui high speed is located at Hubei Province Xianning mountain area cheuch, the bury area of route crosses large area, roadbed model
Weak soil depth in enclosing is 4000mm, and water content is higher, the slope stability of roadbed is poor.It builds highway on it, it is necessary to
It is handled first.But, it is contemplated that traffic of mountain area is inconvenient, the unsuitable large-scale construction operation of progress, at traditional ground
Reason method not only high construction cost, and construction efficiency is low, it is long in time limit.Therefore, this engineering, which uses, is based on gabion wall reinforced earth
And strong tamping combined soft base processing method scheme.Referring to shown in Fig. 3 and Fig. 4, led using excavator Rapid Excavation gabion wall
Slot, regular quadrangle excavate arrangement, trench spacing 2000mm, width 600mm, depth 4000mm.Well in advance stone material is close
The grid gabion filled in fact, gabion will be put into guide groove having a size of 1400mm × 600mm × 1000mm under gabion, and with the stone
Cage is built into gabion wall, reinforces the anchoring of connecting portion, anchoring strength is made to reach design requirement.It is enclosed with tamping machine compacting gabion wall soft
Native area's soil body, first pass are rammed to controlling depth, behind certain discharging consolidation interval (1 week), banket into tamping pit, tamping pit is filled out
Ram for second time after full, crater depth reaches controlling depth, behind certain discharging consolidation interval (1 week), then into tamping pit
Soil is filled up, then carries out third all over ramming, until reaching designed elevation in such a way that this is tamped.It will compacting treated soil layer table
Face carries out careful leveling, and hollow area carries out gravel backfill in advance and makes up a deficiency, soil layer surface and gabion wall top after leveling
On, two-way interval rubble is laid with reinforcement material, is laid with 200mm rubble, one layer of TGXG, 200mm rubble, one layer of geotechnological lattice
Grid are formed with a thickness of 500mm reinforced gravel cushion, and end point is anchored into gabion within the walls.It is perfused to the rubble gap of gabion within the walls
Cement mortar constitutes stabilization zone, is used to undertake upper load together with foundation soil.After being perfused and completing 7 days, tried using dead load
Inspection consolidation effect is tested, bearing capacity meets design requirement, then carries out the construction of top structures and embankment.By to the stone
The application of cage wall earth structure and strong tamping combined soft foundation processing technology in the gulch weak subsoil of mountain area carries out analysis and practice test,
Summarize the new technology formd suitable for the processing of cheuch soft layer.Compared with traditional soft soil foundation reinforcing method, knot of the present invention
Structure and method can improve foundation bearing capacity, reduce uneven settlement of foundation and sedimentation, and be capable of the protuberance in limit levels direction
Deformation.Meanwhile gabion wall and geosynthetics (TGXG or geotechnical grid) reinforcement cushion collectively form it is fairly perfect
Drainage system is conducive to accelerate to apply the weak soil discharging consolidation for ramming place, effectively improves foundation bearing capacity.In construction, in gabion
Stone material using gathering materials on the spot, the grid gabion of well in advance stone material sold stowing, under be put into the groove of digging machine excavation, construction
Mechanization degree is high, and labor intensity is small, avoids to change on a large scale and fill out or pile body construction, had not only reduced cost but also facilitated construction, favorably
In improving construction efficiency, shorten the construction period.
Claims (8)
1. a kind of based on gabion wall reinforced earth and strong tamping combined soft base processing method, it is characterised in that:It is described to be based on gabion
Wall reinforced earth and strong tamping combined soft base processing method include the following steps:
1)Gabion wall guide groove is excavated using excavator;The gabion wall guide groove is arranged in regular quadrangle;
2)Step 1 will be put by the grid gabion of stone material sold stowing)In the gabion wall guide groove excavated, and it is piled into gabion
Wall;
3)With tamping machine compaction in layers by the soil body of the enclosed Soft Soil Area of gabion wall and to designed elevation;
4)Leveling compacting treated soil layer surface, is laid with Application of geosynthetics-reinforced bed course, and by Application of geosynthetics-reinforced
Bed course is anchored into gabion within the walls;
5)In gabion, cement injection mortar, composition stabilization zone undertake upper load together with foundation soil within the walls.
2. according to claim 1 existed based on gabion wall reinforced earth and strong tamping combined soft base processing method, feature
In:The method is in step 5)Further include later:
6)After being perfused and completing 6-9 days, consolidation effect is examined using static load test, after power to be lifted meets design requirement, into
The construction of row upper part work.
3. according to claim 1 or 2 based on gabion wall reinforced earth and strong tamping combined soft base processing method, feature
It is:The step 3)Specific implementation be:In the enclosed Soft Soil Area of gabion wall, rammed for the first time by gabion wall institute with tamping machine
It after the soil body to controlling depth for enclosing Soft Soil Area, bankets into tamping pit, is rammed for the second time after tamping pit is filled up;It is rammed to second
After the crater depth hit reaches controlling depth, then soil is filled up into tamping pit, then carry out third time and ram, it is straight in such a way that this is tamped
To reaching designed elevation.
4. according to claim 3 existed based on gabion wall reinforced earth and strong tamping combined soft base processing method, feature
In:Application of geosynthetics-reinforced bed course layering interval rubble is two-way to be laid on leveling compacting treated soil layer surface, and
It anchors into gabion within the walls.
5. according to claim 4 existed based on gabion wall reinforced earth and strong tamping combined soft base processing method, feature
In:The thickness of the Application of geosynthetics-reinforced bed course takes 400~500mm.
6. according to claim 5 existed based on gabion wall reinforced earth and strong tamping combined soft base processing method, feature
In:The step 4)The specific implementation of middle anchoring is:It, will be geotechnological at the end anchorage of Application of geosynthetics-reinforced bed course
Geosynthetics employed in synthetic material reinforcement cushion is anchored in a manner of anti-package inflection, lays anchor bar.
7. according to claim 6 existed based on gabion wall reinforced earth and strong tamping combined soft base processing method, feature
In:The partial size of rubble employed in the Application of geosynthetics-reinforced bed course is 20-50mm, and clay content is not more than in rubble
5%。
8. according to claim 7 existed based on gabion wall reinforced earth and strong tamping combined soft base processing method, feature
In:The step 5)Employed in cement mortar be M30 mortar.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810777345.6A CN108824412B (en) | 2018-07-16 | 2018-07-16 | Soft foundation treatment method based on gabion wall reinforced soil and dynamic compaction combination |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810777345.6A CN108824412B (en) | 2018-07-16 | 2018-07-16 | Soft foundation treatment method based on gabion wall reinforced soil and dynamic compaction combination |
Publications (2)
Publication Number | Publication Date |
---|---|
CN108824412A true CN108824412A (en) | 2018-11-16 |
CN108824412B CN108824412B (en) | 2020-12-08 |
Family
ID=64139501
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810777345.6A Active CN108824412B (en) | 2018-07-16 | 2018-07-16 | Soft foundation treatment method based on gabion wall reinforced soil and dynamic compaction combination |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108824412B (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109610436A (en) * | 2019-02-19 | 2019-04-12 | 吴慧明 | A kind of sectional type blast-filled ground processing method |
CN110130305A (en) * | 2019-04-12 | 2019-08-16 | 交通运输部天津水运工程科学研究所 | A kind of grid type soft-soil foundation treatment method and foundation structure |
CN114197434A (en) * | 2021-12-13 | 2022-03-18 | 河南锐意工程检测有限公司 | Building foundation treatment method for area with liquefied soil bearing layer |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105220674A (en) * | 2014-05-29 | 2016-01-06 | 中交四航工程研究院有限公司 | Deep soft foundation reinforcing and processing method |
CN106759397A (en) * | 2017-01-06 | 2017-05-31 | 苏州工业园区园林绿化工程有限公司 | Ecological lattice guest method to set up |
CN106988338A (en) * | 2017-03-31 | 2017-07-28 | 中国冶集团有限公司 | Gabion box retaining wall and its construction method |
-
2018
- 2018-07-16 CN CN201810777345.6A patent/CN108824412B/en active Active
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105220674A (en) * | 2014-05-29 | 2016-01-06 | 中交四航工程研究院有限公司 | Deep soft foundation reinforcing and processing method |
CN106759397A (en) * | 2017-01-06 | 2017-05-31 | 苏州工业园区园林绿化工程有限公司 | Ecological lattice guest method to set up |
CN106988338A (en) * | 2017-03-31 | 2017-07-28 | 中国冶集团有限公司 | Gabion box retaining wall and its construction method |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109610436A (en) * | 2019-02-19 | 2019-04-12 | 吴慧明 | A kind of sectional type blast-filled ground processing method |
CN110130305A (en) * | 2019-04-12 | 2019-08-16 | 交通运输部天津水运工程科学研究所 | A kind of grid type soft-soil foundation treatment method and foundation structure |
CN114197434A (en) * | 2021-12-13 | 2022-03-18 | 河南锐意工程检测有限公司 | Building foundation treatment method for area with liquefied soil bearing layer |
Also Published As
Publication number | Publication date |
---|---|
CN108824412B (en) | 2020-12-08 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN204059124U (en) | A kind of sand drain strong rammer grouting behind shaft or drift lining foundation reinforcing structure | |
CN106759473B (en) | The constructing structure and its construction method of underground pipe gallery and road | |
CN206157746U (en) | Gravelly soil slope retaining structure | |
CN102888834B (en) | A kind of construction method of major diameter broken stone pile | |
CN107447778A (en) | The heightening and consolidation structure and method of a kind of in-service reinforced concrete retaining wall | |
CN107859041B (en) | The construction method of collapsible loess zanjon high roadbed structure | |
CN104499479A (en) | Dig-hole pile construction method based on penetration of sand gravel backfilling layer | |
CN115288162B (en) | Reinforcing method for soft soil foundation filling side slope | |
CN108824412A (en) | Based on gabion wall reinforced earth and strong tamping combined soft base processing method | |
CN105113478A (en) | Dynamic compaction treatment method of deep foundation displacement | |
CN110241695A (en) | A kind of gravelly soil superelevation fill foundation reinforcement means | |
CN106522191A (en) | Transformer substation foundation treatment method and application thereof | |
CN113174958A (en) | Construction method for foundation pit of adjacent road under poor ground condition | |
CN207331740U (en) | A kind of heightening and consolidation structure of in-service reinforced concrete retaining wall | |
CN104480956B (en) | A kind of minor diameter mold-bagged concrete pile composite foundation | |
CN208604438U (en) | The high embankment retaining structure in soft clay area | |
CN1043263C (en) | Construction method for building foundation pit stope support | |
CN204000848U (en) | A kind of socketed pile for subaqueous construction | |
CN114164726B (en) | Local deep excavation backfill structural roadbed and rapid construction method | |
CN215976663U (en) | Excavation area composite foundation treatment structure crossing under high-voltage line | |
RU2275470C1 (en) | Method of floating pile load-bearing capacity increase | |
CN211200425U (en) | High side slope composite supporting construction that fills of gravel soil | |
CN209760216U (en) | reinforcement system based on soft soil foundation drainage consolidation | |
CN208152061U (en) | Method steel pipe pile cofferdam structure is unidirectionally attacked and occupied suitable for Soft Clay | |
CN106337409A (en) | Method for treating peat soil foundation through preloading in combination with salt piles |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |