CN201981530U - Down hole deep dynamic compaction pile in collapsible loess area - Google Patents

Down hole deep dynamic compaction pile in collapsible loess area Download PDF

Info

Publication number
CN201981530U
CN201981530U CN2010206746412U CN201020674641U CN201981530U CN 201981530 U CN201981530 U CN 201981530U CN 2010206746412 U CN2010206746412 U CN 2010206746412U CN 201020674641 U CN201020674641 U CN 201020674641U CN 201981530 U CN201981530 U CN 201981530U
Authority
CN
China
Prior art keywords
hole
lime
stake
soil
collapsible loess
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2010206746412U
Other languages
Chinese (zh)
Inventor
骆文龙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guiyang Aluminum Magnesium Design and Research Institute Co Ltd
Original Assignee
Guiyang Aluminum Magnesium Design and Research Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guiyang Aluminum Magnesium Design and Research Institute Co Ltd filed Critical Guiyang Aluminum Magnesium Design and Research Institute Co Ltd
Priority to CN2010206746412U priority Critical patent/CN201981530U/en
Application granted granted Critical
Publication of CN201981530U publication Critical patent/CN201981530U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Abstract

The utility model discloses a down hole deep dynamic compaction pile in the collapsible loess area, which comprises a pile hole (1) arranged in a collapsible loess layer. The lower half part of the pile hole (1) is filled with compacted natural soil (2), and the upper half part of the pile hole (1) is filled with compacted lime soil (3). In the prior art, the whole pile hole is filled with compacted lime soil to form a basic pile, and the used lime soil is more. As the price of lime in the lime soil is high, the construction cost is high. In the utility model, the lower half part of the pile hole is completely compacted by loess on site, only the upper half part of the pile hole adopts a lime soil structure formed by mixing two portions of lime and eight portions of silty clay, so the usage of lime is less, and the construction cost is greatly reduced under the condition for meeting the design requirements.

Description

Deep layer is rammed stake by force in a kind of Collapsible Loess District hole
Technical field
The utility model relates to a kind of strong rammer stake, particularly relates in a kind of Collapsible Loess District hole deep layer and rams stake by force, belongs to the foundation consolidating technology field of construction work.
Background technology
In the hole deep layer ram by force the stake be the foundation consolidating technology that on the strong tamping technology basis, develops, its construction is first pore-forming, filler in the hole again, dash and pound extruding with kinetic energy, the special weight of over pressure deep layer field in the hole, make filler pile body to hole week and bottom squeeze formation under the promotion of brute force.In Collapsible Loess District, usually see with deep layer Treatment by Dynamic Compaction collapsible loess right and wrong in the hole, in the hole in the hole of deep layer dynamic compaction filler generally adopt 2:8 dirt, when eliminating saturated yielding, can also significantly improve the bearing capacity of composite foundation like this.But when collapsible loess was too dark, a large amount of dirt fillers can strengthen engineering cost.
Summary of the invention
The purpose of this utility model is, provides in a kind of Collapsible Loess District hole deep layer to ram stake by force, reduces construction costs under situation about meeting design requirement greatly.
The technical solution of the utility model: deep layer is rammed stake by force in a kind of Collapsible Loess District hole, comprises the stake hole that is located at yellow soil horizon of collapsibility; The Lower Half in stake hole is filled with the plain soil of compacting, and the first half in stake hole is filled with the dirt of compacting.
Deep layer is rammed by force in the stake in the aforementioned Collapsible Loess District hole, and described plain soil is the on-the-spot loess that does not contain lime and sandstone that crude sedimentation forms.
Deep layer is rammed by force in the stake in the aforementioned Collapsible Loess District hole, and described dirt is 2 parts of lime and 8 parts of mixed uniformly composite soil structures of silty clay.
Compared with prior art, prior art all adopts dirt to fill the stake of compacting formation base in whole stake hole, and used dirt is more, because the lime price in the dirt is higher, so construction cost is also higher.Stake of the present utility model hole the latter half is all with on-the-spot loess compacting, only the first half in the stake hole adopts 2 parts of lime and 8 parts of grey soil structures that silty clay mixes, so the consumption of lime is less, under situation about meeting design requirement, reduce construction costs greatly.
Description of drawings
Fig. 1 is a structural representation of the present utility model.
Being labeled as in the accompanying drawing: 1-stake hole, the plain soil of 2-, 3-dirt.
The specific embodiment
The utility model is described in further detail below in conjunction with drawings and Examples, but not as to any restriction of the present utility model.
Embodiment.
Structural representation of the present utility model as shown in Figure 1, deep layer is rammed stake by force in the Collapsible Loess District of the present utility model hole, comprise be located at yellow soil horizon of collapsibility the stake hole 1; The Lower Half in stake hole 1 is filled with the plain soil 2 of compacting, and the first half in stake hole 1 is filled with the dirt 3 of compacting.Described plain soil 2 is the on-the-spot loess that does not contain lime and sandstone that crude sedimentation forms.Described dirt 3 is 2 parts of lime and 8 parts of mixed uniformly composite soil structures of silty clay.
During concrete enforcement, earlier in yellow soil horizon of collapsibility piling hole 1, in stake hole 1, fill the plain soil of a part, then with the rammed earth of weight with filling, and then fill out some element soil 2 again with its compacting, until a half that is filled into a hole depth, in the stake hole 1 of yellow soil horizon of collapsibility, fill 2 parts of lime and 8 parts of dirt 3 that clay evenly mixes again.Adopt preceding method to continue the grey rammed earth that to fill with weight, until filling up whole stake hole 1.Constitute deep layer of the present utility model and ram stake by force.

Claims (2)

1. deep layer is rammed stake by force in the Collapsible Loess District hole, comprises the stake hole (1) that is located at yellow soil horizon of collapsibility; It is characterized in that: the Lower Half in stake hole (1) is filled with the plain soil (2) of compacting, and the first half in stake hole (1) is filled with the dirt (3) of compacting.
2. ram stake by force according to deep layer in the described Collapsible Loess District of claim 1 hole, it is characterized in that: described plain soil (2) is the on-the-spot loess that does not contain lime and sandstone that crude sedimentation forms.
CN2010206746412U 2010-12-22 2010-12-22 Down hole deep dynamic compaction pile in collapsible loess area Expired - Fee Related CN201981530U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2010206746412U CN201981530U (en) 2010-12-22 2010-12-22 Down hole deep dynamic compaction pile in collapsible loess area

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2010206746412U CN201981530U (en) 2010-12-22 2010-12-22 Down hole deep dynamic compaction pile in collapsible loess area

Publications (1)

Publication Number Publication Date
CN201981530U true CN201981530U (en) 2011-09-21

Family

ID=44608993

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2010206746412U Expired - Fee Related CN201981530U (en) 2010-12-22 2010-12-22 Down hole deep dynamic compaction pile in collapsible loess area

Country Status (1)

Country Link
CN (1) CN201981530U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106968235A (en) * 2017-05-10 2017-07-21 广州市城市规划勘测设计研究院 A kind of soil body encryption device and method
CN108708364A (en) * 2018-06-06 2018-10-26 中国电建集团山东电力建设有限公司 DDC pile foundation construction process

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106968235A (en) * 2017-05-10 2017-07-21 广州市城市规划勘测设计研究院 A kind of soil body encryption device and method
CN106968235B (en) * 2017-05-10 2018-10-26 广州市城市规划勘测设计研究院 A kind of soil body encryption device and method
CN108708364A (en) * 2018-06-06 2018-10-26 中国电建集团山东电力建设有限公司 DDC pile foundation construction process

Similar Documents

Publication Publication Date Title
CN101368383B (en) Method for treating soft soil roadbed by artificial composite crust layer
US20140314497A1 (en) Polymer grouting method for constructing gravel pile
CN102465524B (en) Double radial mesh-cage sand-gravel pile and construction technology thereof
CN103215960A (en) Grouting method for high polymer vertical support system
CN105625294A (en) Composite foundation and construction method thereof
CN103233454A (en) Processing method of soaking, vacuum preloading and slurry injecting for sand piles of collapsible loess foundation
CN203174619U (en) Reverse raft concrete terrace
CN103225267A (en) Construction method of deep and thick soft soil foundation bed bridge abutment
CN202324017U (en) Grouting type micro steel pipe pile
CN201981530U (en) Down hole deep dynamic compaction pile in collapsible loess area
CN203247597U (en) Construction structure of deep soft soil foundation bridge abutment
CN202730791U (en) Composite pile foundation of building
CN101736730A (en) Mixed reinforcement method of high-fill sand foundation
CN207003417U (en) Quarrel backfill body sedimentation and stability contorting structure are abandoned in mountain area
CN206486886U (en) A kind of equipment for reinforcing Line for Passenger Transportation Extra-fine sand ground
CN105350512A (en) Construction method for dynamic compaction and impact rolling of carbonate rock block stone padding
CN102605775B (en) Combination pile of flexible pile and rigid pile concentrically arranged at upper end and lower end and pile forming method
CN202672161U (en) Cement-soil mixing drum sheet-pile united slope structure with soil nails
CN212896322U (en) Side-root composite load-bearing pile
CN204825865U (en) Earth composite pile that waters is pressed to replacement formula
CN201520968U (en) Combined hammer
CN202124857U (en) Splitting pile
CN106087946A (en) A kind of carbonate rock boulder strong rammer is combined to change to fill changes foundation reinforcement method
CN209760216U (en) reinforcement system based on soft soil foundation drainage consolidation
CN203256771U (en) Semi-gravity type column and board combined retaining wall structure

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20110921

Termination date: 20141222

EXPY Termination of patent right or utility model