CN101736366A - 内热串接石墨化阴极生产工艺及其装置 - Google Patents
内热串接石墨化阴极生产工艺及其装置 Download PDFInfo
- Publication number
- CN101736366A CN101736366A CN200810228916A CN200810228916A CN101736366A CN 101736366 A CN101736366 A CN 101736366A CN 200810228916 A CN200810228916 A CN 200810228916A CN 200810228916 A CN200810228916 A CN 200810228916A CN 101736366 A CN101736366 A CN 101736366A
- Authority
- CN
- China
- Prior art keywords
- power supply
- cathode
- conductive electrode
- furnace
- hopper
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Landscapes
- Carbon And Carbon Compounds (AREA)
Abstract
本发明涉及一种内热串接石墨化阴极生产工艺,尤其涉及炭素、铝电解行业内热串接石墨化阴极生产工艺及其装置。其工艺包括下述步骤;首先在石墨化炉两个料箱底部设置石墨垫块,然后在石墨垫块上按照顺序放置焙烧阴极碳块并在碳块间安装导电连接材料,填充保温料,炉尾顶推装置对料箱内阴极碳块施加压力到工艺规定的要求压力,随后填充碳块其余侧面和顶部保温料,装炉结束;将炉头导电电极与供电机组连接并按照规定工艺供电曲线供电,对焙烧阴极块进行石墨化处理;供电到规定的要求后,停止供电并断开供电机组与炉头导电电极连接,整个石墨化炉自然冷却;分层抽吸填充保温料,解除炉尾顶推装置施加压力,然后将所有高温石墨化阴极碳块吊运出炉。
Description
技术领域
本发明涉及一种内热串接石墨化阴极生产工艺,尤其涉及炭素、铝电解行业内热串接石墨化阴极生产工艺及其装置。
背景技术
随着我国铝电解技术发展迅速,电解槽容量已由160~180kA发展到300~400kA。由于石墨化阴极碳块具有比电阻小,抗热震性好及抗钠浸蚀高等优点而被认为大容量电解槽最佳的阴极材料。而阴极材料石墨化主要通过石墨化炉装置,采用内热串接石墨化工艺完成。尽管目前国内内热串接石墨化炉生产石墨化阴极的技术已经有了很大的进步,但国内阴极内热串接石墨化工艺方法及装置普遍存在以下问题:生产冷却周期长,喷淋冷却水使用量大;炉尾跨接导电电极在生产过程中,非常容易断裂;炉体结构复杂、维修不便;仅适合生产单一规格的石墨化阴极碳块。
发明内容
为解决上述技术问题本发明提供一种内热串接石墨化阴极生产工艺及其装置,其目的是简化石墨化炉炉体结构;彻底消除炉尾跨接导电电极的断裂;降低冷却周期并消除喷淋冷却水使用;实现单一内热串接石墨炉生产多规格石墨化阴极碳块。
为达上述目的本发明是通过下述技术方案实现的。
内热串接石墨化阴极生产工艺,它包括下述步骤:在石墨化炉料箱底部铺设保温料并设置石墨化垫块;放置焙烧阴极碳块并在碳块间安装导电连接材料;填充焙烧阴极碳块侧面保温料、炉尾顶推装置对料箱内阴极碳块施加压力并填充焙烧阴极碳块顶部保温料,装炉结束;炉头导电电极与供电机组连接并按照规定工艺供电曲线供电,对焙烧阴极碳块进行石墨化处理;供电到规定的要求后,停止供电并断开供电机组与炉头导电电极连接;整个石墨化炉自然冷却;冷却到规定时间后,分层抽吸填充保温料,并解除炉尾顶推装置施加的压力,然后将所有高温石墨化阴极碳块吊运出炉。
内热串接石墨化阴极生产装置,包括料箱,料箱为两个,在料箱的两端分别设有炉头导电电极和顶推导电电极,在两个顶推导电电极之间料箱的外面设有炉尾跨接装置,顶推导电电极与炉尾顶推装置连接。
所述的炉头导电电极由供电机组供电。
所述的炉尾跨接装置为铜母线排结构。
本发明的优点效果如下:内热串接石墨化阴极生产装置结构简单、彻底消除炉尾跨接导电电极的断裂。本发明装置和工艺可以降低冷却周期并减少冷却水使用量、实现单一内热串接石墨炉生产多规格石墨化阴极碳块。
附图说明
图1是本发明内热串接石墨化阴极生产装置的结构示意图。
图中:1.料箱;2.阴极碳块;3.炉头导电电极;4.供电机组;5.炉尾跨接装置;6.顶推导电电极;7.炉尾顶推装置。
具体实施方式
下面对本发明的实施例结合附图加以详细描述,但本发明的保护范围不受实施例所限。
内热串接石墨化阴极生产工艺,包括下述步骤;首先在石墨化炉两个料箱底部分层铺设一定厚度的保温料,并按照规定在铺设好的保温料上面设置石墨垫块,然后在石墨垫块上按照顺序放置焙烧阴极碳块并在碳块间安装导电连接材料,接着在焙烧阴极碳块侧面填充保温料,保温料填充到一定高度时,炉尾顶推装置对料箱内阴极碳块施加压力到工艺规定的要求压力,随后填充碳块其余侧面和顶部保温料,装炉结束;将炉头导电电极与供电机组连接并按照规定工艺供电曲线供电,对焙烧阴极块进行石墨化处理;供电到规定的要求后,停止供电并断开供电机组与炉头导电电极连接,整个石墨化炉自然冷却;冷却到规定时间后,分层抽吸填充保温料,直到石墨化阴极碳块露出要求高度,解除炉尾顶推装置施加压力,然后将所有高温石墨化阴极碳块吊运出炉。
如图1所示,本发明内热串接石墨化阴极生产装置包括料箱1,料箱1为两个,在料箱1的两端分别设有炉头导电电极3和顶推导电电极6,在两个顶推导电电极6之间料箱1的外面设有炉尾跨接装置5,炉尾跨接装置5为铜母线排结构,顶推导电电极6与炉尾顶推装置7连接;炉头导电电极3由供电机组4供电。
料箱全部由钢结构组成,也就是整个料箱制作采用钢制造。料箱宽度可调节,通过调整料箱侧壁上的可移动钢柱的位置将整个料箱的侧壁向两侧移动,从而根据阴极碳块尺寸变化,实现调整料箱宽度的改变,以调整料箱的容积。
Claims (4)
1.内热串接石墨化阴极生产工艺,其特征在于在石墨化炉料箱底部铺设保温料并设置石墨化垫块;放置焙烧阴极碳块并在碳块间安装导电连接材料;填充焙烧阴极碳块侧面保温料、炉尾顶推装置对料箱内阴极碳块施加压力并填充焙烧阴极碳块顶部保温料,装炉结束;炉头导电电极与供电机组连接并按照规定工艺供电曲线供电,对焙烧阴极碳块进行石墨化处理;供电到规定的要求后,停止供电并断开供电机组与炉头导电电极连接;整个石墨化炉自然冷却;冷却到规定时间后,分层抽吸填充保温料并解除炉尾顶推装置施加的压力,然后将所有高温石墨化阴极碳块吊运出炉。
2.内热串接石墨化阴极生产装置,包括料箱,其特征在于料箱为两个,在料箱的两端分别设有炉头导电电极和顶推导电电极,在两个顶推导电电极之间料箱的外面设有炉尾跨接装置,顶推导电电极与炉尾顶推装置连接。
3.根据权利要求2所述的内热串接石墨化阴极生产装置,其特征在于所述的炉头导电电极由供电机组供电。
4.根据权利要求2所述的内热串接石墨化阴极生产装置,其特征在于所述的炉尾跨接装置为铜母线排结构。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2008102289167A CN101736366B (zh) | 2008-11-20 | 2008-11-20 | 内热串接石墨化阴极生产工艺及其装置 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2008102289167A CN101736366B (zh) | 2008-11-20 | 2008-11-20 | 内热串接石墨化阴极生产工艺及其装置 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN101736366A true CN101736366A (zh) | 2010-06-16 |
CN101736366B CN101736366B (zh) | 2011-06-29 |
Family
ID=42460380
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2008102289167A Expired - Fee Related CN101736366B (zh) | 2008-11-20 | 2008-11-20 | 内热串接石墨化阴极生产工艺及其装置 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN101736366B (zh) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102311112A (zh) * | 2010-07-09 | 2012-01-11 | 武建国 | 一种石墨化炉及相应的石墨化处理方法 |
CN102963889A (zh) * | 2012-12-06 | 2013-03-13 | 中钢集团新型材料(浙江)有限公司 | 一种高效环保的石墨化炉冷却工艺 |
CN104743546A (zh) * | 2013-12-25 | 2015-07-01 | 贵阳铝镁设计研究院有限公司 | 一种特种炭素材料内热串接石墨化生产装置 |
CN105967718A (zh) * | 2016-07-08 | 2016-09-28 | 南通扬子碳素股份有限公司 | 耐大电流镁电解用石墨阳极及其制备工艺 |
CN107986269A (zh) * | 2017-12-22 | 2018-05-04 | 中国平煤神马集团开封炭素有限公司 | 一种超高功率石墨电极接头内热串接石墨化工艺 |
-
2008
- 2008-11-20 CN CN2008102289167A patent/CN101736366B/zh not_active Expired - Fee Related
Cited By (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102311112A (zh) * | 2010-07-09 | 2012-01-11 | 武建国 | 一种石墨化炉及相应的石墨化处理方法 |
CN102311112B (zh) * | 2010-07-09 | 2014-08-13 | 武建国 | 一种石墨化处理方法 |
CN102963889A (zh) * | 2012-12-06 | 2013-03-13 | 中钢集团新型材料(浙江)有限公司 | 一种高效环保的石墨化炉冷却工艺 |
CN102963889B (zh) * | 2012-12-06 | 2014-09-17 | 中钢集团新型材料(浙江)有限公司 | 一种高效环保的石墨化炉冷却工艺 |
CN104743546A (zh) * | 2013-12-25 | 2015-07-01 | 贵阳铝镁设计研究院有限公司 | 一种特种炭素材料内热串接石墨化生产装置 |
CN104743546B (zh) * | 2013-12-25 | 2018-03-02 | 贵阳铝镁设计研究院有限公司 | 一种特种炭素材料内热串接石墨化生产装置 |
CN105967718A (zh) * | 2016-07-08 | 2016-09-28 | 南通扬子碳素股份有限公司 | 耐大电流镁电解用石墨阳极及其制备工艺 |
CN105967718B (zh) * | 2016-07-08 | 2019-06-14 | 南通扬子碳素股份有限公司 | 耐大电流镁电解用石墨阳极及其制备工艺 |
CN107986269A (zh) * | 2017-12-22 | 2018-05-04 | 中国平煤神马集团开封炭素有限公司 | 一种超高功率石墨电极接头内热串接石墨化工艺 |
Also Published As
Publication number | Publication date |
---|---|
CN101736366B (zh) | 2011-06-29 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101736366B (zh) | 内热串接石墨化阴极生产工艺及其装置 | |
CN205258011U (zh) | 一种卧式艾奇逊石墨化炉 | |
CN105967718B (zh) | 耐大电流镁电解用石墨阳极及其制备工艺 | |
CN106082189B (zh) | 利用碳化硅炉用变压器和电阻炉生产石墨化材料的方法 | |
CN101066760B (zh) | 串接石墨化炉热处理石墨粉的方法及其石墨坩埚 | |
CN201293543Y (zh) | 一种大容量直流石墨化电炉装置 | |
CN104743546B (zh) | 一种特种炭素材料内热串接石墨化生产装置 | |
CN201296788Y (zh) | 阴极生产装置 | |
CN201049966Y (zh) | 一种异形结构铝电解槽的阴极碳块 | |
CN204324896U (zh) | 一种高纯石墨高温石墨化炉 | |
CN210426088U (zh) | 一种用于焙烧和碳化的电阻炉 | |
CN111595151A (zh) | 用于锂离子电池负极材料炭化处理的炭化炉 | |
CN116951982A (zh) | 一种电极石墨化送电曲线优化方法 | |
CN107986269A (zh) | 一种超高功率石墨电极接头内热串接石墨化工艺 | |
CN203625051U (zh) | 一种内热串接石墨化生产装置 | |
CN204778851U (zh) | 一种石墨化内串炉用导电车 | |
CN108083269A (zh) | 一种石墨制品的石墨化方法及石墨化装置 | |
CN203637222U (zh) | 一种热流道压板 | |
CN110029362B (zh) | 一种分体式填充块连续预焙阳极炭块 | |
CN102995058B (zh) | 铝电解槽铺设焙烧介质及焙烧内衬的方法 | |
CN106495145B (zh) | 埋钵法石墨化生产工艺及密闭式石墨化炉 | |
CN206720744U (zh) | 高效节能的艾奇逊石墨化加热单元及加热系统 | |
CN103660355A (zh) | 一种热流道压板 | |
CN219714024U (zh) | 一种艾奇逊石墨化炉生产大规格石墨砖的装炉系统 | |
CN202808371U (zh) | 一种保温料分区吸收的多功能串接石墨化炉 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20110629 Termination date: 20201120 |
|