CN101705838A - Separate type filling method of goaf - Google Patents
Separate type filling method of goaf Download PDFInfo
- Publication number
- CN101705838A CN101705838A CN200910185318A CN200910185318A CN101705838A CN 101705838 A CN101705838 A CN 101705838A CN 200910185318 A CN200910185318 A CN 200910185318A CN 200910185318 A CN200910185318 A CN 200910185318A CN 101705838 A CN101705838 A CN 101705838A
- Authority
- CN
- China
- Prior art keywords
- filling
- goaf
- barrier bodies
- flexible
- bag
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000000034 method Methods 0.000 title claims abstract description 20
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims abstract description 30
- 239000000463 material Substances 0.000 claims abstract description 27
- 230000004888 barrier function Effects 0.000 claims description 37
- 230000002262 irrigation Effects 0.000 claims description 11
- 238000003973 irrigation Methods 0.000 claims description 11
- 230000007717 exclusion Effects 0.000 claims description 9
- 238000005065 mining Methods 0.000 claims description 8
- 125000006850 spacer group Chemical group 0.000 claims description 6
- 238000012856 packing Methods 0.000 claims description 4
- 239000003245 coal Substances 0.000 abstract description 7
- 238000000926 separation method Methods 0.000 abstract 3
- 238000010586 diagram Methods 0.000 description 7
- 238000005516 engineering process Methods 0.000 description 2
- 229910052500 inorganic mineral Inorganic materials 0.000 description 2
- 239000011707 mineral Substances 0.000 description 2
- 239000011435 rock Substances 0.000 description 2
- 239000002699 waste material Substances 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000010276 construction Methods 0.000 description 1
- 230000006378 damage Effects 0.000 description 1
- 230000007812 deficiency Effects 0.000 description 1
- 238000000280 densification Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 239000006210 lotion Substances 0.000 description 1
- 239000000203 mixture Substances 0.000 description 1
- 239000002002 slurry Substances 0.000 description 1
- 239000002351 wastewater Substances 0.000 description 1
Images
Landscapes
- Revetment (AREA)
Abstract
The invention relates to a separate type filling method of a goaf. A plurality of flexible filling bags are hung at longitudinal or transverse intervals along the propelling direction of a coal face in the goaf and a template supported by a single brace is erected outside the filling bags. Specifically, the method includes: filling high-water materials in the filling bags; after the high-water materials are coagulated, dismantling the template and the single brace to complete a row of separation bodies; advancing along the coal face and repeating the steps until the coal advances to reach the span separating the goaf; then building a row of transverse enclosed separation body walls, irrigating the high-water materials to the enclosed wall; then continuing the work repeatedly until the coal face finishes; subsequently building an enclosed wall in a transportation alley and a track alley; and conducting final filling to complete the filling work of the whole goaf. The method uses the enclosed separation body goaf, irrigates the enclosed goaf on the basis of no accidental fall of top plates. The filling method is simple, the equipment investment is low, the filling efficiency and filling compactness are high, the stability is good and the cost is low.
Description
Technical field
The present invention relates to a kind of separate type filling method of goaf, be applicable under the building, under the water body, railway down with water body on goaf filling behind the coal mining.
Background technology
For a long time, under the building, under the water body, railway caused the deformation failure on overlying rock and the face of land behind the coal mining down with on the water body, and lithic drainage is destroyed, above ground structure destruction is out of shape and is caused and can't use.Therefore, need carry out the rock stratum that filling slows down above goaf to goaf behind the coal mining and move downward, thereby reach the purpose on the protection face of land.
The main filling method in goaf has waste filling, hydraulic filling, lotion and paste-like backfill etc. at present.These filling methods have all played certain effect to the sinking control on the face of land.But waste filling, hydraulic filling because pack completeness is lower, filling cost is high, limited to the sinking control action on the face of land.Paste body filling and paste-like backfill complex process are invested greatlyyer, reach several ten million yuan, thereby have limited the application and the popularization of above-mentioned placement method.
Summary of the invention
Technical problem: the present invention seeks to overcome the deficiency of existing goaf filling technology, method is simple relatively, and filling cost is relatively low, and pack effectiveness is higher.This separate type filling method of goaf is the stronger goaf filling method of a kind of applicability.
Technical scheme: separate type filling method of goaf of the present invention:
A, in treating the goaf of filling along coal-face direction of propulsion, vertical or horizontal arrangement pitch distance L
1Or obstruct goaf span L
3Hang a plurality of flexible filling bag;
B, expose side in the flexible filling bag of hanging and arrange individual prop at interval;
C, set up the template that relies on individual prop in the flexible filling bag outside;
D, by Grouting Pipe filling high-water material in flexible filling bag, until full;
E, treat that high-water material solidifies after, stripping and individual prop are finished row's filling barrier bodies;
F, with the propelling of coal-face, vertically the filling barrier bodies of arranging continues to construct next exclusion spacer, continuous flexible filling bag, repeating step b, c, d, the e of hanging in a last exclusion spacer position, go round and begin again, intercept the goaf span L when the filling barrier bodies of constructing reaches
2The time, vertically and between the filling barrier bodies of vertically arranging constructing a horizontal row,,, finish the totally-enclosed of regional goaf until full by Grouting Pipe flood irrigation high-water material in enclosing wall to filling barrier bodies enclosing wall;
Transversely arranged filling barrier bodies reaches at interval and intercepts the goaf span L
3The time, construct next horizontal row to the enclosing wall filling barrier bodies of arranging, by Grouting Pipe flood irrigation high-water material in enclosing wall filling barrier bodies,, finish the totally-enclosed of regional goaf until full;
G, advance, continue to hang filling bag, repeat above-mentioned steps b, c, d with the continuation of coal-face, e, f goes round and begins again, until the flood irrigation operation with the goaf of constructing of finishing whole goaf barrier bodies;
H, construct enclosing wall, carry out unified at last filling in fortune lane and track lane, with the goaf not pack portion be full of, finish the packing job in whole goaf.
The length a of described flexible filling bag is 10m~20m, and width b is 2m~3m, and c is identical with the work plane mining height for height; The spacing distance L of flexible filling bag is hung in described vertical arrangement
1Be about 10m~25m, intercept the goaf span L
2Should be about 8m~30m less than the step pitch of directly pushing up or old top collapses for the first time and; Described transversely arranged obstruct goaf span L of hanging flexible filling bag
3Should be about 8m~25m less than directly top or the old top step pitch that falls that collapses for the first time.
Beneficial effect: by at the vertical or horizontal extension bag of goaf section construction, adopt high-water material to carry out filling then and form barrier bodies, obturation is solidified the back top board is supported, and reduces the absciss layer of top board.After barrier bodies reaches some, by Grouting Pipe to airtight goaf filling high-water material, until full.After treating that high-water material filling slurries solidify, the top board that the goaf is exposed out supports.At last, after working face mining equipment is taken out of, construct enclosing wall at Liang Xiang and carry out at last unified filling, it is closely knit exploit space integral body filling, finishes whole filling operation.The present invention utilizes barrier bodies to intercept the goaf, do not take place at top board under the prerequisite of inbreak institute's barrier region to be carried out flood irrigation, and the pack effectiveness height, remarkable to the sinking control action on the face of land.The high-water material water supply volume is big, and down-hole waste water can satisfy the requirement of filling water, can reduce part drainage underground expense, and placement method is simple, and equipment investment is few, pack effectiveness and pack densification height, and good stability has practicality widely.
Description of drawings
Fig. 1 is that the first exclusion of vertical arrangement embodiment one of the present invention is arranged schematic diagram every filling bag.
Fig. 2 is the I-I sectional drawing of Fig. 1.
Fig. 3 is that many exclusions that the present invention vertically arranges embodiment one are arranged schematic diagram every obturation.
Fig. 4 is the II-II sectional drawing of Fig. 3.
Fig. 5 is the barrier bodies layout schematic diagram that the present invention vertically arranges embodiment one.
Fig. 6 is the III-III sectional drawing of Fig. 5.
Fig. 7 is a plurality of barrier bodies layout schematic diagrames that the present invention vertically arranges embodiment one.
Fig. 8 is the V-V sectional drawing of Fig. 7.
Fig. 9 is that the first exclusion of transversely arranged embodiment two of the present invention is arranged schematic diagram every filling bag.
Figure 10 is the I-I sectional drawing of Fig. 9.
Figure 11 is that the zone of transversely arranged embodiment two of the present invention intercepts the obturation schematic diagram.
Figure 12 is the II-II sectional drawing of Figure 11.
Figure 13 is the obstruct obturation schematic diagram of horizontally-arranged row embodiment two of the present invention.
Figure 14 is the III-III sectional drawing of Figure 13.
Among the figure: the 1-goaf; The flexible filling bag of 2-; The 3-individual prop; The 4-template; 5-transports the lane; 6-track lane; 7-track inclined gallery; The 8-enclosing wall; The 9-obturation; The 10-barrier bodies; L
1, L
2, L
3-obstruct goaf span; The flexible filling bag length of a-; The flexible filling bag width of b-; The flexible filling bag height of c-.
The specific embodiment
Below in conjunction with accompanying drawing embodiments of the invention are further described:
Embodiment one, Fig. 1~shown in Figure 8,
A, in the goaf 1 for the treatment of filling along coal-face direction of propulsion, vertical arrangement pitch distance L
1Hang a plurality of flexible filling bag 2; The length a of flexible filling bag 2 is about 10m~20m, and width b is about 2m~3m, and c is identical with the work plane mining height for height;
B, expose side in the flexible filling bag 2 of hanging and arrange a plurality of individual props 3 at interval;
C, set up the template 4 that relies on individual prop 3 in flexible filling bag 1 outside;
D, by filling pipe filling high-water material in flexible filling bag 2, until full;
E, treat that high-water material solidifies after, stripping 4 and individual prop 3 are finished row's filling barrier bodies;
F, with the propelling of coal-face, vertically the filling barrier bodies of arranging continues to construct next exclusion spacer, continuous flexible filling bag 2, repeating step b, c, d, the e of hanging in a last exclusion spacer position, go round and begin again, vertically arrange and hang the spacing distance L of flexible filling bag 2
1Be about 10m~25m;
G,, the filling barrier bodies intercepts the goaf span L when reaching
2The time, vertically and between the filling barrier bodies of vertically arranging constructing a horizontal row,,, finish the totally-enclosed of regional goaf until full by filling pipe flood irrigation high-water material in enclosing wall to filling barrier bodies enclosing wall 8; Laterally the filling barrier bodies intercepts the goaf span L
2Should be about 8m~30m less than the step pitch of directly pushing up or old top collapses for the first time and, determine according to on-site actual situations;
H, advance, continue to hang filling bag 2 at interval along the longitudinal direction, repeat to state step b, c, d, e, f, g, go round and begin again, until the flood irrigation operation with the goaf of constructing of finishing whole goaf barrier bodies with the continuation of coal-face;
I, construct enclosing wall 8, carry out unified at last filling in fortune lane 5 and track lane 6, with the goaf not pack portion be full of, finish the packing job in whole goaf.
Embodiment two, Fig. 9~shown in Figure 14,
A, in the goaf 1 for the treatment of filling along coal-face direction of propulsion, transversely arranged obstruct goaf span L
3Hang a plurality of flexible filling bag 2; The length a of flexible filling bag 2 is 10m~20m, and width b is 2m~3m, and c is identical with the work plane mining height for height;
B, expose side in the flexible filling bag 2 of hanging and arrange a plurality of individual props 3 at interval;
C, set up the template 4 that relies on individual prop 3 in flexible filling bag 2 outsides;
D, by filling pipe filling high-water material in flexible filling bag 2, until full;
E, treat that high-water material solidifies after, stripping 4 and individual prop 3 are finished row's filling barrier bodies;
F, with the propelling of coal-face, intercept the goaf span L when advance of the face distance reaches transversely arranged filling barrier bodies
3The time, construct next horizontal row to the enclosing wall filling barrier bodies of arranging, by Grouting Pipe flood irrigation high-water material in enclosing wall filling barrier bodies,, finish the totally-enclosed of regional goaf until full;
G, advance, intercept the goaf span L when advance of the face distance reaches transversely arranged filling barrier bodies again with the continuation of coal-face
3The time, continue to hang filling bag 2, repeat to state step b, c, d, e, f goes round and begins again, until the flood irrigation operation with airtight goaf of constructing of finishing whole goaf barrier bodies; Transversely arranged obstruct goaf span L of hanging flexible filling bag 2
3Should be about 8m~25m less than directly top or the old top step pitch that falls that collapses for the first time, definite according to on-site actual situations;
H, in fortune lane 5 and track lane 6, construct enclosing wall 8, carry out unified at last filling, finish the packing job in whole goaf.
High-water material selected in the foregoing description is made up of A material and B material, and the A material is fired in proportion by multi mineral and formed; B material by multi mineral in proportion mix grinding form, the high-water material water volume can reach more than 85%.
Claims (4)
1. separate type filling method of goaf is characterized in that:
A, in the goaf for the treatment of filling (1) along coal-face direction of propulsion, vertical or horizontal arrangement pitch distance L
1Or obstruct goaf span L
3Hang a plurality of flexible filling bag (2);
B, expose side in the flexible filling bag (2) of hanging and arrange individual prop (3) at interval;
C, set up the template (4) that relies on individual prop (3) in flexible filling bag (1) outside;
D, by Grouting Pipe filling high-water material in flexible filling bag (2), until full;
E, treat that high-water material solidifies after, stripping (4) and individual prop (3) are finished row's filling barrier bodies;
F, with the propelling of coal-face:
Vertically the filling barrier bodies of arranging continues to construct next exclusion spacer, the continuous flexible filling bag (2) of hanging in a last exclusion spacer position, and repeating step b, c, d, e go round and begin again, and intercept the goaf span L when the filling barrier bodies of constructing reaches
2The time, vertically and between the filling barrier bodies of vertically arranging constructing a horizontal row,,, finish the totally-enclosed of regional goaf until full by filling pipe flood irrigation high-water material in enclosing wall to filling barrier bodies enclosing wall (8);
Transversely arranged filling barrier bodies reaches at interval and intercepts the goaf span L
3The time, construct next horizontal row to the enclosing wall filling barrier bodies of arranging, by Grouting Pipe flood irrigation high-water material in enclosing wall filling barrier bodies,, finish the totally-enclosed of regional goaf until full;
G, advance, continue to hang filling bag (2), repeat above-mentioned steps b, c, d with the continuation of coal-face, e, f goes round and begins again, until finishing whole goaf constructing and the flood irrigation operation of goaf (1) to barrier bodies in length and breadth;
H, construct enclosing wall (7), carry out unified at last filling at Yun Xiang (5) and track lane (6), with goaf (1) not pack portion be full of, finish the packing job in whole goaf.
2. separate type filling method of goaf according to claim 1 is characterized in that: the length of described flexible filling bag (2) is 10m~20m, and width is 2m~3m, and height is identical with the work plane mining height.
3. separate type filling method of goaf according to claim 1 is characterized in that: the spacing distance L of flexible filling bag (2) is hung in described vertical arrangement
1Be about 10m~25m, intercept the goaf span L
2Should be about 8m~30m less than the step pitch of directly pushing up or old top collapses for the first time and.
4. separate type filling method of goaf according to claim 1 is characterized in that: described transversely arranged obstruct goaf span L of hanging flexible filling bag (2)
3Should be about 8m~25m less than directly top or the old top step pitch that falls that collapses for the first time.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN200910185318A CN101705838A (en) | 2009-11-05 | 2009-11-05 | Separate type filling method of goaf |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN200910185318A CN101705838A (en) | 2009-11-05 | 2009-11-05 | Separate type filling method of goaf |
Publications (1)
Publication Number | Publication Date |
---|---|
CN101705838A true CN101705838A (en) | 2010-05-12 |
Family
ID=42376087
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN200910185318A Pending CN101705838A (en) | 2009-11-05 | 2009-11-05 | Separate type filling method of goaf |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN101705838A (en) |
Cited By (20)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101881181A (en) * | 2010-06-23 | 2010-11-10 | 华唯金属矿产资源高效循环利用国家工程研究中心有限公司 | Mine goaf tailing-filled concrete enclosing wall |
CN101975085A (en) * | 2010-09-09 | 2011-02-16 | 中国矿业大学 | Gob-side entry retaining reinforcing filling body structure and construction method thereof |
CN102852552A (en) * | 2012-09-17 | 2013-01-02 | 扬州中矿建筑新材料科技有限公司 | High-water material filling column and construction method thereof |
CN102865102A (en) * | 2012-09-26 | 2013-01-09 | 山西焦煤集团有限责任公司 | Self-flowing concrete convex and concave self-connection filling method |
CN102979572A (en) * | 2012-12-26 | 2013-03-20 | 广东宏大爆破股份有限公司 | Active reinforced filling wall and construction method |
CN103498696A (en) * | 2013-10-02 | 2014-01-08 | 中国矿业大学 | Method for grouting, filling and compacting goaf filling body from roof roadway |
CN103742147A (en) * | 2014-01-17 | 2014-04-23 | 淄博王煤矿业有限公司 | Coal mining technology by using continuous beam bridge type filling method |
CN103850690A (en) * | 2012-12-04 | 2014-06-11 | 四川省煤炭产业集团有限责任公司 | Concrete block and anchor rope roof cutting matching god-side entry retaining method for coal mining without pillars |
WO2014086296A1 (en) * | 2012-12-07 | 2014-06-12 | 中国矿业大学 | Method of local filling to control surface subsidence in gob |
CN104846848A (en) * | 2015-03-23 | 2015-08-19 | 安徽理工大学 | Method for controlling earth surface water and soil loss of underground layered mineral product mining subsidence area |
CN105332733A (en) * | 2015-09-25 | 2016-02-17 | 山东科技大学 | Strip filling method of conventional mining face goaf pumping cementing materials |
CN105971669A (en) * | 2016-07-06 | 2016-09-28 | 冀中能源邯郸矿业集团有限公司 | Gob sealing method capable of protecting coal seam from spontaneous combustion |
CN106121722A (en) * | 2016-06-25 | 2016-11-16 | 扬州中矿建筑新材料科技有限公司 | A kind of method quickly constructing fire dam |
CN107676131A (en) * | 2017-11-10 | 2018-02-09 | 缪协兴 | A kind of solid waste packs filling coal mining method |
CN108204244A (en) * | 2016-12-20 | 2018-06-26 | 中国矿业大学(北京) | The spoil interval method of collecting coal by the means of filling |
CN108301870A (en) * | 2017-12-13 | 2018-07-20 | 中国矿业大学 | A kind of underground coal mine filling bag shaped structure and its application method |
CN108729917A (en) * | 2018-05-29 | 2018-11-02 | 中国煤炭地质总局勘查研究总院 | The method for preventing bump |
CN109611134A (en) * | 2018-11-12 | 2019-04-12 | 山东科技大学 | A kind of grouting cable anchor and strip filling method for loose media strip filling |
CN111706392A (en) * | 2020-05-19 | 2020-09-25 | 南昌大学 | Plugging and constructing method suitable for abandoned mine hole and mine tunnel |
CN113389589A (en) * | 2021-07-30 | 2021-09-14 | 西安科技大学 | Goaf coal spontaneous combustion partition isolation prevention method based on coal face pushing progress |
-
2009
- 2009-11-05 CN CN200910185318A patent/CN101705838A/en active Pending
Cited By (28)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101881181A (en) * | 2010-06-23 | 2010-11-10 | 华唯金属矿产资源高效循环利用国家工程研究中心有限公司 | Mine goaf tailing-filled concrete enclosing wall |
CN101975085A (en) * | 2010-09-09 | 2011-02-16 | 中国矿业大学 | Gob-side entry retaining reinforcing filling body structure and construction method thereof |
CN101975085B (en) * | 2010-09-09 | 2013-07-03 | 中国矿业大学 | Gob-side entry retaining reinforcing filling body structure construction method |
CN102852552A (en) * | 2012-09-17 | 2013-01-02 | 扬州中矿建筑新材料科技有限公司 | High-water material filling column and construction method thereof |
CN102865102A (en) * | 2012-09-26 | 2013-01-09 | 山西焦煤集团有限责任公司 | Self-flowing concrete convex and concave self-connection filling method |
CN103850690A (en) * | 2012-12-04 | 2014-06-11 | 四川省煤炭产业集团有限责任公司 | Concrete block and anchor rope roof cutting matching god-side entry retaining method for coal mining without pillars |
AU2013354613B2 (en) * | 2012-12-07 | 2016-05-05 | China University Of Mining And Technology | Method of local filling to control surface subsidence in worked-out area |
WO2014086296A1 (en) * | 2012-12-07 | 2014-06-12 | 中国矿业大学 | Method of local filling to control surface subsidence in gob |
CN102979572A (en) * | 2012-12-26 | 2013-03-20 | 广东宏大爆破股份有限公司 | Active reinforced filling wall and construction method |
CN103498696A (en) * | 2013-10-02 | 2014-01-08 | 中国矿业大学 | Method for grouting, filling and compacting goaf filling body from roof roadway |
CN103498696B (en) * | 2013-10-02 | 2015-08-05 | 中国矿业大学 | A kind of method from roadway in the roof grouting filling compacting goaf filling body |
CN103742147A (en) * | 2014-01-17 | 2014-04-23 | 淄博王煤矿业有限公司 | Coal mining technology by using continuous beam bridge type filling method |
CN104846848B (en) * | 2015-03-23 | 2016-08-24 | 安徽理工大学 | A kind of method controlling the earth's surface soil erosion of stratiform exploitation of mineral resources Subsidence Area, underground |
CN104846848A (en) * | 2015-03-23 | 2015-08-19 | 安徽理工大学 | Method for controlling earth surface water and soil loss of underground layered mineral product mining subsidence area |
CN105332733A (en) * | 2015-09-25 | 2016-02-17 | 山东科技大学 | Strip filling method of conventional mining face goaf pumping cementing materials |
CN106121722A (en) * | 2016-06-25 | 2016-11-16 | 扬州中矿建筑新材料科技有限公司 | A kind of method quickly constructing fire dam |
CN105971669A (en) * | 2016-07-06 | 2016-09-28 | 冀中能源邯郸矿业集团有限公司 | Gob sealing method capable of protecting coal seam from spontaneous combustion |
CN108204244A (en) * | 2016-12-20 | 2018-06-26 | 中国矿业大学(北京) | The spoil interval method of collecting coal by the means of filling |
CN107676131A (en) * | 2017-11-10 | 2018-02-09 | 缪协兴 | A kind of solid waste packs filling coal mining method |
CN108301870A (en) * | 2017-12-13 | 2018-07-20 | 中国矿业大学 | A kind of underground coal mine filling bag shaped structure and its application method |
CN108729917A (en) * | 2018-05-29 | 2018-11-02 | 中国煤炭地质总局勘查研究总院 | The method for preventing bump |
CN108729917B (en) * | 2018-05-29 | 2020-04-03 | 中国煤炭地质总局勘查研究总院 | Method for preventing rock burst |
CN109611134A (en) * | 2018-11-12 | 2019-04-12 | 山东科技大学 | A kind of grouting cable anchor and strip filling method for loose media strip filling |
CN109611134B (en) * | 2018-11-12 | 2020-03-31 | 山东科技大学 | Grouting anchor cable for filling loose body strips and strip filling method |
CN111706392A (en) * | 2020-05-19 | 2020-09-25 | 南昌大学 | Plugging and constructing method suitable for abandoned mine hole and mine tunnel |
CN111706392B (en) * | 2020-05-19 | 2021-06-25 | 南昌大学 | Plugging and constructing method suitable for abandoned mine hole and mine tunnel |
CN113389589A (en) * | 2021-07-30 | 2021-09-14 | 西安科技大学 | Goaf coal spontaneous combustion partition isolation prevention method based on coal face pushing progress |
CN113389589B (en) * | 2021-07-30 | 2023-03-24 | 西安科技大学 | Goaf coal spontaneous combustion partition isolation prevention method based on coal face pushing progress |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101705838A (en) | Separate type filling method of goaf | |
CN101701526B (en) | Goaf bag-type packing method | |
CN101806226B (en) | Mined out space dam-type filling method | |
CN103422469B (en) | Artificial retaining dam for coal mine underground reservoir and connecting method of artificial retaining dam and coal pillar dam bodies as well as surrounding rocks | |
CN103615285B (en) | A kind of stope route arrangement and method being beneficial to Tight filling | |
CN102635392B (en) | Co-extraction method for pillar-less coal and gas of advanced entry-retaining construction extraction engineering | |
CN103410515B (en) | It is a kind of that three-soft seam is reciprocating combines mining method without coal column | |
AU2013354613B2 (en) | Method of local filling to control surface subsidence in worked-out area | |
CN102505963B (en) | Stope face roof water pre-drainage construction method | |
CN105587318A (en) | Filling mining method for continuous backstoping of gently inclined parallel medium thick ore body group | |
CN104061001B (en) | Gob side entry retaining exploitation support process method | |
CN103422886A (en) | Artificial retaining dam for coal mine distributed underground reservoir and damming method thereof | |
CN102011611A (en) | Strip-type filling method of high water-swelling material for controlling movement and deformation of overlying strata | |
CN101196123A (en) | Aquifer preventing and controlling method for coal face roof plate separation layer | |
CN101737052A (en) | Sublevel fill-mining method | |
CN102383820B (en) | Coal mine underground airbridge construction method | |
CN103615250A (en) | Subsection-studding all-open-stoping backfilling collaborative mining method | |
CN102644476A (en) | Method for pumping gas of protected layer by layer penetration and hole drilling on high-position drilling fields of protecting layer machinery tunnel | |
RU2537711C1 (en) | Erection of tunnels in structurally unstable soils with karst phenomena and/or boil processes | |
CN108979638B (en) | Composite gob-side entry retaining method for wedge-shaped regenerated wall and single-leg shed beam of coal mining roadway | |
CN109707442A (en) | A kind of quick grouting filling bag in the goaf synchronous with coal cutting and its coal-mining method | |
CN102852551A (en) | Gob-side entry retaining method using high-water material filling columns | |
CN109538210A (en) | A kind of soft extremely irregularcoal seam fully mechanized coal face gob-side entry retaining method of high methane three | |
CN108005654A (en) | Face upward and adopt large-mining-height working surface and cross old working construction technology | |
CN100999997A (en) | Method for drawing-out near layer gas of top-coal caving face |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C12 | Rejection of a patent application after its publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20100512 |