Summary of the invention
The object of the present invention is to provide a kind of method of processing wharf foundation by geotextile granular material pile, this method can be practiced thrift construction investment, accelerating construction progress, and the minimizing people is the phenomenon of back-silting.
To achieve these goals, technical scheme of the present invention is: the method for processing wharf foundation by geotextile granular material pile is characterized in that it comprises the steps:
1) according to the wharf apron depth condition, basic engineering is not dredged or is carried out shallow slot and dredge, and the foundation trench dredging degree of depth is not more than 250cm;
2) in the scope that is not less than harbour basis length and width size (the long 0~3m that grows up in the harbour basis, be wider than in the scope of the wide 0~3m size in harbour basis) (job practices of geotextile granular pile is seen one Chinese patent application 200810197321.X, and denomination of invention is: the method for processing soft foundation by earthwork fabric granular pile) to lay geotextile granular pile 1; The plane mode of laying out pile is quadrangle or triangle; The stake footpath parameter 40~200cm of geotextile granular pile; The spacing of geotextile granular pile is 0.4~5m; The stake of geotextile granular pile is long to be 1~30m, and the spacing of geotextile granular pile can be calculated or test definite according to the stable of basis and distortion settlement request with stake is long;
3) level is laid layer of geotextile layer 2 on the mud face of geotextile granular pile top bit, and geotextile layer 2 is the composite construction layer of one deck geotextiles or one deck geotextiles and GSZ;
4) on the geotextile layer of having laid 2, lay basic mattress layer 3, the material of basic mattress layer 3 is coarse sand or piece (broken) stone, and the thickness of foundation pad is 50~250cm;
5) basic mattress layer employing tamping or quick-fried rammer are closely knit;
6) material of laying one deck second geogrids layer 5, the second geogrids layer in closely knit basic mattress layer top, horizontal is a GSZ;
7) lay prefabricated reinforced concrete caisson or steel concrete square 6 on second geogrids layer 5.
In the said basic mattress layer, be GSZ by the material of laying first geogrids layer, 4, the first geogrids layer 4 apart from level of per 50~100cm interlamellar spacing.Can establish 1~4 first geogrids layer in the mattress layer of basis.
The distance of said interlamellar spacing is meant: the distance between basecoat first geogrids layer and the geotextile layer 2; First adjacent geogrids layer and the distance between first geogrids layer, the distance between last layer first geogrids layer and second geogrids layer 5.
The maximum particle diameter of piece (broken) stone should not surpass 10cm.
The invention has the beneficial effects as follows: adopt processing wharf foundation by geotextile granular material pile, can accomplish not dredge or reduce the amount of dredging widely, this helps practicing thrift construction investment, accelerating construction progress, can guarantee workmanship simultaneously, and reduces the people and be the phenomenon of back-silting.
The specific embodiment
In order to understand the present invention better, further illustrate content of the present invention below in conjunction with instance, but the present invention not only is confined to following embodiment.
Embodiment 1 (processing has the harbour basis of foundation trench):
The method of processing wharf foundation by geotextile granular material pile, it comprises the steps:
1) according to the wharf apron depth condition, basic engineering is not dredged;
2) in the scope that is not less than harbour basis length and width size (the long 0m that grows up in the harbour basis, be wider than in the scope of the wide 0m size in harbour basis) (job practices of geotextile granular pile is seen one Chinese patent application 200810197321.X to laying geotextile granular pile, and denomination of invention is: the method for processing soft foundation by earthwork fabric granular pile); The plane mode of laying out pile is a quadrangle; The stake footpath parameter 60cm of geotextile granular pile; The spacing of geotextile granular pile is 1.8m, and the stake of geotextile granular pile is long to be 3m, and the spacing of geotextile granular pile can be calculated or test definite according to the stable of basis and distortion settlement request with stake is long;
3) level is laid the layer of geotextile layer on the mud face of geotextile granular pile top bit, and the geotextile layer is one deck geotextiles;
4) on the geotextile layer of having laid, lay basic mattress layer, the material of basic mattress layer is a coarse sand, and the thickness of foundation pad is 50cm;
5) basic mattress layer adopts tamping;
6) lay one deck geogrids layer (for one deck GSZ) in closely knit basic mattress layer top, horizontal, the material of geogrids layer is a GSZ;
7) on geogrids layer, lay prefabricated reinforced concrete caisson.
Embodiment 2 (processing has the harbour basis of foundation trench):
As shown in Figure 1, the method for processing wharf foundation by geotextile granular material pile, it comprises the steps:
1) according to the wharf apron depth condition, basic engineering is carried out shallow slot and is dredged, and the foundation trench dredging degree of depth is 240cm;
2) in the scope that is not less than harbour basis length and width size (the long 1m that grows up in the harbour basis, be wider than in the scope of the wide 1m size in harbour basis) (job practices of geotextile granular pile is seen one Chinese patent application 200810197321.X to laying geotextile granular pile 1, and denomination of invention is: the method for processing soft foundation by earthwork fabric granular pile); The plane mode of laying out pile is a quadrangle; The stake footpath parameter 100cm of geotextile granular pile; The spacing of geotextile granular pile is 2m, and the stake of geotextile granular pile is long to be 10m, and the spacing of geotextile granular pile can be calculated or test definite according to the stable of basis and distortion settlement request with stake is long;
3) level is laid layer of geotextile layer 2 on the mud face of geotextile granular pile top bit; Geotextile layer 2 is the composite construction layer (cover one deck GSZ on one deck geotextiles, or cover one deck geotextiles on one deck GSZ) of one deck geotextiles and one deck GSZ;
4) on the geotextile layer of having laid 2, lay basic mattress layer 3; The material of basis mattress layer 3 is a coarse sand; The thickness of foundation pad is 150cm; In basic mattress layer thickness (as shown in Figure 1), by every 50cm interlamellar spacing lay first geogrids layer 4 (for one deck GSZ) apart from level, the material of first geogrids layer 4 is a GSZ;
5) basic mattress layer adopts tamping;
6) lay one deck second geogrids layer 5 (for one deck GSZ) in closely knit basic mattress layer top, horizontal, the material of second geogrids layer is a GSZ;
7) lay prefabricated reinforced concrete caisson 6 on second geogrids layer 5.
Embodiment 3 (processing has the harbour basis of foundation trench):
As shown in Figure 1, the method for processing wharf foundation by geotextile granular material pile, it comprises the steps:
1) according to the wharf apron depth condition, basic engineering is carried out shallow slot and is dredged, and the foundation trench dredging degree of depth is 50cm;
2) in the scope that is not less than harbour basis length and width size (the long 3m that grows up in the harbour basis, be wider than in the scope of the wide 3m size in harbour basis) (job practices of geotextile granular pile is seen one Chinese patent application 200810197321.X to laying geotextile granular pile 1, and denomination of invention is: the method for processing soft foundation by earthwork fabric granular pile); The plane mode of laying out pile is a triangle; The stake footpath parameter 120cm of geotextile granular pile; The spacing of geotextile granular pile is 3m, and the stake of geotextile granular pile is long to be 30m, and the spacing of geotextile granular pile can be calculated or test definite according to the stable of basis and distortion settlement request with stake is long;
3) level is laid layer of geotextile layer 2 on the mud face of geotextile granular pile top bit; Geotextile layer 2 is the composite construction layer (cover one deck GSZ on one deck geotextiles, or cover one deck geotextiles on one deck GSZ) of one deck geotextiles and one deck GSZ;
4) on the geotextile layer of having laid 2, lay basic mattress layer 3; The material of basis mattress layer 3 is piece (broken) stone; The thickness of foundation pad is 200cm, and in basic mattress layer thickness, (is one deck GSZ by every 100cm interlamellar spacing apart from level laying one deck first geogrids layer 4; The basis mattress layer is divided into two-layer up and down by first geogrids layer, two-layer up and down each 100cm), the material of first geogrids layer 4 is a GSZ;
5) it is closely knit that basic mattress layer adopts quick-fried rammer;
6) lay one deck second geogrids layer 5 (for one deck GSZ) in closely knit basic mattress layer top, horizontal, the material of second geogrids layer is a GSZ;
7) lay prefabricated steel concrete square 6 on second geogrids layer 5.
Embodiment 4:
Basic identical with embodiment 3, difference is: the thickness of foundation pad is 250cm, and level is laid 4 first geogrids layer 4 (by laying apart from level of every 50cm interlamellar spacing) in basic mattress layer thickness.
Embodiment 5 (the geotextile granular pile is handled the harbour basis of no foundation trench):
As shown in Figure 2, the method for processing wharf foundation by geotextile granular material pile and embodiment 2 are basic identical, just do not have foundation trench.