CN101538852B - 一种用于冶炼车间粉煤灰土层与回填山石层地坪地基的压密注浆加固工艺 - Google Patents

一种用于冶炼车间粉煤灰土层与回填山石层地坪地基的压密注浆加固工艺 Download PDF

Info

Publication number
CN101538852B
CN101538852B CN2009101165570A CN200910116557A CN101538852B CN 101538852 B CN101538852 B CN 101538852B CN 2009101165570 A CN2009101165570 A CN 2009101165570A CN 200910116557 A CN200910116557 A CN 200910116557A CN 101538852 B CN101538852 B CN 101538852B
Authority
CN
China
Prior art keywords
grouting
hole
slip casting
soil
layer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN2009101165570A
Other languages
English (en)
Other versions
CN101538852A (zh
Inventor
刘少美
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Metallurgical Industry Co ltd
China MCC17 Group Co Ltd
Original Assignee
China Mcc17 Construction Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Mcc17 Construction Co ltd filed Critical China Mcc17 Construction Co ltd
Priority to CN2009101165570A priority Critical patent/CN101538852B/zh
Publication of CN101538852A publication Critical patent/CN101538852A/zh
Application granted granted Critical
Publication of CN101538852B publication Critical patent/CN101538852B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

本发明公开了一种用于冶炼车间粉煤灰土层与回填山石层地坪地基的压密注浆加固工艺,包括以下工序:(1)测放孔位:孔位测放,做好标记;(2)插管:注浆管采用带堵头的金属管,按设计孔深配置好单孔所需注浆管总根数;将上好堵头的第一节注浆管对正孔位,架设好振动器,徐徐振入土体,然后用活接箍接上第二节,再振入,依此类推,直至将配好的注浆管全部插入;(3)浆液制备:采用水泥为主加水配成浆液,水灰比控制在0.8∶1~1∶1之间;(4)注浆:注浆由下而上,每次拔管高度不超过0.4米,确保注浆段均匀吃浆,注浆量按每立方加固土体体积15%至20%控制。本发明可以在多专业、多工种交叉施工以及施工用地十分紧张的不利环境下方便地实施,满足了粉煤灰土层与回填山石层地质条件下的炼钢车间内地坪地基施工时工序穿插的要求。

Description

一种用于冶炼车间粉煤灰土层与回填山石层地坪地基的压密注浆加固工艺
技术领域
本发明涉及一种复杂的软弱地基加固处理技术,特别是涉及一种用于冶炼车间粉煤灰土层与回填山石层地坪地基的压密注浆加固工艺,并可在钢铁、有色、黄金、化工等工业厂房、车间地坪地基的加固处理中广泛应用。
背景技术
对于软土地区的厂房建筑,若在设计或施工阶段未采取有效的地基处理措施,则建成后较易出现大面积地面沉降而影响正常生产。目前采用的方法大多为桩基、碎石换填、水泥土桩等。
目前,冶金工业厂房车间内的地坪地基的加固处理一般采用桩基或换填分层压实回填土料的方法。中国专利200510134966公开了一种快速“高真空击密、桩基”复合软地基处理方法,该方法首先采用在软土中密布井点管,井点管上端用卧管连接至真空泵抽真空拔除井点管,击密,如此井点管抽真空、击密交叉作用数遍;然后,采用在软土中填入碎石再击密成墩,或采用沉管法成碎石桩,或采用水泥土搅拌成桩,使软土通过井点管真空抽水、击密数遍交叉、再结合碎石墩/桩或水泥土桩形成一个复合地基。该方法能够能有效快速提高地基承载力,工后或差异沉降小,但是施工工序复杂,施工成本高。
炼钢车间因其施工的工序穿插,多专业、多工种交叉施工,且施工用地空间有限、操作空间共享,施工安全隐患多,以及受工期要求等因素的影响,使得采用桩基或换填分层压实回填土料的地基加固处理方法不能够满足粉煤灰土层与回填山石层地质条件下的炼钢车间内地坪地基的施工需要。
发明内容
本发明的目的就是针对现有技术中存在的上述缺陷,而提供一种用于冶炼车间粉煤灰土层与回填山石层地坪地基的压密注浆加固工艺,该工艺不仅能够加固粉煤灰土层与回填山石层类地基,提高土体的承载力和减少地基的沉降变形,而且能够很方便地在多专业、多工种以及施工用地十分紧张的情况下进行正常施工。
为实现本发明的目的,本发明一种用于冶炼车间粉煤灰土层与回填山石层地坪地基的压密注浆加固工艺采用以下技术方案。
本发明一种用于冶炼车间粉煤灰土层与回填山石层地坪地基的压密注浆加固工艺包括测放孔位、插管、浆液制备、注浆工序:
(1)测放孔位:根据控制轴线,用钢尺或其它测量工具进行孔位测放,并做好标记。
(2)插管:注浆管采用带堵头的金属管,按设计孔深配置好单孔所需注浆管总根数。将上好堵头的第一节注浆管对正孔位,架设好振动器,徐徐振入土体,然后用活接箍接上第二节,再振入,依此类推,直至将配好的注浆管全部插入。
在插管过程中如遇山石块则采用风镐钻孔,然后将配好的注浆管插入。插管时应尽量保持垂直,插管后做好孔口密封工作。注浆孔如遇障碍正常移位时,要保证注浆孔数不变。
(3)浆液制备:采用水泥为主加水配成浆液,水灰比控制在0.5∶1~1∶1之间,一般在0.8∶1~1∶1之间。对回填山石层局部孔隙较大部位注浆水灰比提高到0.5∶1~0.8∶1之间。
(4)注浆:注浆由下而上,每次拔管高度不超过0.4米,确保注浆段均匀吃浆,注浆量按每立方加固土体体积15%至20%控制。
在注浆过程中,先注入5~10升水灰比为4∶1~1∶1的稀浆,对注浆通道充分湿润润滑后,再注入水灰比在0.8∶1~1∶1的稠浆,对回填山石层局部孔隙较大部位注浆水灰比提高到0.5∶1~0.8∶1之间。
注浆过程中,注浆压力随深度而变化,一般控制在0.2~0.5Mpa。
在施工过程中,对已施工地段用振动器插孔自检,发现有加固欠佳地段进行二次补浆。确保加固后地基承载力达到140KPa。
注浆参数、注浆设备根据炼钢车间的粉煤灰土层与回填山石层工程地质、水文地质条件以及车间使用荷载要求进行确定的,以确保车间地坪地基的沉降变形控制在容许的范围内,从而达到提高车间地基的承载能力的目的。
本发明采用以上技术方案后,具有以下有益效果:
(1)可以在多专业、多工种交叉施工以及施工用地十分紧张的不利环境下方便地实施,满足了粉煤灰土层与回填山石层地质条件下的炼钢车间内地坪地基施工时工序穿插的要求。
(2)施工工序简单,采用的设备基本为常规设备,施工成本低。
(3)能够满足复杂水文地质条件下使用载荷要求,地基的承载能力高。
附图说明
图1是本发明一种用于冶炼车间粉煤灰土层与回填山石层地坪地基的压密注浆加固工艺的施工工艺流程图。
图2是本发明一种用于冶炼车间粉煤灰土层与回填山石层地坪地基的压密注浆加固工艺的加固立面图。
具体实施方式
下面结合附图和实施例对本发明一种用于冶炼车间粉煤灰土层与回填山石层地坪地基的压密注浆加固工艺作进一步说明。
由图1所示的本发明一种用于冶炼车间粉煤灰土层与回填山石层地坪地基的压密注浆加固工艺施工工艺流程图看出,本发明包括测放孔位、插管、浆液制备、注浆工序:
(1)测放孔位:根据控制轴线,用钢尺进行孔位测放,并做好标记。
(2)插管:采用振动或钻孔法插管,注浆管采用Φ43带堵头的金属管,按设计孔深配置好单孔所需注浆管总根数,每根注浆管长度一般为1.1米左右。将上好堵头的第一节注浆管对正孔位,架设好振动器,徐徐振入土体,然后用活接箍接上第二节,再振入,依此类推,直至将配好的注浆管全部插入;在插管过程中如遇山石块则采用风镐钻孔,然后将配好的注浆管插入。插管时应尽量保持垂直,插管后做好孔口密封工作。注浆孔如遇障碍正常移位时,要保证注浆孔数不变。
(3)浆液制备:采用po32.5级硅酸盐水泥为主加水配成浆液,水灰比控制在0.5∶1~1∶1之间,对回填山石层局部孔隙较大部位注浆水灰比提高到0.5∶1~0.8∶1之间。
(4)注浆:注浆由下而上,每次拔管高度不超过0.4米,确保注浆段均匀吃浆,注浆量按每立方加固土体体积15%至20%控制,注浆压力随深度而变化,一般控制在0.2~0.5Mpa。
注浆过程中,先注入5~10升水灰比为4∶1~1∶1的稀浆,对注浆通道充分湿润润滑后,再注入水灰比控制在0.5∶1~1∶1之间的稠浆。
施工过程中,对已施工地段用振动器插孔自检,发现有加固欠佳地段进行二次补浆。确保加固后地基承载力达到140KPa。
由图2所示的本发明一种用于冶炼车间粉煤灰土层与回填山石层地坪地基的压密注浆加固工艺的加固立面图看出,本发明实施例中的注浆深度为6.0m,注浆标高-1.4~-7.4m;注浆孔孔距1.0m,排距1.0m,为满堂布置。

Claims (1)

1.一种用于冶炼车间粉煤灰土层与回填山石层地坪地基的压密注浆加固工艺,其特征在于包括以下工序:
(1)测放孔位:根据控制轴线,用钢尺或其它测量工具进行孔位测放,并做好标记;
(2)插管:注浆管采用带堵头的金属管,按设计孔深配置好单孔所需注浆管总根数;将上好堵头的第一节注浆管对正孔位,架设好振动器,徐徐振入土体,然后用活接箍接上第二节,再振入,依此类推,直至将配好的注浆管全部插入;
(3)浆液制备:采用水泥为主加水配成浆液,水灰比控制在0.8∶1~1∶1之间;
(4)注浆:注浆由下而上,每次拔管高度不超过0.4米,确保注浆段均匀吃浆,注浆量按每立方加固土体体积15%至20%控制;在注浆过程中,先注入5~10升水灰比为4∶1~1∶1的稀浆,对注浆通道充分湿润润滑后,再注入水灰比在0.8∶1~1∶1的稠浆。
CN2009101165570A 2009-04-15 2009-04-15 一种用于冶炼车间粉煤灰土层与回填山石层地坪地基的压密注浆加固工艺 Active CN101538852B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2009101165570A CN101538852B (zh) 2009-04-15 2009-04-15 一种用于冶炼车间粉煤灰土层与回填山石层地坪地基的压密注浆加固工艺

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2009101165570A CN101538852B (zh) 2009-04-15 2009-04-15 一种用于冶炼车间粉煤灰土层与回填山石层地坪地基的压密注浆加固工艺

Publications (2)

Publication Number Publication Date
CN101538852A CN101538852A (zh) 2009-09-23
CN101538852B true CN101538852B (zh) 2010-11-17

Family

ID=41122228

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2009101165570A Active CN101538852B (zh) 2009-04-15 2009-04-15 一种用于冶炼车间粉煤灰土层与回填山石层地坪地基的压密注浆加固工艺

Country Status (1)

Country Link
CN (1) CN101538852B (zh)

Families Citing this family (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102400698A (zh) * 2010-09-17 2012-04-04 焦作煤业集团赵固(新乡)能源有限责任公司 两硬大采高综采工作面煤壁片帮防治方法
CN102493432A (zh) * 2011-12-09 2012-06-13 中国建筑西南勘察设计研究院有限公司 一种注浆管
CN103205962A (zh) * 2013-04-27 2013-07-17 杨众 沉陷地坪注浆抬升的方法
CN104556869B (zh) * 2014-12-26 2017-11-17 山东三生新材料科技有限公司 一种高硬度地坪及其制备方法
CN107059912A (zh) * 2017-03-20 2017-08-18 中国十七冶集团有限公司 一种坐落于松软土层的人货电梯基础注浆加固处理方法
CN109440757A (zh) * 2018-11-30 2019-03-08 长沙恒德岩土工程技术有限公司 一种用于岩溶区的地基加固方法
CN111119262A (zh) * 2019-12-30 2020-05-08 山东农业大学 一种基于可回收注浆管的对既有桩基进行加固的方法及其应用
CN111303892B (zh) * 2020-03-12 2021-03-23 河南霖牧农业技术有限公司 一种农田改造用铝灰材料及使用方法
CN111303891B (zh) * 2020-03-12 2021-03-23 河南霖牧农业技术有限公司 一种农田改造材料及使用方法
CN111363552B (zh) * 2020-03-12 2021-11-16 河南霖牧农业技术有限公司 一种农田改造用材料及使用方法
CN113502705A (zh) * 2021-08-25 2021-10-15 济南黄河路桥建设集团有限公司 一种粉煤灰堆积场地城市道路路基注浆加固施工工法

Also Published As

Publication number Publication date
CN101538852A (zh) 2009-09-23

Similar Documents

Publication Publication Date Title
CN101538852B (zh) 一种用于冶炼车间粉煤灰土层与回填山石层地坪地基的压密注浆加固工艺
AU2020376449B2 (en) Construction method of pressurized grouting pile based on reinforcing fiber and metakaolin
CN102226336B (zh) 地基加固处理方法
CN102061697B (zh) 建筑物不均匀沉降处理方法
CN109208625B (zh) 一种地下桩基础溶洞加强加固种山施工方法
CN101761237B (zh) 盾构隧道近距离穿越建筑物变形控制的隔离桩施工方法
CN101812843B (zh) 中心灌注后压浆桩施工方法及其使用的灌注器和注浆器
CN109371974A (zh) 一种适用于坚硬地质的phc管桩植入施工方法
CN102296630A (zh) 长螺旋高压搅喷水泥土连续墙施工方法
CN102943466A (zh) 微型钢管混凝土桩穿透路基层加固软弱地基施工工法
CN107975375A (zh) 一种城市隧道微型钢管桩加固软弱地基施工方法
CN114808990A (zh) 一种高压预填充溶洞桩基施工方法
CN106284315B (zh) 一种穿过溶洞的钻孔灌注桩施工方法
CN206070508U (zh) 一种加固地基基础的装置
CN106522191A (zh) 一种变电站地基处理方法及其应用
KR101746654B1 (ko) 광산 대규모 채굴공동 보강을 위한 골재 그라우트 기둥 시공 방법
CN104988914A (zh) 一种水域环境下的钻孔灌注桩断桩处理方法
CN108755671B (zh) 一种富水砾砂层三轴搅拌桩施工方法
CN101565955B (zh) 一种采用微型应力隔离桩加固既有桩基的方法
CN106837343B (zh) 顶管出洞口二次加固的施工方法
CN105064351A (zh) 一种植桩方法
CN213869905U (zh) 松散岩堆体地层下大断面隧道基底防沉降结构
CN101892665A (zh) 一种注浆振冲碎石桩复合地基的施工方法
CN113914304A (zh) 一种cfg桩长螺旋钻孔芯管泵送混合料灌注成桩施工方法
CN110387867B (zh) 适用于泥炭质土地层条件下三轴搅拌桩加固的方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: 243061 Anhui province Ma'anshan mountain rain Yushan Road No. 88

Patentee after: CHINA MCC17 GROUP Co.,Ltd.

Address before: 243061 Anhui province Ma'anshan mountain rain Yushan Road No. 88

Patentee before: CHINA MCC17 CONSTRUCTION Co.,Ltd.

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20201202

Address after: No.28 Shuguang Xili, Chaoyang District, Beijing 100028

Patentee after: China Metallurgical Industry Co.,Ltd.

Address before: 243061 Anhui province Ma'anshan mountain rain Yushan Road No. 88

Patentee before: CHINA MCC17 GROUP Co.,Ltd.