CN101440606A - Pier-side bracket capable of adjusting spatial position of steel beam - Google Patents
Pier-side bracket capable of adjusting spatial position of steel beam Download PDFInfo
- Publication number
- CN101440606A CN101440606A CNA200810188047XA CN200810188047A CN101440606A CN 101440606 A CN101440606 A CN 101440606A CN A200810188047X A CNA200810188047X A CN A200810188047XA CN 200810188047 A CN200810188047 A CN 200810188047A CN 101440606 A CN101440606 A CN 101440606A
- Authority
- CN
- China
- Prior art keywords
- bracket
- pier
- steel
- column
- spatial position
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
The invention discloses a pier-side bracket capable of adjusting the spatial position of a steel girder and relates to pier-side bracket which is used in construction of mounting double cantilevers of a steel truss arch of a bridge project; upper brackets (100), separation interfaces (300) which can adjust the upper brackets and lower brackets, and the lower brackets (200) are mounted sequentially from top to bottom and are in bilateral symmetry; the top end of the upper bracket (100) is fixedly connected with a steel girder (403) of a main bridge; and the lower bracket (200) is arranged on the upper surface of a bearing platform (402) of a bearing pier body (401). The pier-side bracket which can adjust the spatial position of the steel girder is combined with the steep girder of the main bridge, solves the problem about stability in the process of mounting the double cantilevers of the steel truss arch in order that the bracket has the function of adjusting horizontal and vertical displacement, solves the problem of adjusting deviation of the steel girder and ensures the closure precision of the steel girder.
Description
Technical field
The present invention relates to the pier-side bracket of use in the two cantilever erection constructions of steel braced arch in the bridge engineering, specifically a kind of pier-side bracket of adjustable spatial position of steel beam.
Background technology
In big Span Continuous steel braced arch construction,, then need to solve three problems: how to install between (1) pier epimerite if adopt the job practices of backing down two cantilever erections of beginning from pier; (2) how girder steel guarantees the balance and stability of girder steel in two cantilever erection processes in two cantilever erection processes; (3) how installation accuracy guarantees between the pier epimerite.
For the problems referred to above, the solution in the general bridge engineering construction is: the installation between the pier epimerite generally adopts pier-side bracket as operation platform, carriage not with the girder steel co-operation; For guaranteeing the balance and stability of girder steel in two cantilever erection processes, generally adopt the balance pier to support, make the two cantilevers of girder steel tie up to vertical bridge and reach balance that usually, the cost of balance pier is high to two fulcrums are arranged; Because installation accuracy (mainly being the displacement difference of girder steel center line and bridge center line) has a significant impact girder steel closure tool between the pier epimerite, therefore need have adjustable measure.
Summary of the invention
At the defective that exists in the prior art, the object of the present invention is to provide a kind of pier-side bracket of adjustable spatial position of steel beam, pier-side bracket is combined with main bridge girder steel, solved stablizing in the two cantilever erection processes of steel braced arch, and make carriage have level, vertical displacement adjustable function, the deviation that has solved girder steel is adjusted problem, has guaranteed the precision of girder steel closure.
For reaching above purpose, the technical scheme that the present invention takes is:
A kind of pier-side bracket of adjustable spatial position of steel beam, it is characterized in that: be followed successively by the bracket 100 that is symmetrical set, adjustable separation interface 300 of carriage and bottom bracket 200 up and down from top to bottom, fixedly connected with main bridge girder steel 403 in the top of bracket 100, bottom bracket 200 is arranged on the upper surface of the cushion cap 402 of carrying pier shaft 401.
On the basis of technique scheme, bracket 100 comprises six roots of sensation bracket column 101, bracket column 101 triplets are symmetrical set in pier shaft 401 left and right sides, it is 102 that 101 adjacent on two bracket columns are provided with the X-shaped connection, reservation gusset plate bolt on the top of bracket column 101 and the main bridge girder steel 403 is one and bracket column 101 cross sections and strong design such as corresponding girder steel montant, the bottom of bracket column 101 and up and down the bracket bracket 305 of the adjustable separation interface 300 of carriage weld; Bottom bracket 200 comprises six roots of sensation concrete filled steel tube column 201, concrete filled steel tube column 201 triplets are symmetrical set in pier shaft 401 left and right sides, it is 202 that 201 adjacent on two concrete filled steel tube columns are provided with the X-shaped connection, concrete filled steel tube column 201 is a girder steel internode with the spacing of pier shaft 401, the top of concrete filled steel tube column 201 and bottom bracket bracket 303 welding of the adjustable separation interface 300 of carriage up and down.
On the basis of technique scheme, said bracket column 101 adopts box-shaped rod member assembly welding to form.
On the basis of technique scheme, 303 of bracket bracket 305 and bottom bracket brackets are provided with four vertical jack 302 and four level jack 301, bottom bracket bracket 303 is provided with the top lifting position of vertical jack 302 and the counter-force seat 308 of level jack 301, the counter-force seat of the vertical jack 302 of bracket bracket 305 double as; Four vertical jack 302 evenly distribute along bottom bracket bracket 303 longitudinal axis, and four level jack 301 evenly distribute along bottom bracket bracket 303 longitudinal axis.
On the basis of technique scheme, after main bridge girder steel 403 installation and regulating spatial position of steel beam, bracket bracket 305 and 303 of bottom bracket brackets also be welded with some block welding steel plates 304 up and down the adjustable separation interface 300 of carriage lock fully.
The pier-side bracket of adjustable spatial position of steel beam of the present invention, pier-side bracket is combined with main bridge girder steel, solved stablizing in the two cantilever erection processes of steel braced arch, and make carriage have level, vertical displacement adjustable function, the deviation that has solved girder steel is adjusted problem, has guaranteed the precision of girder steel closure.The technology of the present invention advanced person, economical rationality, easy construction, safe and reliable.
Description of drawings
The present invention has following accompanying drawing:
Fig. 1 pier-side bracket elevation
Fig. 2 pier-side bracket lateral plan
Upper and lower supporter bridge joint mouth elevation during the vertical top lifting of Fig. 3
Upper and lower supporter bridge joint mouth vertical view during the vertical top lifting of Fig. 4
Upper and lower supporter bridge joint mouth elevation during the horizontal top lifting of Fig. 5
Upper and lower supporter bridge joint mouth vertical view during the horizontal top lifting of Fig. 6
Upper and lower supporter bridge joint mouth elevation when Fig. 7 locks
Upper and lower supporter bridge joint mouth vertical view when Fig. 8 locks
The specific embodiment
Below in conjunction with accompanying drawing the present invention is described in further detail.
Fig. 1 is the pier-side bracket elevation of adjustable spatial position of steel beam of the present invention, be followed successively by the bracket 100 that is symmetrical set, adjustable separation interface 300 of carriage and bottom bracket 200 up and down from top to bottom, fixedly connected with main bridge girder steel 403 in the top of bracket 100, bottom bracket 200 is arranged on the upper surface of the cushion cap 402 of carrying pier shaft 401.Fig. 2 is the lateral plan of Fig. 1, shown in Fig. 2,3, bracket 100 comprises six roots of sensation bracket column 101, bracket column 101 triplets are symmetrical set in pier shaft 401 left and right sides, it is 102 that 101 adjacent on two bracket columns are provided with the X-shaped connection, reservation gusset plate bolt on the top of bracket column 101 and the main bridge girder steel 403 is one and bracket column 101 cross sections and strong design such as corresponding girder steel montant, the bottom of bracket column 101 and up and down the bracket bracket 305 of the adjustable separation interface 300 of carriage weld; Bottom bracket 200 comprises six roots of sensation concrete filled steel tube column 201, concrete filled steel tube column 201 triplets are symmetrical set in pier shaft 401 left and right sides, it is 202 that 201 adjacent on two concrete filled steel tube columns are provided with the X-shaped connection, concrete filled steel tube column 201 is a girder steel internode with the spacing of pier shaft 401, the top of concrete filled steel tube column 201 and bottom bracket bracket 303 welding of the adjustable separation interface 300 of carriage up and down.Concrete filled steel tube column 201 is the reasons are as follows of a girder steel internode with the spacing of pier shaft 401: when girder steel had overturning moment M, the stressed of column 201 was N, and column 201 is L with the distance of pier shaft, then M=N x L.If spacing L is very little, then column 201 is stressed very big, and the column cross section will be done very greatly, uneconomical, therefore will make L big as far as possible; Because column 201 will be connected with the girder steel node, so spacing L will equal one or several girder steel gap length; But column 201 can not arrive the scope that surpasses cushion cap greatly away from the distance at pier center, otherwise need on the river, drive piles in addition, therefore, in general, it is suitable that column 201 has the distance of a girder steel internode apart from the pier shaft center, can make the two cantilever systems of girder steel in erection process remain stable state.
On the basis of technique scheme, said bracket column 101 adopts box-shaped rod member assembly welding to form.
On the basis of technique scheme, shown in Fig. 3~6,303 of bracket bracket 305 and bottom bracket brackets are provided with four vertical jack 302 and four level jack 301, bottom bracket bracket 303 is provided with the top lifting position of vertical jack 302 and the counter-force seat 308 of level jack 301, the counter-force seat of the vertical jack 302 of bracket bracket 305 double as; Four vertical jack 302 evenly distribute along bottom bracket bracket 303 longitudinal axis, and four level jack 301 evenly distribute along bottom bracket bracket 303 longitudinal axis.Utilize jack can regulate the spatial position of steel beam that has set up.
On the basis of technique scheme, shown in Fig. 7,8, after main bridge girder steel 403 installation and regulating spatial position of steel beam, bracket bracket 305 and 303 of bottom bracket brackets also be welded with some block welding steel plates 304 up and down the adjustable separation interface 300 of carriage lock fully.
The installation steps of the pier-side bracket of adjustable spatial position of steel beam of the present invention are:
After concrete filled steel tube column 201 constructions of bottom bracket 200 finish, the plan-position and the end face absolute altitude of concrete filled steel tube column 201 are accurately measured, and adjusted construction error, installing afterwards is 202 to the X-shaped connection in length and breadth, forms bottom bracket 200 platforms.Install carriage 100 rod members, and the adjustable separation interface 300 of carriage up and down between the carriage locks temporarily up and down, four the internode girder steel rod members in girder steel bearing and pier top are installed afterwards.Measure four the internode girder steel absolute altitudes in pier top, medium line error, remove the interim locking of the adjustable separation interface 300 of carriage up and down, on the bottom bracket bracket 303 of bottom bracket 200, jacking equipment is installed, accurately adjust girder steel center line and absolute altitude after, welding steel 304 locks separating opening 300 fully.Creeper-traveler on the mounting rail then, the intact residue of assembly unit sections girder steel.
Pier-side bracket of the present invention, problem is adjusted in the stable and displacement that has solved in the two cantilever erection processes of steel braced arch, has guaranteed the safety of steel girder cantilever construction, has reduced the risk of girder steel closure, remarkable in economical benefits.The steel braced arch is from pier top during two cantilever erection, the pier-side bracket that can regulate is set in that pier is other, makes the two cantilever systems of girder steel in erection process remain stable state, and the locus of can timely adjustment having set up girder steel, to reduce the risk that girder steel joins the two sections of a bridge, etc.
Claims (5)
1. the pier-side bracket of an adjustable spatial position of steel beam, it is characterized in that: be followed successively by the bracket (100) that is symmetrical set, adjustable separation interface of carriage (300) and bottom bracket (200) up and down from top to bottom, fixedly connected with main bridge girder steel (403) in the top of bracket (100), bottom bracket (200) is arranged on the upper surface of the cushion cap (402) of carrying pier shaft (401).
2. the pier-side bracket of adjustable spatial position of steel beam as claimed in claim 1, it is characterized in that: bracket (100) comprises six roots of sensation bracket column (101), bracket column (101) triplets are symmetrical set in pier shaft (401) left and right sides, be provided with X-shaped between adjacent two bracket columns (101) and connect system (102), reservation gusset plate bolt on the top of bracket column (101) and the main bridge girder steel (403) is one and bracket column (101) cross section and strong design such as corresponding girder steel montant, the bottom of bracket column (101) and up and down the bracket bracket (305) of the adjustable separation interface of carriage (300) weld; Bottom bracket (200) comprises six roots of sensation concrete filled steel tube column (201), concrete filled steel tube column (201) triplets are symmetrical set in pier shaft (401) left and right sides, be provided with X-shaped between adjacent two concrete filled steel tube columns (201) and connect system (202), concrete filled steel tube column (201) is a girder steel internode with the spacing of pier shaft (401), the top of concrete filled steel tube column (201) and bottom bracket bracket (303) welding of the adjustable separation interface of carriage (300) up and down.
3. the pier-side bracket of adjustable spatial position of steel beam as claimed in claim 2 is characterized in that: said bracket column (101) adopts box-shaped rod member assembly welding to form.
4. as the pier-side bracket of claim 1 or 2 or 3 described adjustable spatial position of steel beam, it is characterized in that: be provided with four vertical jack (302) and four level jack (301) between bracket bracket (305) and bottom bracket bracket (303), bottom bracket bracket (303) is provided with the top lifting position of vertical jack (302) and the counter-force seat (308) of level jack (301), the counter-force seat of the vertical jack of bracket bracket (305) double as (302); Four vertical jack (302) evenly distribute along bottom bracket bracket (303) longitudinal axis, and four level jack (301) evenly distribute along bottom bracket bracket (303) longitudinal axis.
The pier-side bracket of 5 adjustable spatial position of steel beam as claimed in claim 4, it is characterized in that: after main bridge girder steel (403) installation and regulating spatial position of steel beam, between bracket bracket (305) and bottom bracket bracket (303), also be welded with some block welding steel plates (304) up and down the adjustable separation interface of carriage (300) lock fully.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CNA200810188047XA CN101440606A (en) | 2008-12-29 | 2008-12-29 | Pier-side bracket capable of adjusting spatial position of steel beam |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CNA200810188047XA CN101440606A (en) | 2008-12-29 | 2008-12-29 | Pier-side bracket capable of adjusting spatial position of steel beam |
Publications (1)
Publication Number | Publication Date |
---|---|
CN101440606A true CN101440606A (en) | 2009-05-27 |
Family
ID=40725192
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CNA200810188047XA Pending CN101440606A (en) | 2008-12-29 | 2008-12-29 | Pier-side bracket capable of adjusting spatial position of steel beam |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN101440606A (en) |
Cited By (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101824801A (en) * | 2010-05-07 | 2010-09-08 | 中铁大桥局集团第五工程有限公司 | Non-in-situ prepressing method of self-anchored type support frame and self-anchored type support frame thereof |
CN101793006B (en) * | 2009-12-23 | 2011-06-22 | 中铁大桥局集团第一工程有限公司 | Construction method for rapid construction of support cast-in-situ continuous beam |
CN103103925A (en) * | 2013-02-06 | 2013-05-15 | 中铁大桥局集团第八工程有限公司 | Combined H-shaped steel column bracket |
CN104894980A (en) * | 2015-04-09 | 2015-09-09 | 中铁第五勘察设计院集团有限公司 | Assembled inclination-angle-adjustable self-frame-falling pier-side bracket and construction method of pier-side bracket |
CN106197277A (en) * | 2016-08-18 | 2016-12-07 | 广西我的科技有限公司 | A kind of quick measuring mechanism of vehicle car volume and construction method thereof |
CN106370101A (en) * | 2016-08-18 | 2017-02-01 | 广西我的科技有限公司 | Support platform for vehicle compartment size measurement and the measurement method |
CN109208485A (en) * | 2018-10-17 | 2019-01-15 | 中铁大桥局集团有限公司 | The method for rapidly positioning of positioning device and packaged type bridges Precast Pier Columns |
CN109356036A (en) * | 2018-11-26 | 2019-02-19 | 中铁六局集团有限公司 | Middle pier pier-side bracket and its construction method |
CN110606430A (en) * | 2019-08-28 | 2019-12-24 | 中铁大桥局集团有限公司 | Cofferdam hanging system and method |
CN112095491A (en) * | 2020-09-09 | 2020-12-18 | 中铁六局集团有限公司 | Bidirectional cantilever erection construction process for Hualun type large-span steel truss girder bridge |
-
2008
- 2008-12-29 CN CNA200810188047XA patent/CN101440606A/en active Pending
Cited By (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101793006B (en) * | 2009-12-23 | 2011-06-22 | 中铁大桥局集团第一工程有限公司 | Construction method for rapid construction of support cast-in-situ continuous beam |
CN101824801A (en) * | 2010-05-07 | 2010-09-08 | 中铁大桥局集团第五工程有限公司 | Non-in-situ prepressing method of self-anchored type support frame and self-anchored type support frame thereof |
CN103103925A (en) * | 2013-02-06 | 2013-05-15 | 中铁大桥局集团第八工程有限公司 | Combined H-shaped steel column bracket |
CN104894980A (en) * | 2015-04-09 | 2015-09-09 | 中铁第五勘察设计院集团有限公司 | Assembled inclination-angle-adjustable self-frame-falling pier-side bracket and construction method of pier-side bracket |
CN104894980B (en) * | 2015-04-09 | 2017-03-08 | 中铁第五勘察设计院集团有限公司 | A kind of assembled tilt adjustable is from fall frame pier-side bracket and its construction method |
CN106197277A (en) * | 2016-08-18 | 2016-12-07 | 广西我的科技有限公司 | A kind of quick measuring mechanism of vehicle car volume and construction method thereof |
CN106370101A (en) * | 2016-08-18 | 2017-02-01 | 广西我的科技有限公司 | Support platform for vehicle compartment size measurement and the measurement method |
CN109208485A (en) * | 2018-10-17 | 2019-01-15 | 中铁大桥局集团有限公司 | The method for rapidly positioning of positioning device and packaged type bridges Precast Pier Columns |
CN109356036A (en) * | 2018-11-26 | 2019-02-19 | 中铁六局集团有限公司 | Middle pier pier-side bracket and its construction method |
CN110606430A (en) * | 2019-08-28 | 2019-12-24 | 中铁大桥局集团有限公司 | Cofferdam hanging system and method |
CN110606430B (en) * | 2019-08-28 | 2020-12-01 | 中铁大桥局集团有限公司 | Cofferdam hanging system and method |
CN112095491A (en) * | 2020-09-09 | 2020-12-18 | 中铁六局集团有限公司 | Bidirectional cantilever erection construction process for Hualun type large-span steel truss girder bridge |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101440606A (en) | Pier-side bracket capable of adjusting spatial position of steel beam | |
CN104631343B (en) | From traveling rhombus keying cradle in truss type structure and suspended basket and construction method | |
CN102733316B (en) | Integral synchronous rotary jacking construction method for small radius horizontal curved bridge | |
CN105568853B (en) | Wide-span reinforced concrete flitch-trussed beam side position is traversing, the construction method of the beam that falls | |
CN102808383B (en) | Curved bridge counter-slope jacking construction process | |
CN103757993A (en) | System and method for high-speed railway subgrade settlement restoration | |
CN110205933A (en) | A kind of arch rib of long-span steel arch bridge assembly falsework | |
CN101691813B (en) | Device and method for elevation synchronous compensation for super-high structure construction | |
CN101289836A (en) | Auxiliary erection method of horizontal cable of steel truss arched bridge | |
CN113718627A (en) | Construction method for adjusting gravity center of open bridge body | |
CN211472207U (en) | Suspension beam system for hoisting prefabricated section box girder | |
CN209538044U (en) | A kind of arch rib of long-span steel arch bridge assembly falsework | |
CN113738125B (en) | Construction method for lifting limited-space large-span steel structure of station house under line | |
CN207047889U (en) | A kind of device for installing forging machine main frame embedded part | |
CN107938854A (en) | A kind of steel girder erection method using built-in fitting | |
CN205804178U (en) | Scalable without holder device for the liftable of bridge coping construction | |
CN210713861U (en) | Deflection correcting device for upper and lower stoplogs during connection | |
CN210439157U (en) | Modular bracket bearing structure | |
CN204919348U (en) | Supplementary head tower of using of self anchored suspension bridge installation | |
CN209428961U (en) | A kind of steel box-girder installation bracket equipped with safe operation platform | |
CN111005324B (en) | Support-free suspension and locking construction method for assembled type segmental box girder | |
CN210658019U (en) | Accurate adjusting and temporary fixing device for verticality of main beam of tied arch bridge with double-layer steel truss beams | |
CN106192715B (en) | The SRC portal-rigid frames bridge structure and its construction method of erection without scaffolding | |
CN112813852B (en) | Repairing and reinforcing method for bridge deck subsidence of in-service bridge | |
CN111962404A (en) | T-shaped rigid frame cantilever bridge synchronous pushing displacement control closure method and cantilever bridge |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C02 | Deemed withdrawal of patent application after publication (patent law 2001) | ||
WD01 | Invention patent application deemed withdrawn after publication |
Open date: 20090527 |