CN101435200A - 组合围堰施工方法 - Google Patents

组合围堰施工方法 Download PDF

Info

Publication number
CN101435200A
CN101435200A CNA2008101875039A CN200810187503A CN101435200A CN 101435200 A CN101435200 A CN 101435200A CN A2008101875039 A CNA2008101875039 A CN A2008101875039A CN 200810187503 A CN200810187503 A CN 200810187503A CN 101435200 A CN101435200 A CN 101435200A
Authority
CN
China
Prior art keywords
stake
pile
construction
interlock
steel sheet
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CNA2008101875039A
Other languages
English (en)
Other versions
CN101435200B (zh
Inventor
秦顺全
田继开
郑大超
刘润泽
涂满明
刘翠云
张爱花
江涌
姚森
张文斌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Major Bridge Engineering Group Co Ltd MBEC
Original Assignee
China Railway Major Bridge Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Major Bridge Engineering Co Ltd filed Critical China Railway Major Bridge Engineering Co Ltd
Priority to CN2008101875039A priority Critical patent/CN101435200B/zh
Publication of CN101435200A publication Critical patent/CN101435200A/zh
Application granted granted Critical
Publication of CN101435200B publication Critical patent/CN101435200B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

本发明公开了一种桥梁基础工程中大堤迎水侧的组合围堰施工方法,包括以下步骤:A.在大堤迎水侧施工钻孔咬合桩,形成地下连续墙的桩基部分,并在钻孔咬合桩两端的桩上安装预埋钢板,然后浇筑上部钢筋混凝土胸墙;B.插打其他三面钢板桩,形成组合围堰;C.围堰内逐层开挖取土,于三面钢板桩顶部的内壁上分别焊接导环,并用若干横向和纵向内支撑架固定,钢板桩一端与预埋钢板焊连;D.浇筑封底混凝土,施工基础;E.基础施工完成后,拆除内支撑、导环和钢板桩,留下地下连续墙作为大堤永久防护结构。本发明利用地下连续墙作为大堤的稳定支护结构,同时作为围堰的一部分,满足了大堤防护和桥梁水中基础施工的需要。

Description

组合围堰施工方法
技术领域
本发明涉及一种围堰施工方法,特别是涉及一种桥梁基础工程中大堤迎水侧的组合围堰施工方法。
背景技术
在国内一般大堤迎水侧的桥梁基础施工中,常常将大堤防护与桥梁基础围堰分开考虑,这样就浪费了成本;并且当桥梁基础侵入大堤护岸时,在施工空间上存在难度。
发明内容
本发明所要解决的技术问题是解决大堤迎水侧的桥梁基础施工不经济、施工难度大的问题。
为了解决上述技术问题,本发明所采用的技术方案是提供一种组合围堰施工方法,包括以下步骤:
A、在大堤迎水侧按设计位置施工完成钻孔咬合桩,形成地下连续墙的桩基部分,并事先在钻孔咬合桩两端的桩上安装预埋钢板,然后浇筑上部钢筋混凝土胸墙;
B、以钻孔咬合桩为基准插打其他三面钢板桩到达设计深度,形成组合围堰,且钢板桩与钻孔咬合桩两端的装预埋钢板相对;
C、在组合围堰的闭合区域内逐层开挖取土,于三面钢板桩顶部的内壁上分别焊接固定导环,并用若干横向和纵向内支撑架固定,围堰内取土时,逐层将钢板桩一端与预埋钢板焊连;
D、闭合区域开挖到设计深度后,浇筑封底混凝土,施工基础;
E、基础施工完成后,拆除内支撑、导环和钢板桩,留下地下连续墙作为大堤永久防护结构。
上述方案中,所述钻孔咬合桩的排列方式为一个a桩和一个b桩间隔布置,边缘为b桩,施工时先施工a桩,后施工b桩,a桩混凝土采用超缓凝混凝土,要求必须在a桩混凝土初凝前完成b桩,其中a桩为素混凝土桩,b桩为钢筋混凝土桩,预埋钢板焊接在b桩的钢筋笼上。
所述钻孔咬合桩中相邻桩之间的咬合厚度根据桩长来选取,桩越短咬合厚度越小,但最小不宜小于100mm,桩越长咬合厚度越大,按下式进行计算:
D—2(kL+Q)≥50mm
式中:
L—桩长,mm;
k—桩的垂直度,以百分数或千分数表示;
Q—孔口定位误差容许值,mm;
D—钻孔咬合桩的设计咬合厚度,mm。
所述钢板桩为常用钢板桩、锁口钢管桩或自制钢板桩。
采用本发明提供的施工方法,在靠近大堤一侧,用地下连续墙作为大堤稳定支护结构,同时作为围堰的一部分,满足了大堤防护和桥梁水中基础施工的需要。
附图说明
图1为本发明施工时立面布置图;
图2为本发明施工时平面布置图;
图3为本发明施工时钢板桩与地下连续墙连接示意图。
具体实施方式
下面结合附图对本发明作出详细的说明。
如图1、图2、图3所示,本发明提供一种组合围堰施工方法,包括以下步骤:
A、在大堤10的迎水侧按设计位置施工完成钻孔咬合桩,形成地下连续墙的桩基部分1,所述钻孔咬合桩的排列方式为一个a桩和一个b桩间隔布置,施工时先施工a桩,后施工b桩,a桩混凝土采用超缓凝混凝土,要求必须在a桩混凝土初凝前完成b桩,其中a桩为素混凝土桩,b桩为钢筋混凝土桩,一排钻孔咬合桩的两端的钻孔桩为b桩,预埋钢板7与地下连续墙两端的b桩的钢筋笼一起安装,该b桩的施工步骤是:钻孔,将预埋钢板焊接在钢筋笼上,安装钢筋笼及预埋钢板,水下灌注b桩的混凝土,最后浇筑上部钢筋混凝土胸墙6;
B、以钻孔咬合桩为基准插打其他三面钢板桩2到达设计深度,形成组合围堰,钢板桩2为常用钢板桩、锁口钢管桩或自制钢板桩且钢板桩2与钻孔咬合桩两端的装预埋钢板相对;
C、在组合围堰的闭合区域内逐层开挖取土,于三面钢板桩顶部的内壁上分别焊接固定导环3,并用若干横向和纵向内支撑架4固定,逐层将钢板桩2一端与预埋钢板7焊连,其中导环3截面为型钢或箱形截面,内支撑4为钢管、桁架或型钢;
D、闭合区域开挖到设计深度后,浇筑封底混凝土5,施工基础,封底混凝土与围堰一起作为止水结构;
E、基础施工完成后,拆除钢板桩2、导环3和内支撑4,留下地下连续墙作为大堤10的永久防护结构。
所述钻孔咬合桩中相邻桩之间的咬合厚度根据桩长来选取,桩越短咬合厚度越小,但最小不宜小于100mm,桩越长咬合厚度越大,按下式进行计算:
D—2(kL+Q)≥50mm
式中:
L—桩长,mm;
k—桩的垂直度,以百分数或千分数表示;
Q—孔口定位误差容许值,mm;
D—钻孔咬合桩的设计咬合厚度,mm。
为了保证咬合桩底部有足够厚度的咬合量,除对其孔口定位误差严格控制外,还应对其垂直度进行严格的控制,根据我国《地下铁道工程施工及验收规范》规定,桩的垂直度标准为3‰。在成孔过程中如发现垂直度偏差过大,必须及时进行纠偏调整,达到设计深度时吊放钢筋笼,下导管,浇筑混凝土,同时逐步拔除混凝土导管和套筒,最后形成桩体。
本发明不局限于上述最佳实施方式,任何人应该得知在本发明的启示下作出的结构变化,凡是与本发明具有相同或相近的技术方案,均落入本发明的保护范围之内。

Claims (4)

1、组合围堰施工方法,其特征在于包括以下步骤:
A、在大堤迎水侧按设计位置施工完成钻孔咬合桩,形成地下连续墙的桩基部分,并事先在钻孔咬合桩两端的桩上安装预埋钢板,然后浇筑上部钢筋混凝土胸墙;
B、以钻孔咬合桩为基准插打其他三面钢板桩到达设计深度,形成组合围堰,且钢板桩与钻孔咬合桩两端的装预埋钢板相对;
C、在组合围堰的闭合区域内逐层开挖取土,于三面钢板桩顶部的内壁上分别焊接固定导环,并用若干横向和纵向内支撑架固定,逐层将钢板桩与预埋钢板焊连;
D、闭合区域开挖到设计深度后,浇筑封底混凝土,施工基础;
E、基础施工完成后,拆除内支撑、导环和钢板桩,留下地下连续墙作为大堤永久防护结构。
2、如权利要求1所述的组合围堰施工方法,其特征在于所述钻孔咬合桩的排列方式为一个a桩和一个b桩间隔布置,边缘为b桩,施工时先施工a桩,后施工b桩,a桩混凝土采用超缓凝混凝土,要求必须在a桩混凝土初凝前完成b桩,其中a桩为素混凝土桩,b桩为钢筋混凝土桩,预埋钢板焊接在b桩的钢筋笼上。
3、如权利要求2所述的组合围堰施工方法,其特征在于所述钻孔咬合桩中相邻桩之间的咬合厚度根据桩长来选取,桩越短咬合厚度越小,但最小不宜小于100mm,桩越长咬合厚度越大,按下式进行计算:
D—2(kL+Q)≥50mm
式中:
L—桩长,mm;
k—桩的垂直度,以百分数或千分数表示;
Q—孔口定位误差容许值,mm;
D—钻孔咬合桩的设计咬合厚度,mm。
4、如权利要求1至3项任一项权利要求所述的组合围堰施工方法,其特征在于所述钢板桩为常用钢板桩、锁口钢管桩或自制钢板桩。
CN2008101875039A 2008-12-24 2008-12-24 组合围堰施工方法 Active CN101435200B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2008101875039A CN101435200B (zh) 2008-12-24 2008-12-24 组合围堰施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2008101875039A CN101435200B (zh) 2008-12-24 2008-12-24 组合围堰施工方法

Publications (2)

Publication Number Publication Date
CN101435200A true CN101435200A (zh) 2009-05-20
CN101435200B CN101435200B (zh) 2011-01-12

Family

ID=40709822

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2008101875039A Active CN101435200B (zh) 2008-12-24 2008-12-24 组合围堰施工方法

Country Status (1)

Country Link
CN (1) CN101435200B (zh)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101914919A (zh) * 2010-07-30 2010-12-15 中铁四局集团第六工程有限公司 复杂地质条件下的联合围堰及其施工方法
CN103397648A (zh) * 2013-08-12 2013-11-20 中铁二局股份有限公司 一种有底钢套箱围堰钢筋混凝土二次封底施工方法
CN104929142A (zh) * 2015-07-09 2015-09-23 中国水利水电第七工程局有限公司 一种组合围堰结构及其建造施工方法
CN108729457A (zh) * 2018-06-27 2018-11-02 中铁十六局集团第三工程有限公司 一种用于桥梁深水基础的钢管桩围堰及其施工方法
CN110258600A (zh) * 2019-06-18 2019-09-20 广东省第二建筑工程有限公司 一种适用于深水水域的立式围堰施工工法

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101914919A (zh) * 2010-07-30 2010-12-15 中铁四局集团第六工程有限公司 复杂地质条件下的联合围堰及其施工方法
CN101914919B (zh) * 2010-07-30 2012-07-25 中铁上海工程局第一工程有限公司 复杂地质条件下的联合围堰的施工方法
CN103397648A (zh) * 2013-08-12 2013-11-20 中铁二局股份有限公司 一种有底钢套箱围堰钢筋混凝土二次封底施工方法
CN103397648B (zh) * 2013-08-12 2015-04-01 中铁二局股份有限公司 一种有底钢套箱围堰钢筋混凝土二次封底施工方法
CN104929142A (zh) * 2015-07-09 2015-09-23 中国水利水电第七工程局有限公司 一种组合围堰结构及其建造施工方法
CN108729457A (zh) * 2018-06-27 2018-11-02 中铁十六局集团第三工程有限公司 一种用于桥梁深水基础的钢管桩围堰及其施工方法
CN110258600A (zh) * 2019-06-18 2019-09-20 广东省第二建筑工程有限公司 一种适用于深水水域的立式围堰施工工法

Also Published As

Publication number Publication date
CN101435200B (zh) 2011-01-12

Similar Documents

Publication Publication Date Title
US9567720B2 (en) Offshore platform for a marine environment
CN105735325B (zh) 一种集约化的永久支护装配式地下室结构体系及施工方法
CN101435200B (zh) 组合围堰施工方法
CN108343071A (zh) 一种钢板桩组合灌注桩的基坑支护结构及施工方法
CN102966108A (zh) 紧临既有建筑物以地下结构为内支撑的深基坑施工方法
WO2015135471A1 (zh) 水上平台结构水底固定用空心筒墩及其安装施工方法
CN104452812A (zh) 地下室外墙的施工方法
CN107012871B (zh) 一种悬挂式围护深大长基坑装配式结构的逆作施工方法
CN210086295U (zh) 一种复合装配式地下结构
JP6454674B2 (ja) 止水作業空間の構築方法
CN201334671Y (zh) 一种组合围堰
CN103321246A (zh) 采用地下连续墙的基坑施工方法
CN113550317A (zh) 大盾构始发井明挖逆作基坑永临结合支护结构及施工方法
CN107059900B (zh) 一种双壁钢套箱围堰在砂卵石地层中快速下沉的施工方法
CN108385693B (zh) 一种用于分期地下室支护的等代锚杆支护方法和支护体系
CN103015446A (zh) 在深水、坚硬不透水层上施工承台的方法
CN106930278A (zh) 一种异型接头管用于支护桩咬合的方法
CN108086307B (zh) 钢管混凝土挖孔灌注复合微型桩
CN111827349B (zh) 采用组合结构技术快速构建地铁车站地下结构的方法
CN213143117U (zh) 一种装配式键槽基础挡土墙结构
CN102493472A (zh) 一种桥梁深水软土地基逆作法低桩承台复合基础施工工艺
CN111809662A (zh) 地铁车站地下结构组合建造方法
CN104480945A (zh) 一种基坑逆作施工方法
CN217517602U (zh) 近江堤基坑支护结构
AU2012313196B2 (en) Partially floating marine platform for offshore wind-power, bridges and marine buildings, and construction method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: GROUP CO., LTD., ZHONGTIE DAQIAO BUREAU

Free format text: FORMER OWNER: CHINA ZHONGTIE MAJOR BRIDGE ENGINEERING CO., LTD.

Effective date: 20150225

C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20150225

Address after: 430050 Hanyang Road, Hanyang District, Hubei, No. 38, No.

Patentee after: Group Co., Ltd., Zhongtie Daqiao Bureau

Address before: 430050 Hanyang Road, Hanyang District, Hubei, No. 38, No.

Patentee before: China Zhongtie Major Bridge Engineering Co., Ltd.