CN101392597B - 建筑电气暗配箱/盒一次到位施工方法 - Google Patents

建筑电气暗配箱/盒一次到位施工方法 Download PDF

Info

Publication number
CN101392597B
CN101392597B CN2008101511066A CN200810151106A CN101392597B CN 101392597 B CN101392597 B CN 101392597B CN 2008101511066 A CN2008101511066 A CN 2008101511066A CN 200810151106 A CN200810151106 A CN 200810151106A CN 101392597 B CN101392597 B CN 101392597B
Authority
CN
China
Prior art keywords
box
case
pipeline
construction
wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN2008101511066A
Other languages
English (en)
Other versions
CN101392597A (zh
Inventor
黄昌学
谢家录
李军伟
邵华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SCEGC NO.3 CONSTRUCTION ENGINEERING GROUP Co.,Ltd.
Original Assignee
SHANXI THIRD ENGINEERING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHANXI THIRD ENGINEERING Co Ltd filed Critical SHANXI THIRD ENGINEERING Co Ltd
Priority to CN2008101511066A priority Critical patent/CN101392597B/zh
Publication of CN101392597A publication Critical patent/CN101392597A/zh
Application granted granted Critical
Publication of CN101392597B publication Critical patent/CN101392597B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

本发明公开了一种建筑电气暗配箱/盒一次到位施工方法,该方法是施工过程中,混凝土浇筑前,将箱/盒一次预埋到位。墙面上的箱盒以该层标高控制线为基准,用水准仪、钢卷尺、水平尺测定箱盒的准确位置;在箱盒表面划线,确定进入管线位置,用开孔器开孔;钢筋混凝土墙面上箱/盒采用“#”字形钢筋固定在钢筋网片上;砖墙、轻质隔墙上箱/盒,在墙体施工前,将配好的管线与箱/盒进行连接固定;进入箱/盒的管线一管一孔,排列整齐;箱盒内用裁好的聚苯乙烯泡沫板进行填充,周边用胶带密封。本发明的目的在于保证箱/盒位置的准确性。

Description

建筑电气暗配箱/盒一次到位施工方法
技术领域
本发明涉及土木工程领域电气暗配箱/盒的施工方法,特别涉及建筑电气暗配箱/盒一次到位施工方法。
背景技术
在建筑电气安装工程中,电气箱/盒的安装,传统的做法是采用预留空洞的方法。需要在钢筋绑扎时,混凝土浇注前,根据箱体在混凝土墙面上的位置及体积,提前用木料加工成六面封闭的木盒,固定在钢筋网片上。土建主体施工完后,再根据预留位置二次进行箱体的安装及配管。这种方法由于空洞位置难以控制,造成预留位置控制不准确,加大了二次箱体安装配管的难度,修补洞口后易产生空鼓、裂缝等质量缺陷,造成人工材料的浪费,影响工程进度和质量。
发明内容
为了克服上述现有技术不足,本发明提供一种建筑电气暗配箱/盒一次到位施工方法,该方法施工简便,易于操作,简化了工序,节约材料和人工,减低工程成本,提高了工程质量。
本发明的技术方案是这样实现的:
1、墙面上的箱/盒以该层标高控制线为基准,用水准仪、钢卷尺、水平尺测定箱/盒的准确位置。
2、在箱/盒表面划线,确定进入管线位置,用开孔器开孔。
3、墙面上箱/盒的固定
3.1钢筋混凝土墙面上箱/盒采用“#”字形钢筋固定在钢筋网片上。
3.2砖墙、轻质隔墙上箱/盒,在墙体施工前,将配好的管线与箱/盒配件进行连接。
4、进入箱/盒的管线一管一孔,排列整齐。
5、箱/盒内用裁好的聚苯乙烯泡沫板进行填充,周边用胶带密封。
本发明的效果是:
1、准确的控制了箱/盒平整度、高度、垂直度,保证了箱/盒安装位置准确。
2、进入箱/盒的管线一次性与箱体连接,敷设到位,减少了施工工序。
3、箱/盒周边不易出现空鼓、裂缝等质量缺陷。
具体实施方式
施工工艺流程:
1)墙面上的箱/盒以该层标高控制线为基准,用水准仪、钢卷尺、水平尺测定箱/盒的准确位置;
2)在箱/盒表面划线,确定进入管线位置,用开孔器开孔;
3)钢筋混凝土墙面上箱/盒采用“#”字形钢筋固定在钢筋网片上;砖墙、轻质隔墙上箱/盒,在墙体施工前,将配好的管线与箱/盒进行连接固定;
4)进入箱/盒的管线一管一孔,排列整齐;
5)箱/盒内用裁好的聚苯乙烯泡沫板进行填充,周边用胶带密封。
操作要点:
1、箱/盒位置的确定
1.1、剪力墙上箱/盒位置的确定:
根据图纸设计以及该层钢筋网片上标注的标高控制线,用水准仪、钢卷尺、水平尺等工具将箱/盒的安装标高坐标,抄测到剪力墙竖向钢筋上,做好标记。
1.2砖墙和轻质隔墙上箱/盒位置的确定:根据图纸设计以及该层建筑标高控制线(50线),确定其位置。
2箱/盒的开孔
根据配电箱的尺寸,结合管线实际敷设情况,先确定好箱内管线的位置,画线做好标记(一般配电箱内进线电源电管布置在箱子的顶部,总电源管线的布置在箱子的左上方,电源出线在箱子的下方)。
然后用开孔器开孔,确保箱内管线一管一孔,排列整齐,布局合理。
3箱/盒的固定
3.1剪力墙结构上箱/盒的固定:
用钢筋对箱/盒进行“#”字形焊接固定,将“#”字形钢筋焊接在钢筋网片上,确保焊接牢固、位置准确。箱/盒外表面与模板控制线平齐、接触紧密、平整,同时做好配电箱的跨接接地连接。
当箱体大边长度大于50mm时,箱体内应用木撑进行加固,防止箱体变形,此处模板应做加强肋。
3.2砖墙和轻质隔墙上箱/盒的固定:
在砌体前,应将配好的管线校正整齐,根据箱/盒的位置,将箱/盒用专用配件与管线紧密连接,确保箱体表面出墙20mm以保证出墙的厚度为抹灰粉刷层的厚度,并做好接地跨接。墙体砌筑时箱/盒上方应加装过梁,防止箱体变形。轻质隔墙施工时,应派专人配合线盒开孔,确保位置准确。
4进入箱/盒管线的敷设
进入箱/盒的管线排列整齐、一管一孔,钢管丝扣连接,内外用锁母锁紧。管线之间应采用“U”型钢筋做跨接接地连接,使用的圆钢直径不小于φ6mm。KBG薄壁管和UPVC塑料管采用专用接头连接紧密。
5箱/盒的填充及密封
在箱/盒内对于G50以内的管口应使用专用塑料管帽进行封堵,对于G50以上的管口使用专用盲板进行封堵。箱/盒内用裁好的聚苯乙烯泡沫板进行填充,填充紧密平整。聚苯乙烯泡沫板板应凸出箱体表面5mm,周边用胶带密封。

Claims (1)

1.建筑电气暗配箱/盒一次到位施工方法,其特征在于,包括以下步骤:
1)墙面上的箱/盒以该层标高控制线为基准,用水准仪、钢卷尺、水平尺测定箱/盒的准确位置;
2)在箱/盒表面划线,确定进入管线位置,用开孔器开孔;
3)钢筋混凝土墙面上箱/盒采用“#”字形钢筋固定在钢筋网片上;砖墙、轻质隔墙上箱/盒,在墙体施工前,将配好的管线与箱/盒进行连接固定;
4)进入箱/盒的管线一管一孔,排列整齐;
5)箱/盒内用裁好的聚苯乙烯泡沫板进行填充,周边用胶带密封。
CN2008101511066A 2008-09-25 2008-09-25 建筑电气暗配箱/盒一次到位施工方法 Active CN101392597B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2008101511066A CN101392597B (zh) 2008-09-25 2008-09-25 建筑电气暗配箱/盒一次到位施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2008101511066A CN101392597B (zh) 2008-09-25 2008-09-25 建筑电气暗配箱/盒一次到位施工方法

Publications (2)

Publication Number Publication Date
CN101392597A CN101392597A (zh) 2009-03-25
CN101392597B true CN101392597B (zh) 2010-08-04

Family

ID=40493090

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2008101511066A Active CN101392597B (zh) 2008-09-25 2008-09-25 建筑电气暗配箱/盒一次到位施工方法

Country Status (1)

Country Link
CN (1) CN101392597B (zh)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102227078A (zh) * 2011-03-31 2011-10-26 中国一冶集团有限公司 设备基础电气管线保护方法
CN103174289B (zh) * 2012-10-20 2015-02-04 中国二十二冶集团有限公司 强弱电配电箱洞口预留施工方法
CN104810744A (zh) * 2014-01-28 2015-07-29 浙江国泰建设集团有限公司 一种墙体管线自由预埋施工方法
CN106930445B (zh) * 2017-05-11 2019-05-07 广州市水电设备安装有限公司 一种混凝土墙体直埋配电开关箱安装施工工艺
CN111997367A (zh) * 2020-09-04 2020-11-27 刘建 一种无背板表框预埋的施工工法

Also Published As

Publication number Publication date
CN101392597A (zh) 2009-03-25

Similar Documents

Publication Publication Date Title
CN101392597B (zh) 建筑电气暗配箱/盒一次到位施工方法
CN110617083A (zh) 一种隧道衬砌混凝土密实度实时智能监控报警施工方法
CN102127968B (zh) 楼板套管孔洞预留预埋模具灌浆施工方法及灌浆模具
CN104746772B (zh) 灰渣混凝土空心隔墙板的防裂施工方法
CN101392560A (zh) 建筑安装管道套管一次到位施工方法
CN103672181A (zh) 给排水管道套管预埋施工方法
CN102758456B (zh) 地下室防水工程的施工方法
CN201280725Y (zh) 一种用于建筑物地下室后浇带施工的预制板
CN102493648B (zh) 带成排管配电箱在砌体墙中前置预埋施工方法及支撑装置
CN203729322U (zh) 一种预制混凝土管道基础
CN202745404U (zh) 钢筋混凝土烟囱筒壁开孔取样后的外部修复补强装置
CN103089014A (zh) 一种穿楼板管道的施工方法
CN110872869A (zh) 一种外墙板接缝防水施工方法
CN110924692A (zh) 砌体管线直埋施工方法
CN110144973A (zh) 一种地下部分竖向后浇带pc防护结构及施工方法
CN104047423B (zh) 一种穿楼地面板精确预留洞口的模具与施工方法
CN202347544U (zh) 地下室外墙后浇带超前止水施工结构
CN207959289U (zh) 一种用于地下室后浇带部位的漏水修补结构
CN201276842Y (zh) 简易建筑预留洞口施工筒模
CN101781935B (zh) 一种替代在混凝土结构中预埋防水套管的方法
CN111271084B (zh) 一种隧道顶拱结构修复方法及修复结构
CN203096762U (zh) 一种防冻胀地梁
CN206220277U (zh) 现场施工的简易型变形缝结构
CN106381883B (zh) 穿墙杆防渗施工方法
CN103590508A (zh) 一种复合保温墙体结构及其施工方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CP01 Change in the name or title of a patent holder

Address after: 710054 No. 68 Anton street, Shaanxi, Xi'an

Patentee after: SCEGC NO.3 CONSTRUCTION ENGINEERING GROUP Co.,Ltd.

Address before: 710054 No. 68 Anton street, Shaanxi, Xi'an

Patentee before: SHAANXI CONSTRUCTION ENGINEERING GROUP NO.3 BUILDING ENGINEERING Co.,Ltd.

Address after: 710054 No. 68 Anton street, Shaanxi, Xi'an

Patentee after: SHAANXI CONSTRUCTION ENGINEERING GROUP NO.3 BUILDING ENGINEERING Co.,Ltd.

Address before: 710054 No. 68 Anton street, Shaanxi, Xi'an

Patentee before: SHAANXI CONSTRUCTION ENGINEERING GROUP THIRD ENGINEERING Co.,Ltd.

CP01 Change in the name or title of a patent holder