- Prior art keywords
- pipe
- clamp
- jacket
- installation
- mounting method
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000009434 installation Methods 0.000 title claims abstract description 38
- 238000000034 method Methods 0.000 title claims abstract description 37
- 238000013507 mapping Methods 0.000 claims abstract description 4
- 230000002787 reinforcement Effects 0.000 claims description 27
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims description 11
- 229910000831 Steel Inorganic materials 0.000 claims description 9
- 239000010959 steel Substances 0.000 claims description 9
- 238000010924 continuous production Methods 0.000 claims description 4
- 239000000725 suspension Substances 0.000 claims description 4
- 230000009189 diving Effects 0.000 description 11
- KFVPJMZRRXCXAO-UHFFFAOYSA-N [He].[O] Chemical compound [He].[O] KFVPJMZRRXCXAO-UHFFFAOYSA-N 0.000 description 4
- 230000008901 benefit Effects 0.000 description 2
- 238000010276 construction Methods 0.000 description 2
- 238000010586 diagram Methods 0.000 description 2
- 238000005516 engineering process Methods 0.000 description 2
- VNWKTOKETHGBQD-UHFFFAOYSA-N methane Chemical compound C VNWKTOKETHGBQD-UHFFFAOYSA-N 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000002950 deficient Effects 0.000 description 1
- 238000004519 manufacturing process Methods 0.000 description 1
- 239000003345 natural gas Substances 0.000 description 1
Images
Landscapes
- Supports For Pipes And Cables (AREA)
- Earth Drilling (AREA)
Abstract
Description
Claims (7)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN200710058603A CN100588779C (en) | 2007-08-06 | 2007-08-06 | Method for installing vertical pipe clamp of jacket |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN200710058603A CN100588779C (en) | 2007-08-06 | 2007-08-06 | Method for installing vertical pipe clamp of jacket |
Publications (2)
Publication Number | Publication Date |
---|---|
CN101363218A true CN101363218A (en) | 2009-02-11 |
CN100588779C CN100588779C (en) | 2010-02-10 |
Family
ID=40389802
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN200710058603A Expired - Fee Related CN100588779C (en) | 2007-08-06 | 2007-08-06 | Method for installing vertical pipe clamp of jacket |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN100588779C (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102284828A (en) * | 2011-04-28 | 2011-12-21 | 中国海洋石油总公司 | Adjustment process for coaxiality of pipe clamp |
CN103090139A (en) * | 2013-01-22 | 2013-05-08 | 天津鹏翎胶管股份有限公司 | Method for rapidly completing hoop assembly through installation marks |
CN103883273A (en) * | 2014-02-19 | 2014-06-25 | 中国海洋石油总公司 | Method for utilizing two cranes on saturation diving support vessel to mount vertical pipe |
CN107584252A (en) * | 2017-09-22 | 2018-01-16 | 中国海洋石油总公司 | The packaging technology of steel tube end part saddle port |
CN114156784A (en) * | 2021-11-03 | 2022-03-08 | 海洋石油工程股份有限公司 | Post-installation method of cable protective pipe |
Family Cites Families (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
NL7801062A (en) * | 1978-01-30 | 1979-08-01 | Seaflo Systems N V | ONE-POINT LAKE BUOY. |
US4273474A (en) * | 1979-05-11 | 1981-06-16 | Brown & Root, Inc. | Grouting of offshore jackets to distribute forces among the anchoring piles |
US4354446A (en) * | 1980-08-22 | 1982-10-19 | Conoco Inc. | Temporary mooring of tension leg platforms |
US4696603A (en) * | 1985-12-05 | 1987-09-29 | Exxon Production Research Company | Compliant offshore platform |
BR9203617A (en) * | 1992-09-16 | 1994-03-22 | Petroleo Brasileiro Sa | RETICULATED STRUCTURE WITH WIDE BASE FOR OFFSHORE PLATFORM SUPPORT |
CN1290829A (en) * | 2000-11-14 | 2001-04-11 | 胜利石油管理局工程建设一公司三分公司 | Pipe dragging method for beach landing pipeline and special device |
-
2007
- 2007-08-06 CN CN200710058603A patent/CN100588779C/en not_active Expired - Fee Related
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102284828A (en) * | 2011-04-28 | 2011-12-21 | 中国海洋石油总公司 | Adjustment process for coaxiality of pipe clamp |
CN102284828B (en) * | 2011-04-28 | 2013-06-19 | 中国海洋石油总公司 | Adjustment process for coaxiality of pipe clamp |
CN103090139A (en) * | 2013-01-22 | 2013-05-08 | 天津鹏翎胶管股份有限公司 | Method for rapidly completing hoop assembly through installation marks |
CN103883273A (en) * | 2014-02-19 | 2014-06-25 | 中国海洋石油总公司 | Method for utilizing two cranes on saturation diving support vessel to mount vertical pipe |
CN103883273B (en) * | 2014-02-19 | 2016-05-11 | 中国海洋石油总公司 | Utilize saturation diving to support the double crane on ship that the method for standpipe is installed |
CN107584252A (en) * | 2017-09-22 | 2018-01-16 | 中国海洋石油总公司 | The packaging technology of steel tube end part saddle port |
CN114156784A (en) * | 2021-11-03 | 2022-03-08 | 海洋石油工程股份有限公司 | Post-installation method of cable protective pipe |
CN114156784B (en) * | 2021-11-03 | 2024-03-22 | 海洋石油工程股份有限公司 | Post-installation method of cable protection tube |
Also Published As
Publication number | Publication date |
---|---|
CN100588779C (en) | 2010-02-10 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN111661273B (en) | Installation and construction method of deep and open sea semi-submersible fan | |
CN100588779C (en) | Method for installing vertical pipe clamp of jacket | |
CN113148030B (en) | Laying and installing method for deepwater submarine cable side launching | |
CN104480865B (en) | A kind of Large Steel open caisson accurate positioning method | |
CN104727336A (en) | Construction method of large single-pipe pile foundation of shallow-sea wind power plant | |
CN106218828B (en) | Removable wellhead platform and application method for offshore marginal oilfield exploitation | |
WO2003074353A1 (en) | A method for underwater transportation and installation or removal of objects at sea | |
EP3436335B1 (en) | Method for installing a subsea structure | |
CN103213654B (en) | A kind of method of construction of platform | |
CN103883273A (en) | Method for utilizing two cranes on saturation diving support vessel to mount vertical pipe | |
CN110185057B (en) | Tool and construction method for lifting and erecting steel pipe piles of offshore wind power single pile foundation | |
CN102213085A (en) | Installation method of vertical pipe of guide pipe rack | |
CN107313350A (en) | A kind of marine integral hoisting method of profile iron Sarasota | |
CN101929581B (en) | Underwater pipe clamp mounting method | |
CN111980594A (en) | Temporary seabed base plate and method for installing deepwater surface layer conduits in batches | |
CN103255775A (en) | Method for installing cofferdam | |
CN207861722U (en) | A kind of Simple water floating type gantry crane | |
CN114455033B (en) | Underwater equipment floating type test platform and use method thereof | |
CN201250067Y (en) | Hydraulic flashboard balance crane | |
CN202578652U (en) | In-place auxiliary bracket for vertical pipe | |
CN113879487A (en) | Non-self-floating immersed tube discharging method | |
CN202765227U (en) | Propeller mounting and locating device | |
CN206049982U (en) | A kind of platform supply vessel mooring gear | |
CN108589750A (en) | Vertical rotating construction method in steel cofferdam water | |
CN108951626A (en) | Jacket pile pipe pitching pile combined console |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
ASS | Succession or assignment of patent right |
Owner name: OFFSHORE OIL ENGINEERING CO., LTD. BLUEOCEAN TECHN Free format text: FORMER OWNER: OFFSHORE OIL ENGINEERING CO., LTD. |
|
C41 | Transfer of patent application or patent right or utility model | ||
TR01 | Transfer of patent right |
Effective date of registration: 20101026 Address after: 100010, 25, North Main Street, Dongcheng, Beijing, Chaoyangmen Co-patentee after: OFFSHORE OIL ENGINEERING Co.,Ltd. Patentee after: CHINA NATIONAL OFFSHORE OIL Corp. Co-patentee after: TIANJIN BLUOCEAN TECHNOLOGY INSPECTION Co.,Ltd. Address before: 100010, 25, North Main Street, Dongcheng, Beijing, Chaoyangmen Co-patentee before: OFFSHORE OIL ENGINEERING Co.,Ltd. Patentee before: CHINA NATIONAL OFFSHORE OIL Corp. |
|
ASS | Succession or assignment of patent right |
Owner name: OFFSHORE OIL ENGINEERING CO., LTD. TIANJIN BLUOCEA Free format text: FORMER OWNER: OFFSHORE OIL ENGINEERING CO., LTD. TIANJIN BLUOCEAN TECHNOLOGY INSPECTION CO., LTD. |
|
C41 | Transfer of patent application or patent right or utility model | ||
TR01 | Transfer of patent right |
Effective date of registration: 20110609 Address after: 100010, 25, North Main Street, Dongcheng, Beijing, Chaoyangmen Co-patentee after: OFFSHORE OIL ENGINEERING Co.,Ltd. Patentee after: CHINA NATIONAL OFFSHORE OIL Corp. Co-patentee after: TIANJIN BLUOCEAN TECHNOLOGY INSPECTION Co.,Ltd. Co-patentee after: COOEC SUBSEA TECHNOLOGY Co.,Ltd. Address before: 100010, 25, North Main Street, Dongcheng, Beijing, Chaoyangmen Co-patentee before: OFFSHORE OIL ENGINEERING Co.,Ltd. Patentee before: CHINA NATIONAL OFFSHORE OIL Corp. Co-patentee before: TIANJIN BLUOCEAN TECHNOLOGY INSPECTION Co.,Ltd. |
|
CP03 | Change of name, title or address |
Address after: 100010 Chaoyangmen North Street, Dongcheng District, Dongcheng District, Beijing Co-patentee after: OFFSHORE OIL ENGINEERING Co.,Ltd. Patentee after: CHINA NATIONAL OFFSHORE OIL Corp. Co-patentee after: TIANJIN BLUOCEAN TECHNOLOGY INSPECTION Co.,Ltd. Co-patentee after: COOEC SUBSEA TECHNOLOGY Co.,Ltd. Address before: No. 25, Chaoyangmen North Street, Dongcheng, Beijing Co-patentee before: OFFSHORE OIL ENGINEERING Co.,Ltd. Patentee before: CHINA NATIONAL OFFSHORE OIL Corp. Co-patentee before: TIANJIN BLUOCEAN TECHNOLOGY INSPECTION Co.,Ltd. Co-patentee before: COOEC SUBSEA TECHNOLOGY Co.,Ltd. |
|
CP03 | Change of name, title or address | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20100210 |