CN206049982U - A kind of platform supply vessel mooring gear - Google Patents

A kind of platform supply vessel mooring gear Download PDF

Info

Publication number
CN206049982U
CN206049982U CN201620979002.4U CN201620979002U CN206049982U CN 206049982 U CN206049982 U CN 206049982U CN 201620979002 U CN201620979002 U CN 201620979002U CN 206049982 U CN206049982 U CN 206049982U
Authority
CN
China
Prior art keywords
platform
supply vessel
mooring
drilling
gear
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201620979002.4U
Other languages
Chinese (zh)
Inventor
赵魏
崔秀达
王孟昊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Waigaoqiao Of Shaihai Shipbuilding Marine Engineering Design Co Ltd
Shanghai Waigaoqiao Shipbuilding Co Ltd
Original Assignee
Waigaoqiao Of Shaihai Shipbuilding Marine Engineering Design Co Ltd
Shanghai Waigaoqiao Shipbuilding Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Waigaoqiao Of Shaihai Shipbuilding Marine Engineering Design Co Ltd, Shanghai Waigaoqiao Shipbuilding Co Ltd filed Critical Waigaoqiao Of Shaihai Shipbuilding Marine Engineering Design Co Ltd
Priority to CN201620979002.4U priority Critical patent/CN206049982U/en
Application granted granted Critical
Publication of CN206049982U publication Critical patent/CN206049982U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Earth Drilling (AREA)

Abstract

The utility model discloses a kind of platform supply vessel mooring gear, which includes two groups of attachment structure units, each attachment structure unit includes a mooring eye plate, a mooring cable and a connection piece being sequentially connected, the mooring eye plate is fixedly welded on the side of drilling platforms, and the connector is used to realize the connection between the mooring cable and supply vessel.Drilling platforms and supply vessel are connected by the platform supply vessel mooring gear that this utility model is provided by mooring gear, it is ensured that supply is smoothly completed;The dynamic positioning system using supply vessel is avoided simultaneously, substantially reduces cost.

Description

A kind of platform supply vessel mooring gear
Technical field
This utility model is related to a kind of platform supply vessel mooring gear.
Background technology
Self-elevating drilling platform is made up of platform, spud leg and elevating mechanism, and platform can be lifted along spud leg, general without from boat energy Power.Spud leg decentralization insertion seabed during work, platform are raised to the trouble free service height for leaving sea, and spud leg are carried out pre- Pressure, will not be sunk with spud leg when ensureing that platform runs into storm.Completion rear platform drops to sea, extracts spud leg and all lifts, whole Individual platform floats on sea, is dragged to new well location by tugboat.Nineteen fifty-three, the U.S. built up First jack-up unit, and this platform is to water Deep strong adaptability, job stability are good, and development is very fast, account for the 1/2 of portable drilling rig sum.What China voluntarily manufactured Four pile lower limbs of self-elevating drilling platform " Bohai Sea one " platform are made by circular steel pipe, and the height of spud leg has more than 70 Rice, lowering or hoisting gear is bolt-type hydraulic control.The type drilling platforms cost is relatively low, migration property is good, sea-floor relief is fitted Ying Xingqiang, thus, using self-elevating drilling platform Chinese offshore drilling more.
Semisubmersible drilling platform is developed by bottom-supported platform, and top is spar deck, and bottom is two pontoons, is used Support post connects.During work, pontoon pulls the plug, and in water safety height, Area of Water Plan is little, and wave effect is little on deck, Good stability, self control ability are strong, operating depth is big, and after the dynamic positioning technology of new development is used for semisubmersible platform, operating depth can Up to 900-1200 rice.Compared with self-elevating drilling platform, advantage is that operating depth is big to semi-submersible type, mobile flexible;Have the disadvantage investment Greatly, standing charges are high, and the utensil under water that need to have a set of complexity, availability are less than self-elevating drilling platform.
Deep water semi-submersible drilling platform and self-elevating drilling platform, are all offshore drillng operations, oil, water on platform, Drilling fluid dispensing and living material etc. are fed all by platform supply vessel.But, platform supply vessel is to platform When being fed, need relative position to be kept with drilling platforms, and ocean current, wave can cause supply vessel away from platform, to mending Impact to work.Generally, platform supply vessel can keep accommodation using its dynamic positioning system for carrying, but, power is fixed The unlatching of position system, will greatly increase the fuel consumption of supply vessel, so as to increase cost payout.Therefore, if can be on platform Side is installed by a set of mooring gear for both fixed drilling platform and platform supply vessel position, it is ensured that supply work, will very Be conducive to production practices.
Utility model content
The technical problems to be solved in the utility model lack between the drilling platforms of prior art and supply vessel to be overcome The device of both weary fixation relative positions, and the defect of the dynamic positioning system of supply vessel is must be turned on, and provide a kind of brill Well platform supply vessel mooring gear.The platform supply vessel mooring gear that this utility model is provided has simple structure, Yi Shi The advantages of existing, easy to operate, performance is good, it is adaptable to all offshore drilling platformses.
This utility model is solving above-mentioned technical problem by following technical proposals:
This utility model provides a kind of platform supply vessel mooring gear, and which includes two groups of attachment structure units, often Attachment structure unit described in one includes a mooring eye plate, a mooring cable and a connection piece being sequentially connected, the mooring eye plate The side of drilling platforms is fixedly welded on, the connector is used to realize the connection between the mooring cable and supply vessel.
It is preferred that the connector is a joining shackle.
It is preferred that the mooring eye plate in two groups of described attachment structure units is connected to the two sides of drilling platforms.
It is preferred that the connector in two groups of described attachment structure units is connected to the two ends of the stern of supply vessel.
It is preferred that when drilling platforms is semisubmersible drilling platform, described mooring eye plate is fixedly welded on the partly latent On the pillar construction of formula drilling platforms.
It is preferred that when drilling platforms is self-elevating drilling platform, described mooring eye plate is fixedly welded on described from liter On the ship side structure of formula drilling platforms.
When using platform supply vessel mooring gear of the present utility model, it is preferred that according to ocean current, the reality of wave Situation, selects supply vessel in drilling platforms dorsad ocean current side, while the stern direction of supply vessel is adjusted to putting down near drilling well The side of platform, and fore direction is adjusted away from the side of drilling platforms.
Positive effect of the present utility model is:The platform supply vessel mooring gear that this utility model is provided leads to Cross mooring gear to connect drilling platforms and supply vessel, it is ensured that supply is smoothly completed;Avoid the power using supply vessel fixed simultaneously Position system, substantially reduces cost.
Description of the drawings
Fig. 1 is applied to semisubmersible drilling platform for the platform supply vessel mooring gear of this utility model embodiment 1 Installation diagram.
Structural representations of the Fig. 2 for the platform supply vessel mooring gear of this utility model embodiment 1.
Fig. 3 is applied to the installation diagram of self-elevating drilling platform for platform supply vessel mooring gear in embodiment 2.
Specific embodiment
Two preferred embodiments are named, and combines accompanying drawing to become apparent from intactly illustrating this utility model.
Embodiment 1
As depicted in figs. 1 and 2, the platform supply vessel mooring gear that the present embodiment is provided, including two groups of attachment structures Unit 3, each attachment structure unit 3 include a mooring eye plate 301, a mooring cable 302 and the connection being sequentially connected Shackle 303, the mooring eye plate 301 are fixedly welded on the pillar construction of semisubmersible drilling platform 1, the joining shackle 303 For realizing that the two ends of the stern of the mooring cable 302 and supply vessel 2 connect.
In the present embodiment, according to ocean current, the practical situation of wave, supply vessel 2 is arranged on into semisubmersible drilling platform 1 dorsad Ocean current side, while the stern direction of supply vessel 2 is adjusted to the side near semisubmersible drilling platform 1, and by fore direction It is adjusted away from the side of semisubmersible drilling platform 1.
Do not affected by ocean current, wave when the structure of the present embodiment may insure to be fed for drilling platforms, kept ship Position, facilitates the supply goods and materials on 1 deck loop wheel machine handling supply vessel 2 of semisubmersible drilling platform, and ensures semisubmersible drilling platform 1 Top oil, water and drilling fluid dispensing flexible pipe it is unaffected with the connection of supply vessel 2.
Embodiment 2
As shown in figure 3, the structure of the platform supply vessel mooring gear of the present embodiment is with embodiment 1, difference exists In:Drilling platforms is self-elevating drilling platform 1, the mooring eye plate 301 in the attachment structure unit 3 be fixedly welded on it is described from On the ship side structure of lift-type drilling platforms 1.
The structure of the present embodiment can take the impact of ocean current, wave when may insure to be fed for drilling platforms, keep ship Position, facilitates the supply goods and materials on the 101 handling supply vessel 2 of deck loop wheel machine on self-elevating drilling platform 1, and ensures that jack up is bored Oil, water and drilling fluid dispensing flexible pipe above well platform 1 is unaffected with the connection of supply vessel 2.
The platform supply vessel mooring gear that this utility model is provided passes through mooring gear by drilling platforms and supply vessel Connection, it is ensured that supply is smoothly completed;The dynamic positioning system using supply vessel is avoided simultaneously, greatly reduces cost.

Claims (6)

1. a kind of platform supply vessel mooring gear, it is characterised in which includes two groups of attachment structure units, each company A mooring eye plate, a mooring cable and a connection piece that construction unit includes being sequentially connected are connect, the mooring eye plate fixes welding In the side of drilling platforms, the connector is used to realize the connection between the mooring cable and supply vessel.
2. platform supply vessel mooring gear as claimed in claim 1, it is characterised in that the connector is that a connection is unloaded Button.
3. platform supply vessel mooring gear as claimed in claim 1, it is characterised in that two groups of described attachment structure lists Mooring eye plate in unit is connected to the two sides of drilling platforms.
4. platform supply vessel mooring gear as claimed in claim 1, it is characterised in that two groups of described attachment structure lists Connector in unit is connected to the two ends of the stern of supply vessel.
5. platform supply vessel mooring gear as claimed in claim 1, it is characterised in that when drilling platforms is that semi-submersible type is bored During well platform, described mooring eye plate is fixedly welded on the pillar construction of the semisubmersible drilling platform.
6. platform supply vessel mooring gear as claimed in claim 1, it is characterised in that when drilling platforms is that jack up is bored During well platform, described mooring eye plate is fixedly welded on the ship side structure of the self-elevating drilling platform.
CN201620979002.4U 2016-08-29 2016-08-29 A kind of platform supply vessel mooring gear Active CN206049982U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620979002.4U CN206049982U (en) 2016-08-29 2016-08-29 A kind of platform supply vessel mooring gear

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620979002.4U CN206049982U (en) 2016-08-29 2016-08-29 A kind of platform supply vessel mooring gear

Publications (1)

Publication Number Publication Date
CN206049982U true CN206049982U (en) 2017-03-29

Family

ID=58377746

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620979002.4U Active CN206049982U (en) 2016-08-29 2016-08-29 A kind of platform supply vessel mooring gear

Country Status (1)

Country Link
CN (1) CN206049982U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110228570A (en) * 2019-07-01 2019-09-13 上海外高桥造船有限公司 Offshore floating type produces oil storage ship

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110228570A (en) * 2019-07-01 2019-09-13 上海外高桥造船有限公司 Offshore floating type produces oil storage ship

Similar Documents

Publication Publication Date Title
CN111661273B (en) Installation and construction method of deep and open sea semi-submersible fan
CN103924566B (en) A kind of Single Pile self-elevating drilling platform
US20110158784A1 (en) Arm assembly and methods of passing a pipe from a first vessel to a second vessel using the arm assembly
CN104029798B (en) Self installation production platform
CN104002937B (en) Offshore oilfield extended testing system platform
CN104627332A (en) Floating type self-elevating drilling platform
CN104727336A (en) Construction method of large single-pipe pile foundation of shallow-sea wind power plant
CN112726548B (en) Construction method for split jacket foundation of deep-open sea converter station
CN105003232B (en) A kind of ultra-deep sea marine oil and gas dry type production system and its installation evacuation method
US20040115006A1 (en) System and method for converting a floating drilling rig to a bottom supported drilling rig
US5775846A (en) Offshore production platform and method of installing the same
US20160229497A1 (en) Floating type self-lifting drilling platform
CN202023182U (en) Waterborne drilling foam platform
CN204589969U (en) Be applicable to the small modular jack-up unit of greater coasting area operation
CN206049982U (en) A kind of platform supply vessel mooring gear
CN106368197A (en) Mat type self-mounted platform with large wellheads
CN109178226A (en) A method of reducing the drinking water of semi-submersible offshore engineering platform
CN203890991U (en) Multifunctional well drilling boat for ocean oil filed
CN104417726A (en) Offshore pontoon construction method
CN104802950A (en) Self-elevating type underwater floater tension leg platform and establishing method thereof
CN108791738A (en) A kind of Large marine wind turbine entirety floating support mounting method
CN206557397U (en) A kind of lifting of exploration ship focus array high pressure airgun is with hanging gunwale
CN204623785U (en) A kind of jack up underwater buoyant body tension leg platform
CN213328975U (en) Semi-submersible pile inserting type ocean hoisting construction platform
CN204979158U (en) Latent floating carrying platform device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant