CN100588779C - Method for installing vertical pipe clamp of jacket - Google Patents

Method for installing vertical pipe clamp of jacket Download PDF

Info

Publication number
CN100588779C
CN100588779C CN200710058603A CN200710058603A CN100588779C CN 100588779 C CN100588779 C CN 100588779C CN 200710058603 A CN200710058603 A CN 200710058603A CN 200710058603 A CN200710058603 A CN 200710058603A CN 100588779 C CN100588779 C CN 100588779C
Authority
CN
China
Prior art keywords
pipe
jacket
clamp
installation
mounting method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN200710058603A
Other languages
Chinese (zh)
Other versions
CN101363218A (en
Inventor
李中华
李庆国
韩长安
商汉城
伊才颖
潘东民
姜进方
宋春娜
王靖
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tianjin Bluocean Technology Inspection Co ltd
China National Offshore Oil Corp CNOOC
Offshore Oil Engineering Co Ltd
COOEC Subsea Technology Co Ltd
Original Assignee
China National Offshore Oil Corp CNOOC
Offshore Oil Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China National Offshore Oil Corp CNOOC, Offshore Oil Engineering Co Ltd filed Critical China National Offshore Oil Corp CNOOC
Priority to CN200710058603A priority Critical patent/CN100588779C/en
Publication of CN101363218A publication Critical patent/CN101363218A/en
Application granted granted Critical
Publication of CN100588779C publication Critical patent/CN100588779C/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The invention discloses an installation method of the vertical pipe clamp of a jacket, which comprises the following steps: marking, clamp installation, swinging, initial installation, continued installation and wiring, wherein, in the step of the marking, a diver sets an underwater mapping and installation location; in the step of the clamp installation, in accordance with the measured sizes, a plurality of small clamps are fixed on the pipe at intervals, lifting points are provided on the pipe and large clamps are opened; in the step of the swinging, the pipes are lifted to the installationlocation and the driver is responsible for the underwater command that a windlass straighten the location of the pipe on a platform; in the step of the initial installation, the large clamps are fixedon a lacing pipe from bottom to top, the small clamps are opened and the pipes are lifted to the platform; in the step of the continued installation, the clamps at the higher installation position are installed in sequence by circularly carrying out clamp installation, swinging and initial installation; and in the step of the wiring, the pipelines are arranged into the small clamps.

Description

The mounting method of the riser clip of jacket
Technical field
The present invention relates to a kind of mounting method of riser clip of jacket, relate in particular to the back mounting method of the riser clip of jacket " the many cards of a pipe ", " the many cards of a pipe " method of using is installed riser clip.
Background technology
The jacket 2 of prior art, as shown in Figure 1, jacket is made of stake pipe 3 and reinforcement tube 4, stake pipe 3 plays a supportive role in vertical direction, it can be 4,6 or more, stake pipe 3 is vertical in the left and right sides, but slightly recede forward,, also have square top and bottom simultaneously so 2 pairs of jackets incline, its height is about 90 meters, reinforcement tube 4 is connected between each pipe 3, has laterally, also has oblique, quantity and structure, the load when depending primarily on operation on the sea and the influence of meteorologic factors such as wave and wind-force of stake pipe 3 and reinforcement tube 4.Platform 1 is being set above the jacket 2, can be used for the sea on the platform 1 and creep into operation, also can be used for the exploration and development and the production of oil and natural gas, jacket can also be used to supporting other any type of marine structure, on the platform 1 hoist engine is being set, pipeline 5 is used clamp 6 and is arranged on the reinforcement tube 4, and the scale in diagram left side is the sea level altitude of each clamp 6.
Jacket 2 is assembling on the coast normally, be provided with to the appointed place with the barge haul then, jacket 2 will be provided with underwater cable usually, the method of prior art is that the mounting method of the riser clip of jacket 2 is the installation sites that one by one clamp 6 winched to reinforcement tube 4 sides with the hoist engine on the platform 1, the diver is fixed on clamp 6 on the reinforcement tube 4 under water then, at last pipeline 5 being included in the clamp 6, next is exactly that submerged pipeline has been laid in the seabed.
There is following defective in the mounting method of the riser clip of the jacket of prior art:
In the mounting method of the riser clip of prior art jacket, helium-oxygen diving is subject to own characteristic, the underwater operation time is very of short duration, the time of diving operation is generally at 20 to 30 minutes, long about 40 minutes, in finishing the riser clip installation work, also need riser clip pitch angle and the adjustment of position, the left and right sides, most of installation work needs continuous production process, and operating efficiency is very low.And because of low its operation continuity of helium-oxygen diving operating efficiency can't be protected, installation work has difficulty.Riser clip is excessive because of weight, and inconvenience is installed, and also exists riser clip pitch angle and position, the left and right sides to adjust problems such as difficulty with one heart in the installation work.
Summary of the invention
Technical problem to be solved by this invention is, a kind of mounting method of riser clip of jacket is provided, and " the many cards of a pipe " method of using is installed riser clip.
In order to solve the problems of the technologies described above, the technical solution used in the present invention is:
Mounting method as the riser clip of a kind of jacket of the present invention, jacket is made of stake pipe and reinforcement tube, the stake pipe plays a supportive role in vertical direction, reinforcement tube is connected between each pipe, platform is being set above the jacket, pipeline is fixed on the reinforcement tube with clamp, clamp comprises that binding is the kilocalorie of one and lesser calorie two parts, this mounting method comprises mark successively, last card, handling, just adorn, continuous dress and wiring step, in markers step, by the diver mapping installation site is set under water, in last card step, according to the size of measuring, the lesser calorie of a plurality of clamps of fixed interval on pipe, and suspension centre is set on pipe, and kilocalorie is opened, in the handling step, pipe is hung the installation site, commanded under water by the diver, step is adorned in the position of the hoist engine alignment pipe on the platform just, from bottom to top, kilocalorie is fixed on the reinforcement tube, opens lesser calorie, and pipe hung get back on the platform, in continuous dress step, circulation is carried out and is gone up card, handling and first dress step are come the higher clamp in installation site successively, in the wiring step, pipeline are arranged in the lesser calorie.
And, pipe is provided with the position of three installation clips, in last card step, three clamps are installed simultaneously, in continuous dress step, only be installed in two clamps of installation site, top, the fixed-site of bottom installation clip has been installed in the lesser calorie of the clamp of the extreme higher position on the jacket, and each so all is that three lesser calories are on same straight line fixedly the time.
And, on this, block step, with rope binding kilocalorie, make kilocalorie keep open state.
And in this handling step, the pipe clamp drop to the upper end that tilts is contacting reinforcement tube, slowly puts down the lower end of pipe again, till the clamp contact reinforcement tube of the lower end of pipe.
And, the hinge of being convenient to open and close is being set on this kilocalorie, be provided with on the hinge and leading chain.
And the distance between this adjacent clamp is 8 meters to 15 meters.
In addition, this markers step is put the bottom that two steel wires go down and are fixed in jacket earlier from the water surface, and in first dress and continuous process of assembling, system has steel wire buckle, pipe just can be with clamp to drop to preposition reposefully along steel wire at clamp.
The invention has the beneficial effects as follows:
Compared with the prior art the mounting method of the riser clip of jacket of the present invention, has following advantage:
At first, link dress more, improved the efficient that riser clip is installed;
Secondly, after the installation, riser clip directly is in coaxial state, saves with axial adjustment work;
And, waterborne finishing transferred in the work of part diving, reduce the diving operation amount, and then improve the diving operation safety;
In addition, shorten riser clip significantly the required duration is installed, significantly save project cost.
Description of drawings
Fig. 1 is the lateral view of prior art jacket, standpipe and clamp
Fig. 2 is the front view of jacket, standpipe and clamp in the mounting method of the riser clip of jacket of the present invention
Among the figure:
1: platform 2: jacket
3: stake pipe 4: reinforcement tube
5: pipeline 6: clamp
7: pipe 8: kilocalorie
9: lesser calorie 10: hinge
The specific embodiment
Be described in further detail below in conjunction with the mounting method of the drawings and specific embodiments the riser clip of jacket of the present invention:
Because in the mounting method of the riser clip of jacket of the present invention, the lateral view of jacket, standpipe and clamp is identical with the prior art content, so do not repeat to provide.
In a specific embodiment of the mounting method of the riser clip of jacket of the present invention, need to adopt helium-oxygen diving 9 cover riser clips to be installed at platform,
As shown in Figure 2, in the mounting method of the riser clip of jacket of the present invention, jacket 2 is made of stake pipe 3 and reinforcement tube 4, stake pipe 3 plays a supportive role in vertical direction, in the left and right sides is vertical, but slightly recede forward, thereby cause 2 pairs of jackets to incline, thereby structure is more firm, its depth of water is about 90 meters, reinforcement tube 4 is connected between each pipe 3, have horizontal, also have oblique, platform 1 is being set above the jacket 2, on the platform 1 hoist engine is being set, pipeline 5 usefulness clamps 6 are fixed on the reinforcement tube 4, the scale at diagram middle part is the sea level altitude of each clamp 6, clamp 6 comprises that binding is the kilocalorie 8 of one and lesser calorie 9 two parts, kilocalorie 8 is used for fixing on reinforcement tube 4, lesser calorie 9 finally is used for fixing pipeline 5, this mounting method comprises mark successively, last card, handling, just adorn, continuous dress and wiring step in markers step, are provided with the mapping installation site under water by the diver, in last card step, according to the size of measuring, the lesser calorie 9 of a plurality of clamps 6 of fixed interval on pipe 7, and kilocalorie 8 opened, simultaneously, on pipe 7, suspension centre is set, on the suspension centre be the hoist cable of hoist engine, in the handling step, hoist engine on the platform 1 hangs the installation site with pipe 7, commanded under water by the diver, step is adorned in the position of the hoist engine alignment pipe 7 on the platform 1 just, from bottom to top, kilocalorie 8 is fixed on the reinforcement tube 4, opens lesser calorie 9, and pipe 7 hung get back on the platform 1, in continuous dress step, circulation is carried out and is gone up card, handling and first dress step are come the higher clamp 6 in installation site successively, in the wiring step, pipeline 5 are arranged in the lesser calorie 9.
Simultaneously, pipe 7 is provided with the position of three installation clips 6, in last card step, three clamps 6 are installed simultaneously, in continuous dress step, only be installed in two clamps 6 of installation site, top, the installation site, bottom is used for fixing the lesser calorie 9 of the clamp 6 that is installed in the extreme higher position on the jacket 2.Each so all is that three lesser calories 9 are on same straight line fixedly the time.At grade, all three adjacent clamps 6 are all on same straight line, and all on same straight line, the concentricity of clamp 6 and pitch angle just do not need the secondary centering to the clamp 6 that just means the place like this.Save diver's working time, reduced diver's working strength.
And,,, make kilocalorie 8 keep open state with rope binding kilocalorie 8 in last card step.
And in the handling step, pipe 7 tilts and descends slowly, embraces reinforcement tube 4 up to the mouth of pipe, at this moment, the clamp 6 contact reinforcement tubes 4 of upper end, the lower end of slowly putting down pipe 7 again touches reinforcement tube 4 to the clamp 6 of the lower end of pipe 7.
And, the hinge of being convenient to open and close 10 is being set on the kilocalorie 8, be provided with on the hinge 10 and leading chain or rope, the diver is easy to kilocalorie 8 is closed.Can certainly hinge 10 be set on lesser calorie 9 equally, lead chain or rope, reduce operation intensity.
And the distance between the adjacent clamp 6 is 8 meters to 15 meters, and the length of pipe 7 is about 23 meters like this, and the gross weight of three cards, one pipe is about 8 tons.
In addition, markers step is put the bottom that two steel wires go down and are fixed in jacket 2 earlier from the water surface, in first dress and continuous process of assembling, is that steel wire buckle is arranged at clamp 6, and pipe 7 just can be with clamp 6 to drop to preposition reposefully along steel wire.
The mounting method of the riser clip of jacket of the present invention is by " the many cards of a pipe ", effectively solved in the prior art with the extremely loaded down with trivial details shortcoming of axial adjustment workload, its principle is: according to by the order that is deep to shallow installation, a plurality of riser clips and concentric cable protecting tube are assembled on Platform Deck in the relative installation on the jacket in advance according to it, integral hoisting begins diving operation then and fixes to the installation site.According to this pattern, former riser clip is installed successively.Like this, 9 cover riser clips just directly are in coaxial state in that fastening back is installed, need not to adjust pitch angle and about skew, greatly reduced the diving workload, shortened the project duration.
Emphasis of the present invention and difficult point are the accuracy control of whole assembling in advance and the Balance Control of integral hoisting." one pipe many card " mounting method just is that than the benefit of prior art maximum it can accomplish that many cover riser clips connect dress, saved simultaneously complicated loaded down with trivial details riser clip pitch angle and about skew adjustment work.
The mounting method of the riser clip of jacket of the present invention is successful Application, achieves noticeable achievement, and its job practices is proved safe and reliable in engineering practice.This mounting technique is applicable to the platform riser clip and installs that it is many especially to be suitable for installation quantity, and the clamp profile is bigger, the project that should not regulate.Because it has reduced the diving operation amount that riser clip is installed significantly, so this method can significantly improve the construction overall security.
In the present embodiment, adopt helium-oxygen diving 9 cover riser clips to be installed at platform, this still belongs to the first time at home, possessed novelty fully, proposition of the present invention and application are actual saves 22 days durations, the saving amplitude reached for 60% (37 days total durations of riser clip), be equivalent to for company save cost reach 200 surplus ten thousand yuan.In the present embodiment, the proposition of mounting technique and use and shortened the duration significantly behind " one pipe many card " method riser clip, the high-quality and efficient construction task of having finished has obtained owner's height approval.

Claims (7)

1, a kind of mounting method of riser clip of jacket, jacket is made of stake pipe and reinforcement tube, the stake pipe plays a supportive role in vertical direction, reinforcement tube is connected between each pipe, platform is being set above the jacket, pipeline is fixed on the reinforcement tube with clamp, clamp comprises that binding is the kilocalorie of one and lesser calorie two parts, it is characterized in that: described mounting method comprises mark successively, last card, handling, just adorn, continuous dress and wiring step, in markers step, by the diver mapping installation site is set under water, in last card step, according to the size of measuring, go up the lesser calorie (9) of a plurality of clamps of fixed interval (6) at pipe (7), and on pipe (7), suspension centre is set, and kilocalorie (8) opened, in the handling step, pipe (7) is hung the installation site, command under water by the diver, the position of the hoist engine alignment pipe (7) on the platform (1), adorn step just, from bottom to top, kilocalorie (8) is fixed on the reinforcement tube (4), opens lesser calorie (9), and pipe (7) hung get back on the platform (1), in continuous dress step, circulation is carried out and is gone up card, operation in handling and the first dress step comes the higher clamp (6) in installation site successively, in the wiring step, pipeline (5) is arranged in the lesser calorie (9).
2, the mounting method of the riser clip of jacket according to claim 1, it is characterized in that: described pipe (7) is provided with the position of three installation clips (6), in last card step, three clamps (6) are installed simultaneously, in continuous dress step, pipe (7) only is installed in two clamps (6) of installation site, top, the fixing lesser calorie (9) that has been installed in the clamp (6) of the extreme higher position on the jacket (2) in installation site, bottom, and each so all is that three lesser calories (9) are on same straight line fixedly the time.
3, the mounting method of the riser clip of jacket according to claim 1 is characterized in that: block step on described, with rope binding kilocalorie (8), make kilocalorie (8) keep open state.
4, according to the mounting method of the riser clip of any one described jacket in the claim 1 to 3, it is characterized in that: in described handling step, the clamp (6) that pipe (7) tilts to drop to the upper end touches reinforcement tube (4), slowly put down the lower end of pipe (7) again, touch reinforcement tube (4) to the clamp (6) of the lower end of pipe (7).
5, the mounting method of the riser clip of jacket according to claim 4 is characterized in that: the hinge of being convenient to open and close (10) is being set on the described kilocalorie (8), is being provided with on the hinge (10) and is leading chain.
6, the mounting method of the riser clip of jacket according to claim 4 is characterized in that: the distance between the adjacent described clamp (6) is 8 meters to 15 meters.
7, the mounting method of the riser clip of jacket according to claim 4, it is characterized in that: in described markers step, from the water surface, put the bottom that two steel wires go down and are fixed in jacket (2) earlier, in first dress and continuous process of assembling, at clamp (6) is that steel wire buckle is arranged, and pipe (7) just can be with clamp (6) to drop to preposition reposefully along steel wire.
CN200710058603A 2007-08-06 2007-08-06 Method for installing vertical pipe clamp of jacket Expired - Fee Related CN100588779C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN200710058603A CN100588779C (en) 2007-08-06 2007-08-06 Method for installing vertical pipe clamp of jacket

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN200710058603A CN100588779C (en) 2007-08-06 2007-08-06 Method for installing vertical pipe clamp of jacket

Publications (2)

Publication Number Publication Date
CN101363218A CN101363218A (en) 2009-02-11
CN100588779C true CN100588779C (en) 2010-02-10

Family

ID=40389802

Family Applications (1)

Application Number Title Priority Date Filing Date
CN200710058603A Expired - Fee Related CN100588779C (en) 2007-08-06 2007-08-06 Method for installing vertical pipe clamp of jacket

Country Status (1)

Country Link
CN (1) CN100588779C (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102284828B (en) * 2011-04-28 2013-06-19 中国海洋石油总公司 Adjustment process for coaxiality of pipe clamp
CN103090139A (en) * 2013-01-22 2013-05-08 天津鹏翎胶管股份有限公司 Method for rapidly completing hoop assembly through installation marks
CN103883273B (en) * 2014-02-19 2016-05-11 中国海洋石油总公司 Utilize saturation diving to support the double crane on ship that the method for standpipe is installed
CN107584252B (en) * 2017-09-22 2019-04-09 中国海洋石油集团有限公司 The packaging technology of steel tube end part saddle port
CN114156784B (en) * 2021-11-03 2024-03-22 海洋石油工程股份有限公司 Post-installation method of cable protection tube

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4254522A (en) * 1978-01-30 1981-03-10 Bluewater Terminal Systems N.V. Single-point mooring buoy
US4273474A (en) * 1979-05-11 1981-06-16 Brown & Root, Inc. Grouting of offshore jackets to distribute forces among the anchoring piles
US4354446A (en) * 1980-08-22 1982-10-19 Conoco Inc. Temporary mooring of tension leg platforms
US4696603A (en) * 1985-12-05 1987-09-29 Exxon Production Research Company Compliant offshore platform
CN1084923A (en) * 1992-09-16 1994-04-06 巴西石油公司 The band that supports ocean platform is widened the jacket structure of base
CN1290829A (en) * 2000-11-14 2001-04-11 胜利石油管理局工程建设一公司三分公司 Pipe dragging method and special device for seashore landing pipeline

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4254522A (en) * 1978-01-30 1981-03-10 Bluewater Terminal Systems N.V. Single-point mooring buoy
US4273474A (en) * 1979-05-11 1981-06-16 Brown & Root, Inc. Grouting of offshore jackets to distribute forces among the anchoring piles
US4354446A (en) * 1980-08-22 1982-10-19 Conoco Inc. Temporary mooring of tension leg platforms
US4696603A (en) * 1985-12-05 1987-09-29 Exxon Production Research Company Compliant offshore platform
CN1084923A (en) * 1992-09-16 1994-04-06 巴西石油公司 The band that supports ocean platform is widened the jacket structure of base
CN1290829A (en) * 2000-11-14 2001-04-11 胜利石油管理局工程建设一公司三分公司 Pipe dragging method and special device for seashore landing pipeline

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
雷卡定位技术在平台导管架海上就位中的应用. 苗文成.中国海洋平台,第16卷第2期. 2001
雷卡定位技术在平台导管架海上就位中的应用. 苗文成.中国海洋平台,第16卷第2期. 2001 *

Also Published As

Publication number Publication date
CN101363218A (en) 2009-02-11

Similar Documents

Publication Publication Date Title
KR101491740B1 (en) A method of installing a submerged tidal hydroelectric turbine
CN100588779C (en) Method for installing vertical pipe clamp of jacket
CN101920771B (en) Method for undock ballasting in ship building
CN104727336A (en) Construction method of large single-pipe pile foundation of shallow-sea wind power plant
CN113148030B (en) Laying and installing method for deepwater submarine cable side launching
CN104480865B (en) A kind of Large Steel open caisson accurate positioning method
CN106218828B (en) Removable wellhead platform and application method for offshore marginal oilfield exploitation
CN111661273B (en) Installation and construction method of deep and open sea semi-submersible fan
WO2003074353A1 (en) A method for underwater transportation and installation or removal of objects at sea
CN103213654B (en) A kind of method of construction of platform
CN103883273A (en) Method for utilizing two cranes on saturation diving support vessel to mount vertical pipe
CN110185057B (en) Tool and construction method for lifting and erecting steel pipe piles of offshore wind power single pile foundation
CN101370708B (en) A method of contemporaneously constructing more than one semi-submersible rig using transverse skidding
CN107313350A (en) A kind of marine integral hoisting method of profile iron Sarasota
CN102213085A (en) Installation method of vertical pipe of guide pipe rack
CN107084784B (en) A kind of four body ship type underwater measurement platform of movable lifting
CN101929581B (en) Underwater pipe clamp mounting method
CN104963521A (en) System and construction method used for integral hoisting and rotation of steel tower
WO1999048753A9 (en) Spar construction method
CN103255775A (en) Method for installing cofferdam
CN111980594B (en) Temporary seabed base plate and method for installing deepwater surface layer conduits in batches
CN202578652U (en) In-place auxiliary bracket for vertical pipe
CN114455033B (en) Underwater equipment floating type test platform and use method thereof
CN201250067Y (en) Hydraulic flashboard balance crane
CN113879487A (en) Non-self-floating immersed tube discharging method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: OFFSHORE OIL ENGINEERING CO., LTD. BLUEOCEAN TECHN

Free format text: FORMER OWNER: OFFSHORE OIL ENGINEERING CO., LTD.

C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20101026

Address after: 100010, 25, North Main Street, Dongcheng, Beijing, Chaoyangmen

Co-patentee after: OFFSHORE OIL ENGINEERING Co.,Ltd.

Patentee after: CHINA NATIONAL OFFSHORE OIL Corp.

Co-patentee after: TIANJIN BLUOCEAN TECHNOLOGY INSPECTION Co.,Ltd.

Address before: 100010, 25, North Main Street, Dongcheng, Beijing, Chaoyangmen

Co-patentee before: OFFSHORE OIL ENGINEERING Co.,Ltd.

Patentee before: CHINA NATIONAL OFFSHORE OIL Corp.

ASS Succession or assignment of patent right

Owner name: OFFSHORE OIL ENGINEERING CO., LTD. TIANJIN BLUOCEA

Free format text: FORMER OWNER: OFFSHORE OIL ENGINEERING CO., LTD. TIANJIN BLUOCEAN TECHNOLOGY INSPECTION CO., LTD.

C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20110609

Address after: 100010, 25, North Main Street, Dongcheng, Beijing, Chaoyangmen

Co-patentee after: OFFSHORE OIL ENGINEERING Co.,Ltd.

Patentee after: CHINA NATIONAL OFFSHORE OIL Corp.

Co-patentee after: TIANJIN BLUOCEAN TECHNOLOGY INSPECTION Co.,Ltd.

Co-patentee after: COOEC SUBSEA TECHNOLOGY Co.,Ltd.

Address before: 100010, 25, North Main Street, Dongcheng, Beijing, Chaoyangmen

Co-patentee before: OFFSHORE OIL ENGINEERING Co.,Ltd.

Patentee before: CHINA NATIONAL OFFSHORE OIL Corp.

Co-patentee before: TIANJIN BLUOCEAN TECHNOLOGY INSPECTION Co.,Ltd.

CP03 Change of name, title or address
CP03 Change of name, title or address

Address after: 100010 Chaoyangmen North Street, Dongcheng District, Dongcheng District, Beijing

Co-patentee after: OFFSHORE OIL ENGINEERING Co.,Ltd.

Patentee after: CHINA NATIONAL OFFSHORE OIL Corp.

Co-patentee after: TIANJIN BLUOCEAN TECHNOLOGY INSPECTION Co.,Ltd.

Co-patentee after: COOEC SUBSEA TECHNOLOGY Co.,Ltd.

Address before: No. 25, Chaoyangmen North Street, Dongcheng, Beijing

Co-patentee before: OFFSHORE OIL ENGINEERING Co.,Ltd.

Patentee before: CHINA NATIONAL OFFSHORE OIL Corp.

Co-patentee before: TIANJIN BLUOCEAN TECHNOLOGY INSPECTION Co.,Ltd.

Co-patentee before: COOEC SUBSEA TECHNOLOGY Co.,Ltd.

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20100210